CN104314081A - Deep foundation pit driftway-free basement concrete pumping construction device - Google Patents

Deep foundation pit driftway-free basement concrete pumping construction device Download PDF

Info

Publication number
CN104314081A
CN104314081A CN201410553552.5A CN201410553552A CN104314081A CN 104314081 A CN104314081 A CN 104314081A CN 201410553552 A CN201410553552 A CN 201410553552A CN 104314081 A CN104314081 A CN 104314081A
Authority
CN
China
Prior art keywords
shuttle groove
foundation pit
construction
foundation ditch
deep foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410553552.5A
Other languages
Chinese (zh)
Inventor
赵柱明
黄玉祥
彭舸
李俊杰
刘彦
杨勇
何志忠
张丽
何启
李靖伟
王思威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Construction Co of China Railway No 8 Engineering Group Co Ltd
Original Assignee
Construction Co of China Railway No 8 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Construction Co of China Railway No 8 Engineering Group Co Ltd filed Critical Construction Co of China Railway No 8 Engineering Group Co Ltd
Priority to CN201410553552.5A priority Critical patent/CN104314081A/en
Publication of CN104314081A publication Critical patent/CN104314081A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

The invention discloses a deep foundation pit driftway-free basement concrete pumping construction device and belongs to the field of building construction. The deep foundation pit driftway-free basement concrete pumping construction device comprises a discharge port formed in the top of a foundation pit, a ground pump arranged at the bottom of the foundation pit, a shuttle groove used for connecting the discharge port with the ground pump, a pluraity of pull ropes fixedly connected between the shuttle groove and the crown beam of the foundation pit and between the shuttle groove and a breast wall pile, and a supporting rack body used for supporting and fixing the shuttle groove, wherein the pull ropes incline downward, are arranged at intervals and are parallel along the height of the shuttle groove; the supporting rack body comprises a vertically-supported vertical rod, upper cross rods, lower cross rods, left connecting rods and right connecting rods; the upper cross rods and the lower cross rods are fixedly arranged on the vertical rod and are tangential to the upper and lower edges of the shuttle groove; the left connecting rods and the right connecting rods are fixedly arranged between the upper cross rods and the lower cross rods and are tangential to the left and right edges of the shuttle groove; a plurality of groups of upper cross rods and lower cross rods are arranged along the height of the shuttle groove; the shuttle groove is made of a metal tube; the erection slop of the shuttle groove is 45-50 degrees. The deep foundation pit driftway-free basement concrete pumping construction device can be used for solving the problems of narrow construction yard, high deep foundation pit operation and basement construction workload and difficulty in concrete construction of an annular road around a construction site.

Description

A kind of deep foundation ditch is without packway concrete of basement pumping construction device
Technical field
The invention belongs to the realm of building construction, particularly relate to that construction plant is narrow, deep foundation ditch operation, the basement construction scale of construction is large, building site surrounding cannot form circumferential road construction field.
Background technology
Modern architecture is constructed, face that construction plant is narrow more and more, deep foundation ditch operation, the basement construction scale of construction is large, building site surrounding cannot form circumferential road construction difficult problem.
A lot of building project construction plant is narrow and small, in addition the duration is nervous and basement construction intensity is large, Construction unit requires not stay and establish a cubic metre of earth packway, thus cannot utilize packway as construction basement occasional passage is convenient to reinforcing bar haulage vehicle, commercial concrete haulage vehicle moves to foundation pit construction operation.Simultaneously large for foundation ditch, the degree of depth is dark, and concrete of basement always just measures high project, and Concrete Pumping Construction exists larger difficulty.
Prior art Normal practice:
1, ground pump is installed on the ground to build, but due to normal throw large, farthest horizontal range is wide, and reaching pumping limit and easily forming " plugging " affects construction speed and pouring quality.
2, use periphery Site access and town road, utilize sky pump to build simultaneously, affect the appearance of the city, traffic and other site construction progresses, be difficult to coordinate, and 1m built by sky pump 3concrete need increase income 30 yuan, greatly increases cost payout.
Summary of the invention
The object of the invention is to: a kind of deep foundation ditch, without packway concrete of basement pumping construction device, solves narrow, the deep foundation ditch operation in construction plant, the basement construction scale of construction is large, building site surrounding cannot form circumferential road a concrete construction difficult problem.
The object of the invention is realized by following technical proposals:
A kind of deep foundation ditch is without packway concrete of basement pumping construction device, comprise the discharge port being arranged at foundation ditch top, be arranged at the ground pump bottom foundation ditch, connect the shuttle groove of described discharge port and ground pump, be connected and fixed on the some stay cords between described shuttle groove and foundation ditch Guan Liang and lagging pile, and support the supporting frame of fixing described shuttle groove, described each stay cord obliquely, arrange along shuttle groove height parallel interval, support frame as described above body comprises the vertical rod vertically supported, to be fixed in described vertical rod and with on described shuttle groove, tangent upper in lower edge, sheer pole, and be fixed on described on, with described shuttle groove left between sheer pole, the right is along a tangent fixing left side, right connecting rod, on described, sheer pole is provided with some groups along shuttle groove height, described shuttle groove is made by metal tube, it is 45 ° ~ 50 ° that shuttle groove sets up the gradient.
In such scheme, in such scheme by ingenious arrange discharge port, pump, connect the shuttle groove of discharge port and ground pump, commercial concrete haulage vehicle carries out blowing at ground discharge port, concrete utilizes deadweight by oblique shuttle groove arrival point stock hopper, be delivered to each operation side after secondary agitation, can simply, quickly and reliably concrete be carried thus.Because ground pump setting position and foundation ditch top exist the larger discrepancy in elevation, shuttle groove is needed concrete to be guided in tank car ground pump, for avoiding causing concrete to produce segregation in water conservancy diversion process because shuttle trough slope is excessive, shuttle groove is set up the gradient and is arranged at 45 ° ~ 50 °, simultaneously, shuttle groove metal tube is made, and can produce air downforce when concrete flows in pipeline, can concrete coarse aggregate be stoped further to be separated with slurry.In addition, supporting frame supports fixing shuttle groove, wherein vertical rod vertical supporting, the upper and lower clamping shuttle groove of upper and lower spaced some groups of upper and lower cross bars, shuttle groove and upper sheer pole is fixed about upper and lower spaced some groups of left and right connecting rods, upper and lower spaced some stay cords then draw fixing shuttle groove further, guarantee its stability.
As selection, support frame as described above body is also provided with bridging, the vertical bridging that described bridging comprises horizontal cross brace and intersects in X-shaped.
In such scheme, make supporting frame more solid and reliable.
As selection, described upper and lower cross bar arranges described left and right connecting rod every one group.
In such scheme, under taking into account the condition of reliability, simplify structure further.
The main scheme of aforementioned the present invention and each further selection scheme thereof can independent assortment to form multiple scheme; be the present invention can adopt and claimed scheme: as the present invention; each selection can select any combination with other; those skilled in the art can understand there is multiple combination according to prior art and common practise after understanding the present invention program; be the claimed technical scheme of the present invention, do not do exhaustive at this.
Beneficial effect of the present invention: solve that construction plant is narrow, deep foundation ditch operation, the basement construction scale of construction is large, building site surrounding cannot form circumferential road a concrete construction difficult problem, concrete is without segregation and plugging phenomenon.
Accompanying drawing explanation
Fig. 1 is the facade structures schematic diagram of the embodiment of the present invention;
Fig. 2 is the shuttle groove fixed structure schematic diagram of the embodiment of the present invention;
Fig. 3 is the bridging fixed structure schematic diagram of the embodiment of the present invention;
1 be foundation ditch, 2 be wherein discharge port, 3 for ground pump, 4 be shuttle groove, 5 be Guan Liang, 6 be lagging pile, 7 be stay cord, 8 be supporting frame, 9 be bridging, 81 be vertical rod, 82 be cross tube, 83 be sheer pole, 84 be left connecting rod, 85 be right connecting rod, 91 be horizontal cross brace, 92 for vertical bridging.
Detailed description of the invention
Following non-limiting examples is for illustration of the present invention.
Shown in figure 1-3, a kind of deep foundation ditch is without packway concrete of basement pumping construction device, as selection, as shown in this embodiment, comprise the discharge port 2 being arranged at foundation ditch 1 top, be arranged at the ground pump 3 bottom foundation ditch 1, connect the shuttle groove 4 of discharge port 2 and ground pump 3, be connected and fixed on shuttle groove 4 and foundation ditch 1 and be preced with some stay cords 7 between beam 5 and lagging pile 6, and support the supporting frame 8 of fixing shuttle groove 4, each stay cord 7 obliquely, arrange along shuttle groove 4 height parallel interval, along the every 2m of shuttle groove 4 short transverse, one stay cord 7 (diameter is the wire rope of 12mm) is set, be illustrated in figure 16 roads, supporting frame 8 comprises the vertical rod 81 vertically supported, to be fixed in vertical rod 81 and with on shuttle groove 4, tangent upper in lower edge, sheer pole 82, 83, and be fixed on, sheer pole 82, with shuttle groove 4 left between 83, the right is along a tangent fixing left side, right connecting rod 84, 85, on, sheer pole 82, 83 are highly provided with some groups along shuttle groove 4.Foundation ditch 1 shape is rectangle 140*140m, and the degree of depth is 20m, and concrete of basement is always just measured as 75000m 3, there is the 17m discrepancy in elevation in ground pump 3 setting position and foundation ditch 1 top, shuttle groove 4 is made by the cast iron pipe of diameter to be 300mm wall thickness be 5mm, and shuttle groove 4 is set up the gradient and arranged at 45 ° ~ 50 °.Supporting frame 8 is also provided with bridging 9, the vertical bridging 92 that bridging comprises horizontal cross brace 91 and intersects in X-shaped.Upper and lower cross bar 82,83 arranges left and right connecting rod 84,85 every one group.
Final this project smooth delivery of power 75000m 3concrete, does not find once to emanate and plugging, saves 20 days durations simultaneously, saves concrete of basement sky transport pump expense (rule of thumb calculating according to 60%): 75000*30*0.6=1350000 unit.
The foregoing is only preferred embodiment of the present invention, not in order to limit the present invention, all any amendments done within the spirit and principles in the present invention, equivalent replacement and improvement etc., all should be included within protection scope of the present invention.

Claims (3)

1. a deep foundation ditch is without packway concrete of basement pumping construction device, it is characterized in that: comprise the discharge port being arranged at foundation ditch top, be arranged at the ground pump bottom foundation ditch, connect the shuttle groove of described discharge port and ground pump, be connected and fixed on the some stay cords between described shuttle groove and foundation ditch Guan Liang and lagging pile, and support the supporting frame of fixing described shuttle groove, described each stay cord obliquely, arrange along shuttle groove height parallel interval, support frame as described above body comprises the vertical rod vertically supported, to be fixed in described vertical rod and with on described shuttle groove, tangent upper in lower edge, sheer pole, and be fixed on described on, with described shuttle groove left between sheer pole, the right is along a tangent fixing left side, right connecting rod, on described, sheer pole is provided with some groups along shuttle groove height, described shuttle groove is made by metal tube, it is 45 ° ~ 50 ° that shuttle groove sets up the gradient.
2. deep foundation ditch as claimed in claim 1 is without packway concrete of basement pumping construction device, it is characterized in that: support frame as described above body is also provided with bridging, the vertical bridging that described bridging comprises horizontal cross brace and intersects in X-shaped.
3. deep foundation ditch as claimed in claim 1 is without packway concrete of basement pumping construction device, it is characterized in that: described upper and lower cross bar arranges described left and right connecting rod every one group.
CN201410553552.5A 2014-10-17 2014-10-17 Deep foundation pit driftway-free basement concrete pumping construction device Pending CN104314081A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410553552.5A CN104314081A (en) 2014-10-17 2014-10-17 Deep foundation pit driftway-free basement concrete pumping construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410553552.5A CN104314081A (en) 2014-10-17 2014-10-17 Deep foundation pit driftway-free basement concrete pumping construction device

Publications (1)

Publication Number Publication Date
CN104314081A true CN104314081A (en) 2015-01-28

Family

ID=52369382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410553552.5A Pending CN104314081A (en) 2014-10-17 2014-10-17 Deep foundation pit driftway-free basement concrete pumping construction device

Country Status (1)

Country Link
CN (1) CN104314081A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476308A (en) * 2017-09-29 2017-12-15 中铁八局集团建筑工程有限公司 A kind of pipe-line system for the downward pumping concrete of deep basal pit
CN108118901A (en) * 2017-12-08 2018-06-05 中国建筑第八工程局有限公司 The anti-pump concrete device and construction method of basement
CN108894231A (en) * 2018-09-19 2018-11-27 北京城建集团有限责任公司 A kind of concrete chute structural system and its construction method
CN109750825A (en) * 2018-12-29 2019-05-14 杭州江润科技有限公司 The construction method of foundation pit suspension type riding track
CN111719559A (en) * 2020-07-16 2020-09-29 湖南建工集团有限公司 Concrete conveying construction method for deep foundation pit by vertical synchronous full-reverse construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6131074Y2 (en) * 1982-11-22 1986-09-10
CN201786031U (en) * 2010-08-11 2011-04-06 中国一冶集团有限公司 Slip-formed concrete distributing bin device
CN202689002U (en) * 2012-07-25 2013-01-23 上海建工二建集团有限公司 Concrete pouring rotary chute material distribution system
CN202881906U (en) * 2012-10-16 2013-04-17 赵庆锌 Lining cutting machine
CN103266613A (en) * 2013-04-17 2013-08-28 中天建设集团有限公司 Large-scale chute device for casting mass concrete in deep foundation pit
CN103485524A (en) * 2013-10-11 2014-01-01 四川省第四建筑工程公司 Bracket type overhanging scaffold and construction method thereof at erection time
CN203403420U (en) * 2013-02-01 2014-01-22 河南省水利第二工程局 Concrete vertical conveying pouring system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6131074Y2 (en) * 1982-11-22 1986-09-10
CN201786031U (en) * 2010-08-11 2011-04-06 中国一冶集团有限公司 Slip-formed concrete distributing bin device
CN202689002U (en) * 2012-07-25 2013-01-23 上海建工二建集团有限公司 Concrete pouring rotary chute material distribution system
CN202881906U (en) * 2012-10-16 2013-04-17 赵庆锌 Lining cutting machine
CN203403420U (en) * 2013-02-01 2014-01-22 河南省水利第二工程局 Concrete vertical conveying pouring system
CN103266613A (en) * 2013-04-17 2013-08-28 中天建设集团有限公司 Large-scale chute device for casting mass concrete in deep foundation pit
CN103485524A (en) * 2013-10-11 2014-01-01 四川省第四建筑工程公司 Bracket type overhanging scaffold and construction method thereof at erection time

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476308A (en) * 2017-09-29 2017-12-15 中铁八局集团建筑工程有限公司 A kind of pipe-line system for the downward pumping concrete of deep basal pit
CN108118901A (en) * 2017-12-08 2018-06-05 中国建筑第八工程局有限公司 The anti-pump concrete device and construction method of basement
CN108118901B (en) * 2017-12-08 2020-03-20 中国建筑第八工程局有限公司 Reverse pumping concrete device for basement and construction method
CN108894231A (en) * 2018-09-19 2018-11-27 北京城建集团有限责任公司 A kind of concrete chute structural system and its construction method
CN109750825A (en) * 2018-12-29 2019-05-14 杭州江润科技有限公司 The construction method of foundation pit suspension type riding track
CN111719559A (en) * 2020-07-16 2020-09-29 湖南建工集团有限公司 Concrete conveying construction method for deep foundation pit by vertical synchronous full-reverse construction method

Similar Documents

Publication Publication Date Title
CN104314081A (en) Deep foundation pit driftway-free basement concrete pumping construction device
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN104612713A (en) Super-shallow-buried section tunnel construction method
CN203795446U (en) Steel-plate concrete caisson
CN102587663A (en) Concrete construction process of steel tube columns of super-high-rise building
CN203834926U (en) Formwork erecting structure for bare concrete basement exterior wall
CN204152530U (en) Water burst tunnel tunnel face seepproof screen
CN103216102A (en) Construction method for tremie guiding pouring inside steel pipe column
CN204059420U (en) Late poured band support structure
CN204510989U (en) Multistage concrete towers cylinder integral structure
CN204139172U (en) A kind of deep foundation ditch is without packway concrete of basement pumping construction device
CN204000885U (en) Metro Deep Excavation concrete support hangs mould mould
CN204359161U (en) A kind of cooling stack with horizontal adapter ring girder construction
CN203498850U (en) Raft foundation reinforcement support of super high-rising building
CN204001705U (en) Outer wall of basement single surface formwork constructing structure based on earth anchor truss
CN207485469U (en) A kind of light-duty flexible retaining wall structure
CN203008470U (en) Roof guyed tower
CN204139190U (en) A kind of Liftable preformed bricks fetal membrane
CN204080820U (en) A kind of concrete structure foundation ditch support replacement device
CN205242407U (en) A cluster pipe, chute combination system for deep basal pit concrete placement
CN204000936U (en) Outer wall of basement single surface formwork system based on fastener type steel pipe earth anchor truss
CN202466591U (en) Device for suppressing disturbance of foundation soil during removal of steel plate pile
CN207512742U (en) A kind of pipe-line system for the downward pumping concrete of deep basal pit
CN205711756U (en) A kind of distance vertical prestressing pipeline pneumatic mortar device
CN205100354U (en) Side slope with escape canal

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20150128