CN105867290B CN201610217989.0A CN201610217989A CN105867290B CN 105867290 B CN105867290 B CN 105867290B CN 201610217989 A CN201610217989 A CN 201610217989A CN 105867290 B CN105867290 B CN 105867290B
Authority
CN
China
Prior art keywords
load
power supply
electric power
safety utilization
intelligent socket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610217989.0A
Other languages
Chinese (zh)
Other versions
CN105867290A (en
Inventor
陈杰春
赵丽萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Northeast Electric Power University
Original Assignee
Northeast Dianli University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Northeast Dianli University filed Critical Northeast Dianli University
Priority to CN201610217989.0A priority Critical patent/CN105867290B/en
Publication of CN105867290A publication Critical patent/CN105867290A/en
Application granted granted Critical
Publication of CN105867290B publication Critical patent/CN105867290B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/04Programme control other than numerical control, i.e. in sequence controllers or logic controllers
    • G05B19/05Programmable logic controllers, e.g. simulating logic interconnections of signals according to ladder diagrams or function charts
    • G05B19/058Safety, monitoring
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/10Plc systems
    • G05B2219/14Plc safety
    • G05B2219/14006Safety, monitoring in general

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Automation & Control Theory (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The present invention is a kind of office space safety utilization of electric power monitoring system and its method, and safety utilization of electric power monitoring system in office space includes a monitoring room subsystem and at least one office's subsystem;Monitoring room subsystem includes at least one operation person's active station, at least one data server and at least one clock sync server;Office's subsystem includes a safety utilization of electric power controlling terminal, at least one intelligent socket, load and load closedown controller.With automated procedures height, multiple functional, good reliability can identify violation electricity consumption, avoid that fire occurs, it is ensured that the advantages of Electrical Safety;Office space safety utilization of electric power monitoring method, can be according to the working and resting arrangement of unit, and timing automatically shuts off and be closed power supply line;It is able to detect " cutting " and " closed " event of power supply line, moreover it is possible to distinguish the type of event;When cutting off power supply line, power supply line is cut off in such load that can first shut down computer again, and then not will lead to load and break down.

Description

Office space safety utilization of electric power monitoring system and its method
Technical field
It is a kind of office space safety utilization of electric power monitoring system and its method the present invention relates to safety utilization of electric power monitoring field.
Background technique
It is real for the office spaces such as the laboratory of the office of enterprise and institution or institution of higher learning, scientific research institutions Existing safety utilization of electric power avoids that fire occurs to be an extremely important problem.Incorrect or unreasonable electricity consumption behavior, is to cause The principal element of office space generation fire.For example, not cutting off the power After Hours and having electric appliance longtime running, or upper The powerful electric appliance of Misuse between shift, these are all the principal elements for causing office space that fire occurs.It can be seen that hair A kind of bright system and method for realizing office space safety utilization of electric power monitoring are very important.
Chinese patent Authorization Notice No. CN100411270C, discloses title are as follows: distributed visible intelligent power consumption control pipe Reason system, the system include distributed visible intelligent dsm controller, network manager, hand-held visual wireless controller, IC card Reader is, it can be achieved that distribution detection is measured and the function of integrated management and monitoring.But the system has the disadvantage in that (1) no Can according to the working and resting arrangement of unit timing, automatically shut off and be closed power supply line;(2) it cannot detect and to occur in power supply line " cutting " and " closed " event, can not distinguish the type of event;(3) whether when cutting power supply, can not understand has computer Such load is in operating status or standby mode.Therefore when cutting off power supply, it is easy to cause the such load of computer It breaks down.
Summary of the invention
For overcome the deficiencies in the prior art, it is high that it is an object of the present invention to provide a kind of automated procedures, and function is neat Entirely, good reliability can identify violation electricity consumption, avoid that fire occurs, it is ensured that the office space safety utilization of electric power of Electrical Safety monitors System;And scientific and reasonable, strong applicability is provided, the good office space safety utilization of electric power monitoring method of effect.
Realize one of the object of the invention the technical solution adopted is that: a kind of office space safety utilization of electric power monitoring system includes One monitoring room subsystem and at least one office's subsystem, the monitoring room subsystem pass through internet and office's subsystem System connection, it is characterized in that: the monitoring room subsystem include at least one operation person's active station, at least one data server and At least one clock sync server, operation person's active station, data server and clock sync server pass through net respectively Network adapter and signal wire are connected to internet;Office's subsystem includes a safety utilization of electric power controlling terminal and at least one A intelligent socket, the safety utilization of electric power controlling terminal are connected to internet by network adapter, the intelligent socket with it is described The electrical connection of safety utilization of electric power controlling terminal.
Office's subsystem also includes load and load closedown controller, and the load is electrically connected with the intelligent socket It connects, the load closedown controller is electrically connected by general purpose I/O Interface with load.
The safety utilization of electric power controlling terminal includes electronic switch, phase line current sensor, phases line voltage sensor, zero curve electricity The input terminal of flow sensor and terminal control circuitry, the phases line voltage sensor is connected on the phase line of electronic switch output end On, the terminal control circuitry includes that embeded processor, internet interface circuit, audio collection and driving circuit, video are adopted Collector, interface of internet of things circuit, voltage and current Acquisition Circuit, ic for energy metering and switch driving circuit, the insertion Formula processor, internet interface circuit, audio collection and driving circuit, video capture circuit, interface of internet of things circuit, voltage and Current collection circuit, ic for energy metering and switch driving circuit are electrically connected by bus.
The intelligent socket includes electronic switch, phase line current sensor, Switch main body and socket control circuit, described to insert Seat control circuit includes embeded processor, current signal Acquisition Circuit, switch driving circuit, interface of internet of things circuit, loudspeaking Device or buzzer, " closed " button, the " Cancel " button and load remote control circuit, the embeded processor, current signal acquisition Circuit, switch driving circuit, interface of internet of things circuit, loudspeaker or buzzer, " closed " button, the " Cancel " button and load are distant Circuit is controlled to be electrically connected by bus.
The load closedown controller includes embeded processor, general purpose I/O Interface and signal reception and transmitting line, institute Embeded processor, general purpose I/O Interface and signal reception is stated to be electrically connected with transmitting line by bus.
Realize the object of the invention two the technical solution adopted is that: a kind of office space safety utilization of electric power autocontrol method, The following steps are included:
Step 401, safety utilization of electric power controlling terminal reads the current time in system;
Step 402, if power supply line should be closed at this time, step 403 is executed, it is no to then follow the steps 404;
Step 403, safety utilization of electric power controlling terminal is closed power supply line, and executes step 406;
Step 404, if power supply line should be cut off at this time, step 405 is executed, it is no to then follow the steps 406;
Step 405, safety utilization of electric power controlling terminal cuts off power supply line;
Step 406, safety utilization of electric power controlling terminal reads the phases line voltage numerical value and phase line current of electronic switch output end With the numerical value of neutral line current;
Step 407, safety utilization of electric power controlling terminal judges whether the event and event that cutting has occurred, is closed power supply line Type, or whether someone's Misuse electric appliance the case where occur;
Step 408, it in case of cutting or the event or someone's Misuse electric appliance of closure power supply line, executes Step 409, no to then follow the steps 401;
Step 409, safety utilization of electric power controlling terminal sends disappear relevant to event to operation person's active station and data server Then breath executes step 401.
The step 407 is further are as follows:
Step 501, if the virtual value of phases line voltage is there is no jump, i.e. jump between nonzero sum zero executes step Rapid 502, it is no to then follow the steps 505;
Step 502, by the numerical value of phases line voltage and phase line current, the active power of computational load consumption;
Step 503, if the active power of load consumption is not more than preset threshold value, step 517 is executed, is otherwise held Row step 504;
Step 504, it is believed that the event of Misuse electric appliance has occurred, and executes step 517;
Step 505, if the virtual value of phases line voltage have occurred zero to non-zero positive transition, execute step 506, otherwise hold Row step 507;
Step 506, it is believed that the event of closure power supply line has occurred, and executes step 517;
Step 507, by the numerical value of phases line voltage and phase line current, the active power of computational load consumption;
Step 508, if the numerical value of the active power of load consumption is greater than preset threshold value, step 509 is executed, it is no Then follow the steps 510;
Step 509, it is believed that the event of air switch overload protection tripping has occurred, and executes step 517;
Step 510, if the numerical value of phase line current is greater than pre-set threshold value, step 511 is executed, it is no to then follow the steps 512;
Step 511, it is believed that the event of air switch short-circuit protection tripping has occurred, and executes step 517;
Step 512, if the numerical value of phase line current and neutral line current is unequal, step 513 is executed, it is no to then follow the steps 514;
Step 513, it is believed that the event of air switch earth leakage protective tripping has occurred, and executes step 517;
Step 514, if the numerical value of phases line voltage is less than pre-set threshold value, step 515 is executed, it is no to then follow the steps 516;
Step 515, it is believed that the event of air switch low-voltage protection tripping has occurred, and executes step 517;
Step 516, it is believed that artificial cutting power supply line has occurred or safety utilization of electric power controlling terminal automatically cuts off supply lines The event on road, and execute step 517;
Step 517, the execution of end step 407.
The step 405 is further are as follows:
Step 801, safety utilization of electric power controlling terminal reads the numerical value of phase line current;
Step 802, if the virtual value of phase line current is greater than zero, step 803 is executed, it is no to then follow the steps 807;
Step 803, safety utilization of electric power controlling terminal sends the order of " cutting power supply line " to intelligent socket;
Step 805, safety utilization of electric power controlling terminal waits for a period of time;
Step 806, if someone terminates the process of intelligent socket cutting power supply line, step 808 is executed, is otherwise executed Step 807;
Step 807, the electronic switch in safety utilization of electric power controlling terminal cuts off power supply line;
Step 808, the execution of end step 405.
Between the step 803 and step 805 further include:
Step 804, intelligent socket cuts off power supply line, and the step 804 is further are as follows:
Step 901, intelligent socket reads the numerical value of phase line current;
Step 902, if the virtual value of phase line current is greater than zero, step 903 is executed, it is no to then follow the steps 911;
Step 903, intelligent socket plays one section of prompt tone, reminds the people using load, and intelligent socket will cut off power supply Route;
Step 904, if the process of intelligent socket cutting power supply line is terminated, step 905 is executed, it is no to then follow the steps 906;
Step 905, intelligent socket sends " process of intelligent socket cutting power supply is terminated " to safety utilization of electric power controlling terminal Message, then execute step 912;
Step 906, intelligent socket sends query messages to load closedown controller, obtains the status message of load;
Step 907, if intelligent socket can directly cut off power supply, step 911 is executed, it is no to then follow the steps 908;
Step 908, intelligent socket sends the order of " closing load " to load closedown controller;
Step 910, intelligent socket waits load shutdown;
Step 911, the electronic switch in intelligent socket cuts off power supply line;
Step 912, the execution of end step 804.
Between the step 908 and step 910 further include:
Step 909, load closedown controller closes load, and the step 909 is further are as follows:
Step 1001, if load is in standby mode, step 1002 is executed, it is no to then follow the steps 1004;
Step 1002, by general purpose I/O Interface, closedown controller is loaded to load and sends control signal, is detached from load Standby mode;
Step 1003, load closedown controller waits load to be detached from standby mode;
Step 1004, it by general purpose I/O Interface, loads closedown controller and is sent to resident control program in the load The order of " closing load ";
Step 1005, load closedown controller waits load shutdown.
Due to the adoption of the above technical scheme, safety utilization of electric power monitoring system and method in office space provided by the invention has Beneficial effect is:
(1) can be according to the working and resting arrangement of unit, timing automatically shuts off and is closed power supply line;
(2) " cutting " and " closed " event of power supply line are able to detect, moreover it is possible to distinguish the type of event;
(3) can detecte whether someone's Misuse electric appliance the case where generation;
It (4), can be with if there is load as computer is in operating status or standby mode when cutting off power supply line It first closes load and cuts off power supply line again, and then not will lead to the such load of computer and break down;
(5) by using operation person's active station, operation person both can may be used also taking human as the power supply line of cutting office Taking human as the power supply line of specified station in cutting office;
(6) by clock sync server, it is regularly directed at the clock of safety utilization of electric power controlling terminal, makes safety utilization of electric power control Terminal can cut off and be closed on time power supply line.
Detailed description of the invention
Shown in fig. 1 is the functional block diagram of safety utilization of electric power monitoring system embodiment in office space of the invention;
Fig. 2 shows be safety utilization of electric power controlling terminal embodiment of the invention functional block diagram;
Fig. 3 shows the functional block diagram of the electronic switch embodiment in safety utilization of electric power controlling terminal of the invention;
Fig. 4 shows the flow chart of safety utilization of electric power autocontrol method in office space of the invention;
Fig. 5 shows that cutting, closure supply lines has occurred for judging whether in safety utilization of electric power controlling terminal of the invention The flow chart of the method for the event on road, event type and Misuse electric appliance situation;
Fig. 6 shows the functional block diagram of intelligent socket embodiment of the invention;
Fig. 7 shows the functional block diagram of load closedown controller embodiment of the invention;
Fig. 8 shows the flow chart of safety utilization of electric power controlling terminal cutting power supply line's method of the invention;
Fig. 9 shows the flow chart of intelligent socket cutting power supply line's method of the invention;
Figure 10 shows that load closedown controller of the invention closes the flow chart of carrying method;
Figure 11 shows the comprising modules and its annexation figure of operation person's active station of the invention;
Figure 12 shows the comprising modules and its annexation figure of data server of the invention.
Specific embodiment
In conjunction with the attached drawing in the embodiment of the present invention, technical solution in the embodiment of the present invention is clearly and completely retouched It states.Obviously, the described embodiment is only a part of the embodiment of the present invention, instead of all the embodiments.Based in the present invention Embodiment, every other embodiment obtained by those of ordinary skill in the art without making creative efforts, It shall fall within the protection scope of the present invention.
Fig. 1 shows the functional block diagram of 10 embodiment of office space safety utilization of electric power monitoring system, and in embodiment, safety is used Electricity consumption monitoring system 10 includes monitoring room subsystem 11 and at least one office's subsystem 13, monitoring room subsystem 11 and is done Public room subsystem 13 realizes the exchange of information by internet 12.Internet 12 is local area network or wide area network.
Monitoring room subsystem 11 includes at least one operation person's active station 111, at least one data server 112, at least One clock sync server 113, operation person's active station 111, data server 112 and clock sync server 113 are led to respectively It crosses network adapter and signal wire is connected to internet 12.Clock sync server 113 is for realizing office space safety utilization of electric power The time alignment of monitoring device in monitoring system 10 is consistent the system time of all monitoring devices in system.
In the embodiment of office space safety utilization of electric power monitoring system 10, office's subsystem 13 includes a safety utilization of electric power Controlling terminal 131, at least one video camera 134, at least one loudspeaker 135, at least one microphone 136.Fig. 2 shows peaces The functional block diagram of complete 131 embodiment of power consumption control terminal.In embodiment, safety utilization of electric power controlling terminal 131 includes electronic switch 201, phases line voltage sensor 202, phase line current sensor 203, neutral line current sensor 204 and terminal control circuitry 205.Figure 3 show the functional block diagram of 201 embodiment of electronic switch in safety utilization of electric power controlling terminal 131.In embodiment, electronic switch 201 include a 2P air switch 301 and an A.C. contactor 302, two output ends of air switch 301 respectively with exchange The input terminal L1 and L2 of contactor 302 are cascaded.Air switch 301 is protected for realizing overload protection, short-circuit protection, electric leakage Shield and low-voltage protection.Contact winding wiring A1, A2 and auxiliary normally opened contact N0 of A.C. contactor 302 are for receiving terminal The control signal of control circuit 205, and then realize cutting and the closed procedure of power supply line.Phases line voltage sensor 202 and phase The input terminal of line current sensor 203 is connected in the phase line of 201 output end of electronic switch, is respectively used to measurement electronic switch The phases line voltage and phase line current of 201 output ends.The input terminal of neutral line current sensor 204 is connected on the output of electronic switch 201 On the zero curve at end, for measuring the neutral line current of 201 output end of electronic switch.
Terminal control circuitry 205 includes embeded processor 214 and memory 211.Embeded processor 214 is control electricity The core element on road is used for executing application.Memory 211 is for storing data and application program.Terminal control circuitry 205 It also include voltage and current Acquisition Circuit 208, ic for energy metering 209, voltage and current Acquisition Circuit 208 is for acquiring phase line The output signal of voltage sensor 202, phase line current sensor 203 and neutral line current sensor 204, ic for energy metering 209 For the active power of computational load and the electric energy of accumulative load consumption.Terminal control circuitry 205 also includes real time clock circuit 213, real time clock circuit 213 is used to obtain the current time of system.Terminal control circuitry 205 also includes wireless network card 212, nothing Gauze card 212 is a kind of internet interface circuit, for connecting internet.Terminal control circuitry 205 can also use other classes The internet interface circuit of type, such as ethernet interface circuit, realize the linkage function of internet.Terminal control circuitry 205 is also Comprising switch driving circuit 207, switch driving circuit 207 is used to receive the control signal of embeded processor 214 and drives electricity Sub switch 201, and then realize the cutting and closure control of power supply line.Terminal control circuitry 205 is also comprising low-voltage PLC(electricity Powerline carrier communication) modulation-demodulation circuit 210, the terminals and electronic switch output end of low-voltage PLC modulation-demodulation circuit 210 Phase line and zero curve coupling.Low-voltage PLC modulation-demodulation circuit 210 is a kind of interface of internet of things circuit, passes through low-voltage PLC tune Demodulator circuit 210 processed, safety utilization of electric power controlling terminal 131 exchange information with intelligent socket 132.Terminal control circuitry 205 can also be with Using other kinds of interface of internet of things circuit, such as Zigbee interface circuit, safety utilization of electric power controlling terminal 131 and intelligence are realized Information exchange functions between socket 132.Terminal control circuitry 205 is also comprising audio collection and driving circuit 215, audio collection It is used to acquire the signal of microphone 136, and drive the speaker 135 with driving circuit 215.Terminal control circuitry 205 is also comprising view Frequency Acquisition Circuit 216, video capture circuit 216 are used for the vision signal that acquisition camera 134 is shot.Terminal control circuitry 205 It also include DC-stabilized circuit 206, DC-stabilized circuit 206 is the embedded processing in terminal control circuitry 205 Device 214 and other modular circuits provide direct current supply.Terminal control circuitry 205 also includes generalized device interface 218, such as USB interface or RS232 interface, by generalized device interface 218, safety utilization of electric power controlling terminal 131 can receive other equipment hairs The data sent, for example receive cutting power supply line and be closed the time parameter of power supply line.Insertion in terminal control circuitry 205 Formula processor 214 and other modular circuits pass through bus 217 and set up connection, and bus 217 is one group of signal wire, including data letter Number line, address signal line, control signal wire, power supply line and ground wire.
Safety utilization of electric power controlling terminal 131 plays an important role in office's subsystem 13, because passing through safety utilization of electric power Controlling terminal 131 can realize the automatic control of office space safety utilization of electric power.Fig. 4 shows office space safety utilization of electric power automatic control The flow chart of method 40, office space safety utilization of electric power autocontrol method 40 the following steps are included:
Step 401, safety utilization of electric power controlling terminal reads the current time in system.In the terminal control of safety utilization of electric power controlling terminal In circuit, real time clock circuit is contained.By real time clock circuit, safety utilization of electric power controlling terminal can obtain system it is current when Between.
Step 402, if power supply line should be closed at this time, step 403 is executed, it is no to then follow the steps 404.According to preparatory Whether the parameter (should cut off and be closed the time of power supply line) of setting, the judgement of safety utilization of electric power controlling terminal should cut at this time Disconnected or closure power supply line.
Step 403, safety utilization of electric power controlling terminal is closed power supply line, and executes step 406.
Step 404, if power supply line should be cut off at this time, step 405 is executed, it is no to then follow the steps 406.
Step 405, safety utilization of electric power controlling terminal cuts off power supply line.
Step 406, safety utilization of electric power controlling terminal reads phases line voltage, phase line current and the zero curve electricity of electronic switch output end The numerical value of stream.In safety utilization of electric power controlling terminal, contains phases line voltage sensor, phase line current sensor, neutral line current and pass Sensor and voltage and current Acquisition Circuit, and the input terminal of phases line voltage sensor, phase line current sensor is connected on electricity In the phase line of sub switch output end, the input terminal of neutral line current sensor is connected on the zero curve of electronic switch output end, therefore Safety utilization of electric power controlling terminal can be with the number of the phases line voltage of real-time measurement electronic switch output end, phase line current and neutral line current Value.
Step 407, safety utilization of electric power controlling terminal judges whether the event and event that cutting has occurred, is closed power supply line Type, or whether someone's Misuse electric appliance the case where occur.
Step 408, it in case of cutting or the event or someone's Misuse electric appliance of closure power supply line, executes Step 409, no to then follow the steps 401.
Step 409, safety utilization of electric power controlling terminal sends disappear relevant to event to operation person's active station and data server Then breath executes step 401.In the database the logout occurred in system, operation person's active station is then for data server According to the type of message, decide whether or not to prompt operation person by way of alarm.
Fig. 5 shows event, thing of the safety utilization of electric power controlling terminal for judging whether that cutting has occurred, is closed power supply line The flow chart of the method 407 of part type and Misuse electric appliance situation.Method 407 the following steps are included:
Step 501, if the virtual value of phases line voltage executes step there is no jump (jump i.e. between nonzero sum zero) Rapid 502, it is no to then follow the steps 505.The instantaneous value of safety utilization of electric power controlling terminal real-time measurement phases line voltage, and calculate each period Phases line voltage virtual value.If the phases line voltage virtual value of adjacent periods is jumped, i.e., non-zero to zero or zero is to non-zero Jump, then illustrate the event for being cut off or being closed power supply line in office's subsystem.
Step 502, by the numerical value of phases line voltage and phase line current, the active power of computational load consumption.
Step 503, if the active power of load consumption is not more than preset threshold value, step 517 is executed, is otherwise held Row step 504.In different offices, the load number and the load type difference that use.Therefore, it is necessary to according to each office The power load situation of room, presets load active power threshold value.On this basis, can determine whether someone disobeys in office Rule have used electric appliance.
Step 504, it is believed that the event of Misuse electric appliance has occurred, executes step 517.
Step 505, if the virtual value of phases line voltage have occurred zero to non-zero positive transition, execute step 506, otherwise hold Row step 507.
Step 506, it is believed that the event of closure power supply line has occurred, and executes step 517.
Step 507, by the numerical value of phases line voltage and phase line current, the active power of computational load consumption.
Step 508, if the numerical value of the active power of load consumption is greater than preset threshold value, step 509 is executed, it is no Then follow the steps 510.
Step 509, it is believed that the event of air switch overload protection tripping has occurred, and executes step 517.
Step 510, if the numerical value of phase line current is greater than pre-set threshold value, step 511 is executed, it is no to then follow the steps 512。
Step 511, it is believed that the event of air switch short-circuit protection tripping has occurred, and executes step 517.
Step 512, if the numerical value of phase line current and neutral line current is unequal, step 513 is executed, it is no to then follow the steps 514。
Step 513, it is believed that the event of air switch earth leakage protective tripping has occurred, and executes step 517.
Step 514, if the numerical value of phases line voltage is less than pre-set threshold value, step 515 is executed, it is no to then follow the steps 516。
Step 515, it is believed that the event of air switch low-voltage protection tripping has occurred, and executes step 517.
Step 516, it is believed that artificial cutting power supply line has occurred or safety utilization of electric power controlling terminal automatically cuts off supply lines The event on road, and execute step 517.
Step 517, the execution of ending method 407.
In office space, computer is most important power load.It is different from other power loads, when computer is in When operating status or standby mode, power supply cannot be directly closed, otherwise will lead to computer failure.For example, There is bad track in the hard disk that may result in computer, and then computer is made to be not normally functioning program.In order to avoid occurring in this way The problem of, office's subsystem 13 is also comprising intelligent socket 132 and load closedown controller 133.Intelligent socket 132 passes through conducting wire It is connected to safety utilization of electric power controlling terminal 131, cannot directly cut off the load 137 of power supply and can directly cut off the load of power supply 138 are connected to intelligent socket 132 by conducting wire, and load closedown controller 133 is connected to by general purpose I/O Interface and cannot directly be cut The load 137(such as computer of cut-off electricity).Intelligent socket 132 and load closedown controller 133 use infrared ray or electromagnetic wave As the carrier of transmission information, the exchange of information is realized.For example, intelligent socket 132 sends life to load closedown controller 133 It enables, it is enabled to close load.For some specific intelligent socket, only it is connected to those and is obtained by its (intelligent socket) Load closedown controller in the load of power supply exchanges information.Therefore, intelligent socket 132 and load closedown controller 133 are all answered The offer be arranged ID(identifier) means (such as toggle switch), thus can determine whether intelligent socket 132 and load shutdown control Whether one-to-one device 133 is.On this basis, intelligent socket can only send to load closedown controller corresponding with it and order It enables, it is enabled to close load.
Fig. 6 shows the functional block diagram of 132 embodiment of intelligent socket.Intelligent socket 132 includes electronic switch 601, phase line Current sensor 602, Switch main body 603, socket control circuit 604.Electronic switch 601 can be a relay, can also be with It is an A.C. contactor.Electronic switch 601 receives the control signal of socket control circuit 604, realizes the cutting of power supply line With closed procedure.The input terminal of phase line current sensor 602 is connected in phase line, for measuring phase line current.Socket control electricity Road 604 includes embeded processor 609, and embeded processor 609 is used for executing application.Socket control circuit 604 is also wrapped Containing memory 610, memory 610 is for storing data and application program.Socket control circuit 604 is also acquired comprising current signal Circuit 608, current signal Acquisition Circuit 608 are used to acquire the signal of the output of current sensor 602.Socket control circuit 604 is also Comprising switch driving circuit 605, switch driving circuit 605 is used to receive the control signal of embeded processor 609 and drives electricity Sub switch 601 realizes cutting and the closed procedure of power supply line.Socket control circuit 604 also includes low-voltage PLC(power line Carrier communication) modulation-demodulation circuit 606.By low-voltage PLC modulation-demodulation circuit 606, intelligent socket 132 and safety utilization of electric power control Terminal 131 processed exchanges information.Low-voltage PLC modulation-demodulation circuit 606 is a kind of interface of internet of things circuit.Socket control circuit 604 can also use other kinds of interface of internet of things circuit, realize intelligent socket 132 and safety utilization of electric power controlling terminal 131 it Between information exchange functions, but require socket control circuit 604 use interface of internet of things circuit and terminal control circuitry 205 The interface of internet of things circuit of use is same type.Socket control circuit 604 is also comprising load remote control circuit 612, by negative Remote control circuit 612 is carried, intelligent socket 132 exchanges information with load closedown controller 133.Socket control circuit 604 is also comprising raising Sound device or buzzer 611, loudspeaker or buzzer 611 are used for playing alert tones, and prompting will using people's intelligent socket of load Cutting is powered.Socket control circuit 604 includes also " closed " button 613, when intelligent socket is in an off state, by pressing " closed " button 613 can make intelligent socket be closed power supply line.Socket control circuit 604 also includes the " Cancel " button 614, When intelligent socket is prompted by way of playing alert tones will cut off power supply using people's intelligent socket of load, make It can be by pressing the " Cancel " button 614 with the people of load, stop intelligent socket cuts off the process of power supply line, that is, makes intelligence Socket no longer cuts off power supply line.Socket control circuit 604 includes also voltage-stabilized power supply circuit 607, and voltage-stabilized power supply circuit 607 is slotting Embeded processor 609 and other modular circuits in seat control circuit 604 provide direct current supply.Socket control circuit 604 Circuit 616 also is set comprising ID, ID setting circuit 616 is used to be arranged the ID(identifier of intelligent socket).Embeded processor 609 Between other modular circuits, connection is set up by bus 615.Bus 615 is one group of signal wire, including data signal line, Address signal line, control signal wire, power supply line and ground wire.
Fig. 7 shows the functional block diagram of load closedown controller 133.Loading closedown controller 133 includes embedded processing Device 702, embeded processor 702 are used for executing application.Loading closedown controller 133 also includes memory 704, memory 704 for storing data and application program.Closedown controller 133 is loaded also comprising signal reception and transmitting line 701, passes through letter It number receives and to exchange information with intelligent socket 132 with transmitting line 701, load closedown controller 133, such as reception intelligent socket 132 orders sent, or response message is sent to intelligent socket 132.Load closedown controller 133 also connects comprising general purpose I/O Mouth 703 loads closedown controller 133 with the load 137 that cannot directly cut off power supply and exchanges letter by general purpose I/O Interface 703 Breath.Loading closedown controller 133 also includes power module 705, and power module 705 is that load closedown controller 133 is powered.Power supply Module 705 can be one and rechargeable battery, when loading in operating status, load can be by general purpose I/O Interface Load the battery charging in closedown controller 133.It loads closedown controller 133 and circuit 706 also is set comprising ID, circuit is arranged in ID 706 for being arranged the identifier of load closedown controller.Signal receives and transmitting line 701, embeded processor 702, general I/O interface 703, memory 704, power module 705 are linked together by bus 707.
Fig. 8 shows the flow chart that safety utilization of electric power controlling terminal 131 cuts off power supply line's method 405.Safety utilization of electric power control Terminal cut off power supply line's method 405 the following steps are included:
Step 801, safety utilization of electric power controlling terminal reads the numerical value of phase line current.Safety utilization of electric power controlling terminal contains phase line Current sensor and voltage and current Acquisition Circuit, therefore safety utilization of electric power controlling terminal can be with the number of real-time measurement phase line current Value.
Step 802, if the virtual value of phase line current is greater than zero, step 803 is executed, it is no to then follow the steps 807.It is negative when having When load is in operating status or standby mode, the virtual value of phase line current is greater than zero, and otherwise the virtual value of phase line current is equal to Zero.
Step 803, safety utilization of electric power controlling terminal sends the order of " cutting power supply line " to intelligent socket.
Step 805, safety utilization of electric power controlling terminal waits for a period of time.The mesh that safety utilization of electric power controlling terminal waits for a period of time , it is that the load (such as computer) that those cannot directly be cut off the power has time enough shutdown.Safety utilization of electric power controlling terminal The time of waiting is determined by pre-set numerical value.There are also other embodiments, for example, intelligent socket cuts off power supply line Afterwards, the message of " power supply line has been turned off " is sent to safety utilization of electric power controlling terminal, on this basis, safety utilization of electric power controlling terminal can The case where to understand intelligent socket cutting power supply line, and then judge that safety utilization of electric power controlling terminal can cut off power supply line.
Step 806, if someone terminates the process of intelligent socket cutting power supply line, step 808 is executed, is otherwise executed Step 807.When intelligent socket receives the order of " cutting power supply line ", it passes through loudspeaker first or buzzer broadcasting mentions Show sound, prompt the people using load, intelligent socket will cut off power supply line.If load is used in someone at this time, can By the way that by the " Cancel " button on intelligent socket, stop intelligent socket cuts off the process of power supply line.When someone terminates intelligence When the process of energy socket cutting power supply line, intelligent socket can send message to safety utilization of electric power controlling terminal, notify its intelligence The process of socket cutting power supply line is terminated.
Step 807, the electronic switch in safety utilization of electric power controlling terminal cuts off power supply line.
Step 808, the execution of ending method 405.
Fig. 9 shows the flow chart of intelligent socket cutting power supply line's method 804.Intelligent socket cuts off power supply line's method 804 the following steps are included:
Step 901, intelligent socket reads the numerical value of phase line current.Phase line current sensor and electricity are contained in intelligent socket Signal acquisition circuit is flowed, wherein the input terminal of phase line current sensor is connected in phase line, therefore intelligent socket can be surveyed in real time Measure the numerical value of the phase line current of intelligent socket output end.
Step 902, if the virtual value of phase line current is greater than zero, step 903 is executed, it is no to then follow the steps 911.If phase The virtual value of line current is greater than zero, illustrates have load to be in operating status or standby mode, otherwise illustrates all loads all It has been switched off.
Step 903, intelligent socket plays one section of prompt tone, reminds the people using load, and intelligent socket will cut off power supply Route.It in this course, then can be by being inserted by intelligence if someone needs to continue to use load in office office work The " Cancel " button on seat, stop intelligent socket cut off the process of power supply line.
Step 904, if the process of intelligent socket cutting power supply line is terminated, step 905 is executed, it is no to then follow the steps 906。
Step 905, intelligent socket sends " process of intelligent socket cutting power supply is terminated " to safety utilization of electric power controlling terminal Message, then execute step 912.Intelligent socket sends the " process of intelligent socket cutting power supply to safety utilization of electric power controlling terminal It is terminated " purpose of message, be notice safety utilization of electric power controlling terminal: someone is working in office, some intelligent socket is also not It can cutting power supply.
Step 906, intelligent socket sends query messages to load closedown controller, obtains the status message of load.As a result There are three types of possible: (1) at the appointed time, intelligent socket does not receive the response message of load closedown controller, and explanation does not have There is the load that cannot directly cut off power supply to be connected on intelligent socket, intelligent socket can directly cut off power supply;It (2) cannot be direct The load of cutting power supply all has been switched off, and intelligent socket can directly cut off power supply;(3) at the load that cannot directly cut off the power In operating status or standby mode, intelligent socket cannot directly cut off power supply.
Step 907, if intelligent socket can directly cut off power supply, step 911 is executed, it is no to then follow the steps 908.
Step 908, intelligent socket sends the order of " closing load " to load closedown controller.
Step 910, intelligent socket waits load shutdown.In this course, load closedown controller can be by general The state of I/O interface real-time monitoring load just sends disappearing for " load having been shut down " to intelligent socket once discovery load has been shut down Breath.
Step 911, the electronic switch in intelligent socket cuts off power supply line.Once those cannot directly close the negative of power supply Load has all been shut down, and intelligent socket can cut off power supply line.
Step 912, the execution of end step 804.
Figure 10 shows the flow chart that load closedown controller closes carrying method 909.It is negative to load closedown controller closing Support method 909 the following steps are included:
Step 1001, if load is in standby mode, step 1002 is executed, it is no to then follow the steps 1004.
Step 1002, by general purpose I/O Interface, closedown controller is loaded to load and sends control signal, is detached from load Standby mode.For example, load closedown controller can send control signal to load by USB interface or RS-232 interface, make Load is detached from standby mode.
Step 1003, load closedown controller waits load to be detached from standby mode.Load is waited to be switched to by standby mode Normal operating condition.
Step 1004, it by general purpose I/O Interface, loads closedown controller and is sent to resident control program in the load The order of " closing load ".
Step 1005, load closedown controller waits load shutdown.In this course, load closedown controller can lead to General purpose I/O Interface real-time detection load state is crossed, for example passes through the voltage value on the power supply line in USB interface, it can be determined that Whether load has been switched off.
Step 1006, load closedown controller sends " load has been shut down " message to intelligent socket.
Figure 11 shows the module composition and its annexation figure of 111 embodiment of operation person's active station.In embodiment, it transports Office staff's active station 111 include network connection management module 1101, event query module 1102, control command sending module 1103, Video data receiving module 1104, voice data receiving module 1105, voice data sending module 1106, speech signal collection mould Block 1107, event display module 1108, video display module 1109, voice playing module 1110.Wherein, event query module 1102, control command sending module 1103, video data receiving module 1104, voice data receiving module 1105 and voice data Sending module 1106 is connect with network connection management module 1101 respectively, and speech signal collection module 1107 and voice data are sent Module 1106 connects, and event display module 1108 is connect with event query module 1102, video display module 1109 and video counts It is connected according to receiving module 1104, voice playing module 1110 is connect with voice data receiving module 1105.
Network connection management module 1101 is for management operating person's active station 111 and 131 sum number of safety utilization of electric power controlling terminal According to the network connection between server 112, such as the foundation and disconnection that are connected to the network;Event query module 1102 is used for from data The historical data and real time data of the various events occurred in acquisition system in server 112;Event display module 1108 is used for Show the data obtained by event query module 1102;Control command sending module 1103 is used for into office's subsystem 13 Safety utilization of electric power controlling terminal 131 and intelligent socket 132 send control command, for example send " closure power supply line " or " cutting confession The order of electric line ";Video data receiving module 1104 is acquired and by interconnecting for receiving by safety utilization of electric power controlling terminal 131 The video data that net 12 is sent;Video display module 1109 is for showing by the received video counts of video data receiving module 1104 According to;Voice data receiving module 1105 is used to receive by safety utilization of electric power controlling terminal 131 acquisition and send by internet 12 Voice data;Voice playing module 1110 is for playing by the received voice data of voice data receiving module 1105;Voice letter Number acquisition module 1107 is used to acquire the voice signal of operation person;Voice data sending module 1106 is used for speech signal collection The voice data that module 1107 acquires is sent to safety utilization of electric power controlling terminal 131 by internet 12.
Figure 12 shows the module composition and its annexation figure of 112 embodiment of data server.In embodiment, data Server 112 includes data query operation processing module 1201, data reception module 1202 and data storage and management module 1203.Data reception module 1202 is for receiving by safety utilization of electric power controlling terminal 131, by internet 12, the various things of transmission Part information;Data storage and management module 1203 is used for storage and management, various events received by data reception module 1202 Data;Data query operation processing module 1201 is for handling, by the event query module 1102 in operation person's active station 111 It is sent by internet 12, event query operational order, and is obtained from data storage and management module 1203 and meet inquiry item The data of part, the event query module 1102 being then again sent to query result in operation person's active station 111.
Using office space safety utilization of electric power monitoring system 10, not only can arrange to automatically cut off according to the daily schedule of unit With closure power supply line, operation person can also be by using operation person's active station 111, and the safety into office's subsystem 13 is used Electric control terminal 131 or intelligent socket 132 send order, it is enabled to cut off the power supply line of entire office or the confession of some station Electric line.For example, being arranged according to the daily schedule of unit, safety utilization of electric power controlling terminal 131 has sent to intelligent socket 132 and " cuts The order of cut-off electric line ".But due to someone's overtime work in office, the staff of overtime work is by using on intelligent socket The " Cancel " button, terminate the cutting power supply line process of intelligent socket.In this case, intelligent socket 132 can pass through Safety utilization of electric power controlling terminal 131 sends message to data server 112, notifies individual intelligence in operation person office subsystem Socket does not cut off power supply.In this case, operation person can check installation in an office by operation person's active station 111 The video that shoots of video camera 134, installation microphone 136 in an office and loudspeaker 135 also can be used and adding Staff's call of class, exhorts that he will After Hours cut off power supply line.Even if the staff of overtime work does not have when going home There is a cutting power supply line, operation person can also safety utilization of electric power control by operation person's active station 111, into office's subsystem 13 Terminal 131 processed or intelligent socket 132 send order, it is enabled to cut off power supply line.
As previously mentioned, safety utilization of electric power controlling terminal 131 can according to the automatic disjunction power supply circuit of working and resting arrangement of unit and Connect power supply line.But crystal oscillator frequency is inaccurate or other due to, may result in safety utilization of electric power controlling terminal 131 after longtime running system time inaccuracy, and then will lead to safety utilization of electric power controlling terminal 131 cannot be accurately according to prior Arrangement cutting or closure power supply line.In order to solve this problem, clock sync server is configured in monitoring room subsystem 113.In this case, safety utilization of electric power controlling terminal 131 can be asked regularly to 113 transmission timing of clock sync server It asks, then clock sync server 113 sends response message to safety utilization of electric power controlling terminal 131, and then realizes safety utilization of electric power control The clock alignment of terminal processed.

Claims (9)

1. a kind of office space safety utilization of electric power monitoring system includes a monitoring room subsystem and at least one office's subsystem System, the monitoring room subsystem are connect by internet with office subsystem, and the monitoring room subsystem includes at least one Operation person's active station, at least one data server and at least one clock sync server, operation person's active station, data Server and clock sync server pass through network adapter respectively and are connected to internet, it is characterized in that: office's subsystem System includes a safety utilization of electric power controlling terminal, at least one intelligent socket, the load that cannot directly cut off power supply and load shutdown Controller, the safety utilization of electric power controlling terminal are connected to internet, the intelligent socket and the safety by network adapter The electrical connection of power consumption control terminal, the load that cannot directly cut off power supply are electrically connected with the intelligent socket, and the load is closed Machine controller is connected to the load that cannot directly cut off power supply by general purpose I/O Interface, and the safety utilization of electric power controlling terminal includes The input terminal of electronic switch and phases line voltage sensor, the phases line voltage sensor is connected on the phase line of electronic switch output end On, the phases line voltage sensor is used to measure the voltage of electronic switch output end, and the safety utilization of electric power controlling terminal is according to electricity Whether the virtual value of sub switch output end voltage jumps, and judges whether that closure power supply line and cutting power supply line has occurred Event, the intelligent socket include phase line current sensor and socket control circuit, the socket control circuit include loudspeaking Device or buzzer, the " Cancel " button and load remote control circuit, the load closedown controller is received comprising signal and transmitting line, The intelligent socket and load closedown controller are received by the load remote control circuit and signal exchanges information with transmitting line, The intelligent socket is before cutting power supply, first by the virtual value of the phase line current sensor measurement phase line current, and It judges whether there is and loads in operating status or standby mode, if the virtual value of phase line current is zero, the intelligent socket is straight Cutting power supply is connect, otherwise the intelligent socket plays one section of prompt tone by loudspeaker or buzzer, prompts intelligence described in user Socket will cut off power supply, if user terminates the process of cutting power supply, the intelligent socket by the " Cancel " button Stop cutting power supply immediately, otherwise the intelligent socket is sent by the load remote control circuit to the load closedown controller Query messages, for obtaining the status message of load, if power supply can directly be cut off, the intelligent socket cuts off confession immediately Electricity, otherwise the intelligent socket sends the order of " closing load " to the load closedown controller and load is waited to shut down, so The intelligent socket cuts off power supply again afterwards.
2. safety utilization of electric power monitoring system in office space according to claim 1, it is characterized in that: safety utilization of electric power control is eventually End also includes phase line current sensor, neutral line current sensor and terminal control circuitry, and the terminal control circuitry includes insertion Formula processor, internet interface circuit, audio collection and driving circuit, video capture circuit, interface of internet of things circuit, voltage and Current collection circuit, ic for energy metering and switch driving circuit, the embeded processor, internet interface circuit, audio Acquisition with driving circuit, video capture circuit, interface of internet of things circuit, voltage and current Acquisition Circuit, ic for energy metering and Switch driving circuit is electrically connected by bus.
3. safety utilization of electric power monitoring system in office space according to claim 1, it is characterized in that: the intelligent socket also includes Electronic switch and Switch main body, the socket control circuit also include embeded processor, current signal Acquisition Circuit, switch drive Dynamic circuit, interface of internet of things circuit and " closed " button, the embeded processor, current signal Acquisition Circuit, switch driving Circuit, interface of internet of things circuit, loudspeaker or buzzer, " closed " button, the " Cancel " button and load remote control circuit pass through total Line electrical connection.
4. safety utilization of electric power monitoring system in office space according to claim 1, it is characterized in that: the load closedown controller It also include embeded processor and general purpose I/O Interface, the embeded processor, general purpose I/O Interface and signal are received and sent Circuit is electrically connected by bus.
5. a kind of office space safety utilization of electric power monitoring side for safety utilization of electric power monitoring system in office space described in claim 1 Method, it is characterized in that: the following steps are included:
Step 401, safety utilization of electric power controlling terminal reads the current time in system;
Step 402, if power supply line should be closed at this time, step 403 is executed, it is no to then follow the steps 404;
Step 403, safety utilization of electric power controlling terminal is closed power supply line, and executes step 406;
Step 404, if power supply line should be cut off at this time, step 405 is executed, it is no to then follow the steps 406;
Step 405, safety utilization of electric power controlling terminal cuts off power supply line;
Step 406, safety utilization of electric power controlling terminal reads the phases line voltage numerical value and phase line current and zero of electronic switch output end The numerical value of line current;
Step 407, safety utilization of electric power controlling terminal judges whether that cutting has occurred, is closed the event of power supply line and the class of event Type, or whether someone's Misuse electric appliance the case where occur;
Step 408, in case of cutting or the event or someone's Misuse electric appliance of closure power supply line, step is executed 409, it is no to then follow the steps 401;
Step 409, safety utilization of electric power controlling terminal sends message relevant to event to operation person's active station and data server, so Step 401 is executed afterwards.
6. safety utilization of electric power monitoring method in office space according to claim 5, it is characterized in that: the step 407 is further Are as follows:
Step 501, if the virtual value of phases line voltage is there is no jump, i.e. jump between nonzero sum zero executes step 502, it is no to then follow the steps 505;
Step 502, by the numerical value of phases line voltage and phase line current, the active power of computational load consumption;
Step 503, if the active power of load consumption is not more than preset threshold value, step 517 is executed, step is otherwise executed Rapid 504;
Step 504, it is believed that the event of Misuse electric appliance has occurred, and executes step 517;
Step 505, if the virtual value of phases line voltage have occurred zero to non-zero positive transition, execute step 506, otherwise execute step Rapid 507;
Step 506, it is believed that the event of closure power supply line has occurred, and executes step 517;
Step 507, by the numerical value of phases line voltage and phase line current, the active power of computational load consumption;
Step 508, if the numerical value of the active power of load consumption is greater than preset threshold value, step 509 is executed, is otherwise held Row step 510;
Step 509, it is believed that the event of air switch overload protection tripping has occurred, and executes step 517;
Step 510, if the numerical value of phase line current is greater than pre-set threshold value, step 511 is executed, it is no to then follow the steps 512;
Step 511, it is believed that the event of air switch short-circuit protection tripping has occurred, and executes step 517;
Step 512, if the numerical value of phase line current and neutral line current is unequal, step 513 is executed, it is no to then follow the steps 514;
Step 513, it is believed that the event of air switch earth leakage protective tripping has occurred, and executes step 517;
Step 514, if the numerical value of phases line voltage is less than pre-set threshold value, step 515 is executed, it is no to then follow the steps 516;
Step 515, it is believed that the event of air switch low-voltage protection tripping has occurred, and executes step 517;
Step 516, it is believed that artificial cutting power supply line has occurred or safety utilization of electric power controlling terminal automatically cuts off power supply line Event, and execute step 517;
Step 517, the execution of end step 407.
7. safety utilization of electric power monitoring method in office space according to claim 5, it is characterized in that: the step 405 is further Are as follows:
Step 801, safety utilization of electric power controlling terminal reads the numerical value of phase line current;
Step 802, if the virtual value of phase line current is greater than zero, step 803 is executed, it is no to then follow the steps 807;
Step 803, safety utilization of electric power controlling terminal sends the order of " cutting power supply line " to intelligent socket;
Step 805, safety utilization of electric power controlling terminal waits for a period of time;
Step 806, if someone terminates the process of intelligent socket cutting power supply line, step 808 is executed, it is no to then follow the steps 807;
Step 807, the electronic switch in safety utilization of electric power controlling terminal cuts off power supply line;
Step 808, the execution of end step 405.
8. safety utilization of electric power monitoring method in office space according to claim 7, it is characterized in that: the step 803 and step Between 805 further include:
Step 804, intelligent socket cuts off power supply line, and the step 804 is further are as follows:
Step 901, intelligent socket reads the numerical value of phase line current;
Step 902, if the virtual value of phase line current is greater than zero, step 903 is executed, it is no to then follow the steps 911;
Step 903, intelligent socket plays one section of prompt tone, reminds the people using load, and intelligent socket will cut off power supply line;
Step 904, if the process of intelligent socket cutting power supply line is terminated, step 905 is executed, it is no to then follow the steps 906;
Step 905, intelligent socket sends disappearing for " process of intelligent socket cutting power supply being terminated " to safety utilization of electric power controlling terminal Then breath executes step 912;
Step 906, intelligent socket sends query messages to load closedown controller, obtains the status message of load;
Step 907, if intelligent socket can directly cut off power supply, step 911 is executed, it is no to then follow the steps 908;
Step 908, intelligent socket sends the order of " closing load " to load closedown controller;
Step 910, intelligent socket waits load shutdown;
Step 911, the electronic switch in intelligent socket cuts off power supply line;
Step 912, the execution of end step 804.
9. safety utilization of electric power monitoring method in office space according to claim 8, it is characterized in that: the step 908 and 910 it Between further include:
Step 909, load closedown controller closes load, and the step 909 is further are as follows:
Step 1001, if load is in standby mode, step 1002 is executed, it is no to then follow the steps 1004;
Step 1002, by general purpose I/O Interface, closedown controller is loaded to load and sends control signal, is detached from load standby State;
Step 1003, load closedown controller waits load to be detached from standby mode;
Step 1004, by general purpose I/O Interface, closedown controller is loaded to resident control program in the load and sends " closing The order of load ";
Step 1005, load closedown controller waits load shutdown.
CN201610217989.0A 2016-04-10 2016-04-10 Office space safety utilization of electric power monitoring system and its method Expired - Fee Related CN105867290B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610217989.0A CN105867290B (en) 2016-04-10 2016-04-10 Office space safety utilization of electric power monitoring system and its method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610217989.0A CN105867290B (en) 2016-04-10 2016-04-10 Office space safety utilization of electric power monitoring system and its method

Publications (2)

Publication Number Publication Date
CN105867290A CN105867290A (en) 2016-08-17
CN105867290B true CN105867290B (en) 2018-12-18

Family

ID=56637257

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610217989.0A Expired - Fee Related CN105867290B (en) 2016-04-10 2016-04-10 Office space safety utilization of electric power monitoring system and its method

Country Status (1)

Country Link
CN (1) CN105867290B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107168190A (en) * 2017-07-10 2017-09-15 杭州天时亿科技有限公司 A kind of artificial intelligence monitoring management system for formula of handling official business
JP6571144B2 (en) * 2017-09-08 2019-09-04 シャープ株式会社 Monitoring system, monitoring device, server, and monitoring method
CN111324061B (en) * 2020-01-21 2021-07-20 生态环境部长江流域生态环境监督管理局生态环境监测与科学研究中心 Equipment verification calibration management method and related equipment and storage device thereof
CN112162498A (en) * 2020-09-27 2021-01-01 重庆市海普软件产业有限公司 Intelligent switch protection system and method based on Internet of things
CN114784960A (en) * 2022-03-30 2022-07-22 海南电网有限责任公司电力科学研究院 Intelligent power consumption monitoring system

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202282863U (en) * 2011-10-28 2012-06-20 韩雪 Remote opening and closing control device of computer
CN103404165A (en) * 2011-01-27 2013-11-20 北卡罗来纳科姆斯科普公司 Automated infrastructure management systems and methods for enabling real time energy management
CN203773322U (en) * 2014-03-13 2014-08-13 国家电网公司 Electrical-power safe utilization monitoring device
CN104298184A (en) * 2013-07-19 2015-01-21 尹梦寒 Intelligent electric appliance management system based on Internet of things
CN204633060U (en) * 2015-05-28 2015-09-09 杭州普创电子有限公司 A kind of intelligent socket system
CN105182923A (en) * 2015-08-06 2015-12-23 国网山东省电力公司 Integrated intelligent electricity usage system for building and electricity usage method thereof
CN105182922A (en) * 2015-08-06 2015-12-23 山东建筑大学 Electrical information collection and energy-saving control system and method for office building
CN105305171A (en) * 2015-10-20 2016-02-03 西安文理学院 Remote-controlled intelligent socket
CN105406287A (en) * 2015-10-08 2016-03-16 黎宜 Intelligent socket capable of remote control

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103404165A (en) * 2011-01-27 2013-11-20 北卡罗来纳科姆斯科普公司 Automated infrastructure management systems and methods for enabling real time energy management
CN202282863U (en) * 2011-10-28 2012-06-20 韩雪 Remote opening and closing control device of computer
CN104298184A (en) * 2013-07-19 2015-01-21 尹梦寒 Intelligent electric appliance management system based on Internet of things
CN203773322U (en) * 2014-03-13 2014-08-13 国家电网公司 Electrical-power safe utilization monitoring device
CN204633060U (en) * 2015-05-28 2015-09-09 杭州普创电子有限公司 A kind of intelligent socket system
CN105182923A (en) * 2015-08-06 2015-12-23 国网山东省电力公司 Integrated intelligent electricity usage system for building and electricity usage method thereof
CN105182922A (en) * 2015-08-06 2015-12-23 山东建筑大学 Electrical information collection and energy-saving control system and method for office building
CN105406287A (en) * 2015-10-08 2016-03-16 黎宜 Intelligent socket capable of remote control
CN105305171A (en) * 2015-10-20 2016-02-03 西安文理学院 Remote-controlled intelligent socket

Also Published As

Publication number Publication date
CN105867290A (en) 2016-08-17

Similar Documents

Publication Publication Date Title
CN105867290B (en) Office space safety utilization of electric power monitoring system and its method
US6628207B1 (en) Method and apparatus for detecting and reporting a power outage
CN102931731B (en) Be applicable to the comprehensive intelligent supervisory control system of transforming plant DC power supply
CN202957668U (en) Intelligent electric interaction terminal and system
CN105322659A (en) Intelligent home terminal
CN205105003U (en) Wisdom family terminal
CN110032083A (en) Home furnishings intelligent power supply management system and configuration, management method based on Cloud Server
CN105955132A (en) Re-closing controller
CN203849376U (en) Breaker anti-tripping loop testing apparatus
CN210927077U (en) Residual current protection device with uninterrupted power supply test function
CN210985631U (en) Monitoring equipment
CN104123791A (en) Prepayment electricity meter balance lower-limit alarm system
CN204720712U (en) Control circuit of intelligent power strip and intelligent power strip
CN2907022Y (en) Intelligent power limiter
CN110911245A (en) Near-field control remote transmission's electric energy meter intelligence circuit breaker
CN216670875U (en) Security protection commercial power outage alarm
JP2004229400A (en) Power transmission remote controller and power transmission remote control system
CN214849827U (en) Intelligent cloud control distribution box
CN201682328U (en) Intelligent control terminal of leakage protector remote control system
CN211265395U (en) Near-field control remote transmission's electric energy meter intelligence circuit breaker
CN211208368U (en) Circuit breaker
CN212229020U (en) Three-phase safety electric meter
CN108683031B (en) Intelligent plug, control method thereof and patch board with intelligent plug
CN112798835A (en) Uninterrupted meter replacing device
CN202014037U (en) Demarcation switch cabinet for cable line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181218

CF01 Termination of patent right due to non-payment of annual fee