Talus unloading reinforcement structure for karst depression Download PDFInfo
- Publication number
- CN104294832A CN104294832A CN201410563085.4A CN201410563085A CN104294832A CN 104294832 A CN104294832 A CN 104294832A CN 201410563085 A CN201410563085 A CN 201410563085A CN 104294832 A CN104294832 A CN 104294832A
- Authority
- CN
- China
- Prior art keywords
- talus
- breast boards
- pile
- antislide
- karst depression
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
Abstract
The invention belongs to the field of talus protection and control and provides a talus unloading reinforcement structure for karst depression. The talus unloading reinforcement structure comprises a protective screen, supporting anchor rods and vertical breast boards. The supporting anchor rods are arranged vertically and fixed onto the vertical breast boards, the lower ends of the supporting anchor rods extend to the outer sides of the vertical breast boards, one side of the protective screen is fixed to the upper ends of the vertical breast boards, and anchor nails are fixed onto the protective screen. The problems that existing anchor rod reinforcement methods which can only reinforce talus peripheries are difficult to enable the taluses to form a whole so as to be limited in reinforcement effect while using anti-slide piles for reinforcement can evidently increase engineering investment and construction period input even though reinforcement effects are remarkable are solved.
Description
Technical field
The present invention relates to talus reinforced structure, belong to talus and administer field.
Background technology
Talus refers generally to the accumulation body comprising falling rocks landwaste not of uniform size being positioned at high steep toe place, avalanche slope.Its relevant governing problem is the difficult problem that geotechnical engineering circle faced and paid close attention to always.Owing to lacking relevant authority file and technical support so far both at home and abroad, this problem is still in partly grope, the semiempirical extensive stage.Grow area at karst, especially there is the carbonate rock area of great amount of soluble in Southwestern China portion, strong corrosion often forms large-area karst depression, and mound, surrounding karst peak, depression, sinkhole, cliff, spring are generally all comparatively grown; Lapies, fluid bowl and corrosion broad slit dense distribution; There are karst and underground river distribution in underground, and place periphery often spreads all over Dangerous Rock Body, block stone (talus) layer.And the talus of karst depression and the talus of general significance different, because of under gravity, due to the control of depression landform, it is subject to the effect of lateral restraint and has class granary phenomenon.And usually must carry out excavate and unload to the talus of this form to meet requirement of engineering in the karst depression engineering of reality, it certainly will cause talus stresses re-distribution and produce new geological disaster.Therefore, how by a kind of effective method and measure, while can ensureing the stability under the talus excavate and unload effect of depression, can also effectively prevent rock mass above the talus of depression from producing secondary disaster, be the engineering challenge needing in karst depression engineering to solve.
Summary of the invention
The object of the invention is to: a kind of karst depression talus off-load reinforced structure is provided, usually must carry out excavate and unload to karst depression talus to meet requirement of engineering to solve in actual karst depression engineering, it certainly will cause talus stresses re-distribution and produce the problem of new geological disaster.
The solution of the present invention is as follows: karst depression talus off-load reinforced structure, comprises antislide pile 1, is all fixedly installed breast boards 2 between any two adjacent antislide piles 1, and the pile body top of antislide pile 1 is provided with hat beam 3, and hat beam 3 is equipped with passive protection net 4;
Described hat beam 3 comprises pedestal 31 and column 32, and pedestal 31 is fixedly installed on the upper end of antislide pile 1 or breast boards 2, and the lower end of column 32 is fixedly installed on pedestal 31, and described passive protection net 4 is laid on column 32;
Described reinforcing device also includes anchor line 5 and location holdfast 6, one end of anchor line 5 is fixed on the upper end of column 32, the other end of anchor line 5 is fixed on holdfast 6, after stretching anchor line 5, holdfast 6 is embedded in the talus on the upside of antislide pile 1, for reinforcing for column 32, when preventing Rolling Stone, the upper end of column 32 is due to stressed excessive and collapse.
Described antislide pile 1 is square-section socketed pile.
Any two antislide piles 1 are parallel mutually, and any one antislide pile 1 all parallels with the breast boards 2 be fixed on this antislide pile 1.
Described antislide pile 1 and breast boards 2 are reinforced concrete structure.
The bottom of described breast boards 2 offers the spilled water hole 7 at through breast boards 2 two ends.
Compared with prior art, major advantage is as follows in the present invention:
When excavate and unload is carried out to karst depression talus, described karst depression talus off-load reinforced structure is installed in the upstream of off-load place before excavation, the sliding force of upstream talus is born by antislide pile and breast boards, prevent the upstream talus when off-load from occurring collapsing, avoid the excavation because of downstream talus to cause talus stresses re-distribution, thus produce the problem of new geological disaster;
Effectively can be stopped the landing of upstream Rolling Stone by the passive protection net of Guan Liang and upper laying thereof, when preventing downstream from constructing, upstream Rolling Stone landing causes security incident, eliminates potential safety hazard.
Accompanying drawing explanation
Fig. 1 is the present invention's cross-sectional view in use;
Fig. 2 is the present invention's main TV structure schematic diagram in use.
Detailed description of the invention
For making the object, technical solutions and advantages of the present invention clearly, below the present invention is described in further detail,
See figures.1.and.2, the embodiment of the present invention provides karst depression talus off-load reinforced structure, comprising:
Antislide pile 1, antislide pile 1 is square-section socketed pile, breast boards 2 is all fixedly installed between any two adjacent antislide piles 1, breast boards 2 is mainly used in preventing Study on Rock from extruding from the space between antislide pile 1, the bottom of described breast boards 2 offers the spilled water hole 7 at through breast boards 2 two ends, spilled water hole 7 is for discharging talus internal water accumulation, prevent ponding from too much causing antislide pile 1 or breast boards 2 to collapse, described antislide pile 1 and breast boards 2 are reinforced concrete structure, the pile body top of antislide pile 1 is provided with hat beam 3, described hat beam 3 comprises pedestal 31 and column 32, pedestal 31 is fixedly installed on the upper end of antislide pile 1 or breast boards 2, the lower end of column 32 is fixedly installed on pedestal 31, described passive protection net 4(preferred flexible net) be laid on column 32 that (described hat beam 3 also can adopt other braced structuress, such as lower end embeds the bar construction of antislide pile 1 or breast boards 2, passive protection net 4 is laid on and stretches on the bar construction of antislide pile 1 or breast boards 2 outside, realize the passive protection that Rolling Stone tumbles),
Described reinforcing device also includes anchor line 5 and location holdfast 6, one end of anchor line 5 is fixed on the upper end of column 32, the other end of anchor line 5 is fixed on holdfast 6, after stretching anchor line 5, holdfast 6 is embedded in the talus on the upside of antislide pile 1, for reinforcing for column 32, when preventing Rolling Stone, the upper end of column 32 is due to stressed excessive and collapse.
Preferably, any two antislide piles 1 are parallel mutually, and any one antislide pile 1 all parallels with the breast boards 2 be fixed on this antislide pile 1.
(the method is only wherein a kind of feasible implementation to concrete reinforcement means, for construction and the use of structure strong described in explaining, not as a limitation of the invention) as follows: first by antislide pile 1 build-in in the forward position of karst depression talus with gear talus a downslide, pile body socket length is not less than 4 meters (the concrete degree of depth is determined according to the volume of landform and Study on Rock), breast boards 2 is set between each pile body, first assembling reinforcement during construction, again steel form is installed after colligation, insert pvc pipe (preferred 100mm aperture) in the position, hole of spilled water hole 7 simultaneously, concrete (preferred more than C30 concrete) is finally made to build, breast boards 2 is able to shaping,
Breast boards 2 construction and maintenance is complete, namely carries out the construction being preced with beam 3.Hat beam 3 is also reinforced concrete structure, first assembling reinforcement, again formwork during construction, finally with concreting and maintenance, the complete installation namely carrying out passive protection net 4 of maintenance, passive protection net 4 is RXI-150 type net preferably, one end of anchor line 5 is fixed on the upper end of column 32, the other end of anchor line 5 is fixed on holdfast 6, embeds in the talus on the upside of antislide pile 1 after stretching anchor line 5 by holdfast 6, for reinforcing for column 32, when preventing Rolling Stone, the upper end of column 32 is due to stressed excessive and collapse.
Claims (7)
1. karst depression talus off-load reinforced structure, comprise antislide pile (1), it is characterized in that: be all fixedly installed breast boards (2) between any two adjacent antislide piles (1), the pile body top of antislide pile (1) is provided with Guan Liang (3), Guan Liang (3) is equipped with passive protection net (4).
2. karst depression talus off-load reinforced structure according to claim 1, it is characterized in that: described Guan Liang (3) comprises pedestal (31) and column (32), pedestal (31) is fixedly installed on the upper end of antislide pile (1) or breast boards (2), the lower end of column (32) is fixedly installed on pedestal (31), and described passive protection net (4) is laid on column (32).
3. karst depression talus off-load reinforced structure according to claim 1, it is characterized in that: also include anchor line (5) and location holdfast (6), one end of anchor line (5) is fixed on the upper end of column (32), and the other end of anchor line (5) is fixed on holdfast (6).
4. karst depression talus off-load reinforced structure according to claim 1, is characterized in that: described antislide pile (1) is square-section socketed pile.
5. karst depression talus off-load reinforced structure according to claim 2, it is characterized in that: any two antislide piles (1) are parallel mutually, and any one antislide pile (1) all parallels with the breast boards (2) be fixed on this antislide pile (1).
6. karst depression talus off-load reinforced structure according to claim 1, is characterized in that: described antislide pile (1) and breast boards (2) are reinforced concrete structure.
7. karst depression talus off-load reinforced structure according to claim 1, is characterized in that: the bottom of described breast boards (2) offers the spilled water hole (7) at through breast boards (2) two ends.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410563085.4A CN104294832A (en) | 2014-10-22 | 2014-10-22 | Talus unloading reinforcement structure for karst depression |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410563085.4A CN104294832A (en) | 2014-10-22 | 2014-10-22 | Talus unloading reinforcement structure for karst depression |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104294832A true CN104294832A (en) | 2015-01-21 |
Family
ID=52314762
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410563085.4A Pending CN104294832A (en) | 2014-10-22 | 2014-10-22 | Talus unloading reinforcement structure for karst depression |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104294832A (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2151843C1 (en) * | 1999-12-24 | 2000-06-27 | Ефремов Леонид Григорьевич | Lattice for localization of material |
KR100556668B1 (en) * | 2005-08-12 | 2006-03-10 | (주)천일기술단 | Structure of a slop reinforced of carrying out by physical environment |
CN102031760A (en) * | 2010-12-17 | 2011-04-27 | 河南省新开元路桥工程咨询有限公司 | Anti-rockfall method for subgrade in rock deposit zone |
CN202610815U (en) * | 2012-06-19 | 2012-12-19 | 四川奥特机械设备有限公司 | Separating passive protective net |
CN203361033U (en) * | 2013-05-27 | 2013-12-25 | 中铁工程设计咨询集团有限公司 | Protective device for intercepting falling rocks of through cut |
CN103643687A (en) * | 2013-12-25 | 2014-03-19 | 中铁二院工程集团有限责任公司 | Frame type anti-skid cutting structure |
CN204212163U (en) * | 2014-10-22 | 2015-03-18 | 贵州正业工程技术投资有限公司 | Karst depression talus off-load reinforced structure |
-
2014
- 2014-10-22 CN CN201410563085.4A patent/CN104294832A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2151843C1 (en) * | 1999-12-24 | 2000-06-27 | Ефремов Леонид Григорьевич | Lattice for localization of material |
KR100556668B1 (en) * | 2005-08-12 | 2006-03-10 | (주)천일기술단 | Structure of a slop reinforced of carrying out by physical environment |
CN102031760A (en) * | 2010-12-17 | 2011-04-27 | 河南省新开元路桥工程咨询有限公司 | Anti-rockfall method for subgrade in rock deposit zone |
CN202610815U (en) * | 2012-06-19 | 2012-12-19 | 四川奥特机械设备有限公司 | Separating passive protective net |
CN203361033U (en) * | 2013-05-27 | 2013-12-25 | 中铁工程设计咨询集团有限公司 | Protective device for intercepting falling rocks of through cut |
CN103643687A (en) * | 2013-12-25 | 2014-03-19 | 中铁二院工程集团有限责任公司 | Frame type anti-skid cutting structure |
CN204212163U (en) * | 2014-10-22 | 2015-03-18 | 贵州正业工程技术投资有限公司 | Karst depression talus off-load reinforced structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106499413B (en) | A kind of Shallow-buried section tunnel stratum consolidation construction method | |
CN105239586B (en) | Method for supporting foundation pit by adopting support structure | |
CN109209389B (en) | Construction method for entering semi-open and semi-closed tunnel | |
CN104532857A (en) | Flexible expansion reduced ecological slope protection construction | |
CN103938634B (en) | A kind of deep foundation pit supporting structure and construction method | |
CN105332380B (en) | Strut changing structure and method for underground building | |
CN103696784A (en) | Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure | |
CN105220654A (en) | A kind of ruggedized construction of earth and rockfill dam and construction method thereof | |
CN103437370A (en) | Method and supporting structure for slip resisting and soil retaining of abrupt slope | |
CN102704497B (en) | RPW (ranked position weight) process for treating high fill slope | |
CN104594297B (en) | A kind of double face slab rock-fill dams and construction method thereof | |
CN103806451B (en) | A kind of anchorage type foundation ditch strengthening structure and construction method thereof | |
CN103334450B (en) | Construction method of pile precast slab retaining wall with drainage ditch | |
CN205205832U (en) | Structure is propped in trading of underground building | |
CN203668942U (en) | Pile protective self-hanging thin plate in supporting structure of deep foundation pit | |
CN204212163U (en) | Karst depression talus off-load reinforced structure | |
CN204356788U (en) | Flexibility subtracts swollen ecological revetment structure | |
CN109577322A (en) | A kind of constructing device for inside soil body existing pile foundation pile extension | |
CN204174636U (en) | In-situ deposited prefabricated combined retaining wall structure | |
CN106567365B (en) | Earth and rockfill dam longitudinal reinforcement construction method | |
CN202730796U (en) | Existing retaining wall rib plate type unloading reinforcing structure | |
CN204112348U (en) | Talus integral reinforcement ruggedized construction | |
CN203821399U (en) | Deep foundation pit supporting structure | |
CN206204970U (en) | A kind of high fill foundation weeper drain | |
CN107630706A (en) | A kind of tunnel bottom structure and construction method for eliminating highland nip tunnel inverted arch protuberance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150121 |
|
RJ01 | Rejection of invention patent application after publication |