CN104131579A - Method for quickening earthwork digging and transporting in top-down construction - Google Patents

Method for quickening earthwork digging and transporting in top-down construction Download PDF

Info

Publication number
CN104131579A
CN104131579A CN201410227019.XA CN201410227019A CN104131579A CN 104131579 A CN104131579 A CN 104131579A CN 201410227019 A CN201410227019 A CN 201410227019A CN 104131579 A CN104131579 A CN 104131579A
Authority
CN
China
Prior art keywords
basement
construction
permanent
permanent track
unearthed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410227019.XA
Other languages
Chinese (zh)
Inventor
苏伟
艾姣姣
欧阳琳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201410227019.XA priority Critical patent/CN104131579A/en
Publication of CN104131579A publication Critical patent/CN104131579A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a method for quickening earthwork digging and transporting in top-down construction. The method includes: optimally designing permanent lane structures of a basement during basement design so that permanent lanes in the basement can meet requirements on free height, load, width and turning radius of unearthing trucks; when a top-down method is adopted in the basement construction, firstly completing construction of the permanent lanes on each layer of the basement, and then connecting the permanent lanes on each layer of the basement with the construction site ground via temporary excavated slopes, so that excavators and the earth moving trucks can enter the permanent lanes of each layer of the basement for underground construction through the temporary excavated slopes, and earthwork digging and transporting speed in the top-down construction in the basement can be increased. With the method, concrete steel trestles can be omitted, reserved holes for unearthing can be decreased, construction duration can be saved by the aid of the permanent lanes in the basement, construction cost can be saved, and meanwhile, requirements on unearthing in the basement by the top-down method can be met.

Description

A kind of method of accelerating excavation of earthwork and transportation in adverse construction method
Technical field
the present invention relates to a kind of method of accelerating excavation of earthwork and transportation in adverse construction method, belong to highrise building Construction Technique of Underground Works field.
Background technology
along with the development of Building Trade in China, all kinds of types of construction continue to bring out, and the super dark engineering of super large is more and more, in conventional project reverse construction, need to again build concrete steel trestle, and reserved opening is more, and construction hidden danger is large and expense is higher.This practice causes larger waste, does not meet the thinking that current national energy-saving reduces discharging.
Summary of the invention
the object of the invention is to, a kind of method of accelerating excavation of earthwork and transportation in adverse construction method is provided.Need not build concrete steel trestle, utilize the permanent car ramp of basement to carry out basement against being unearthed, save duration and cost.
technical scheme of the present invention:
a kind of method of accelerating excavation of earthwork and transportation in adverse construction method, the method be when design of basement to the permanent lane structure optimal design of basement, the permanent track of basement can be met be unearthed the requirement of headway, load, width and the turning radius of vehicle; When adopting contrary sequence method to carry out basement construction, first complete the permanent track construction of each layer of basement, then through the interim ramp of being unearthed, the permanent track of each layer of basement is connected with ground, building site; So that underground construction is carried out in the permanent track that excavator and muck haulage vehicle can enter each layer of basement by the interim ramp of being unearthed, to accelerate excavation of earthwork and transportation progress in basement adverse construction method.
in preceding method, carry out after the construction that completes basement diaphragm wall and basement steel column in the permanent track of described basement.
in preceding method, the permanent track construction of described basement is to be excavated to design elevation according to plan, then will after levelling of the land, with C20 concrete, lay the thick cure process of carrying out of 200mm; Place formwork after sclerosis again, and the concreting in the permanent track of basement is carried out in assembling reinforcement in template.
in preceding method, described permanent track is built rear maintenance and is removed formwork after 28 days, and then excavator and muck haulage vehicle are allowed for access, and cut the earth in permanent track and muck haulage operation.
in preceding method, in negative two layers of permanent track, be provided with the interim platform that is unearthed with the interim place, ramp of being unearthed.
compared with prior art, the present invention determines the initial stage in scheme, cancels concrete steel trestle, and the permanent lane structure of basement is optimized to design, guarantees be unearthed vehicle headway, cubic metre of earth vehicular load and vehicle width operating radius.Advantage of the present invention is, can cancel concrete steel trestle, reduces the reserved opening that is unearthed, and utilizes the permanent track of basement, saves the construction period, saves construction costs, meets the unearthed requirement of basement top-down method simultaneously.
Accompanying drawing explanation
fig. 1 is schematic diagram of the present invention;
fig. 2 is the floor map in permanent track.
being labeled as in figure: 1-first floor floor, the permanent track of 2-, 3-muck haulage vehicle, 4-bears one deck floor, and 5-is unearthed ramp temporarily, 6-excavator, ground, 7-building site, 8-basement diaphragm wall, 9-steel column, 10-is unearthed platform temporarily.
The specific embodiment
below in conjunction with drawings and Examples, the present invention is described in further detail, but not as any limitation of the invention.
accelerate a method for excavation of earthwork and transportation in adverse construction method, as depicted in figs. 1 and 2.The method be when design of basement to the permanent lane structure optimal design of basement, the permanent track 2 of basement can be met be unearthed the requirement of headway, load, width and the turning radius of vehicle 3; When adopting contrary sequence method to carry out basement construction, first complete the permanent track construction of each layer of basement, then through the interim ramp 5 of being unearthed, the permanent track of each layer of basement is connected with ground, building site 7; So that underground construction is carried out in the permanent track 2 that excavator 6 and muck haulage vehicle 3 can enter each layer of basement by the interim ramp 5 of being unearthed, to accelerate excavation of earthwork and transportation progress in basement adverse construction method.Carry out after the construction that completes basement diaphragm wall 8 and basement steel column 9 in the permanent track of basement.Basement permanent track construction is to be excavated to design elevation according to plan, then will after levelling of the land, with C20 concrete, lay the thick cure process of carrying out of 200mm; Place formwork after sclerosis again, and the concreting in the permanent track of basement is carried out in assembling reinforcement in template.Permanent track is built rear maintenance and is removed formwork after 28 days, and then excavator and muck haulage vehicle are allowed for access, and cut the earth in permanent track and muck haulage operation.In negative two layers of permanent track, be provided with the interim platform 10 that is unearthed with the interim place, ramp of being unearthed.
Embodiment
the present invention digs pile foundation, diaphragm wall 8 and comes of age after beam construction revolving, and adopts contrary sequence method to carry out the construction in the permanent track of basement.Sequence of construction is followed successively by: basement diaphragm wall 8 is constructed → revolved and digs 2 layers of pile foundation and basement steel column 9 construction → basement permanent tracks 2 constructions → negative 2 layers of interim platforms 10 constructions of being unearthed → negative to negative 3 layers and negative 4 layers of interim ramps 5 construction of being unearthed.When carrying out the permanent car ramp construction of basement, be first excavated to design elevation, cubic metre of earth levelling of the land and the thick C20 hardening of concrete of 200mm.Steel tube frame, apart from being 600 * 600mm, step pitch is 1500mm in length and breadth.Template installation, reinforcing bar binding and concreting.The permanent lane structure concrete of basement carries out soil excavation transportation after 28 days.Original template supporting steel pipe scaffold is removed simultaneously.In order to prevent the unearthed differential settlement that occurs after basement permanent ramp construction.Must carry out the limit for tonnage measure to earthwork vehicle.

Claims (5)

1. a method of accelerating excavation of earthwork and transportation in adverse construction method, it is characterized in that: the method be when design of basement to the permanent lane structure optimal design of basement, the permanent track of basement can be met be unearthed the requirement of headway, load, width and the turning radius of vehicle; When adopting contrary sequence method to carry out basement construction, first complete the permanent track construction of each layer of basement, then through the interim ramp of being unearthed, the permanent track of each layer of basement is connected with ground, building site; So that underground construction is carried out in the permanent track that excavator and muck haulage vehicle can enter each layer of basement by the interim ramp of being unearthed, to accelerate excavation of earthwork and transportation progress in basement adverse construction method.
2. method according to claim 1, is characterized in that: carry out after the construction that completes basement diaphragm wall and basement steel column in the permanent track of described basement.
3. method according to claim 2, is characterized in that: the permanent track construction of described basement is to be excavated to design elevation according to plan, then will be by the thick cure process of carrying out of C20 concrete laying 200mm after levelling of the land; Place formwork after sclerosis again, and the concreting in the permanent track of basement is carried out in assembling reinforcement in template.
4. method according to claim 3, is characterized in that: described permanent track is built rear maintenance and removed formwork after 28 days, and then excavator and muck haulage vehicle are allowed for access, and cut the earth in permanent track and muck haulage operation.
5. method according to claim 4, is characterized in that: in negative two layers of permanent track, be provided with the interim platform that is unearthed with the interim place, ramp of being unearthed.
CN201410227019.XA 2014-05-27 2014-05-27 Method for quickening earthwork digging and transporting in top-down construction Pending CN104131579A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410227019.XA CN104131579A (en) 2014-05-27 2014-05-27 Method for quickening earthwork digging and transporting in top-down construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410227019.XA CN104131579A (en) 2014-05-27 2014-05-27 Method for quickening earthwork digging and transporting in top-down construction

Publications (1)

Publication Number Publication Date
CN104131579A true CN104131579A (en) 2014-11-05

Family

ID=51804418

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410227019.XA Pending CN104131579A (en) 2014-05-27 2014-05-27 Method for quickening earthwork digging and transporting in top-down construction

Country Status (1)

Country Link
CN (1) CN104131579A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104480944A (en) * 2014-11-27 2015-04-01 中建一局集团第五建筑有限公司 Unearthed ramp structure and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101498133A (en) * 2009-02-25 2009-08-05 广州市住宅建设发展有限公司 Method and supporting construction for enlarging basement top-down method earth excavation space
KR101014796B1 (en) * 2008-03-03 2011-02-15 주식회사 한빛구조엔지니어링 Top-down underground construction method using prefabricated concrete column member as temporary bridge column
CN102704507A (en) * 2012-05-28 2012-10-03 中国建筑第八工程局有限公司 Construction method of cover-and-cut reverse construction concrete walls and columns with vertical structures
CN102900099A (en) * 2011-07-26 2013-01-30 上海市第二建筑有限公司 Drop-slab construction process for underground concrete structures
KR101383817B1 (en) * 2012-07-04 2014-04-08 삼표건설 주식회사 Top down method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101014796B1 (en) * 2008-03-03 2011-02-15 주식회사 한빛구조엔지니어링 Top-down underground construction method using prefabricated concrete column member as temporary bridge column
CN101498133A (en) * 2009-02-25 2009-08-05 广州市住宅建设发展有限公司 Method and supporting construction for enlarging basement top-down method earth excavation space
CN102900099A (en) * 2011-07-26 2013-01-30 上海市第二建筑有限公司 Drop-slab construction process for underground concrete structures
CN102704507A (en) * 2012-05-28 2012-10-03 中国建筑第八工程局有限公司 Construction method of cover-and-cut reverse construction concrete walls and columns with vertical structures
KR101383817B1 (en) * 2012-07-04 2014-04-08 삼표건설 주식회사 Top down method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈耿等: "逆作法土方开挖的应用和研究", 《山西建筑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104480944A (en) * 2014-11-27 2015-04-01 中建一局集团第五建筑有限公司 Unearthed ramp structure and construction method thereof
CN104480944B (en) * 2014-11-27 2016-04-06 中建一局集团第五建筑有限公司 Unearthed pits rampway structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN107059667B (en) Door shape assembled armored concrete box culvert and its construction method
CN101886479B (en) Underground storey-adding process of frame structural building by one-by-one independent foundation underpinning method
CN102995659B (en) Method for constructing from central area to periphery of ultra-large type underground engineering
CN104674846A (en) Construction method for evacuating subway station by prefabricated structure cover
WO2022016720A1 (en) Temporary passage construction method employing support structure in deep foundation pit
CN105421463B (en) Longitudinal excavation construction method of long-span dense-support super-long deep foundation pit
CN203846796U (en) Temporary soil discharge slope for top-down construction of basement
CN104131565B (en) A kind of against making the construction method that the earthwork is just made to excavate
CN105236275A (en) Soil lifting system and soil lifting method for building deep foundation pit construction in narrow zone
CN105736001A (en) Construction method for building subway station through precast parts
CN110439574B (en) Tunnel structure for shield lateral translation starting and slag discharging material conveying and construction method
CN105201516A (en) Subway station body structure and four-joint-arch PBA underground excavation construction method thereof
CN110578339A (en) construction method of shaft type underground stereo garage
CN102434717A (en) Construction method of joist steel pipe-jacking work pit
CN104234082A (en) Jump-layer reversed construction method for deep foundation pit
CN102410031B (en) Underground space structure constructed by pile wall construction method
CN105756091A (en) Metro station foundation pit construction method for controlling deformation of neighboring buildings
CN106246200A (en) Tunnel weakness substrate small-sized pile tube reinforcement system and construction method thereof
CN105256836A (en) Construction method for fast restoring road traffic in construction of underground project
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN104213567B (en) Underground pipe gallery controls the construction method of slope section slippage
CN105986830B (en) The tunneling method of construction of roadside strip underground garage
CN104895100B (en) Building close quarters builds underground space Caisson method
CN104131579A (en) Method for quickening earthwork digging and transporting in top-down construction
CN107313454B (en) Construction method of underground garage

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20141105