CN104120884A - Construction method for concrete floor in factory building - Google Patents
Construction method for concrete floor in factory building Download PDFInfo
- Publication number
- CN104120884A CN104120884A CN201310153813.XA CN201310153813A CN104120884A CN 104120884 A CN104120884 A CN 104120884A CN 201310153813 A CN201310153813 A CN 201310153813A CN 104120884 A CN104120884 A CN 104120884A
- Authority
- CN
- China
- Prior art keywords
- concrete
- construction
- construction method
- ground
- factory
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention discloses a construction method for a concrete floor in a factory building. The construction method includes the following steps of (1) preparing materials and equipment, (2) leveling a site, (3) protecting peripheral finished products, (4) positioning and paying off lines, (5) laying concrete, (6) vibrating the concrete, (7) purifying mortar and troweling the floor through a troweling machine, (8) mechanically calendaring, (9) curing, and (10) slotting. According to the construction method for the concrete floor in the factory building, construction is easy and convenient, the construction method is scientific and keeps the rules, and the concrete floor, manufactured through the method, in the factory building is high in bearing capacity and not prone to dusting.
Description
Technical field
The construction method that the present invention relates to a kind of Factory Concrete ground, belongs to technical field of building construction.
Background technology
Concrete is one of contemporary topmost civil engineering material, finger by cementitious matter (organic, inorganic or organic-inorganic compound), graininess is gathered materials and the chemical admixture that must add and the compound of mineral admixture component reasonable constituents, or after sclerosis, form and there is the composite material of heap poly structure (common is with cementitious material, water, fines, coarse aggregate, while needing, mix Admixture and mineral admixture, by proper proportion, coordinate the artificial stone material forming through even mixing, closely knit moulding and maintenance sclerosis).
Concrete has abundant raw material, cheap, the simple feature of production technology, thereby make its consumption increasing.It is high that while concrete also has compressive strength, good endurance, the features such as strength grade wide ranges.These features make its scope of application very extensive, not only in various civil engineerings, use, and be exactly shipbuilding industry, mechanical industry, the exploitation of ocean, geothermal engineering etc., concrete is also important material.
Summary of the invention
Goal of the invention: the object of the present invention is to provide the construction method on a kind of Factory Concrete ground, easy construction, normal science, the facility floor bearing capacity making by the method is high, is difficult for dusting.
Technical scheme: the construction method on a kind of Factory Concrete of the present invention ground, comprises the steps:
(1) material installation is prepared: before construction, should pre-determine concrete ground construction flow process, configure suitable construction equipment and labour;
(2) levelling of the land: survey crew ejects the high line of ground top mark at factory building metope, coordinates forklift to carry out place Cast-in-situ Piles in Sand-filling levelling work, control the top mark of Cast-in-situ Piles in Sand-filling high at-200 ㎜ between-210 ㎜;
(3) periphery finished product protection: need, with multicolored cloth or plastic sheeting, factory building is safeguarded to wall, steel column, colored steel safeguard before construction, carry out finished product protection;
(4) location unwrapping wire, a side form: before installation form, should hang logical line, by logical line position, side template is placed in basic unit, tentatively fixes its position, with level gauge, check whether template top absolute altitude meets designing requirement, and check that whether template is straight, strictly control side form absolute altitude;
(5) concrete speading: concrete adopts jumping storehouse to build, constuction joint should arrange together in conjunction with shrinkage joint, short is every across formwork in each section, thereby accomplish every across concreting, after concrete strength reaches designing requirement, utilize the concrete surface build for the first time to carry out second this concrete building as the side form of concreting for the second time;
(6) concrete vibrating: concrete surface is vibrated, struck off and flattens with striking off the evener that vibrates;
(7) finisher is carried slurry troweling: when concrete is in critical initial setting time, adopt finisher repeatedly troweling, propose slurry, compacting, after often smearing and finishing for one time, after concrete surface moisture evaporate, beat and smear next time again;
(8) mechanical press polish: in strict accordance with pouring order of concrete, carry out floating, press polish, corner and local mechanical smear less than place by manually rubbing hair, press polish with the hands with machinery.
(9) maintenance: carry out maintenance after concreting 24h, take common covering, trickle or sprinkling to carry out maintenance;
(10) slot: on the concrete surface of having built perpendicular to concreting direction cutting machine joint-cutting.
Further improve technique scheme, concrete the paving of described step (five) adopts the method construction of longitudinal itemize, and longitudinally the width of itemize and partitioning slot, with wide, pave from end, when mixing concrete thing is poured in mould, discharging will be concentrated, and speed is slow, the empty thick template 2cm left and right that exceeds, carry out if desired material reducing or feed supplement work, vertical and horizontal section meets the requirements, and during spread concrete, should pave continuously, must not interrupt.
Further, during the operation of described step (six) evener, can by vibrating motor rotation direction, be drawn back and forth by operating personnel the drag cable that is located at evener two ends, concrete is vibrated and struck off, come and go vibration secondary, gait of march is controlled at 1-2 rice per minute, can reach requirement smooth and compacting.
Further, in described step (ten), the time of slot is to be that concrete crushing strength reaches 6~10MPa the suitable time.
Further, described step (ten) concrete operation method is as follows: on the cement concrete of intending joint-cutting, eject the line of ink marker, good and sound guide rail leading truck, joint cutter is located, start joint cutter, discharge water lubricated, rotating turret handle, slowly feed, adopt the thick diamond saw blade joint-cutting of 0.7mm, make saw blade first reach design seam dark, then screwing screw, pin screw mandrel and start walking, thereby forming the seam that the degree of depth is greater than 50mm, wide 0.8mm.
Compared with prior art, its beneficial effect is in the present invention: the construction method on Factory Concrete of the present invention ground, and easy construction, well-behaved science, the facility floor bearing capacity making by the method is high, is difficult for dusting.
The specific embodiment
Below technical solution of the present invention is elaborated, but protection scope of the present invention is not limited to described embodiment.
embodiment 1:the construction method on Factory Concrete ground, is characterized in that, comprises the steps:
(1) material installation is prepared: before construction, should pre-determine concrete ground construction flow process, configure suitable construction equipment and labour;
(2) levelling of the land: survey crew ejects the high line of ground top mark at factory building metope, coordinates forklift to carry out place Cast-in-situ Piles in Sand-filling levelling work, control the top mark of Cast-in-situ Piles in Sand-filling high at-200 ㎜ between-210 ㎜;
(3) periphery finished product protection: need, with multicolored cloth or plastic sheeting, factory building is safeguarded to wall, steel column, colored steel safeguard before construction, carry out finished product protection;
(4) location unwrapping wire, a side form: before installation form, should hang logical line, by logical line position, side template is placed in basic unit, tentatively fixes its position, with level gauge, check whether template top absolute altitude meets designing requirement, and check that whether template is straight, strictly control side form absolute altitude;
(5) concrete speading: concrete adopts jumping storehouse to build, constuction joint should arrange together in conjunction with shrinkage joint, short is every across formwork in each section, thereby accomplish every across concreting, after concrete strength reaches designing requirement, utilize the concrete surface build for the first time to carry out second this concrete building as the side form of concreting for the second time;
(6) concrete vibrating: concrete surface is vibrated, struck off and flattens with striking off the evener that vibrates;
(7) finisher is carried slurry troweling: when concrete is in critical initial setting time, adopt finisher repeatedly troweling, propose slurry, compacting, after often smearing and finishing for one time, after concrete surface moisture evaporate, beat and smear next time again;
(8) mechanical press polish: in strict accordance with pouring order of concrete, carry out floating, press polish, corner and local mechanical smear less than place by manually rubbing hair, press polish with the hands with machinery.
(9) maintenance: carry out maintenance after concreting 24h, take common covering, trickle or sprinkling to carry out maintenance;
(10) slot: on the concrete surface of having built perpendicular to concreting direction cutting machine joint-cutting.
Concrete the paving of described step (five) adopts the method construction of longitudinal itemize, longitudinally the width of itemize and partitioning slot are with wide, pave from end, when mixing concrete thing is poured in mould, discharging will be concentrated, speed is slow, the empty thick template 2cm left and right that exceeds, carries out material reducing or feed supplement work if desired, and vertical and horizontal section meets the requirements, during spread concrete, should pave continuously, must not interrupt.
During the operation of described step (six) evener, can by operating personnel, by vibrating motor rotation direction, be drawn back and forth the drag cable that is located at evener two ends, concrete is vibrated and struck off, come and go vibration secondary, gait of march is controlled at 1-2 rice per minute, can reach requirement smooth and compacting.
In described step (ten), the time of slot is to be that concrete crushing strength reaches 6~10MPa the suitable time.
Described step (ten) concrete operation method is as follows: on the cement concrete of intending joint-cutting, eject the line of ink marker, good and sound guide rail leading truck, by joint cutter location, starts joint cutter, discharge water lubricated, rotating turret handle, slowly feed, adopts the thick diamond saw blade joint-cutting of 0.7mm, make saw blade first reach design seam dark, then screwing screw, pins screw mandrel and starts walking, thereby forms the seam that the degree of depth is greater than 50mm, wide 0.8mm.
As mentioned above, although represented and explained the present invention with reference to specific preferred embodiment, it shall not be construed as the restriction to the present invention self.Not departing under the spirit and scope of the present invention prerequisite of claims definition, can make in the form and details various variations to it.
Claims (5)
1. the construction method on Factory Concrete ground, is characterized in that, comprises the steps:
(1) material installation is prepared: before construction, should pre-determine concrete ground construction flow process, configure suitable construction equipment and labour;
(2) levelling of the land: survey crew ejects the high line of ground top mark at factory building metope, coordinates forklift to carry out place Cast-in-situ Piles in Sand-filling levelling work, control the top mark of Cast-in-situ Piles in Sand-filling high at-200 ㎜ between-210 ㎜;
(3) periphery finished product protection: need, with multicolored cloth or plastic sheeting, factory building is safeguarded to wall, steel column, colored steel safeguard before construction, carry out finished product protection;
(4) location unwrapping wire, a side form: before installation form, should hang logical line, by logical line position, side template is placed in basic unit, tentatively fixes its position, with level gauge, check whether template top absolute altitude meets designing requirement, and check that whether template is straight, strictly control side form absolute altitude;
(5) concrete speading: concrete adopts jumping storehouse to build, constuction joint should arrange together in conjunction with shrinkage joint, short is every across formwork in each section, thereby accomplish every across concreting, after concrete strength reaches designing requirement, utilize the concrete surface build for the first time to carry out second this concrete building as the side form of concreting for the second time;
(6) concrete vibrating: concrete surface is vibrated, struck off and flattens with striking off the evener that vibrates;
(7) finisher is carried slurry troweling: when concrete is in critical initial setting time, adopt finisher repeatedly troweling, propose slurry, compacting, after often smearing and finishing for one time, after concrete surface moisture evaporate, beat and smear next time again;
(8) mechanical press polish: in strict accordance with pouring order of concrete, carry out floating, press polish, corner and local mechanical smear less than place by manually rubbing hair, press polish with the hands with machinery;
(9) maintenance: carry out maintenance after concreting 24h, take common covering, trickle or sprinkling to carry out maintenance;
(10) slot: on the concrete surface of having built perpendicular to concreting direction cutting machine joint-cutting.
2. the construction method on Factory Concrete according to claim 1 ground, is characterized in that, concrete the paving of described step (five) adopts the method construction of longitudinal itemize, longitudinally the width of itemize and partitioning slot are with wide, pave from end, when mixing concrete thing is poured in mould, discharging will be concentrated, speed is slow, the empty thick template 2cm left and right that exceeds, carries out material reducing or feed supplement work if desired, and vertical and horizontal section meets the requirements, during spread concrete, should pave continuously, must not interrupt.
3. the construction method on Factory Concrete according to claim 1 ground, it is characterized in that, during the operation of described step (six) evener, by operating personnel, by vibrating motor rotation direction, drawn back and forth the drag cable that is located at evener two ends, concrete is vibrated and struck off, come and go vibration secondary, gait of march is controlled at 1-2 rice per minute, can reach requirement smooth and compacting.
4. the construction method on Factory Concrete according to claim 1 ground, is characterized in that, in described step (ten), the time of slot is that concrete crushing strength reaches 6~10MPa.
5. the construction method on Factory Concrete according to claim 1 ground, it is characterized in that, described step (ten) concrete operation method is as follows: on the cement concrete of intending joint-cutting, eject the line of ink marker, good and sound guide rail leading truck, joint cutter is located, start joint cutter, discharge water lubricated, rotating turret handle, slowly feed, adopts the thick diamond saw blade joint-cutting of 0.7mm, make saw blade first reach design seam dark, then screwing screw, pins screw mandrel and starts walking, thereby forms the seam that the degree of depth is greater than 50mm, wide 0.8mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310153813.XA CN104120884A (en) | 2013-04-28 | 2013-04-28 | Construction method for concrete floor in factory building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310153813.XA CN104120884A (en) | 2013-04-28 | 2013-04-28 | Construction method for concrete floor in factory building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104120884A true CN104120884A (en) | 2014-10-29 |
Family
ID=51766500
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310153813.XA Pending CN104120884A (en) | 2013-04-28 | 2013-04-28 | Construction method for concrete floor in factory building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104120884A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107268854A (en) * | 2016-04-06 | 2017-10-20 | 五冶集团上海有限公司 | Industrial premises high-flatness large-area concrete construction method of ground |
CN108756143A (en) * | 2018-05-25 | 2018-11-06 | 广州市东方文旅产业开发有限公司 | A kind of embossing concrete ground construction method of high-resistance wear-resistant |
CN110295722A (en) * | 2019-06-27 | 2019-10-01 | 中建三局第一建设工程有限责任公司 | A kind of high-precision flooring construction method that flatness is controllable |
CN113530147A (en) * | 2021-07-31 | 2021-10-22 | 中冶建工集团有限公司 | Terrace construction method capable of controlling elevation and flatness with high precision |
CN113550576A (en) * | 2021-07-30 | 2021-10-26 | 重庆建工第三建设有限责任公司 | Deep beam steel bar binding side mold cabin jumping dislocation construction process |
-
2013
- 2013-04-28 CN CN201310153813.XA patent/CN104120884A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107268854A (en) * | 2016-04-06 | 2017-10-20 | 五冶集团上海有限公司 | Industrial premises high-flatness large-area concrete construction method of ground |
CN108756143A (en) * | 2018-05-25 | 2018-11-06 | 广州市东方文旅产业开发有限公司 | A kind of embossing concrete ground construction method of high-resistance wear-resistant |
CN110295722A (en) * | 2019-06-27 | 2019-10-01 | 中建三局第一建设工程有限责任公司 | A kind of high-precision flooring construction method that flatness is controllable |
CN113550576A (en) * | 2021-07-30 | 2021-10-26 | 重庆建工第三建设有限责任公司 | Deep beam steel bar binding side mold cabin jumping dislocation construction process |
CN113530147A (en) * | 2021-07-31 | 2021-10-22 | 中冶建工集团有限公司 | Terrace construction method capable of controlling elevation and flatness with high precision |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104120884A (en) | Construction method for concrete floor in factory building | |
CN102535296B (en) | Construction method of superheavy-load reinforcement-free large-area seamless epoxy self-leveling terrace | |
CN106401144A (en) | Construction technology for addition type wear resisting concrete ground | |
CN108952080A (en) | Concrete dense curing agent abrasion-proof terrace monolithic construction method | |
CN107143111A (en) | A kind of construction method of abrasion-proof terrace | |
CN107060171A (en) | The super flat reinforced concrete flooring of large area and colored diamond dust surface layer one-step moulding method | |
CN103556831B (en) | Huge area is without muscle abrasion-proof concrete method for constructing terrace | |
CN104929365B (en) | Refuse of refuse burning generating plant discharging platform combined type surface construction technology | |
CN104712085A (en) | Large-area wear-resistant concrete ground construction method | |
CN110230380B (en) | Construction method of pouring and tamping integrated grindstone terrace | |
CN105401654A (en) | Environment-friendly assembled type ecological house and construction method thereof | |
CN103206085A (en) | Construction method for heat-insulation waterproofing system of roof comprising foam glass plates | |
CN210195143U (en) | Large-area integral seamless epoxy grindstone artistic floor anti-cracking paving structure | |
CN108468413A (en) | A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering | |
CN106284998A (en) | Plastering on inner walls completely spreads fiberglass gridding cloth construction method | |
CN205840248U (en) | A kind of cast-type concrete abrasion-resistant ground | |
CN103899090A (en) | Premixed slurry fluid foam concrete construction technology | |
CN203716410U (en) | Novel roof grid seam | |
CN204826468U (en) | Environment -friendly perron | |
CN104612343A (en) | Method for constructing extruded polystyrene board molding of building outer wall | |
CN111779226A (en) | Large stone parquet floor and construction method thereof | |
CN203066443U (en) | Ground troweling machine | |
CN104878672A (en) | Stone-planted cement concrete bridge deck paving structure and method | |
CN205329714U (en) | Compound retaining wall structure of highway precast concrete piece | |
CN202248504U (en) | Composite wallboard structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20141029 |