CN104358215B - 整体预应力全装配箱型模块式钢栈桥制作装配工艺 - Google Patents
整体预应力全装配箱型模块式钢栈桥制作装配工艺 Download PDFInfo
- Publication number
- CN104358215B CN104358215B CN201410701267.3A CN201410701267A CN104358215B CN 104358215 B CN104358215 B CN 104358215B CN 201410701267 A CN201410701267 A CN 201410701267A CN 104358215 B CN104358215 B CN 104358215B
- Authority
- CN
- China
- Prior art keywords
- trestle
- prestress
- steel
- single span
- box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D15/00—Movable or portable bridges; Floating bridges
- E01D15/12—Portable or sectional bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
整体预应力全装配箱型模块式钢栈桥制作装配工艺,属于带式输送机走廊钢栈桥技术领域,所解决的技术问题是提供一种制作简单、质量稳定、适合较大跨度的带式输送机走廊钢栈桥的制作装配工艺,所采用的技术方案:第一步,保证起吊组装场地平整压实,第二步,依次分段吊装至少两个箱形模块至垫木上,并连接紧固相邻两段箱形模块,第三步,在单跨栈桥底板下完成一次预应力张拉;第四步,将单跨栈桥吊装至栈桥支架的铰支座上临时固定,第五步,重复组装若干单跨栈桥并将其两两连接紧固组成整条多跨栈桥,第六步,对整条多跨栈桥顶板完成二次预应力张拉;第七步,对完成二次预应力的整条多跨栈桥进行验收,本发明应用于带式输送机。
Description
技术领域
整体预应力全装配箱型模块式钢栈桥制作装配工艺,属于带式输送机走廊钢栈桥技术领域。
背景技术
现有带式输送机走廊钢栈桥制作采用:施工现场地面整体制作和高处分片(散)拼装两种方法,受力结构形式为简支钢桁架,桁架节点、杆件形式为:钢板节点型钢杆件和钢球节点钢管杆件两种。存在的主要缺点有:施工现场作业量大,制作工艺复杂、工期长、质量不稳定、临时占地多;围护结构与受力结构不能整体工作,相同型号胶带机输送廊钢栈桥每延米单位耗钢量较大;钢栈桥受力结构为简支形式,工作挠度变形大,不适合较大跨度。
发明内容
本发明克服现有技术存在的不足,所要解决的技术问题是提供一种制作简单、质量稳定、适合较大跨度的带式输送机走廊钢栈桥的制作装配工艺。
为解决上述技术问题,本发明所采用的技术方案是:整体预应力全装配箱型模块式钢栈桥制作装配工艺,按照以下步骤进行:
第一步,保证起吊组装场地平整压实,地面承载力、平整度满足装配要求;
第二步,准确测设垫木位置,找准垫木顶面标高,在单跨中按设计起拱;
第三步,依次分段吊装至少两个箱形模块至垫木上,并且对齐箱形模块接口,找直箱形模块纵向通长;
第四步,依次用螺栓连接紧固相邻两段箱形模块,且拧紧力矩应达到设计值;
第五步,对装配完成的单跨栈桥进行中间验收;
第六步,在单跨栈桥底板下敷设一次预应力钢绞线、锚具;
第七步,对一次预应力钢绞线张拉,且该张拉为应力应变双控制;
第八步,锚具顶紧锁死;
第九步,对完成一次预应力的单跨栈桥进行验收;
第十步,将验收后的单跨栈桥整体从垫木上吊装至栈桥支架的铰支座上临时固定;
第十一步,重复第三步至第十步组装若干单跨栈桥;
第十二步,将第十一步的若干单跨栈桥的每相邻跨栈桥段分别用螺栓连接紧固,拧紧力矩达到设计值,进而组成整条多跨栈桥;
第十三步,对由第十二步的整条多跨栈桥进行中间验收;
第十四步,在整条多跨栈桥顶板敷设二次预应力钢绞线、锚具;
第十五步,对二次预应力钢绞线张拉,且该张拉为应力应变双控制;
第十六步,锚具顶紧锁死;
第十七步,对完成二次预应力的整条多跨栈桥进行验收。
所述箱型模块包括带横梁的顶板、第一侧板、第二侧板、底板、设置在顶板横梁下方的带式输送机吊架。
在所述第八步后对一次预应力钢绞线钢端头进行处理。
在所述第十六步后对二次预应力钢绞线钢端头进行处理。
所述第一侧板和第二侧板为中厚冷轧压型钢板。
所述底板为热镀锌4mm厚钢板。
本发明和现有技术相比具有以下有益效果。
一、箱形模块采用工厂化、标准化生产工艺制作,先将箱形模块运至现场预先在工程起吊位准备好的装配工作面上,再通过装配施加预应力完成单跨栈桥的地面高效组装,然后通过多个单跨栈桥组装成整条多跨栈桥。装配过程先每个单跨栈桥吊装就位简支受力后,再对整条多跨栈桥实施二次张拉构建负弯矩区预应力,实现了钢栈桥的先简支受力后连续受力转换,这种栈桥结构较现有栈桥桁架结构受力更合理,相同动荷载作用下工作挠度变形减小,因此整条多跨栈桥在质量稳定、安全隐患少的同时还使得装配效率提高、工期缩短、也节省了现场用地。
二、先通过箱形模块组装成单跨栈桥,再通过单跨栈桥组装成整条多跨栈桥,采用单跨栈桥先简支受力向整条多跨栈桥后连续受力转换,较现有栈桥桁架结构受力更合理,相同动荷载作用下工作挠度变形减小,适合较大跨度栈桥建设,跟现有技术相比,同型号胶带机的单位延长米栈桥耗钢量节约明显,起到节能环保、降低成本的作用。
附图说明
下面结合附图对本发明作进一步的说明。
图1为单跨栈桥结构的侧视图。
图2为图1-1向剖视图。
图3为整条多跨栈桥结构的侧视图。
图中,1为带横梁的顶板,2为横梁,3为带式输送机吊架,4为二次预应力钢绞线,5为第一侧板,6为一次预应力钢绞线,7为垫木,8为底板,9为第二侧板,10为箱型模块,11为栈桥支架,12为铰支座。
具体实施方式
如图1-图3所示,整体预应力全装配箱型模块式钢栈桥制作装配工艺,按照以下步骤进行:
第一步,保证起吊组装场地平整压实,地面承载力、平整度满足装配要求;
第二步,准确测设垫木7位置,找准垫木7顶面标高,在单跨中按设计起拱;
第三步,依次分段吊装至少两个箱形模块10至垫木7上,并且对齐箱形模块10接口,找直箱形模块10纵向通长;
第四步,依次用螺栓连接紧固相邻两段箱形模块10,且拧紧力矩应达到设计值;
第五步,对装配完成的单跨栈桥进行中间验收;
第六步,在单跨栈桥底板下敷设一次预应力钢绞线6、锚具;
第七步,对一次预应力钢绞线6张拉,且该张拉为应力应变双控制;
第八步,锚具顶紧锁死;
第九步,对完成一次预应力的单跨栈桥进行验收;
第十步,将验收后的单跨栈桥整体从垫木7上吊装至栈桥支架11的铰支座12上临时固定;
第十一步,重复第三步至第十步组装若干单跨栈桥;
第十二步,将第十一步的若干单跨栈桥的每相邻跨栈桥段分别用螺栓连接紧固,拧紧力矩达到设计值,进而组成整条多跨栈桥;
第十三步,对由第十二步的整条多跨栈桥进行中间验收;
第十四步,在整条多跨栈桥顶板敷设二次预应力钢绞线4、锚具;
第十五步,对二次预应力钢绞线4张拉,且该张拉为应力应变双控制;
第十六步,锚具顶紧锁死;
第十七步,对完成二次预应力的整条多跨栈桥进行验收。
所述箱型模块10包括带横梁2的顶板1、第一侧板5、第二侧板9、底板8、设置在顶板1横梁2下方的带式输送机吊架3。
在所述第八步后对一次预应力钢绞线6钢端头进行处理。
在所述第十六步后对二次预应力钢绞线4钢端头进行处理。
所述第一侧板5和第二侧板9为中厚冷轧压型钢板。
所述底板8为热镀锌4mm厚钢板。
所述一次预应力钢绞线6、二次预应力钢绞线4均为现有技术。
所述栈桥支架11、铰支座12均为现有技术,在钢栈桥组装前已经提前布置完毕。
所述垫木7仅在所述制作装配的第二步使用,钢栈桥制作装配完毕后撤掉即可。
箱形模块10是采用工厂化、标准化生产工艺以中厚钢板冷轧压形、裁剪、冲切、拼焊、螺栓连接工艺制作装配而成。
上述实施例是对本发明的解释而非限制,在不脱离本发明原理前提下所作的变化也在本发明的保护范围之内。
Claims (6)
1.整体预应力全装配箱型模块式钢栈桥制作装配工艺,其特征在于按照以下步骤进行:
第一步,保证起吊组装场地平整压实,地面承载力、平整度满足装配要求;
第二步,准确测设垫木位置,找准垫木顶面标高,在单跨中按设计起拱;
第三步,依次分段吊装至少两个箱形模块至垫木上,并且对齐箱形模块接口,找直箱形模块纵向通长;
第四步,依次用螺栓连接紧固相邻两段箱形模块,且拧紧力矩应达到设计值;
第五步,对装配完成的单跨栈桥进行中间验收;
第六步,在单跨栈桥底板下敷设一次预应力钢绞线、锚具;
第七步,对一次预应力钢绞线张拉,且该张拉为应力应变双控制;
第八步,锚具顶紧锁死;
第九步,对完成一次预应力的单跨栈桥进行验收;
第十步,将验收后的单跨栈桥整体从垫木上吊装至栈桥支架的铰支座上临时固定;
第十一步,重复第三步至第十步组装若干单跨栈桥;
第十二步,将第十一步的若干单跨栈桥的每相邻跨栈桥段分别用螺栓连接紧固,拧紧力矩达到设计值,进而组成整条多跨栈桥;
第十三步,对由第十二步的整条多跨栈桥进行中间验收;
第十四步,在整条多跨栈桥顶板敷设二次预应力钢绞线、锚具;
第十五步,对二次预应力钢绞线张拉,且该张拉为应力应变双控制;
第十六步,锚具顶紧锁死;
第十七步,对完成二次预应力的整条多跨栈桥进行验收。
2.根据权利要求1所述的整体预应力全装配箱型模块式钢栈桥制作装配工艺,其特征在于:所述箱型模块包括带横梁的顶板、第一侧板、第二侧板、底板、设置在顶板横梁下方的带式输送机吊架。
3.根据权利要求1或2所述的整体预应力全装配箱型模块式钢栈桥制作装配工艺,其特征在于:在所述第八步后对一次预应力钢绞线钢端头进行处理。
4.根据权利要求1或2所述的整体预应力全装配箱型模块式钢栈桥制作装配工艺,其特征在于:在所述第十六步后对二次预应力钢绞线钢端头进行处理。
5.根据权利要求2所述的整体预应力全装配箱型模块式钢栈桥制作装配工艺,其特征在于:所述第一侧板和第二侧板为中厚冷轧压型钢板。
6.根据权利要求2所述的整体预应力全装配箱型模块式钢栈桥制作装配工艺,其特征在于:所述底板为热镀锌4mm厚钢板。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410701267.3A CN104358215B (zh) | 2014-11-28 | 2014-11-28 | 整体预应力全装配箱型模块式钢栈桥制作装配工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410701267.3A CN104358215B (zh) | 2014-11-28 | 2014-11-28 | 整体预应力全装配箱型模块式钢栈桥制作装配工艺 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104358215A CN104358215A (zh) | 2015-02-18 |
CN104358215B true CN104358215B (zh) | 2016-05-11 |
Family
ID=52525514
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410701267.3A Active CN104358215B (zh) | 2014-11-28 | 2014-11-28 | 整体预应力全装配箱型模块式钢栈桥制作装配工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104358215B (zh) |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106144418A (zh) * | 2016-07-13 | 2016-11-23 | 滨海金地矿业工程技术(北京)有限公司 | 一种模块化栈桥及其施工方法 |
CN106593471A (zh) * | 2016-12-22 | 2017-04-26 | 中铁五局集团有限公司 | 一种大区段隧道仰拱施工步进式自行桁架结构移动栈桥 |
CN107618815A (zh) * | 2017-08-30 | 2018-01-23 | 焦作科瑞森重装股份有限公司 | 一种模块化廊道带式输送机及其组装方法 |
DE102020207826A1 (de) * | 2020-06-24 | 2022-02-10 | FB Industry Automation GmbH | Rollenshuttle und Hängerollen Shuttle |
CN115030518A (zh) * | 2022-05-27 | 2022-09-09 | 山东电力工程咨询院有限公司 | 一种钢结构输煤栈桥的分段整体吊装方法 |
CN115478468B (zh) * | 2022-11-03 | 2024-01-19 | 石家庄铁道大学 | 一种装配式钢筋混凝土t型梁桥 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101368373A (zh) * | 2008-09-19 | 2009-02-18 | 中铁大桥局股份有限公司 | 长连续结构钢箱梁或组合箱梁施工方法 |
CN102434006A (zh) * | 2011-12-19 | 2012-05-02 | 中煤建安第七工程有限公司 | 大型钢栈桥输送系统地面整体制作吊装施工方法 |
CN203767643U (zh) * | 2014-03-22 | 2014-08-13 | 中煤建筑安装工程集团有限公司 | 一种封闭式钢结构输送栈桥 |
CN203782539U (zh) * | 2014-02-21 | 2014-08-20 | 北京国鼎板业有限公司 | 一种轻质环保易于安装的栈桥通廊 |
-
2014
- 2014-11-28 CN CN201410701267.3A patent/CN104358215B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101368373A (zh) * | 2008-09-19 | 2009-02-18 | 中铁大桥局股份有限公司 | 长连续结构钢箱梁或组合箱梁施工方法 |
CN102434006A (zh) * | 2011-12-19 | 2012-05-02 | 中煤建安第七工程有限公司 | 大型钢栈桥输送系统地面整体制作吊装施工方法 |
CN203782539U (zh) * | 2014-02-21 | 2014-08-20 | 北京国鼎板业有限公司 | 一种轻质环保易于安装的栈桥通廊 |
CN203767643U (zh) * | 2014-03-22 | 2014-08-13 | 中煤建筑安装工程集团有限公司 | 一种封闭式钢结构输送栈桥 |
Also Published As
Publication number | Publication date |
---|---|
CN104358215A (zh) | 2015-02-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104358215B (zh) | 整体预应力全装配箱型模块式钢栈桥制作装配工艺 | |
CN203594213U (zh) | 灵活拆装式承重桁架 | |
CN203173749U (zh) | 液压复式起重机塔架组装整体式竖向自顶升装置 | |
CN102092394B (zh) | 铁路客车模块化地板安装方法 | |
CN205257792U (zh) | 带有三角形支撑主梁的桥式起重机 | |
CN101962975A (zh) | 一种新型预应力钢管-混凝土组合梁 | |
CN102864840B (zh) | 采用支座位移法施加预应力的预应力钢框架及其制作方法 | |
CN214940962U (zh) | 一种大跨度钢结构连廊 | |
CN101787795B (zh) | 大型网架悬索安装平台及悬索施工方法 | |
CN204826620U (zh) | 一种建筑施工梁架 | |
CN104652833A (zh) | 钢结构厂房檩条安装提升滑轮的固定装置制作方法 | |
CN204369358U (zh) | 一种杂物梯用快搭井架 | |
CN202913357U (zh) | 维修方便的空间桁架架桥机 | |
CN102251665B (zh) | 预应力金属薄板结构体系施工方法 | |
CN203361596U (zh) | 一种集成式升降操作平台辅助支架 | |
CN201486458U (zh) | 一种通用组合式工作梯 | |
CN201211997Y (zh) | 乘客输送设备的桁架的分段装置 | |
CN105350788A (zh) | 利用辅助钢架进行吊顶及设备管道布设的方法 | |
CN212001582U (zh) | 一种旧钢柱组合连接结构 | |
CN103938719B (zh) | 大柱间距厂房墙面的t形墙架 | |
CN104085702A (zh) | 用于水电工程座环部件的运输装置及其运输方法 | |
CN205135469U (zh) | 承重梁及油管举升机 | |
CN113668709B (zh) | 屋面主次结构组装单元整体吊装的施工方法 | |
CN102914446A (zh) | 一种箱型桥梁静载试验架 | |
CN202337340U (zh) | 集装箱船上层建筑脚手架结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20230607 Address after: No. 112 Luchan Street, Yongnian District, Handan City, Hebei Province, 057150 Patentee after: Middling coal Leo Handan Environmental Protection Technology Co.,Ltd. Address before: 036000 middling coal Jian'an Shanxi Branch, Zhenhua West Street, Shuozhou City, Shanxi Province Patentee before: CHINA COAL BUILDING & INSTALLATION ENGINEERING GROUP Co.,Ltd. |