CN202405731U - Special cable clamp for live installation of lightning arrester at ground potential - Google Patents

Special cable clamp for live installation of lightning arrester at ground potential Download PDF

Info

Publication number
CN202405731U
CN202405731U CN2012200015465U CN201220001546U CN202405731U CN 202405731 U CN202405731 U CN 202405731U CN 2012200015465 U CN2012200015465 U CN 2012200015465U CN 201220001546 U CN201220001546 U CN 201220001546U CN 202405731 U CN202405731 U CN 202405731U
Authority
CN
China
Prior art keywords
cable clamp
lightning arrester
groove
clamp body
ground potential
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2012200015465U
Other languages
Chinese (zh)
Inventor
赵国良
雒文博
刘晓刚
陈东
季宁
刘树清
顾铁利
肖建国
王树军
武荣伟
曹红军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengde Power Supply Co Of Jibei Electric Power Co ltd
State Grid Corp of China SGCC
Original Assignee
CHENGDE POWER SUPPLY Co Ltd OF NORTH CHINA GRID Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHENGDE POWER SUPPLY Co Ltd OF NORTH CHINA GRID Co Ltd filed Critical CHENGDE POWER SUPPLY Co Ltd OF NORTH CHINA GRID Co Ltd
Priority to CN2012200015465U priority Critical patent/CN202405731U/en
Application granted granted Critical
Publication of CN202405731U publication Critical patent/CN202405731U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model discloses a special cable clamp for live installation of a lightning arrester at a ground potential, which comprises a cable clamp body, wherein one end of the cable clamp body is provided with a hole which is connected with the lightning arrester, the other end of the cable clamp body is provided with a groove which is used for hanging and connecting wires, a pressing block is arranged opposite to the groove, the pressing block is connected with a threaded rod, the threaded rod is fit with a screw hole on the cable clamp body, and a lifting lug is arranged outside one end of the groove and provided with a lifting hole. An operator at the ground potential lifts the cable clamp, hangs the cable clamp on a wire on which the lightning arrester is installed by using an insulating operation rod with a hook and then tightens the threaded rod by using an insulating operation rod with a socket spanner, so that the pressing block and the groove which is used for hanging and connecting wires are matched and the wire is clamped, and then the operator connects the lightning arrester and the cable clamp body. The special cable clamp is simple in structure and capable of achieving ground potential operation, so that the operator is not in direct contact with a charged body, the safety of staffs and devices is improved greatly, time for live installation of the lightning arrester is shortened to 16 minutes from the original 28 minutes, and manpower and material resources are saved.

Description

A kind of at the special-purpose wire clamp of earth potential live installation lightning arrester
Technical field:
The utility model relates to a kind of electric power facility apparatus for mounting, particularly relates to a kind of at the special-purpose wire clamp of earth potential live installation lightning arrester.
Background technology:
Chengde electrical network is located in many Leishans district, because the power grid accident that thunder and lightning causes is increasing, the power grid accident that the minimizing damage to crops caused by thunder of adopting an effective measure causes is particularly important.It is one of effective technology means of current power transmission circuit reduction tripping rate with lightning strike that leakage conductor is installed.Charged installation lightning arrester has improved power supply reliability, has avoided interruption maintenance and causes and send electric weight less.Also strengthen simultaneously maintenance scheduling property, after the employing hotline maintenance method, can keep the operational mode of system constant, guaranteed the safe operation of electrical network, reduced equipment and personal injury.Compare the equipment and the personal injury that greatly reduce fault rod climbing tower, mistakenly entering charged chamber, misoperation and cause because of formalities such as power failure repeatedly, electrical verification, hanging earthing conductors with the power failure operation.Live line working is meant the operation that high voltage electric equipment and facility are not had a power failure.The live line working method is divided into three kinds: (1) equal potential working: refer to that operating personnel and electrified body are in the operation of same current potential, equipotential electrician gets into current potential generally will use instruments such as flat ladder or rope ladder; (2) earth potential working: the operating personnel is in earth potential (standing on the shaft tower) state when referring to live line working, utilizes the operation of insulating tool indirect contact high-voltage charged body; (3) medial potential working: the operating personnel is in the operation on the current potential between electrified body current potential and the earth potential when referring to live line working.At present; China is in charged installation lightning arrester operation process, and the method for work of use all is the equal potential working method, and the equal potential working method needs the equal potential working electrician to climb rope ladder or flat ladder gets into current potential; Multiple insulation power tool need be set; And it is very loaded down with trivial details that these power tools are set, and task difficulty is big, and labour intensity is big.Through the activity duration of charged installation lightning arrester is added up, adopt the equal potential working method that the activity duration average out to 28 minutes of a lightning arrester is installed, and equal potential working require very high to electrician's physical efficiency, technical ability.Simultaneously the equal potential working method can only be confined in the part shaft tower that safe distance such as combinational gap meets the demands, and some little spacing shaft towers are owing to receive the restriction of air gap can not carry out charged installation lightning arrester to work.
The utility model content:
The utility model provides a kind of and at earth potential live the special-purpose wire clamp of lightning arrester is installed to the deficiency of prior art, and this wire clamp is rational in infrastructure; Can be implemented in earth potential live lightning arrester is installed, safety, convenient, time saving and energy saving; The utility model technical problem to be solved is to make the operating personnel use insulating tool easily wire clamp to be fixed on the lead at the earth potential place, and the technical scheme that the utility model is taked is following: the utility model comprises the wire clamp body, and an end of wire clamp body is provided with the hole that is connected with lightning arrester; The other end is provided with the groove that articulates lead; Relative with groove is a briquetting, and briquetting links to each other with screw rod, and screw rod cooperates with screw on the wire clamp body; It is characterized in that being provided with hanger in the outside of groove one end, hanger is provided with lifting hole(eyelet).
The method for using of the utility model is following:
Operating personnel's earth potential place uses the insulating bar of band hook that wire clamp is provoked and is suspended on the lead that lightning arrester is installed; The insulating bar that re-uses the band box spanner is tightened screw rod; Make briquetting and articulate the groove fit clamping wire of lead, lightning arrester is connected with the wire clamp body gets final product then.
Compared with prior art; The utlity model has simple and reasonablely, cost is low, can realize earth potential working; Make the not direct contact electrification body of operating personnel; The fail safe of personnel, equipment improves greatly, and the time of charged installation lightning arrester shortened to 16 minutes by original 28 minutes, saved manpower and materials.
Description of drawings:
Accompanying drawing 1 is the utility model front view,
Accompanying drawing 2 is the utility model left views
Embodiment:
The utility model comprises wire clamp clamp 6, and its effect is to connect lightning arrester and lead, and an end of wire clamp clamp is provided with the hole 1 that is connected with lightning arrester; The other end is provided with the groove 9 that articulates lead, to the lead 5 in collinear footpath not, can establish the grooves of different sizes; Relative with groove is a briquetting 4, and the surface of briquetting is an arc, and briquetting links to each other with screw rod 3; Screw rod cooperates with screw on the wire clamp body, also is provided with locking nut 2 on the screw rod, is provided with hanger 7 in the outside of groove one end; Hanger is provided with lifting hole(eyelet) 8, and the utility model can be realized earth potential working installation lightning arrester.

Claims (1)

1. at earth potential live the special-purpose wire clamp of lightning arrester is installed for one kind, is comprised the wire clamp body, an end of wire clamp body is provided with the hole that is connected with lightning arrester; The other end is provided with the groove that articulates lead; Relative with groove is a briquetting, and briquetting links to each other with screw rod, and screw rod cooperates with screw on the wire clamp body; It is characterized in that being provided with hanger in the outside of groove one end, hanger is provided with lifting hole(eyelet).
CN2012200015465U 2012-01-01 2012-01-01 Special cable clamp for live installation of lightning arrester at ground potential Expired - Fee Related CN202405731U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012200015465U CN202405731U (en) 2012-01-01 2012-01-01 Special cable clamp for live installation of lightning arrester at ground potential

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012200015465U CN202405731U (en) 2012-01-01 2012-01-01 Special cable clamp for live installation of lightning arrester at ground potential

Publications (1)

Publication Number Publication Date
CN202405731U true CN202405731U (en) 2012-08-29

Family

ID=46703348

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012200015465U Expired - Fee Related CN202405731U (en) 2012-01-01 2012-01-01 Special cable clamp for live installation of lightning arrester at ground potential

Country Status (1)

Country Link
CN (1) CN202405731U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102983427A (en) * 2012-11-16 2013-03-20 辽宁省电力有限公司营口供电公司 Hot-line work cable clamp
CN103269037A (en) * 2013-05-28 2013-08-28 国家电网公司 Line arrestor replacing device
CN104767166A (en) * 2015-04-15 2015-07-08 国家电网公司 Ground potential installation tool for line arrester
CN105680370A (en) * 2016-03-31 2016-06-15 国网辽宁省电力有限公司辽阳供电公司 Discharge gap live-line installation and dismounting method
CN105762700A (en) * 2016-03-28 2016-07-13 国网山东省电力公司章丘市供电公司 Cable laying manual traction auxiliary tool
CN112564020A (en) * 2020-11-02 2021-03-26 国网浙江省电力有限公司宁波供电公司 Drainage wire fixing auxiliary device for replacing drop-out fuse or lightning arrester

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102983427A (en) * 2012-11-16 2013-03-20 辽宁省电力有限公司营口供电公司 Hot-line work cable clamp
CN103269037A (en) * 2013-05-28 2013-08-28 国家电网公司 Line arrestor replacing device
CN104767166A (en) * 2015-04-15 2015-07-08 国家电网公司 Ground potential installation tool for line arrester
CN105762700A (en) * 2016-03-28 2016-07-13 国网山东省电力公司章丘市供电公司 Cable laying manual traction auxiliary tool
CN105680370A (en) * 2016-03-31 2016-06-15 国网辽宁省电力有限公司辽阳供电公司 Discharge gap live-line installation and dismounting method
CN112564020A (en) * 2020-11-02 2021-03-26 国网浙江省电力有限公司宁波供电公司 Drainage wire fixing auxiliary device for replacing drop-out fuse or lightning arrester

Similar Documents

Publication Publication Date Title
CN202405731U (en) Special cable clamp for live installation of lightning arrester at ground potential
CN102025035A (en) Insulated conductor grounding potentiometer
CN201673736U (en) Pin type insulator
CN108808280A (en) A kind of portable short-circuit grounding wire and its installation method
CN104535804A (en) Portable current transformer test clamp
CN102931609A (en) Operation method for replacing 10kV drop-out fuse in on-load manner
CN201515026U (en) Vertical grounding wire clamp
CN204964657U (en) Test device suitable for research 10kV line gap ground connection form
CN203895633U (en) Short circuit grounding wire suitable for box transformer substation and electricity distribution room
CN202424088U (en) Socket spanner special for charged installation of arrester in ground potential
CN204012185U (en) The multi-functional lightning arrester of a kind of overhead transmission line adjustable clearance
CN105304244A (en) Arrester special for power equipment
CN206022675U (en) Universal shaped cable clamp earth lead
CN204694795U (en) Surge arrester failure indicating circuit
CN205141184U (en) Wiring of multi -functional portable ground of overhead line
CN104348122B (en) Ground potential mounting type shunt wire clamp device and mounting method thereof
CN204118031U (en) Indoor high-voltage vacuum on-load switch fuse combined electric apparatus
CN202333710U (en) Lightening protection earthing rod
CN105610116A (en) Protection device having functions of lightning protection, electricity inspection and grounding, and protection method
CN205211967U (en) Join in marriage electric network line maintenance and use ground connection discharge device
CN103762517A (en) High-voltage ground wire installation method
CN204481404U (en) 10kV live installation of bird repeller combination tool
CN203690870U (en) Lightning arrester drainage wire clamp
CN210775567U (en) Wiring device for main transformer detection test
RU191069U1 (en) Transformer for pole substation

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHENGDE POWER SUPPLY COMPANY JIBEI POWER CO., LTD.

Effective date: 20130815

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: CHENGDE POWER SUPPLY COMPANY JIBEI POWER CO., LTD.

Effective date: 20130815

C41 Transfer of patent application or patent right or utility model
C56 Change in the name or address of the patentee

Owner name: CHENGDE POWER SUPPLY COMPANY JIBEI POWER CO., LTD.

Free format text: FORMER NAME: CHENGDE POWER SUPPLY CO., LTD. OF NORTH CHINA GRID CO., LTD.

COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 067000 CHENGDE, HEBEI PROVINCE TO: 100031 XICHENG, BEIJING

CP03 Change of name, title or address

Address after: 067000 No. 10 Xinhua North Road, Shuangqiao District, Hebei, Chengde

Patentee after: Chengde Power Supply Company of Jibei Electric Power Co.,Ltd.

Address before: 067000 Xinhua Road, 10, Hebei, Chengde

Patentee before: Chengde Power Supply Company of North China Grid Co.,Ltd.

TR01 Transfer of patent right

Effective date of registration: 20130815

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Patentee after: State Grid Corporation of China

Patentee after: Chengde Power Supply Company of Jibei Electric Power Co.,Ltd.

Address before: 067000 No. 10 Xinhua North Road, Shuangqiao District, Hebei, Chengde

Patentee before: Chengde Power Supply Company of Jibei Electric Power Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120829

Termination date: 20200101

CF01 Termination of patent right due to non-payment of annual fee