CN104345245A - Method for checking voltage transformer wiring correctness by using transformer turn ratio & group tester - Google Patents

Method for checking voltage transformer wiring correctness by using transformer turn ratio & group tester Download PDF

Info

Publication number
CN104345245A
CN104345245A CN201310319639.1A CN201310319639A CN104345245A CN 104345245 A CN104345245 A CN 104345245A CN 201310319639 A CN201310319639 A CN 201310319639A CN 104345245 A CN104345245 A CN 104345245A
Authority
CN
China
Prior art keywords
voltage
transformer
phase
winding
voltage ratio
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310319639.1A
Other languages
Chinese (zh)
Other versions
CN104345245B (en
Inventor
李贵平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CMTCC Shanghai Shisanye Construction Co Ltd filed Critical CMTCC Shanghai Shisanye Construction Co Ltd
Priority to CN201310319639.1A priority Critical patent/CN104345245B/en
Publication of CN104345245A publication Critical patent/CN104345245A/en
Application granted granted Critical
Publication of CN104345245B publication Critical patent/CN104345245B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a method for checking voltage transformer change and voltage loop wiring correctness by using a transformer turn ratio & group tester. The method comprises the following steps: (1) checking the grounding and voltage loops of three single-phase grounding type voltage transformers, (2) using a transformer turn ratio & group tester to check the change of primary and secondary main windings of the three single-phase grounding type voltage transformers and system voltage loop wiring, (3) checking the change of primary and secondary assisted windings of the three single-phase grounding type voltage transformers and zero sequence voltage loop wiring and removing all temporary test lines. According to the method, the transformer turn ratio & group tester is used to check the change of three single voltage transformers in Y0/y0/delta wiring and the voltage loop wiring, and the voltage transformer turn ratio, the lead wire phase sequence, the phase and the grounding correctness of different connection group windings can be ensured.

Description

No-load voltage ratio group tester is utilized to check the method for voltage transformer (VT) wiring correctness
Technical field
The present invention relates to independently three single-phase earthing type voltage transformer (VT) no-load voltage ratio and voltage circuit wiring correctness when the wiring of Y0/y0/ Δ and check field, be specially a kind of method utilizing no-load voltage ratio group tester to check voltage transformer (VT) no-load voltage ratio and voltage circuit wiring correctness.
Background technology
Voltage transformer (VT) is in transformation and distribution system, the essential and equipment easily gone wrong, and often shows as Secondary Circuit of Potential Transformer incorrect polarity, causes the phase sequence mistake of WV, no-load voltage ratio mistake and the different ground connection mistake connecting group winding, even short circuit.When voltage transformer (VT) is newly installed or after overhaul, its no-load voltage ratio and wiring whether correct, necessary inspection and test must be carried out, and whether rationally and can improve be the key differentiating wiring correctness detection method.Conventional inspection method is that three single-phase earthing type voltage transformer (VT) are after installation and wiring complete, three-phase 380V voltage is added from the high-pressure side of three voltage transformer (VT), in low-pressure side, each main Secondary Winding and auxiliary winding voltage are measured, thus try to achieve each winding no-load voltage ratio, but can not ensure once and the phase sequence of each Secondary Winding extension line, phase place and different to connect group winding earth correct.
Summary of the invention
The object of the invention is to, there is provided one transformer voltage ratio group tester to check 3 single-phase earthing type voltage transformer (VT) no-load voltage ratio and wiring correctness when the wiring of Y0/y0/ Δ, check the no-load voltage ratio of voltage transformer (VT), phase sequence, phase place and the different method connecting the correctness of group winding earth.
In order to achieve the above object, the present invention is achieved in that
Utilize transformer voltage ratio group tester to check a method for voltage transformer (VT) wiring correctness, it comprises the steps:
Step 1, the ground connection of three single-phase earthing type voltage transformer (VT) and voltage circuit to be checked;
Step 2, with transformer voltage ratio group tester to three single-phase earthing type voltage transformer (VT) once and the no-load voltage ratio of secondary main winding and system voltage circuit connection check, wherein, the high-pressure side test port of no-load voltage ratio tester is connected on system bus, and low-pressure side test port is connected on WV corresponding to mutual inductor secondary main winding outlet;
Step 3, with transformer voltage ratio group tester to three single-phase earthing type voltage transformer (VT) once and the no-load voltage ratio of secondary assistant winding (residual voltage winding) and residual voltage circuit connection check;
Step 3.1, open the 3rd (i.e. C phase) voltage transformer secondary and assist winding dn terminate ground wire;
Step 3.2, connect extraction one interim trial line from the secondary assistant winding outlet terminal da of second (i.e. B phase) voltage transformer (VT) or First (i.e. A phase) outlet terminal dn;
Step 3.3, connect extraction one interim trial line from secondary assistant winding outlet terminal dn or the 3rd (i.e. C phase) the outlet terminal da of second (i.e. B phase) voltage transformer (VT);
Step 3.4, the secondary assistant winding outlet da of First (i.e. A phase) voltage transformer (VT) and the 3rd (i.e. C phase) voltage transformer secondary are assisted winding dn interim trial line short circuit (or by WV YML and YMn interim trial line short circuit);
Step 3.5, transformer voltage ratio group tester is utilized to check the secondary assistant winding wiring of three voltage transformer (VT) and no-load voltage ratio, wherein the high-pressure side test port of tester is connected in system bus A, B, C phase, and low-pressure side test port is connected on WV YML and step 3.2, the 3.3 interim trial lines of drawing successively;
Step 3.6, recovery the 3rd (i.e. C phase) voltage transformer secondary assist winding dn terminate ground wire;
Step 3.7, remove all interim trial lines.
The present invention uses transformer voltage ratio group tester, three independent voltage transformer (VT) no-load voltage ratio and voltage circuit wiring when the wiring of Y0/y0/ Δ are checked, can guarantee new install or voltage transformer (VT) no-load voltage ratio after overhaul, extension line phase sequence, phase place, the different ground connection connecting group winding correct, avoid when checking by the method usually adding 380V voltage in voltage transformer (VT) high-pressure side, the secondary outgoing line phase sequence that may exist, phase place and differently connect the mistakes such as the ground connection of group winding.
Accompanying drawing explanation
Fig. 1 is that each main Secondary Winding no-load voltage ratio of the present invention and system voltage circuit connection check schematic diagram.
Fig. 2 is that secondary assistant winding no-load voltage ratio of the present invention and residual voltage circuit connection check schematic diagram.
Fig. 3 is that the exact connect ion of voltage transformer (VT) of the present invention when the wiring of Y0/y0/ Δ checks schematic diagram.
There are three earthed voltage transformers in Fig. 1, Fig. 2 and Fig. 3, are respectively three-phase arrangement from left to right.Often group (21,31,41), (22,32,42), (23,33,43), (24,34,44), (25,35,45), (26,36,46) are the wiring leading-out terminal of a voltage transformer (VT), wherein (21,31,41), (22,32,42) are a main winding outlet terminal, (23,33,43), (24,34,44) are secondary main winding outlet terminal, (25,35,45), (26,36,46) are secondary assistant winding outlet terminal.FU is high pressure, low-voltage variation fuse (5,10); (52,53,54) are three-phase bus; the little bus of secondary voltage that (27,37,47) are slotted line voltage; YML, YMn are the little bus of secondary voltage (6,9) measuring residual voltage, b2, c2(7,9) be the interim trial line position of drawing.
Be transformer voltage ratio group tester 1 in dotted line frame on the right side of Fig. 1 and Fig. 2, high-pressure side test port label is 11,12,13, and low-pressure side test port label is 111,112,113.
Embodiment
The present invention is further illustrated below by way of specific embodiment.
A kind of method utilizing transformer voltage ratio group tester to check voltage transformer (VT) wiring correctness it comprise:
As shown in Figure 3, to voltage transformer (VT) once, secondary voltage circuit checks, guarantees that external cabling and label are all correct.
The wiring of step 1, an inspection voltage transformer (VT) winding.Be specially: three voltage transformer (VT) outlet terminal 21,31,41 is connected with corresponding high voltage protective fuse 5, high voltage protective fuse 5 other end is connected with corresponding once bus 52,53,54, the outlet terminal 22,32,42 of three voltage transformer (VT) is interconnected and reliable ground on one point, and the fuse in primary circuit is installed, switch closes;
Check the wiring of voltage transformer secondary main winding.Be specially: the main Secondary Winding outlet terminal 23,33,43 of three mutual inductors is connected with corresponding low-voltage variation fuse 10, low-voltage variation fuse 10 other end is connected with 27,37,47 WVs respectively, the outlet terminal 24,34,44 of three voltage transformer (VT) is interconnected and is connected on 9 WVs after reliable ground on one point, and the fuse in secondary circuit is installed, switch closes;
Check boosting voltage circuit connection.Be specially: the da terminal 25 of the first from left voltage transformer (VT) is connected with low-tension fuse 10, the other end of low-tension fuse 10 is connected with YML WV 27, the dn terminal 46 of a right voltage transformer (VT) is connected with YMn WV 9, the second from left voltage transformer (VT) da secondary outlet terminal 35 is connected with the first from left voltage transformer (VT) dn secondary outlet terminal 26, the second from left voltage transformer (VT) dn secondary outlet terminal 36 is connected with a right voltage transformer (VT) da secondary outlet terminal 45, and the fuse in loop is installed, switch closes.
Step 2, transformer voltage ratio group tester is utilized to check the no-load voltage ratio of each main Secondary Winding of voltage transformer (VT) and system voltage circuit connection.
As shown in Figure 1, the height of first connection transformer no-load voltage ratio group tester 1, low-pressure side test port 11, 12, 13, 111, 112, 113 externally measured circuits, namely the high-pressure side 11 of transformer voltage ratio group tester 1, 12, 13 ports are connected to corresponding system bus 52, 53, on 54, the low-pressure side 111 of transformer voltage ratio group tester 1, 112, 113 ports are connected to corresponding WV 27, 37, 47, on, connect the power supply of transformer voltage ratio group tester 1 again, to connection group and no-load voltage ratio (or once, secondary voltage) arrange, measure no-load voltage ratio and group, the no-load voltage ratio recorded should consistent with voltage transformer (VT) nameplate and system requirements (be such as 10kV for rated voltage, no-load voltage ratio is the no-load voltage ratio AB/ab that records of voltage transformer (VT), BC/bc, CA/ca all should be 100, and error is in allowed band), the connection group recorded is Y/y0, then show voltage transformer (VT) once and the main Secondary Winding no-load voltage ratio of correspondence and wiring all correct.When finding that there is mistake, reexamine after wiring should being corrected in time, till correct.
Step 3, transformer voltage ratio group tester is utilized to assist the no-load voltage ratio of winding and residual voltage circuit connection to check to voltage transformer secondary.
(1) open a right voltage transformer secondary and assist winding 46 terminate ground wire;
(2) when voltage transformer (VT) connection terminal is not easy to connect instrument test line, connect extraction one interim trial line from the secondary assistant winding outlet terminal 35 of the second from left voltage transformer (VT) or the first from left outlet terminal 26, it is connected on the position that can conveniently be connected with transformer voltage ratio tester 1 (as in Fig. 2 being the position of 7);
(3) when voltage transformer (VT) connection terminal is not easy to connect instrument test line, connect extraction one interim trial line from the secondary assistant winding outlet terminal 46 of the second from left voltage transformer (VT) or a right outlet terminal 45, it is connected on the position that can conveniently be connected with transformer voltage ratio tester 1 (as in Fig. 2 being the position of 8);
(4) WV 6 and 9 interim trial line short circuit;
(5) the secondary assistant winding no-load voltage ratio of three voltage transformer (VT) and residual voltage circuit connection are checked.
Connect the line of three voltage transformer (VT) and transformer voltage ratio group tester 1 as shown in Figure 2, namely the high-pressure side 11 of tester, 12, 13 ports are connected to a corresponding bus 52, 53, on 54, the low-pressure side 111 of transformer voltage ratio group tester 1, 112, 113 ports are connected to corresponding WV 6 and 7, on 8, connect transformer voltage ratio group tester 1 power supply, butted line group and no-load voltage ratio (or once, secondary voltage) arrange, measure no-load voltage ratio and group, the no-load voltage ratio recorded should be consistent with voltage transformer (VT) nameplate and system requirements (as being 10kV for rated voltage, no-load voltage ratio is voltage transformer (VT), the no-load voltage ratio AB/ab recorded, BC/bc, CA/ca are 300, and error is within allowed band), the secondary assistant winding connected mode recorded is Δ, then the no-load voltage ratio of secondary assistant winding and wiring all correct.When finding that there is mistake, reexamine after should correcting in time, till correct.
(6) grounding connection of right voltage transformer (VT) 46 terminal is recovered.
(7) all interim trial lines are removed.
The present embodiment only provides one group of main Secondary Winding, and when there being the main Secondary Winding of many groups, test mode is identical with this group.When voltage transformer secondary voltage circuit is without fuse but when selecting switch to protect, during inspection, switch is just equal to the fuse in this figure.
In the present invention, the no-load voltage ratio measurement range of no-load voltage ratio group tester should meet the requirement that in system, voltage transformer (VT) no-load voltage ratio is measured, generally, because the no-load voltage ratio of a winding to auxiliary winding is maximum, select during test apparatus and can meet the requirement that the no-load voltage ratio measuring auxiliary winding just can meet whole measurement, such as 10kV system, tester no-load voltage ratio measurement range should be greater than 300:1, for 35kV system, tester no-load voltage ratio measurement range should be greater than 1050:1, for 110kV system, no-load voltage ratio measurement range should be greater than 3300:1.The no-load voltage ratio measurement range of current no-load voltage ratio tester is different, but maximum measurement range can reach more than 10000:1.

Claims (1)

1. utilize no-load voltage ratio group tester to check a method for voltage transformer (VT) no-load voltage ratio and voltage circuit wiring correctness, it comprises the steps:
Step 1, the ground connection of three single-phase earthing type voltage transformer (VT) and voltage circuit to be checked;
Step 2, with transformer voltage ratio group tester to three single-phase earthing type voltage transformer (VT) once and the no-load voltage ratio of secondary main winding and system voltage circuit connection check, wherein, the high-potting port of tester is connected on system bus, and low pressure test (LPT) port is connected on WV corresponding to mutual inductor main Secondary Winding outlet;
Step 3, with transformer voltage ratio group tester to three single-phase earthing type voltage transformer (VT) once and the no-load voltage ratio of secondary assistant winding (residual voltage winding) and residual voltage circuit connection check;
Step 3.1, open C phase voltage mutual inductor secondary assistant winding terminate ground wire;
Step 3.2, connect extraction one interim trial line from the secondary assistant winding outlet terminal of B phase voltage mutual inductor or A phase outlet terminal;
Step 3.3, connect extraction one interim trial line from the secondary assistant winding outlet terminal of B phase voltage mutual inductor or C phase outlet terminal;
Step 3.4, the secondary assistant winding outlet of A phase voltage mutual inductor and C phase voltage mutual inductor secondary assistant winding with interim trial line short circuit or by WV short circuit;
Step 3.5, transformer voltage ratio group tester is utilized to check the secondary assistant winding wiring of three voltage transformer (VT) and no-load voltage ratio;
Step 3.6, recovery C phase voltage mutual inductor secondary assistant winding terminate ground wire;
Step 3.7, remove all interim trial lines.
CN201310319639.1A 2013-07-26 2013-07-26 Method for checking voltage transformer wiring correctness by using transformer turn ratio & group tester Active CN104345245B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310319639.1A CN104345245B (en) 2013-07-26 2013-07-26 Method for checking voltage transformer wiring correctness by using transformer turn ratio & group tester

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310319639.1A CN104345245B (en) 2013-07-26 2013-07-26 Method for checking voltage transformer wiring correctness by using transformer turn ratio & group tester

Publications (2)

Publication Number Publication Date
CN104345245A true CN104345245A (en) 2015-02-11
CN104345245B CN104345245B (en) 2017-04-19

Family

ID=52501271

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310319639.1A Active CN104345245B (en) 2013-07-26 2013-07-26 Method for checking voltage transformer wiring correctness by using transformer turn ratio & group tester

Country Status (1)

Country Link
CN (1) CN104345245B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104820161A (en) * 2015-05-21 2015-08-05 国家电网公司 Multi-tap current transformer secondary wiring detection device
CN104833836A (en) * 2015-04-23 2015-08-12 本钢板材股份有限公司 Zero sequence voltage detection method for voltage transformer
CN108051662A (en) * 2017-11-08 2018-05-18 保定天威集团特变电气有限公司 More device body series transformer test methods, assembly and test system
CN110531214A (en) * 2019-08-28 2019-12-03 中广核工程有限公司 For detecting the detection verification method of Secondary Circuit of Potential Transformer winding short circuit
CN110824388A (en) * 2019-10-22 2020-02-21 国网浙江省电力有限公司绍兴供电公司 4PT wiring polarity discrimination method for small current grounding system
CN110850352A (en) * 2019-12-01 2020-02-28 国网辽宁省电力有限公司锦州供电公司 Secondary circuit wiring checking method of 10kV voltage transformer
CN113156276A (en) * 2021-02-22 2021-07-23 云南建投第二安装工程公司 Method for checking and debugging secondary voltage loop in AC withstand voltage test of switchgear bus

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201166700Y (en) * 2008-02-29 2008-12-17 宁波三维电测设备有限公司 Apparatus for measuring voltage mutual inductor error base on parameter measurement
CN201956668U (en) * 2010-12-15 2011-08-31 中国神华能源股份有限公司 Clearance over-voltage protecting device
KR101157362B1 (en) * 2010-08-26 2012-06-15 주식회사 광성계측기 Measure method and device of Three phase instrument transformer ratio error test
CN102508191A (en) * 2011-12-23 2012-06-20 中国北车集团大连机车车辆有限公司 Device and method for detecting fault of high voltage transformer of electric locomotive
CN102780234A (en) * 2012-08-08 2012-11-14 中国二十二冶集团有限公司 High-voltage electric debugging method for power generation project

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201166700Y (en) * 2008-02-29 2008-12-17 宁波三维电测设备有限公司 Apparatus for measuring voltage mutual inductor error base on parameter measurement
KR101157362B1 (en) * 2010-08-26 2012-06-15 주식회사 광성계측기 Measure method and device of Three phase instrument transformer ratio error test
CN201956668U (en) * 2010-12-15 2011-08-31 中国神华能源股份有限公司 Clearance over-voltage protecting device
CN102508191A (en) * 2011-12-23 2012-06-20 中国北车集团大连机车车辆有限公司 Device and method for detecting fault of high voltage transformer of electric locomotive
CN102780234A (en) * 2012-08-08 2012-11-14 中国二十二冶集团有限公司 High-voltage electric debugging method for power generation project

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104833836A (en) * 2015-04-23 2015-08-12 本钢板材股份有限公司 Zero sequence voltage detection method for voltage transformer
CN104820161A (en) * 2015-05-21 2015-08-05 国家电网公司 Multi-tap current transformer secondary wiring detection device
CN104820161B (en) * 2015-05-21 2017-11-07 国家电网公司 A kind of multi-tap secondary wiring of current mutual inductor detection means
CN108051662A (en) * 2017-11-08 2018-05-18 保定天威集团特变电气有限公司 More device body series transformer test methods, assembly and test system
CN110531214A (en) * 2019-08-28 2019-12-03 中广核工程有限公司 For detecting the detection verification method of Secondary Circuit of Potential Transformer winding short circuit
CN110531214B (en) * 2019-08-28 2022-06-07 中广核工程有限公司 Detection and verification method for detecting short circuit of secondary circuit winding of voltage transformer
CN110824388A (en) * 2019-10-22 2020-02-21 国网浙江省电力有限公司绍兴供电公司 4PT wiring polarity discrimination method for small current grounding system
CN110850352A (en) * 2019-12-01 2020-02-28 国网辽宁省电力有限公司锦州供电公司 Secondary circuit wiring checking method of 10kV voltage transformer
CN113156276A (en) * 2021-02-22 2021-07-23 云南建投第二安装工程公司 Method for checking and debugging secondary voltage loop in AC withstand voltage test of switchgear bus
CN113156276B (en) * 2021-02-22 2024-03-29 云南建投第二安装工程公司 Method for checking and debugging secondary voltage loop of bus alternating-current withstand voltage test of switching equipment

Also Published As

Publication number Publication date
CN104345245B (en) 2017-04-19

Similar Documents

Publication Publication Date Title
CN104345245A (en) Method for checking voltage transformer wiring correctness by using transformer turn ratio & group tester
CN102780234B (en) High-voltage electric debugging method for power generation project
CN108490304A (en) Generator stator winding single-phase earthing abort situation localization method
CN107807282B (en) Method for testing dielectric loss factor and capacitance of transformer without disassembling high-voltage lead
CN101354418A (en) Power transformer test method without disconnecting wire
CN101958530A (en) Main transformer differential protection CT polarity check method of pumped storage power station
CN102608485B (en) Detection method for zero-sequence current loops of transformer substations
CN102565618A (en) Method for detecting zero-sequence voltage circuit of transformer substation
CN110031718B (en) Method for verifying integrity of alternating current circuit by pressurizing low-voltage side of railway traction station
CN102540001A (en) Method of checking alternating current loop of a 500kV transformer substation through carrying out simulated through-type three-phase short circuit
CN105785157A (en) Double main transformer longitudinal differential protection loop closing testing method
CN107300684B (en) A kind of check method in transformer differential protection secondary circuit
CN110703152A (en) Method for testing braking characteristic of differential protection ratio of transformer
CN102565614B (en) Alternating voltage loop test method
CN104505863B (en) A method for determining and adjusting wireless phase detection
CN104155627B (en) Error characteristic detection method of extra high voltage capacitive voltage transformer
CN111913060B (en) Verification system and method for checking differential protection polarity through main transformer inverted power transmission on load
CN111624426B (en) System and method for verifying bus differential protection polarity in double-bus system wiring mode
CN104267276B (en) Method high-tension motor longitudinal differential protection checked with low pressure locked rotor current
CN103809146A (en) Test method of main transformer CT (Current Transformer)
CN104698335A (en) Method for debugging high-voltage transformer substation in systematization mode by using low tension electricity
CN103048586A (en) Verification method for wiring correction of voltage transformer
CN103414159B (en) Solve the method that generator stator ground protects delayed excision fault
CN206541018U (en) A kind of multipoint grounding seeking instrument of voltage transformer
CN107449987A (en) Based on the test method of transferring the files for not tearing 750 kv transformer high pressure lead technologies open

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee after: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: CMTCC Shanghai 13th Construction Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190815

Address after: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Co-patentee after: CHINA MCC20 GROUP Corp.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201900 Shanghai city Baoshan District Tieli Road No. 2469

Patentee before: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.