CN104348122A - Ground potential mounting type shunt wire clamp device and mounting method thereof - Google Patents

Ground potential mounting type shunt wire clamp device and mounting method thereof Download PDF

Info

Publication number
CN104348122A
CN104348122A CN201410661630.3A CN201410661630A CN104348122A CN 104348122 A CN104348122 A CN 104348122A CN 201410661630 A CN201410661630 A CN 201410661630A CN 104348122 A CN104348122 A CN 104348122A
Authority
CN
China
Prior art keywords
wire clamp
bolt
clamp device
wire
action bars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410661630.3A
Other languages
Chinese (zh)
Other versions
CN104348122B (en
Inventor
陈言团
林福
王涛
阮肇华
吴元锦
吴光晃
傅友忠
张�杰
李传兵
阮奕辉
黄思锦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Fujian Electric Power Co Ltd
Ningde Power Supply Co of State Grid Fujian Electric Power Co Ltd
State Grid Corp of China SGCC
Original Assignee
State Grid Fujian Electric Power Co Ltd
Ningde Power Supply Co of State Grid Fujian Electric Power Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Fujian Electric Power Co Ltd, Ningde Power Supply Co of State Grid Fujian Electric Power Co Ltd, State Grid Corp of China SGCC filed Critical State Grid Fujian Electric Power Co Ltd
Priority to CN201410661630.3A priority Critical patent/CN104348122B/en
Publication of CN104348122A publication Critical patent/CN104348122A/en
Application granted granted Critical
Publication of CN104348122B publication Critical patent/CN104348122B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G7/00Overhead installations of electric lines or cables

Landscapes

  • Electric Cable Installation (AREA)

Abstract

本发明涉及一种地电位安装式分流线夹装置及其安装方法,该分流线夹装置包括设于左、右两侧的两块线夹以及连接两块线夹的引流线,左侧线夹上端与一支架相连接,所述支架向右固定连接有一第一螺栓,右侧线夹上端开设有直径大于所述第一螺栓的通孔,并套设于所述第一螺栓上;右侧线夹下端铰接有一转动块,所述转动块上开设有螺纹通孔,并穿设有第二螺栓,左侧线夹下端设有一卡口,所述第二螺栓左端设有可卡住所述卡口的头部,所述第一螺栓、第二螺栓右端分别设有锁紧螺母。该装置及其安装方法可实现地电位安装分流线夹,不仅安全性高,适用范围广,而且操作简单,作业效率高。

The invention relates to a ground potential installation type shunt wire clamp device and its installation method. The shunt wire clamp device includes two wire clamps arranged on the left and right sides and a drain wire connecting the two wire clamps. The upper end of the clamp is connected to a bracket, and the bracket is fixedly connected to the right with a first bolt, and the upper end of the right clamp is provided with a through hole with a diameter larger than the first bolt, and is sleeved on the first bolt; The lower end of the right wire clamp is hinged with a rotating block, the rotating block is provided with a threaded through hole, and the second bolt is pierced, the lower end of the left wire clamp is provided with a bayonet, and the left end of the second bolt is provided with a catchable The head of the bayonet socket, the right ends of the first bolt and the second bolt are respectively provided with locking nuts. The device and its installation method can realize the installation of shunt line clips at the ground potential, and not only have high safety and wide application range, but also are easy to operate and high in operation efficiency.

Description

地电位安装式分流线夹装置及其安装方法Ground potential installation type shunt clamp device and installation method thereof

技术领域 technical field

本发明涉及输电线路施工技术领域,特别涉及一种地电位安装式分流线夹装置及其安装方法。 The invention relates to the technical field of transmission line construction, in particular to a ground potential installation type shunt clamp device and an installation method thereof.

背景技术 Background technique

螺栓松动或线路过载引起的发热是线路运行中的常见缺陷,长时间发热或短时间过热会引起设备寿命减少甚至损坏,而通过安装分流线夹来分流是处理发热缺陷的基本方法,效果高且适用范围广。 Heat generation caused by loose bolts or line overload is a common defect in line operation. Long-term heat generation or short-term overheating will cause equipment life to be reduced or even damaged, and shunting by installing a shunt clip is the basic method to deal with heat generation defects. The effect is high And it has a wide range of applications.

目前分流线夹都是由两块铝制线夹采用引流线连接、两侧通过螺栓紧固,而安装分流线夹采用等电位作业方式完成,具体方法为将绝缘硬梯两端分别架在杆塔横担和导线侧(挂点为发热点附近),然后等电位作业人员穿高压屏蔽服通过绝缘硬梯进入导线侧高压电场,拆除分流线夹一侧螺栓套进导线然后拧紧两侧螺栓使其固定。 At present, the shunt clamps are connected by two aluminum clamps with drain wires, and the two sides are fastened by bolts. The installation of the shunt clamps is completed by equipotential operation. The specific method is to install the two ends of the insulated hard ladder separately. On the side of the tower cross arm and the conductor (the hanging point is near the heating point), and then the equipotential workers wear high-voltage shielding clothing and enter the high-voltage electric field on the conductor side through an insulated hard ladder, remove the bolt on one side of the shunt clamp and insert the conductor, and then tighten both sides. Bolt to keep it in place.

由于现有分流线夹的局限性,安装分流线夹只能采用等电位作业方式进行,而采用等电位作业方式存在诸多不足:一是等电位作业人员的安全问题,等电位作业人员在高压电场作业,任何疏忽或是安全措施不到位都有可能造成高压触电事故;二是等电位安装分流线夹适用范围的问题,等电位作业对安全距离的要求十分严格,对于部分线路组合间隙小尤其是变电站内带电设备紧凑的情况下,达不到安全规程规定的安全距离,等电位作业无法进行;三是等电位安装分流线夹作业繁琐的问题,等电位作业程序多、工具杂,要求配合等电位作业人员的辅助人员也多,作业效率较低。 Due to the limitations of the existing shunt clamps, the installation of the shunt clamps can only be carried out by using the equipotential operation method, but there are many shortcomings in the use of the equipotential operation method: one is the safety of the equipotential operators. For high-voltage electric field operations, any negligence or inadequate safety measures may cause high-voltage electric shock accidents; the second is the scope of application of equipotential installation shunt clamps. Equipotential operations have strict requirements for safety distances. Especially when the live equipment in the substation is compact, the safety distance specified in the safety regulations cannot be reached, and the equipotential operation cannot be carried out; the third is the cumbersome operation of the equipotential installation of the shunt clamp, and the equipotential operation has many procedures and tools. , There are many auxiliary personnel who are required to cooperate with the equipotential operators, and the operating efficiency is low.

发明内容 Contents of the invention

本发明的目的在于提供一种地电位安装式分流线夹装置及其安装方法,该装置及其安装方法可实现地电位安装分流线夹,不仅安全性高,适用范围广,而且操作简单,作业效率高。 The purpose of the present invention is to provide a ground potential installation type shunt clamp device and its installation method, the device and its installation method can realize the ground potential installation shunt clamp, not only high safety, wide application range, but also easy to operate , High operating efficiency.

为实现上述目的,本发明的技术方案是:一种地电位安装式分流线夹装置,包括设于左、右两侧的两块线夹以及连接两块线夹的引流线,左侧线夹上端与一支架相连接,所述支架向右固定连接有一第一螺栓,右侧线夹上端开设有直径大于所述第一螺栓的通孔,并套设于所述第一螺栓上;右侧线夹下端铰接有一转动块,所述转动块上开设有螺纹通孔,并穿设有第二螺栓,左侧线夹下端设有一卡口,所述第二螺栓左端设有可卡住所述卡口的头部,所述第一螺栓、第二螺栓右端分别设有锁紧螺母。 In order to achieve the above object, the technical solution of the present invention is: a ground potential installation type shunt wire clip device, including two wire clips on the left and right sides and a drainage wire connecting the two wire clips, the left wire The upper end of the clip is connected with a bracket, and the bracket is fixedly connected to the right with a first bolt, and the upper end of the right side clamp is provided with a through hole with a diameter larger than the first bolt, and is sleeved on the first bolt; The lower end of the side wire clamp is hinged with a rotating block, the rotating block is provided with a threaded through hole, and a second bolt is pierced, the lower end of the left wire clamp is provided with a bayonet, and the left end of the second bolt is provided with a clamping hole. The head of the bayonet socket, the right ends of the first bolt and the second bolt are respectively provided with lock nuts.

进一步的,左侧线夹上端经销轴铰接于所述支架上,以使左侧线夹可绕所述销轴左右摆动。 Further, the upper end of the left wire clamp is hinged to the bracket through a pin shaft, so that the left wire clamp can swing left and right around the pin shaft.

进一步的,所述支架上设有用于连接操作杆的操作杆连接部。 Further, the bracket is provided with an operating rod connecting portion for connecting the operating rod.

本发明还公开了上述分流线夹装置的安装方法,包括以下步骤: The invention also discloses a method for installing the above-mentioned shunt clamp device, which includes the following steps:

(1)将第一操作杆与所述操作杆连接部相连接,通过第一操作杆将分流线夹装置传递到发热点处; (1) Connect the first operating rod to the connecting part of the operating rod, and transfer the shunt clamp device to the heating point through the first operating rod;

(2)采用第二操作杆将所述左侧线夹转动到可卡住所述第二螺栓的位置; (2) Use the second operating lever to turn the left clamp to a position where the second bolt can be clamped;

(3)采用第二操作杆拉动所述第二螺栓,使其头部卡住所述左侧线夹的卡口,从而将分流线夹装置套进发热点处的导线; (3) Use the second operating lever to pull the second bolt so that its head catches the bayonet of the left wire clamp, so that the shunt wire clamp device is inserted into the wire at the heating point;

(4)采用第二操作杆杆头的扳手套旋紧锁紧螺母,从而固定住分流线夹装置,至此分流线夹装置安装完成。 (4) Tighten the lock nut with the wrench set on the head of the second operating rod, so as to fix the shunt wire clamp device, and the installation of the shunt wire clamp device is completed.

本发明的有益效果是提供了一种地电位安装式分流线夹装置及其安装方法,可实现在地电位采用操作杆和辅助工具远程安装分流线夹,相较于传统的等电位安装方法及装置,一是避免了等电位作业人员进出高压电场,转而采用地电位作业方式,作业人员在杆塔横担或是塔身即可操作,最大程度保证了作业人员的安全,杜绝了安装分流线夹可能发生的触电事故,二是解决了等电位作业中硬梯架设位置和辅助人员占位的问题,扩大了地电位操作人员占位可选范围,减少了因安全距离不足而无法安装的作业,扩大了适用范围,三是减少了高压等电位作业人员和架设绝缘硬梯等程序,简化了安装流程,使得分流线夹的装拆作业更加简单、高效,具有很强的实用性。 The beneficial effect of the present invention is to provide a ground potential installation type shunt clamp device and its installation method, which can realize the remote installation of the shunt clamp at the ground potential by using the operating lever and auxiliary tools, compared with the traditional equipotential installation The method and device, one is to avoid the equipotential operators entering and exiting the high-voltage electric field, and instead adopt the ground potential operation method, and the operators can operate on the pole or tower cross arm or the tower body, which ensures the safety of the operators to the greatest extent and eliminates the need for installation The electric shock accident that may occur in the shunt clamp, the second is to solve the problem of the erection position of the hard ladder and the occupation of auxiliary personnel in the equipotential operation, expand the optional range of occupation of the ground potential operator, and reduce the number of people who cannot work due to insufficient safety distance. The installation operation has expanded the scope of application. The third is to reduce the procedures such as high-voltage equipotential operation personnel and erecting insulating hard ladders, which simplifies the installation process and makes the assembly and disassembly of the shunt clamp more simple and efficient. It has strong practicality. sex.

附图说明 Description of drawings

图1是本发明实施例的结构示意图。 Fig. 1 is a schematic structural diagram of an embodiment of the present invention.

图2是本发明实施例处于第一工作状态的示意图。 Fig. 2 is a schematic diagram of an embodiment of the present invention in a first working state.

图3是本发明实施例处于第二工作状态的示意图。 Fig. 3 is a schematic diagram of the embodiment of the present invention in a second working state.

图4是本发明实施例处于第三工作状态的示意图。 Fig. 4 is a schematic diagram of the embodiment of the present invention in a third working state.

图中,1-左侧线夹,2-右侧线夹,3-引流线,4-支架,5-第一螺栓,6-通孔,7-转动块,8-螺纹通孔,9-第二螺栓,10-卡口,11-第二螺栓的头部,12-锁紧螺母,13-锁紧螺母,14-操作杆连接部。 In the figure, 1-left wire clamp, 2-right wire clamp, 3-drain wire, 4-bracket, 5-first bolt, 6-through hole, 7-rotating block, 8-threaded through hole, 9- The second bolt, 10-bayonet, 11-the head of the second bolt, 12-lock nut, 13-lock nut, 14-operating rod connecting part.

具体实施方式 Detailed ways

下面结合附图及具体实施例对本发明作进一步的详细说明。 The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

本发明地电位安装式分流线夹装置,如图1所示,包括设于左、右两侧的两块线夹1、2以及连接两块线夹的引流线3,左侧线夹1上端与一支架4相连接,支架4向右固定连接有一第一螺栓5,右侧线夹2上端开设有直径大于第一螺栓5的通孔6,并套设于第一螺栓5上。右侧线夹2下端铰接有一转动块7,转动块7上开设有螺纹通孔8,并穿设有第二螺栓9,从而第二螺栓9既可随转动快7左右摆动,也可随右侧线夹2绕第一螺栓5转动。左侧线夹1下端设有一卡口10,第二螺栓9左端设有可卡住卡口10的头部11,第一螺栓5、第二螺栓9右端分别设有锁紧螺母12、13。为了与操作杆连接,支架4上设有用于连接操作杆的操作杆连接部14。 The ground potential installation type shunt wire clip device of the present invention, as shown in Figure 1, comprises two wire clips 1, 2 located on the left and right sides and the drainage wire 3 connecting the two wire clips, the left wire clip 1 The upper end is connected with a bracket 4, the bracket 4 is fixedly connected to the right with a first bolt 5, and the upper end of the right side clamp 2 is provided with a through hole 6 with a diameter larger than the first bolt 5, and is sleeved on the first bolt 5. The lower end of the right side clamp 2 is hinged with a rotating block 7, and the rotating block 7 is provided with a threaded through hole 8, and is pierced with a second bolt 9, so that the second bolt 9 can swing left and right with the rotation speed 7, and can also move with the right The side clamp 2 rotates around the first bolt 5 . The lower end of the left wire clamp 1 is provided with a bayonet 10, the left end of the second bolt 9 is provided with a head 11 that can block the bayonet 10, and the first bolt 5 and the right end of the second bolt 9 are respectively provided with lock nuts 12,13. In order to connect with the operating rod, the bracket 4 is provided with an operating rod connecting portion 14 for connecting the operating rod.

在本实施例中,左侧线夹1上端经销轴铰接于支架4上,以使左侧线夹1可绕销轴左右摆动,如图1、2所示。 In this embodiment, the upper end of the left wire clamp 1 is hinged to the support 4 via a pin shaft, so that the left wire clamp 1 can swing left and right around the pin shaft, as shown in Figs. 1 and 2 .

在此对本发明涉及的地电位作业、等电位作业进行相应说明。地电位作业是指人体处于地(零)电位状态下,使用绝缘工具间接接触带电设备,来达到检修目的的方法。等电位作业是指作业人员通过电气连接上升至带电部分电位,且与周围不同电位适当隔离,直接对带电部分进行的作业。 The ground potential work and equipotential work involved in the present invention will be described accordingly. Ground potential work refers to the method of using insulated tools to indirectly contact live equipment to achieve the purpose of maintenance when the human body is in the state of ground (zero) potential. Equipotential work refers to the work that the operator raises to the potential of the live part through the electrical connection, and is properly isolated from the surrounding different potentials, and directly performs the work on the live part.

本发明还公开了上述分流线夹装置的地电位安装方法,包括以下步骤: The invention also discloses a ground potential installation method of the above shunt clamp device, which includes the following steps:

(1)将第一绝缘操作杆与支架4上的操作杆连接部14相连接,然后通过第一绝缘操作杆将分流线夹装置传递到发热点处。 (1) Connect the first insulating operating rod to the operating rod connecting part 14 on the bracket 4, and then transfer the shunt clamp device to the heating point through the first insulating operating rod.

(2)采用第二绝缘操作杆将左侧线夹1转动到可卡住第二螺栓9的位置,其工作状态如图2所示。 (2) Use the second insulating operating lever to turn the left clamp 1 to the position where the second bolt 9 can be stuck, and its working state is shown in Figure 2.

(3)采用第二绝缘操作杆拉动第二螺栓9,使其头部11卡住左侧线夹1的卡口10,从而将分流线夹装置套进发热点处的导线,其工作状态如图3所示。 (3) Use the second insulating lever to pull the second bolt 9, so that its head 11 is caught in the bayonet 10 of the left wire clamp 1, so that the shunt wire clamp device is inserted into the wire at the heating point, and its working state is as follows: Figure 3 shows.

(4)采用第二绝缘操作杆杆头的扳手套旋紧锁紧螺母12、13,从而固定住分流线夹装置,其工作状态如图4所示,至此分流线夹装置安装完成。 (4) Tighten the locking nuts 12 and 13 with the wrench set on the head of the second insulating operating rod to fix the shunt clamp device. The working state is shown in Figure 4, and the installation of the shunt clamp device is completed.

以上是本发明的较佳实施例,凡依本发明技术方案所作的改变,所产生的功能作用未超出本发明技术方案的范围时,均属于本发明的保护范围。 The above are the preferred embodiments of the present invention, and all changes made according to the technical solution of the present invention, when the functional effect produced does not exceed the scope of the technical solution of the present invention, all belong to the protection scope of the present invention.

Claims (4)

1. an earth potential installing type shunting wire clamp device, it is characterized in that, comprise the two pieces of wire clamps being located at arranged on left and right sides and the drainage thread connecting two pieces of wire clamps, wire clamp upper end, left side is connected with a support, described support is fixedly connected with one first bolt to the right, wire clamp upper end, right side offers the through hole that diameter is greater than described first bolt, and is sheathed on described first bolt; Wire clamp lower end, right side is hinged with a moving block, described moving block offers tapped through hole, and is equipped with the second bolt, wire clamp lower end, left side is provided with a bayonet socket, described second bolt left end is provided with the head that can block described bayonet socket, and described first bolt, the second bolt right-hand member are respectively equipped with locking nut.
2. earth potential installing type shunting wire clamp device according to claim 1, it is characterized in that, wire clamp upper end, left side is articulated with on described support through bearing pin, can swing to make left side wire clamp around described bearing pin.
3. earth potential installing type shunting wire clamp device according to claim 2, it is characterized in that, described support is provided with the action bars connecting portion for attended operation bar.
4. the installation method of earth potential installing type shunting wire clamp device according to claim 3, is characterized in that, comprise the following steps:
(1) the first action bars is connected with described action bars connecting portion, by the first action bars, shunting wire clamp device is delivered to heat generating spot place;
(2) adopt the second action bars that described left side wire clamp is turned to the position can blocking described second bolt;
(3) adopt the second action bars to pull described second bolt, make its head block the bayonet socket of described left side wire clamp, thus shunting wire clamp device is packed into the wire at heat generating spot place;
(4) adopt the spanner cover of the second operation club head to screw locking nut, thus fix shunting wire clamp device, so far shunting wire clamp device installation.
CN201410661630.3A 2014-11-19 2014-11-19 Ground potential mounting type shunt wire clamp device and mounting method thereof Active CN104348122B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410661630.3A CN104348122B (en) 2014-11-19 2014-11-19 Ground potential mounting type shunt wire clamp device and mounting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410661630.3A CN104348122B (en) 2014-11-19 2014-11-19 Ground potential mounting type shunt wire clamp device and mounting method thereof

Publications (2)

Publication Number Publication Date
CN104348122A true CN104348122A (en) 2015-02-11
CN104348122B CN104348122B (en) 2017-02-08

Family

ID=52503182

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410661630.3A Active CN104348122B (en) 2014-11-19 2014-11-19 Ground potential mounting type shunt wire clamp device and mounting method thereof

Country Status (1)

Country Link
CN (1) CN104348122B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104868403A (en) * 2015-05-08 2015-08-26 国家电网公司 A portable 120-400mm2 steel-cored aluminum stranded wire shunt line fixture and its application method
WO2018231823A1 (en) * 2017-06-12 2018-12-20 Hubbell Incorporated All-angle ground clamps
CN110867816A (en) * 2019-12-05 2020-03-06 徐志辉 Novel special cable box for hydraulic turnout switching equipment
CN116207661A (en) * 2023-03-01 2023-06-02 杭州兴德龙电力科技有限公司 Ground potential installation and shunt device

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB800980A (en) * 1956-06-19 1958-09-03 Hugh Fraser Improved means for connecting overhead high tension electrical cables to the insulators of transmission towers
CN202034703U (en) * 2010-11-26 2011-11-09 北京市电力公司 Operating lever for jumper conductor clamper
CN202696052U (en) * 2012-06-29 2013-01-23 武汉里得科技有限公司 Drainage wire fixing device
CN202917668U (en) * 2012-08-10 2013-05-01 国家电网公司 Live-line processing apparatus for heating due to failed contact of equipment wiring board and current leading wire clamp
CN204144862U (en) * 2014-11-19 2015-02-04 国家电网公司 The shunting wire clamp that earth potential is installed can be adopted

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB800980A (en) * 1956-06-19 1958-09-03 Hugh Fraser Improved means for connecting overhead high tension electrical cables to the insulators of transmission towers
CN202034703U (en) * 2010-11-26 2011-11-09 北京市电力公司 Operating lever for jumper conductor clamper
CN202696052U (en) * 2012-06-29 2013-01-23 武汉里得科技有限公司 Drainage wire fixing device
CN202917668U (en) * 2012-08-10 2013-05-01 国家电网公司 Live-line processing apparatus for heating due to failed contact of equipment wiring board and current leading wire clamp
CN204144862U (en) * 2014-11-19 2015-02-04 国家电网公司 The shunting wire clamp that earth potential is installed can be adopted

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104868403A (en) * 2015-05-08 2015-08-26 国家电网公司 A portable 120-400mm2 steel-cored aluminum stranded wire shunt line fixture and its application method
CN104868403B (en) * 2015-05-08 2017-11-28 国家电网公司 A kind of portable 120~400mm2Steel-cored aluminium strand shunt line fixture and application method
WO2018231823A1 (en) * 2017-06-12 2018-12-20 Hubbell Incorporated All-angle ground clamps
US10230181B2 (en) 2017-06-12 2019-03-12 Hubbell Incorporated All-angle ground clamps
CN110867816A (en) * 2019-12-05 2020-03-06 徐志辉 Novel special cable box for hydraulic turnout switching equipment
CN116207661A (en) * 2023-03-01 2023-06-02 杭州兴德龙电力科技有限公司 Ground potential installation and shunt device

Also Published As

Publication number Publication date
CN104348122B (en) 2017-02-08

Similar Documents

Publication Publication Date Title
CN104348122B (en) Ground potential mounting type shunt wire clamp device and mounting method thereof
CN102025036A (en) Multi-angle wire earthing potentiometer
CN104734068A (en) Distributing line foreign matter insulation removal device
CN202405731U (en) Special cable clamp for live installation of lightning arrester at ground potential
CN201549607U (en) A multi-angle grounding clamp
CN104242149A (en) Strain-resistant tower drainage plate bolt tightener
CN103441350A (en) Low-voltage grounding wire device for compact electrical structure
CN102185267A (en) 66KV ground potential hot-line make-and-break bypassing method
CN204030026U (en) Gravity self-locking formula Anti-dropping earthing clip
CN101834415A (en) Method and special tool for live replacement of zinc oxide lightning arrester
CN104157997A (en) Gravity self-locking type anti-drop ground wire clamp
CN205921107U (en) Electric line earth connection wire end hawk hook -type chuck
CN204144862U (en) The shunting wire clamp that earth potential is installed can be adopted
CN203707670U (en) Tool for lively processing bolt of by-pass jumper clamp
CN104410022B (en) Wire clamp diverter of ground potential installation equipment
CN203398349U (en) Auxiliary device of ground wire installation
CN204558688U (en) Earthing clamp
CN204517346U (en) A kind of earth potential erecting tools for leakage conductor
CN207834608U (en) A kind of Multi-angle earthing wire clip
CN206022675U (en) Universal shaped cable clamp earth lead
CN202997469U (en) Compact line jumper wire expander
CN203967279U (en) Corner pole circuit interior angle side joint device for connecting earth
CN102420402A (en) New Technology of Live Fastening Drainage Wire Clamp
CN106253128B (en) A kind of Press arm bolt clipper
CN103532040A (en) Special tool and method for fixing middle-phase bypass jumper during 10kV hot-line working

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant