CN104196247A - Special-shaped spatial network structure node control installation method - Google Patents

Special-shaped spatial network structure node control installation method Download PDF

Info

Publication number
CN104196247A
CN104196247A CN201410425899.1A CN201410425899A CN104196247A CN 104196247 A CN104196247 A CN 104196247A CN 201410425899 A CN201410425899 A CN 201410425899A CN 104196247 A CN104196247 A CN 104196247A
Authority
CN
China
Prior art keywords
special
node
assembled
control point
coordinate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410425899.1A
Other languages
Chinese (zh)
Inventor
邹航
刘中华
王留成
邢遵胜
王强强
张伟
卢福生
江涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Jinggong Steel Structure Group Co Ltd
Original Assignee
Zhejiang Jinggong Steel Structure Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Jinggong Steel Structure Group Co Ltd filed Critical Zhejiang Jinggong Steel Structure Group Co Ltd
Priority to CN201410425899.1A priority Critical patent/CN104196247A/en
Publication of CN104196247A publication Critical patent/CN104196247A/en
Pending legal-status Critical Current

Links

Abstract

The invention belongs to the technical field of installation of steel structures of buildings and particularly relates to a special-shaped spatial network structure node control installation method. The method comprises the following steps that (1) three-dimensional space coordinates of related control points A1(x1,y1,z1), A2(x2,y2,z2) and A3(x3,y3,z3) are obtained by means of three-dimensional modeling through a computer; (2) land samples are placed according to the coordinates (x3,y3) of the related control point A3; (3) the height of a special molding bed is selected and adjusted according to the coordinate z2 of the related control point A2; (4) the height of a threaded rod in the molding bed is adjusted; (5) after nodes are positioned, rod pieces between all the nodes are spliced in sequence according to the size relation between all the rod pieces and the corresponding nodes; (6) after splicing of a grid structure is completed, the structure is measured repeatedly. The special-shaped spatial network structure node control installation method can solve the problems that a special-shaped spatial network structure is low in splicing efficiency, and the accuracy can not be easily controlled.

Description

A kind of special-shaped spacial framework node control mounting method
Technical field
The invention belongs to construction steel structure mounting technique field, be specifically related to a kind of special-shaped spacial framework node control mounting method.
Background technology
Special-shaped space structures is due to moulding uniqueness, and Form of Architecture is rich and varied, is deeply subject to liking of building designers.In order to reach a good architectural effect, and meet relevant code requirement when structure construction, the building course of this type of building, is a link of crucial importance and difficulty is larger, especially for the control of Steel Structure Installation precision.
, there are following technological difficulties in the installation of this type of space structures: one,, except the three dimensional space coordinate of node needs accurately to locate, also needs the space angle of node to position, cause the more difficult location, locus of each node; Two, because space structures is for being generally special-shaped curved, the angle of its rod member centre of form axle can change along with the variation of surface normal, causes the also more difficult accurate location of space angle of each rod member.
According to the installation of conventional full hall scaffold high altitude bulk, can cause full hall scaffold to set up that difficulty is large, consumption is large, installation effectiveness is low, and cannot solve preferably the shortcomings such as above-mentioned technological difficulties; And adopt the mounting method of burst lifting, assembled moulding bed large usage quantity, splicing accuracy are difficult for ensureing, assembled efficiency is low etc. shortcoming also cannot solving preferably above-mentioned technological difficulties simultaneously.So, how in ensureing installation accuracy, improve installation effectiveness, reduce costs and become a problem demanding prompt solution.
The technical problem existing in sum, the applicant provides a kind of special-shaped spacial framework node control mounting method, and this case produces thus.
Summary of the invention
The object of the present invention is to provide a kind of special-shaped spacial framework node control mounting method, to solve, the assembled efficiency of spatial special network is low, the uppity problem of precision.
For solving the problems of the technologies described above, the technical scheme that the present invention specifically provides is: a kind of special-shaped spacial framework node control mounting method, it is characterized in that, and comprise the steps:
1), by Computerized three-dimensional modeling, set up the three-dimensional entity model in the assembled process of structure, or the deduce mathematical of passing through calculates, obtain relevant control point A1 (x1, y1, z1),
A2 (x2, y2, z2), A3 (x3, y3, z3) three dimensional space coordinate;
2), place ground sample according to (x3, y3) coordinate of relevant control point A3;
3), according to the z2 coordinate of relevant control point A2, choose and adjust jig frame special height, jig frame special is positioned over ground by base area sample, by each node placement on special assembled moulding bed.
4), by adjusting the height of screw rod in moulding bed, the corner of each node is adjusted to required direction.
5), after node locating, according to the size relationship of each rod member and respective nodes, rod member between assembled each node successively.
6), network is assembled completes, and structure is carried out to repetition measurement, determine respectively whether to meet splicing accuracy requirement to index.
Compared with prior art, this real beneficial effect of the invention is:
One, the present invention is simple to operate, uses safety, convenient, efficient, and its assembled moulding bed can Reusability, greatly cost-saving;
Two, the special-shaped spatial mesh structure assembling method of one provided by the present invention, can meet relevant requirement to the precision control of structure;
Three, operating process of the present invention is easily understood, and can allow relevant staff grasp in the shorter time, has good circulation promotional value.
Brief description of the drawings
Fig. 1 is the assembled schematic diagram of the present invention;
Fig. 2 is the special assembled moulding bed of the present invention.
Detailed description of the invention
Below in conjunction with drawings and the specific embodiments, the present invention is described in further detail.
As shown in Figure 1, 2, be preferred embodiments of the present invention: a kind of special-shaped spacial framework node control mounting method, comprises the steps:
1), by Computerized three-dimensional modeling, set up the three-dimensional entity model in the assembled process of structure, or the deduce mathematical of passing through calculates, obtain relevant control point A1 (x1, y1, z1),
A2 (x2, y2, z2), A3 (x3, y3, z3) three dimensional space coordinate;
2), place ground sample according to (x3, y3) coordinate of relevant control point A3;
3), according to the z2 coordinate of relevant control point A2, choose and adjust jig frame special height, jig frame special is positioned over ground by base area sample, by each node placement on special assembled moulding bed;
4), by adjusting the height of screw rod in moulding bed, the corner of each node is adjusted to required direction;
5), after node locating, according to the size relationship of each rod member and respective nodes, rod member between assembled each node successively.
By adjusting screw 22 and control point A2 coordinate, the z2 of A2 that can fine adjustment moulding bed top regulating rotary gusset 21 is to coordinate and corner; According to control point A1 coordinate, can knot modification 11 with the correlation of moulding bed top regulating rotary gusset 21, determine space coordinates and the corner of node 11.
6), network is assembled completes, and structure is carried out to repetition measurement, determine respectively whether to meet splicing accuracy requirement to index.
Above-described embodiment and graphic and non-limiting form of the present invention and style, suitable variation or modification that any person of ordinary skill in the field does it, as increased or reduce moulding bed screw rod quantity, change special assembled moulding bed form, all should be considered as not departing from the category of patent of the present invention.

Claims (1)

1. a special-shaped spacial framework node control mounting method, is characterized in that, comprises the steps:
1), by Computerized three-dimensional modeling, set up the three-dimensional entity model in the assembled process of structure, or the deduce mathematical of passing through calculates, obtain relevant control point A1 (x1, y1, z1), A2 (x2, y2, z2), A3 (x3, y3, z3) three dimensional space coordinate;
2), place ground sample according to (x3, y3) coordinate of relevant control point A3;
3), according to the z2 coordinate of relevant control point A2, choose and adjust jig frame special height, jig frame special is positioned over ground by base area sample, by each node placement on special assembled moulding bed;
4), by adjusting the height of screw rod in moulding bed, the corner of each node is adjusted to required direction;
5), after node locating, according to the size relationship of each rod member and respective nodes, rod member between assembled each node successively;
6), network is assembled completes, and structure is carried out to repetition measurement, determine respectively whether to meet splicing accuracy requirement to index.
CN201410425899.1A 2014-08-27 2014-08-27 Special-shaped spatial network structure node control installation method Pending CN104196247A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410425899.1A CN104196247A (en) 2014-08-27 2014-08-27 Special-shaped spatial network structure node control installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410425899.1A CN104196247A (en) 2014-08-27 2014-08-27 Special-shaped spatial network structure node control installation method

Publications (1)

Publication Number Publication Date
CN104196247A true CN104196247A (en) 2014-12-10

Family

ID=52081596

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410425899.1A Pending CN104196247A (en) 2014-08-27 2014-08-27 Special-shaped spatial network structure node control installation method

Country Status (1)

Country Link
CN (1) CN104196247A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105370049A (en) * 2015-11-16 2016-03-02 上海振华重工(集团)股份有限公司 Rotating wheel section pre-assembly method for ferris wheel
CN107237501A (en) * 2017-05-26 2017-10-10 浙江精工钢结构集团有限公司 A kind of circular hollow section bending component assembling method
CN107327146A (en) * 2017-07-13 2017-11-07 上海二十冶建设有限公司 Assembled simple jig frame and its application method for steel structure assembling
CN107907080A (en) * 2017-09-22 2018-04-13 中冶天工集团有限公司 A kind of measuring method of the spacial special-shaped grid wall stand of suspension type
CN108731658A (en) * 2018-08-14 2018-11-02 河北建设集团股份有限公司 The method of precise positioning reticulated shell welded spherical node

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2434903A1 (en) * 1978-09-04 1980-03-28 Martinez Apezteguia Juan Node and bar prefabricated space frame - has bar connector with two opposite threads and tightening nut
CN101255767A (en) * 2008-03-25 2008-09-03 浙江大学 Method for measuring and locating virtual tetrahedron top of abnormity component
CN101328746A (en) * 2007-06-18 2008-12-24 浙江展诚建设集团股份有限公司 Steel structure high altitude mounting method
CN101525945A (en) * 2009-03-27 2009-09-09 中建钢构有限公司 Installation and positioning method for steel casting spatial position
CN101864840A (en) * 2010-05-14 2010-10-20 深圳市建工集团股份有限公司 Construction method for spatial special multi-curved surface netlike shell formed by connecting gusset plates
CN103061524A (en) * 2013-02-05 2013-04-24 广东省工业设备安装公司 Movable copying positioning frame of steel structure complex joint
CN103352574A (en) * 2013-04-25 2013-10-16 江苏沪宁钢机股份有限公司 Aloft installing and positioning method for steel casting

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2434903A1 (en) * 1978-09-04 1980-03-28 Martinez Apezteguia Juan Node and bar prefabricated space frame - has bar connector with two opposite threads and tightening nut
CN101328746A (en) * 2007-06-18 2008-12-24 浙江展诚建设集团股份有限公司 Steel structure high altitude mounting method
CN101255767A (en) * 2008-03-25 2008-09-03 浙江大学 Method for measuring and locating virtual tetrahedron top of abnormity component
CN101525945A (en) * 2009-03-27 2009-09-09 中建钢构有限公司 Installation and positioning method for steel casting spatial position
CN101864840A (en) * 2010-05-14 2010-10-20 深圳市建工集团股份有限公司 Construction method for spatial special multi-curved surface netlike shell formed by connecting gusset plates
CN103061524A (en) * 2013-02-05 2013-04-24 广东省工业设备安装公司 Movable copying positioning frame of steel structure complex joint
CN103352574A (en) * 2013-04-25 2013-10-16 江苏沪宁钢机股份有限公司 Aloft installing and positioning method for steel casting

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105370049A (en) * 2015-11-16 2016-03-02 上海振华重工(集团)股份有限公司 Rotating wheel section pre-assembly method for ferris wheel
CN107237501A (en) * 2017-05-26 2017-10-10 浙江精工钢结构集团有限公司 A kind of circular hollow section bending component assembling method
CN107327146A (en) * 2017-07-13 2017-11-07 上海二十冶建设有限公司 Assembled simple jig frame and its application method for steel structure assembling
CN107907080A (en) * 2017-09-22 2018-04-13 中冶天工集团有限公司 A kind of measuring method of the spacial special-shaped grid wall stand of suspension type
CN107907080B (en) * 2017-09-22 2020-05-01 中冶天工集团有限公司 Measuring method of hanging type space special-shaped grid wall frame
CN108731658A (en) * 2018-08-14 2018-11-02 河北建设集团股份有限公司 The method of precise positioning reticulated shell welded spherical node

Similar Documents

Publication Publication Date Title
CN109523107A (en) A kind of Construction Management System and method based on BIM
CN104196247A (en) Special-shaped spatial network structure node control installation method
CN104778316B (en) A kind of photovoltaic power generation equipment radiation analysis method based on BIM
CN106840124B (en) A method of for skyscraper rapid survey setting-out
CN103114732B (en) Cast steel penetration pipe node space positioning method
WO2022047959A1 (en) Artificially intelligent urban design morphological layout method for enhancing wind environment
CN107010542B (en) A kind of assembled architecture intelligence hanging method
CN103942361B (en) Automatic calculation method and module of support hanger in three-dimensional process plant design
CN104463954B (en) A kind of analogy method and system of 3-D view surface details
CN106997511A (en) Railway beam course management system and railway beam a management method based on BIM technology
CN111877616A (en) Curtain wall installation method based on three-dimensional laser scanning
CN108733911A (en) Building aluminum alloy pattern plate construction code Design method based on three-dimensional digital model
CN109635501A (en) A kind of reduction water supply network leakage loss method based on hydraulic model
CN108756292A (en) A kind of building synchronization of jacking up control method and system based on technology of Internet of things
CN102953552A (en) Method for positioning through hole of pipe truss
CN104750938A (en) GIS (Geographic Information System)-based urban ventilating gallery identifying method and system
CN104931027B (en) A kind of projection line-putting method of decorative pattern
CN107422376B (en) A kind of non-stationary non-gaussian earthquake motion time history analogy method
CN109885939A (en) A kind of photovoltaic plant building method and system based on Building Information Model
CN103617563A (en) Water supply pipeline non-monitoring node pressure determining method based on ground statistics space analysis theory
CN109282817A (en) A kind of multirobot co-located and control method
CN104951581A (en) Equipment installation construction scheme simulation verification method and device based on CAM platform
CN109543231A (en) A kind of Garment Parametric pushes away an edition method and system
CN108984876A (en) A kind of service sleeve automation modeling method and system based on BIM
CN106546229B (en) A kind of surveying and locating method convenient for floor manager

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20141210

RJ01 Rejection of invention patent application after publication