Large-sized prefabricated part hoisting device and method Download PDFInfo
- Publication number
- CN104229621A CN104229621A CN201410420095.2A CN201410420095A CN104229621A CN 104229621 A CN104229621 A CN 104229621A CN 201410420095 A CN201410420095 A CN 201410420095A CN 104229621 A CN104229621 A CN 104229621A
- Authority
- CN
- China
- Prior art keywords
- fixed block
- shaped
- pin
- falling
- bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Load-Engaging Elements For Cranes (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The invention discloses a large-sized prefabricated part hoisting device and a hoisting method, relates to the technical field of the hoisting of a large-sized prefabricated part, and particularly belongs to a device and a method for hoisting the large-sized prefabricated part by utilizing an inverted T-shaped hoisting rod. The large-sized prefabricated part hoisting device is provided with an inverted T-shaped rod (5) and an auxiliary device, and is characterized in that the auxiliary device comprises a fixed block (2) and a locking device, the locking device consists of a pin hole (3) which is welded on the inverted T-shaped rod and a pin (4) which is matched with the pin hole to use, an insertion hole (6) is formed in the fixed block, the fixed block is arranged on the upper side of a T-shaped head (1) of the inverted T-shaped rod, and a rotating handle (7) is arranged above the inverted T-shaped rod. The hoisting method comprises the steps of installing a lifting appliance on the ground and installing parts under the water, and removing the lifting appliances under the water. The large-sized prefabricated part hoisting device has the beneficial effects of simplicity in operation, safety, reliability and high working efficiency.
Description
Technical field
The present invention relates to Large Precast Members hoisting technology field, belong to the devices and methods therefor that a kind of use suspension rod of falling T-shaped carries out large scale prefabricated lifting especially.
Background technology
At present, along with the development of water transport engineering project technology, concrete lifting component technology is increasingly mature, but the overwhelming majority adopts suspension ring and " suspension rod of falling T-shaped " to carry out concrete lifting component as suspender in the middle of harbour, Wharf Construction, when adopting " suspension rod of falling T-shaped " to lift, because its hole for hoist is reserved comparatively dark, easily cause land peace suspender, pluck the phenomenons such as suspender difficulty, work efficiency are low under water.
Summary of the invention
The object of the present invention is to provide a kind of novel Large Precast Members hanging apparatus and method, to reach simple and quick, to reduce costs, increase substantially the object of work efficiency.
Large Precast Members hanging apparatus provided by the present invention, there is the bar of falling T-shaped and auxiliary device, it is characterized in that, described auxiliary device comprises fixed block and securing arrangement, securing arrangement be welded on pin-and-hole on the bar of falling T-shaped and with it with the use of pin, fixed block is provided with jack, and fixed block is positioned on the upside of the T prefix of the bar of falling T-shaped, arranges rotary handle above the bar of falling T-shaped.
Large Precast Members hanging method provided by the present invention, is characterized in that, comprise the steps:
1) the land installation of suspender
Step 1-1, the suspension rod of falling T-shaped and auxiliary device winch to above component by operating personal simultaneously, and it is synchronously moved to component and reserves directly over hole for hoist by workmen;
Step 1-2, makes fixed block and T prefix on same level axis, and the large hook of crane ship slowly drops to above component and carries out coarse positioning;
Step 1-3, crane ship continues to weigh hook in the hand, and fixed block and T-shaped bar at maintenance fixed block and T prefix, are put into component and reserved hole for hoist, and pinned in jack pin being inserted fixed block under the state of same level axis by workmen;
Step 1-4, after fixed block arrives position of rotation, stop declining, pull out on pin, workman, by T-shaped bar 90-degree rotation, makes the axes normal of T prefix and fixed block, and pin is stayed in pin-and-hole, and workman withdraws scene, and crane ship ship starts lifting;
2) component is installed and suspender excision under water
Step 2-1, crane ship is by Large Precast Members handling under water, and prefabricated components are arranged on design attitude by Divers under the guidance of technology people;
Step 2-2, after Components installation completes, crane ship is weighed hook in the hand and is relaxed one's efforts to steel rope, and Divers puts in place;
Step 2-3, Divers will the bar of falling T-shaped rotate to fixed block same level axis, insert pin, and withdraw to safety zone;
Step 2-4, because fixed block can keep the suspension rod of falling T-shaped to reserve vertical center in hole for hoist at component, suspender can successfully be left the water by crane ship;
Step 2-5, enters the lifting flow process of next component.
Present invention effectively prevents the generation of the phenomenons such as the hole clipping that existing Large Precast Members hoisting process is installed, excision T-shaped bar easily occurs, effectively shorten the bottom time of Divers, reduce the probability of occurrence of submarine sickness, ensured its personal safety; This method has easy and simple to handle, safe and reliable, that work efficiency is high good effect.
Accompanying drawing explanation
Accompanying drawing part discloses specific embodiments of the invention, wherein
Fig. 1, fixed block birds-eye view of the present invention;
Fig. 2, the structural representation of hanging apparatus of the present invention;
Fig. 3, hanging apparatus of the present invention enters concrete test block view;
Fig. 4, view after T-shaped bar 90-degree rotation of the present invention.
Detailed description of the invention
As shown in Figure 1 and Figure 2, Large Precast Members hanging apparatus provided by the present invention, there is the bar of falling T-shaped 5 and auxiliary device, wherein, described auxiliary device comprises fixed block 2 and securing arrangement, securing arrangement be welded on pin-and-hole 3 on the bar of falling T-shaped and with it with the use of pin 4, fixed block is provided with jack 6, fixed block is positioned on the upside of the T prefix 1 of the bar of falling T-shaped, arranges rotary handle 7 above the bar of falling T-shaped.
First Large Precast Members hanging method provided by the present invention is the land installation of suspender, and the suspension rod of falling T-shaped and auxiliary device winch to above component by operating personal simultaneously, and it is synchronously moved to component and reserves directly over hole for hoist by workmen; Make fixed block and T prefix on same level axis, the large hook of crane ship slowly drops to above component and carries out coarse positioning.
As shown in Figure 3, after hanging apparatus carries out coarse positioning above component 8, crane ship continues to weigh hook in the hand, workmen is keeping fixed block and T prefix under the state of same level axis, fixed block and T-shaped bar are put into component and reserves hole for hoist 9, and pinned in jack pin being inserted fixed block, fixed block and reserved hole for hoist close contact in this process, serve the effect of location simultaneously, avoid the hole clipping phenomenon that the displacement of T-shaped bar causes.
As shown in Figure 4, after fixed block arrives position of rotation, stop declining, pull out on pin, workman, by T-shaped bar 90-degree rotation, makes the axes normal of T prefix and fixed block, and pin is stayed in pin-and-hole, and workman withdraws scene, and crane ship ship starts lifting.
Crane ship is by after Large Precast Members handling extremely under water, and prefabricated components are arranged on design attitude by Divers under the guidance of technology people; After Components installation completes, crane ship is weighed hook in the hand and is relaxed one's efforts to steel rope, and now the bar of falling T-shaped rotates to parallel with fixed block by Divers, inserts pin, and withdraws to safety zone; Because fixed block can keep the suspension rod of falling T-shaped vertical center in hole for hoist, suspender can successfully be left the water by crane ship.
Hanging apparatus of the present invention, coordinates the reserved hole for hoist in Large Precast Members to use, simply efficiently, safe and reliable.
Claims (2)
1. a Large Precast Members hanging apparatus, there is the bar of falling T-shaped (5) and auxiliary device, it is characterized in that, described auxiliary device comprises fixed block (2) and securing arrangement, securing arrangement be welded on pin-and-hole (3) on the bar of falling T-shaped and with it with the use of pin (4), fixed block is provided with jack (6), and fixed block is positioned at T prefix (1) upside of the bar of falling T-shaped, arranges rotary handle (7) above the bar of falling T-shaped.
2. a Large Precast Members hanging method, is characterized in that, comprises the steps:
1) the land installation of suspender
Step 1-1, the suspension rod of falling T-shaped and auxiliary device are winched to component (8) top by operating personal simultaneously, and it is synchronously moved to component and reserves directly over hole for hoist (9) by workmen;
Step 1-2, makes fixed block and T prefix on same level axis, and the large hook of crane ship slowly drops to above component and carries out coarse positioning;
Step 1-3, crane ship continues to weigh hook in the hand, and fixed block and T-shaped bar at maintenance fixed block and T prefix, are put into component and reserved hole for hoist, and pinned in jack pin being inserted fixed block under the state of same level axis by workmen;
Step 1-4, after fixed block arrives position of rotation, stop declining, pull out on pin, workman, by T-shaped bar 90-degree rotation, makes the axes normal of T prefix and fixed block, and pin is stayed in pin-and-hole, and workman withdraws scene, and crane ship ship starts lifting;
2) component is installed and suspender excision under water
Step 2-1, crane ship is by Large Precast Members handling under water, and prefabricated components are arranged on design attitude by Divers under the guidance of technology people;
Step 2-2, after Components installation completes, crane ship is weighed hook in the hand and is relaxed one's efforts to steel rope, and Divers puts in place;
Step 2-3, Divers will the bar of falling T-shaped rotate to fixed block same level axis, insert pin, and withdraw to safety zone;
Step 2-4, because fixed block can keep the suspension rod of falling T-shaped vertical center in hole for hoist, suspender can successfully be left the water by crane ship;
Step 2-5, enters the lifting flow process of next component.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410420095.2A CN104229621B (en) | 2014-08-25 | 2014-08-25 | Large Precast Members hanging apparatus and method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410420095.2A CN104229621B (en) | 2014-08-25 | 2014-08-25 | Large Precast Members hanging apparatus and method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104229621A true CN104229621A (en) | 2014-12-24 |
CN104229621B CN104229621B (en) | 2016-08-24 |
Family
ID=52218654
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410420095.2A Expired - Fee Related CN104229621B (en) | 2014-08-25 | 2014-08-25 | Large Precast Members hanging apparatus and method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104229621B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105236256A (en) * | 2015-11-13 | 2016-01-13 | 中国船舶重工集团公司第七二六研究所 | Underwater hoisting device and fast connecting device thereof |
CN108016985A (en) * | 2017-12-13 | 2018-05-11 | 广新海事重工股份有限公司 | A kind of simple easily container examination box hanger |
CN108033355A (en) * | 2017-12-11 | 2018-05-15 | 合肥中科离子医学技术装备有限公司 | A kind of through hole suspender and its application method |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1059673A (en) * | 1996-06-12 | 1998-03-03 | Masaaki Mizuta | Hoisting accessory |
CN101857169A (en) * | 2010-06-07 | 2010-10-13 | 孙效 | Sling tool using interstitial hole |
CN201746225U (en) * | 2010-07-22 | 2011-02-16 | 卫华集团有限公司 | Twist lock connection device of upper and lower crane bodies and crane using same |
CN201817192U (en) * | 2010-08-05 | 2011-05-04 | 中建筑港集团有限公司 | Large-tonnage concrete block lifting appliance |
CN201864459U (en) * | 2010-11-26 | 2011-06-15 | 贵阳铝镁设计研究院 | Buckle type hoisting and fastening device for hoisting electrode of large diameter |
CN202625591U (en) * | 2012-05-24 | 2012-12-26 | 无锡西姆莱斯石油专用管制造有限公司 | Saw blade lifting device for sampling saw |
CN204022268U (en) * | 2014-08-25 | 2014-12-17 | 山东港湾建设集团有限公司 | Large Precast Members hanging apparatus |
-
2014
- 2014-08-25 CN CN201410420095.2A patent/CN104229621B/en not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1059673A (en) * | 1996-06-12 | 1998-03-03 | Masaaki Mizuta | Hoisting accessory |
CN101857169A (en) * | 2010-06-07 | 2010-10-13 | 孙效 | Sling tool using interstitial hole |
CN201746225U (en) * | 2010-07-22 | 2011-02-16 | 卫华集团有限公司 | Twist lock connection device of upper and lower crane bodies and crane using same |
CN201817192U (en) * | 2010-08-05 | 2011-05-04 | 中建筑港集团有限公司 | Large-tonnage concrete block lifting appliance |
CN201864459U (en) * | 2010-11-26 | 2011-06-15 | 贵阳铝镁设计研究院 | Buckle type hoisting and fastening device for hoisting electrode of large diameter |
CN202625591U (en) * | 2012-05-24 | 2012-12-26 | 无锡西姆莱斯石油专用管制造有限公司 | Saw blade lifting device for sampling saw |
CN204022268U (en) * | 2014-08-25 | 2014-12-17 | 山东港湾建设集团有限公司 | Large Precast Members hanging apparatus |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105236256A (en) * | 2015-11-13 | 2016-01-13 | 中国船舶重工集团公司第七二六研究所 | Underwater hoisting device and fast connecting device thereof |
CN108033355A (en) * | 2017-12-11 | 2018-05-15 | 合肥中科离子医学技术装备有限公司 | A kind of through hole suspender and its application method |
CN108016985A (en) * | 2017-12-13 | 2018-05-11 | 广新海事重工股份有限公司 | A kind of simple easily container examination box hanger |
Also Published As
Publication number | Publication date |
---|---|
CN104229621B (en) | 2016-08-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203284095U (en) | Tower crane for cooling tower | |
CN203247009U (en) | Automatic detacher of under water hanging object | |
CN204355946U (en) | A kind of device lifting large wt pts | |
CN104229621A (en) | Large-sized prefabricated part hoisting device and method | |
CN103552664B (en) | For the barge rocker arrangement of jacket launching | |
CN105337218A (en) | Power transmission line lifting device | |
CN201334306Y (en) | Hoisting machine for upright post member | |
CN103556626B (en) | Hanging structure for hoisting large-diameter hole drilling filling pile steel bar cage | |
CN103922232B (en) | A kind of tower crane fall tower process | |
CN202864675U (en) | Shaft-type part hoisting tool | |
CN204022268U (en) | Large Precast Members hanging apparatus | |
CN204281054U (en) | A kind of small-sized caisson suspender | |
CN206842835U (en) | A kind of suspender of balancing earth-pressure shielding machine section of jurisdiction crane | |
CN202785255U (en) | Turnover hoisting tool for reinforced concrete pipe joint | |
CN202785542U (en) | Reactor dome hanging basket | |
CN205772790U (en) | Circular spherical tank integral hoisting specific purpose tool | |
CN108163142A (en) | A kind of hanging method of stern springboard | |
CN103979442A (en) | Method for lifting Fischer-Tropsch reactor by 6400t hydraulic combined crane | |
CN201599058U (en) | Quick installation platform for water drainage emergency rescue device of mine shaft | |
CN203834458U (en) | Hammer dropping device of dynamic compaction machine | |
CN204265345U (en) | A kind of tower crane lift hook is rushed to summit rope broken protector | |
CN101734549A (en) | Lifting sling | |
CN205218474U (en) | Piston servomotor shifts out device | |
CN204113145U (en) | A kind of hydraulic control chela mechanism | |
CN205835172U (en) | A kind of tower kind equipment changes gasket tool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||