CN104297679B - Early warning method of breaker tripping messages - Google Patents

Early warning method of breaker tripping messages Download PDF

Info

Publication number
CN104297679B
CN104297679B CN201410596989.7A CN201410596989A CN104297679B CN 104297679 B CN104297679 B CN 104297679B CN 201410596989 A CN201410596989 A CN 201410596989A CN 104297679 B CN104297679 B CN 104297679B
Authority
CN
China
Prior art keywords
information
circuit breaker
early warning
trip
fault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410596989.7A
Other languages
Chinese (zh)
Other versions
CN104297679A (en
Inventor
包磊
王纪军
许建刚
李辉
孙波
张斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Jiangsu Electric Power Information Technology Co Ltd
Zhenjiang Power Supply Co of Jiangsu Electric Power Co
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Jiangsu Electric Power Information Technology Co Ltd
Zhenjiang Power Supply Co of Jiangsu Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Jiangsu Electric Power Information Technology Co Ltd, Zhenjiang Power Supply Co of Jiangsu Electric Power Co filed Critical State Grid Corp of China SGCC
Priority to CN201410596989.7A priority Critical patent/CN104297679B/en
Publication of CN104297679A publication Critical patent/CN104297679A/en
Application granted granted Critical
Publication of CN104297679B publication Critical patent/CN104297679B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Telephonic Communication Services (AREA)

Abstract

The invention discloses an early warning method of breaker tripping messages. The early warning method comprises the steps of 1), configuring and obtaining operation information of a breaker, sending a timed task of the early warning messages, setting the execution frequency of the timed task and binding a designated mobile phone; 2), obtaining the operation state information of the breaker, analyzing fault tripping information and non-fault tripping information according to the stripping information and sending the information to the designated mobile phone; 3), processing the breaker with fault tripping. The early warning method is suitable for monitoring and early warning of fault tripping of the breaker in a transformer substation, and the risk pre-control level of a production system power grid is increased through smart message warning.

Description

Circuit breaker trip message method for early warning
Technical field
The present invention relates to chopper, more particularly to circuit breaker trip message method for early warning, belong to electrical equipment technical field.
Background technology
With the continuous development of social economy and science and technology, the reliability of power transformation network operation is more and more important.In power transformation Circuit breaker failure tripping operation smart message warning function is added during network operation, circuit breaker failure not only can be immediately treated, really Protect the reliability of operation of power networks;Foundation can also be provided for operation of power networks, so as to improve power grid risk pre-control level.
Circuit breaker failure tripping operation early warning is the emphasis of production management system (PMS) power transformation early warning part, and it can carry in time Awake substation operation and maintenance team staff circuit breaker failure tripping operation information, guide field personnel carry out recovery operation immediately to help management level. In prior art, power transformation O&M crewmember may only poll by two ways circuit breaker failure tripping operation information:1. enter Enter scheduling system to be analyzed breaker data;2. scene checks to equipment one by one and carries out artificial judgment.Both modes The drawbacks of having respective, although first kind of way can inquire circuit breaker trip information, cannot judge it is fault trip Or non-faulting tripping operation.Although the second way precisely, takes substantial amounts of manpower and materials.Add in production system disconnected Road device fault trip monitoring and early warning technology, can remind teams and groups personnel to understand circuit breaker failure tripping operation information, so not only in time One by one review time of the manpower to equipment is reduced, and can allow teams and groups personnel that corresponding process is more timely done to equipment, So as to improve production system power grid risk pre-control level.
The content of the invention
It is an object of the invention to provide a kind of circuit breaker trip message method for early warning, in order to overcome PMS in prior art The problem that the early warning of system circuit breaker fault trip is present, the method will be in high-risk open circuit in time by Unified frame platform Device information and operation information send to related personnel and are allowed to recognize immediately corresponding situation, timely process so as to make. Simultaneously by being periodically analyzed to circuit breaker failure tripping operation information, the recent ruuning situation of all choppers is grasped, is from now on The strong data basis of maintenance, buying accumulation, provide preferably guarantee for electric power netting safe running.
The purpose of the present invention is achieved by the following technical programs:
A kind of circuit breaker trip message method for early warning, the method step are as follows:
1) configuration obtains chopper operation information and sends the timed task of early warning information, and sets timed task execution Frequency, and tie nation's designated mobile phone;
2) obtain the High Voltage Circuit Breaker Condition information, and according to tripping operation information analysiss be out of order tripping operation and non-faulting tripping operation believe Breath, sends to designated mobile phone;
3) chopper of fault trip is processed:
(1) todo list is sent to production system, log in production system and check the todo list;
(2) send note to designated mobile phone, log in immediately mobile terminal of mobile telephone check specific fault trip information and The operation information of other equipment in transformer station;
(3) send a message in the wechat of designated mobile phone, scene is made in wechat group immediately and instruct work;
(4) Processing for removing is made to this todo list in production system after having processed.
The purpose of the present invention can also be further realized by following technical measures:
Aforementioned circuit breaker trip message method for early warning, wherein step 1) it is specific as follows:
In production system bus registration by way of configuring timing tasks, obtain chopper operation information frequency be Five minutes once, and the frequency for sending early warning information is arranged manually by user, is defaulted as 12 hours once;Mobile communication is kept to lead to Freely, and guarantee on mobile phone, to be mounted with wechat and mobile terminal.
Aforementioned circuit breaker trip message method for early warning, wherein step 2) fault trip and non-faulting trip information analysis step It is rapid as follows:
(1) scheduling system break road device real-time running state information is obtained, circuit-breaker status is obtained according to the change of state The state of the information for changing, i.e. chopper is become out by conjunction or becomes to close by opening, and the time that state changes;
(2) judge the circuit breaker trip reason:
Obtain the circuit breaker voltage, electric current, power information in scheduling system;Obtain the platform of chopper in production management system Account information, including rated current, unit type, date of putting into operation;
It is as follows according to the method for voltage x current information analysiss circuit breaker trip reason:
A. chopper be located loop on electric current, it is active, idle be zero, explanation is normal divide-shut brake, is not belonging to failure Tripping operation;
B. chopper by open become to close after become out immediately and by conjunction, place loop current is undergone mutation, and explanation is short The fault trip that pass rises, investigates reason immediately;
C. chopper by open become close after a period of time and become out by conjunction, place loop current more than chopper it is specified Electric current, illustrates fault trip caused by circuit overload, investigates reason immediately.
Aforementioned circuit breaker trip message method for early warning, wherein step 2) also include mistrip analysis method, step is as follows:Jump Before lock, meter is normal, fault-free is caused in electrical network electric current, voltage pulsation, is judged as breaker operation mechanism misoperation, belongs to False tripping, is resumed operation as early as possible.
Aforementioned circuit breaker trip message method for early warning, wherein step 2) also include mistrip analysis method, step is as follows:Directly Flow back to road insulation to decline, send electric current, voltage pulsation that fault-free in ground signalling, electrical network is caused, be judged as that 2 points of direct current connects Ground, belongs to false tripping, resumes operation as early as possible.
Compared with prior art, the invention has the beneficial effects as follows:The present invention, in time will be in high by Unified frame platform The breaker information and operation information of danger is sent to related personnel, recognizes immediately corresponding situation, so as to make timely Process.Simultaneously by being periodically analyzed to circuit breaker failure tripping operation information, you can recognize that all load transformers are recent Ruuning situation is maintenance from now on, purchase the strong data basis of accumulation, provides preferably guarantee for electric power netting safe running.This It is bright circuit breaker failure to be tripped monitoring and early warning in Substation Station, remind to improve production system electricity by smart message Net Risk Pre-control level.
Description of the drawings
Fig. 1 is the flow chart of the present invention.
Specific embodiment
The invention will be further described with specific embodiment below in conjunction with the accompanying drawings.
As shown in figure 1, circuit breaker trip message method for early warning step is as follows:
1) configuration obtains chopper operation information and sends the timed task of early warning information, and sets timed task execution Frequency, and tie nation's designated mobile phone;It is specific as follows:
In production system bus registration by way of configuring timing tasks, obtain chopper operation information frequency be Five minutes once, and the frequency for sending early warning information is arranged manually by user, is defaulted as 12 hours once;
Keep mobile communication unobstructed, and guarantee on mobile phone, to be mounted with wechat and mobile terminal.
2) obtain the High Voltage Circuit Breaker Condition information, and according to tripping operation information analysiss be out of order tripping operation and non-faulting tripping operation believe Breath, sends to designated mobile phone;Fault trip and non-faulting trip information analytical procedure are as follows:
(1) scheduling system break road device real-time running state information is obtained, circuit-breaker status is obtained according to the change of state The state of the information for changing, i.e. chopper is become out by conjunction or becomes to close by opening, and the time that state changes;
(2) judge the circuit breaker trip reason:
Obtain the circuit breaker voltage, electric current, power information in scheduling system;Obtain the platform of chopper in production management system Account information, including rated current, unit type, date of putting into operation;
It is as follows according to the method for voltage x current information analysiss circuit breaker trip reason:
A. chopper be located loop on electric current, it is active, idle be zero, explanation is normal divide-shut brake, is not belonging to failure Tripping operation;
B. before tripping, meter is normal, fault-free is caused in electrical network electric current, voltage pulsation, is judged as breaker operation mechanism Misoperation, belongs to false tripping, resumes operation as early as possible;
C. DC loop insulation declines, and sends electric current, voltage pulsation that fault-free in ground signalling, electrical network is caused, judges For direct current two points ground fault, belong to false tripping, resume operation as early as possible;
D. chopper by open become to close after become out immediately and by conjunction, place loop current is undergone mutation, and explanation is short The fault trip that pass rises, investigates reason immediately;
E. chopper by open become close after a period of time and become out by conjunction, place loop current more than chopper it is specified Electric current, illustrates fault trip caused by circuit overload, investigates reason immediately.
3) chopper of fault trip is processed:
(1) todo list is sent to production system, log in production system and check the todo list;
(2) send note to designated mobile phone, log in immediately mobile terminal of mobile telephone check specific fault trip information and The operation information of other equipment in transformer station;
(3) send a message in the wechat of designated mobile phone, scene is made in wechat group immediately and instruct work;
(4) Processing for removing is made to this todo list in production system after having processed.
In addition to the implementation, the present invention can also have other embodiment, all employing equivalents or equivalent transformation shape Into technical scheme, all fall within the protection domain of application claims.

Claims (5)

1. a kind of circuit breaker trip message method for early warning, it is characterised in that the method step is as follows:
1) configuration obtains the High Voltage Circuit Breaker Condition information and sends the timed task of early warning information, and sets timed task execution Frequency, and bundle designated mobile phone;
2) obtain the High Voltage Circuit Breaker Condition information, and according to tripping operation information analysiss be out of order tripping operation and non-faulting trip information, send out Deliver to designated mobile phone;
3) chopper of fault trip is processed:
(1) todo list is sent to production system, log in production system and check the todo list;
(2) note is sent to designated mobile phone, log in mobile terminal of mobile telephone immediately and check specific fault trip information and power transformation The operation information of other equipment in standing;
(3) send a message in the wechat of designated mobile phone, scene is made in wechat group immediately and instruct work;
(4) Processing for removing is made to this todo list in production system after having processed.
2. circuit breaker trip message method for early warning according to claim 1, it is characterised in that step 1) it is specific as follows:
In production system bus registration by way of configuring timing tasks, obtain the High Voltage Circuit Breaker Condition information frequency be Five minutes once, and the frequency for sending early warning information is arranged manually by user, is defaulted as 12 hours once;
Keep designated mobile phone communication unobstructed, and guarantee on designated mobile phone, to be mounted with wechat and mobile terminal of mobile telephone.
3. circuit breaker trip message method for early warning according to claim 1, it is characterised in that step 2) fault trip and Non-faulting trip information analytical procedure is as follows:
(1) scheduling system break road device running state information is obtained, circuit-breaker status is obtained according to the change of state and is changed Information, i.e. the state of chopper is become out by conjunction or becomes to close by opening, and the time that state changes;
(2) judge the circuit breaker trip reason:
Obtain the circuit breaker voltage, electric current and power information in scheduling system;The account information of chopper in production system is obtained, Including rated current, unit type and date of putting into operation;
It is as follows according to the method for voltage and current information analysiss circuit breaker trip reason:
A. chopper be located loop on electric current, it is active, idle be zero, explanation is normal divide-shut brake, is not belonging to fault trip;
B. chopper by open become to close after become out immediately and by conjunction, place loop current is undergone mutation, and explanation is that short circuit is drawn The fault trip for rising, investigates reason immediately;
C. chopper by open become close after a period of time and become out by conjunction, place loop current be more than the specified electricity of chopper Stream, illustrates fault trip caused by circuit overload, investigates reason immediately.
4. circuit breaker trip message method for early warning according to claim 3, it is characterised in that step 2) also include mistrip Analysis method, step are as follows:Before tripping operation, meter is normal, and electric current and voltage pulsation that in electrical network, fault-free is caused are judged as open circuit Device operating mechanism misoperation, belongs to false tripping, resumes operation as early as possible.
5. circuit breaker trip message method for early warning according to claim 3, it is characterised in that step 2) also include mistrip Analysis method, step are as follows:DC loop insulation declines, and sends ground signalling, fault-free is caused in electrical network electric current and voltage Fluctuation, is judged as direct current two points ground fault, belongs to false tripping, resume operation as early as possible.
CN201410596989.7A 2014-10-30 2014-10-30 Early warning method of breaker tripping messages Active CN104297679B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410596989.7A CN104297679B (en) 2014-10-30 2014-10-30 Early warning method of breaker tripping messages

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410596989.7A CN104297679B (en) 2014-10-30 2014-10-30 Early warning method of breaker tripping messages

Publications (2)

Publication Number Publication Date
CN104297679A CN104297679A (en) 2015-01-21
CN104297679B true CN104297679B (en) 2017-05-17

Family

ID=52317482

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410596989.7A Active CN104297679B (en) 2014-10-30 2014-10-30 Early warning method of breaker tripping messages

Country Status (1)

Country Link
CN (1) CN104297679B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110429556A (en) * 2019-07-04 2019-11-08 天津市中力神盾电子科技有限公司 Breaker opening and closing event recording method and system
CN111047464B (en) * 2019-12-04 2023-06-13 国网湖南省电力有限公司 Automatic short message sending method and system for power system fault tripping

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102565572A (en) * 2011-12-04 2012-07-11 江苏省电力公司南京供电公司 Platform and method for judging fault of match power grid
CN102684311A (en) * 2012-06-15 2012-09-19 河南省电力公司郑州供电公司 10 kilovolt (KV) cascade switching station graded protection device and protection method thereof
CN102738896A (en) * 2012-06-15 2012-10-17 河南省电力公司郑州供电公司 HP-9000 type switching station fault treatment system
CN202679073U (en) * 2012-06-15 2013-01-16 河南省电力公司郑州供电公司 HP-9000 type switching station fault processing system
CN203259188U (en) * 2013-04-01 2013-10-30 河南理工大学 Vacuum section switch fault pre-warning system for urban and rural power supply line

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102007006385B4 (en) * 2007-02-08 2019-02-14 Infineon Technologies Ag A circuit arrangement, a processor with a circuit arrangement, an electrical device and a method for operating a circuit arrangement
US8923113B2 (en) * 2012-06-27 2014-12-30 Cisco Technology, Inc. Optimizations in multi-destination tree calculations for layer 2 link state protocols

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102565572A (en) * 2011-12-04 2012-07-11 江苏省电力公司南京供电公司 Platform and method for judging fault of match power grid
CN102684311A (en) * 2012-06-15 2012-09-19 河南省电力公司郑州供电公司 10 kilovolt (KV) cascade switching station graded protection device and protection method thereof
CN102738896A (en) * 2012-06-15 2012-10-17 河南省电力公司郑州供电公司 HP-9000 type switching station fault treatment system
CN202679073U (en) * 2012-06-15 2013-01-16 河南省电力公司郑州供电公司 HP-9000 type switching station fault processing system
CN203259188U (en) * 2013-04-01 2013-10-30 河南理工大学 Vacuum section switch fault pre-warning system for urban and rural power supply line

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
500 kV GIS断路器控制回路故障的有效处理;郝飞进等;《现代工业经济和信息化》;20131130(第60期);第62-63、65页 *

Also Published As

Publication number Publication date
CN104297679A (en) 2015-01-21

Similar Documents

Publication Publication Date Title
CN103607042B (en) The distribution network failure processing method of long fault indicator for overhead lines towards outskirts of a town
CN105048303A (en) Intelligent control distribution box system capable of remotely early warning
CN103490514B (en) Rural power distribution grid electricity leakage protection device monitoring, controlling and fault detecting method
CN104701986A (en) Intelligent terminal of box-type substation
CN105226814A (en) GPRS Based Intelligent Control distribution box system
CN107968486A (en) A kind of method for scheduling task of intelligent power distribution room monitoring system
CN102299563A (en) Digital-analog (DA) protection method for intelligent distribution network
CN103558494A (en) Online monitoring system and monitoring method for turn-to-turn short circuit of power distribution transformer
CN201876517U (en) Atmosphere over-voltage intrusion wave monitoring system
CN104297679B (en) Early warning method of breaker tripping messages
CN204408024U (en) A kind of 10kV circuit operation information acquisition system
CN108306264A (en) A kind of intelligent distributed feeder line fault of distribution network immediate processing method
CN203596664U (en) Power-theft real-time early-warning system
CN207799852U (en) A kind of intelligent electric fire hazard monitoring early warning system
CN104135079A (en) Failure processing method for intelligent power distribution network comprising distributed power supply
CN203368148U (en) Intelligent substation network message recording analyzer system
CN202956465U (en) Power distribution line fault detection device
CN102915513A (en) Typhoon risk information processing method for power grid equipment
CN102937690A (en) Lightning stroke failure disconnection positioning method based on information interaction
CN103235224B (en) Grid fault analytical method
CN201774316U (en) Transmission and distribution line real-time GSM (Global System For Mobile Communications) network monitoring system
CN107967783A (en) A kind of intelligent electric fire hazard monitoring early warning system and method
CN205565886U (en) Intelligent substation SF6 breaker state monitored control system
CN106410961A (en) Smart distribution network device monitoring method
CN110445107B (en) Processing method for 110kV line fault tripping

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant