CN104120847A - Construction method for whitewashing-free puttying processing of concrete porous brick wall - Google Patents

Construction method for whitewashing-free puttying processing of concrete porous brick wall Download PDF

Info

Publication number
CN104120847A
CN104120847A CN201410340627.1A CN201410340627A CN104120847A CN 104120847 A CN104120847 A CN 104120847A CN 201410340627 A CN201410340627 A CN 201410340627A CN 104120847 A CN104120847 A CN 104120847A
Authority
CN
China
Prior art keywords
putty
construction method
construction
special putty
special
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410340627.1A
Other languages
Chinese (zh)
Other versions
CN104120847B (en
Inventor
葛明华
丁勇国
陶华
唐建华
张晓卿
宋晓华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Sijian Construction Group Co Ltd
Original Assignee
Nantong Sijian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Sijian Construction Group Co Ltd filed Critical Nantong Sijian Construction Group Co Ltd
Priority to CN201410340627.1A priority Critical patent/CN104120847B/en
Publication of CN104120847A publication Critical patent/CN104120847A/en
Application granted granted Critical
Publication of CN104120847B publication Critical patent/CN104120847B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Paints Or Removers (AREA)

Abstract

The invention discloses a construction method for whitewashing-free puttying processing of a concrete porous brick wall. According to the method, special putty is utilized for replacing a traditional composite mortar floated coat process and is directly puttied on the concrete porous brick wall, quality is stable, the method is free of hollowing and cracking, appearance quality is good, green construction requirements are met, and the usable area is increased at the same time. Thus, the construction method has the advantages of being advanced, practical, economical, environmentally friendly and capable of being applied and popularized widely under the current engineering background.

Description

A kind of concrete perforated brick metope exempts to whitewash the construction method of batch putty processing
Technical field
What the present invention relates to is the construction method that a kind of concrete perforated brick metope exempts to whitewash batch putty processing.
Background technology
Time-consuming when traditional concrete perforated brick wall plaster construction, take a lot of work, Fei Cai, and workmanship is difficult for ensureing, the common quality defect such as hollowing, cracking is comparatively common, is having a strong impact on impression quality and the durability of body of wall, does not also meet requirement energy-saving and cost-reducing, environmental protection.
Summary of the invention
Technical problem to be solved by this invention is to be the problem existing in construction for prior art in concrete perforated brick wall plaster, provides a kind of concrete perforated brick metope to exempt to whitewash the construction method of batch putty processing.
Technical scheme of the present invention is as follows:
Concrete perforated brick metope exempts to whitewash a construction method for batch putty processing, and its step is as follows:
(1) preparation of construction: first with cable inlet bracket, guiding ruler to metope carry out verticality, planeness prediction is known the real situation, install the Founder of the putty base mixing gelling thickness of coating layer on different two sides, negative and positive angle, and ensure that metope is vertical, smooth, negative and positive angle Founder, external corner be straight;
(2) the floating ash in cleaning masonry surface, slurry, rejects post beam face ridge, carries watering the previous day moisteningly, and construction was wetting to body of wall boiling water the same day;
(3) special putty preparation: cement, French chalk, building glue are poured in bucket and stirred and be mixed with paste material by weight 1:2.5:2.6; Wherein, building add water be by cellulose, reinforcing agent and water by weight 0.4:7.5:100 formulated;
(4) wall and frame column intersection perps are filled and led up with special putty, and the wide putty of crowd 300mm pastes the pressing of strengthening grid cloth one deck;
(5) criticize in advance and scrape indivedual concave surfaces, after carry out the thick special putty of bottom 3-5mm and criticize and scrape, after completing, lengthen iron plate with 600mm and catch up with concora crush real, guarantee smooth, vertical;
(6) surface layer special putty is criticized and is scraped, and laterally completely scrapes, and an a plate immediately plate is scraped, and joint must not stay raft;
(7) a batch common putty on special putty finished surface;
(8) carry out according to a conventional method two times emulsion paint brushings.
Described special putty, its preparation is that cement, French chalk, building glue are poured in bucket and stirred and within 3~5 minutes, make it become uniform paste material with portable electric mixer by weight 1:2.5:2.6, leaves standstill 5~10 minutes, again stirs and uses; The special putty of mixing should be finished in 4h, in use, stirs once every 30 minutes again.
Described reinforcing agent is anhydrous calcium chloride.
The present invention replaces conventional hybrid mortar plastering layer process with " special putty ", and directly criticize and scrape on concrete perforated brick metope, steady quality, without hollowing cracking, impression quality is good, meets green construction requirement, has increased usable floor area simultaneously.Therefore, construction method of the present invention has the feature of advanced person, practicality, economy, environmental protection, can wide popularization and application under current engineering background.
The present invention meets the relevant requirements of country about energy conservation project, focus on research and development and the utilization of green main material, strengthen the management of job site simultaneously, strengthening field operation personnel's environmental consciousness, realize monitoring of environment and the pollution-free processing of overall process, technical energy saving, material-saving whitewash in more traditional basic unit, economize on water, save land, environmental benefit significantly improves.
Brief description of the drawings
Fig. 1 is for exempting to whitewash process chart
Detailed description of the invention
Below in conjunction with specific embodiment, the present invention is described in detail.
Embodiment
Invest newly-built scientific research and design business building by Nanjing Municipal Architecture Design and Research Institute Co., Ltd, be positioned at high-tech industrial park, Baixia District, Nanjing, superstructure area is 22200m 2, underground building area is 12800m 2, overall floorage 35000m 2.Method of the present invention is this architectural enforcement, and its concrete grammar is (as Fig. 1) as follows:
(1) preparation of construction: first with cable inlet bracket, guiding ruler to metope carry out verticality, planeness prediction is known the real situation, install the Founder of the putty base mixing gelling thickness of coating layer on different two sides, negative and positive angle, and ensure that metope is vertical, smooth, negative and positive angle Founder, external corner be straight.
(2) the floating ash in cleaning masonry surface, slurry, rejects post beam face ridge, carries watering the previous day moisteningly, and construction was wetting to body of wall boiling water the same day.
(3) special putty preparation: cement, French chalk, building glue are poured in bucket and stirred and be mixed with paste material by weight 1:2.5:2.6.Wherein, to add water be that by weight 0.4:7.5:100 is formulated by cellulose, reinforcing agent (anhydrous calcium chloride) and water to building;
(4) wall and frame column intersection perps are filled and led up with special putty, and the wide putty of crowd 300mm pastes the pressing of strengthening grid cloth one deck.
(5) criticize in advance and scrape indivedual concave surfaces, after carry out the thick special putty of bottom 3-5mm and criticize and scrape, after completing, lengthen iron plate with 600mm and catch up with concora crush real, guarantee smooth, vertical.
(6) surface layer special putty is criticized and is scraped, and laterally completely scrapes, and an a plate immediately plate is scraped, and joint must not stay raft.
(7) a batch common putty on special putty finished surface.
(8) carry out according to a conventional method two times emulsion paint brushings.
Replace conventional hybrid mortar plastering layer process with " special putty ", directly criticize and scrape on concrete perforated brick metope, steady quality, without hollowing cracking, impression quality is good, meets green construction requirement, has increased usable floor area simultaneously, has obtained the favorable comment of each side.
This construction method has unique requirement to materials for wall configuration, keeping and use.
1, concrete perforated brick body of wall medical record
(1) concrete perforated brick is marched into the arena and should be checked work certificate, Performance Detection report, and building block exceedes more than 28 days the length of time.
(2) concrete perforated brick transports floor to and handles with care, stacks neat.
(3) block wall construction deviation must not exceed following standard: verticality 4, planeness 5.Mortar joint, with building with jointing, stays the dark 20mm of 20mm perps jointing with frame column junction; The paper envelope of taping along constructional column Cha Kou and waist rail place mould concreting.
(4) filled wall has been built be allowed for access after 15 days next procedure construction of interval by laying bricks or stones.Before construction to be reserved in water power pipeline hole on metope, after the groove etc. that bursts at the seams, with 1:3 cement mortar or C15 pea gravel concreten fill out embedding closely knit after, can criticize and scrape.
2, concrete perforated brick metope base treatment main points
(1) the floating ash in cleaning masonry surface, slurry, rejects post beam face ridge, carry water the previous day moistening.
(2) wall and frame column intersection perps are filled and led up and are criticized the wide putty of 300mm and paste the compacting of strengthening grid cloth one deck.
(3) guiding ruler inspection indivedual concave surfaces are criticized and scraped in advance.
3, special putty preparation main points
(1) cement, French chalk, building glue are pressed the preparation of constant weight.
(2) pour in bucket and stir and within 3~5 minutes, make it become uniform paste material with portable electric mixer, leave standstill 5~10 minutes, again stir and can use.
(3) having mixed special putty should be finished in 4h, in use, stirs once every 30 minutes again.
4, criticize special putty main points
(1), after local Puttying completes, 600mm lengthens iron plate and catches up with concora crush real, guarantees smooth.
(2) after basic unit is dry, keypoint part is made up a deficiency, mainly adopted flexible waterproof putty to implement operation, treat just can carry out next process construction after putty is done solid work.
(3) laterally completely scrape with squeegee, an a plate immediately plate is scraped, and joint must not stay raft, often scrape when a plate is last to be received, to note receiving efficiently.
(4) adopt sand papering to ensure its planeness in relevant contact site.
5, be coated with surface layer emulsion paint coating main points
(1) need relevant surfaces brushing resin emulsion paint surface layer smearing after putty operation finishes, mainly play alkali resistant, sealing and the effect of joint face coating, be coated with emulsion paint operation and can select 1 road or 2 procedures.
(2) order of brushing is carried out according to first up and then down order, is started by one end, brushes gradually to other one end, note and upper and lower mutually be connected along brush, processes the problem of joint after avoiding appearance to be dried again
(3) before brushing, to be stirred, be made that thickness is consistent in brushing process, coating is even, and must be avoided the generation of holiday situation.
(4) in brushing process, to note brushing gimmick, adopt and upwards exert oneself, the mode of reverberating gently is downwards to reach good effect, and brushing will note setting line of demarcation simultaneously, inner corner trim, leader or partitioning slot etc. taking corner are brushed as boundary, and coating should not be brushed blocked up.
(5) in the process of brushing, will note avoiding inhomogeneous, pop-off size is different from density, meanwhile, carry out surface layer processing according to designing requirement.
Should be understood that, for those of ordinary skills, can be improved according to the above description or convert, and all these improvement and conversion all should belong to the protection domain of claims of the present invention.

Claims (3)

1. concrete perforated brick metope exempts to whitewash a construction method for batch putty processing, it is characterized in that, its step is as follows:
(1) preparation of construction: first with cable inlet bracket, guiding ruler to metope carry out verticality, planeness prediction is known the real situation, install the Founder of the putty base mixing gelling thickness of coating layer on different two sides, negative and positive angle, and ensure that metope is vertical, smooth, negative and positive angle Founder, external corner be straight;
(2) the floating ash in cleaning masonry surface, slurry, rejects post beam face ridge, carries watering the previous day moisteningly, and construction was wetting to body of wall boiling water the same day;
(3) special putty preparation: cement, French chalk, building glue are poured in bucket and stirred and be mixed with paste material by weight 1:2.5:2.6; Wherein, building add water be by cellulose, reinforcing agent and water by weight 0.4:7.5:100 formulated;
(4) wall and frame column intersection perps are filled and led up with special putty, and the wide putty of crowd 300mm pastes the pressing of strengthening grid cloth one deck;
(5) criticize in advance and scrape indivedual concave surfaces, after carry out the thick special putty of bottom 3-5mm and criticize and scrape, after completing, lengthen iron plate with 600mm and catch up with concora crush real, guarantee smooth, vertical;
(6) surface layer special putty is criticized and is scraped, and laterally completely scrapes, and an a plate immediately plate is scraped, and joint must not stay raft;
(7) a batch common putty on special putty finished surface;
(8) carry out according to a conventional method two times emulsion paint brushings.
2. construction method according to claim 1, it is characterized in that, described special putty, its preparation is that cement, French chalk, building glue are poured in bucket and stirred and within 3~5 minutes, make it become uniform paste material with portable electric mixer by weight 1:2.5:2.6, leave standstill 5~10 minutes, again stir and use; The special putty of mixing should be finished in 4h, in use, stirs once every 30 minutes again.
3. construction method according to claim 1, is characterized in that, described reinforcing agent is anhydrous calcium chloride.
CN201410340627.1A 2014-07-16 2014-07-16 A kind of concrete porous brick wall exempts to paint the construction method that batch putty processes Active CN104120847B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410340627.1A CN104120847B (en) 2014-07-16 2014-07-16 A kind of concrete porous brick wall exempts to paint the construction method that batch putty processes

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410340627.1A CN104120847B (en) 2014-07-16 2014-07-16 A kind of concrete porous brick wall exempts to paint the construction method that batch putty processes

Publications (2)

Publication Number Publication Date
CN104120847A true CN104120847A (en) 2014-10-29
CN104120847B CN104120847B (en) 2016-08-31

Family

ID=51766463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410340627.1A Active CN104120847B (en) 2014-07-16 2014-07-16 A kind of concrete porous brick wall exempts to paint the construction method that batch putty processes

Country Status (1)

Country Link
CN (1) CN104120847B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350729A (en) * 2015-11-23 2016-02-24 中国二十冶集团有限公司 Inner wall whitewash-free coating construction method
CN105619546A (en) * 2016-03-10 2016-06-01 广西南宁侨盛木业有限责任公司 System capable of achieving double-sided mechanical and automatic pouring and filling of spackling compound for laminated board
CN107130750A (en) * 2017-06-10 2017-09-05 东莞市华美乐建材超市有限公司 A kind of brushing method of pair of putty layer
CN107304622A (en) * 2016-04-25 2017-10-31 李平远 A kind of integrated special putty construction technology of moistureproof anti-soil
CN107476514A (en) * 2016-06-08 2017-12-15 宜兴市周铁镇生力钻探机械厂 A kind of wall surface putty construction process
CN112031341A (en) * 2020-08-07 2020-12-04 云南亚龙建筑工程有限公司 Construction method of building engineering beneficial to environmental protection

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1414196A (en) * 2001-10-25 2003-04-30 云南建工装饰工程有限公司 External wall magnetic surface whitewash technology
US20030136072A1 (en) * 2001-11-28 2003-07-24 Weiling Peng Panelized wall system utilizing adhesive-edge building panels
CN1532232A (en) * 2003-03-24 2004-09-29 深圳市海川实业股份有限公司 Double component anti-cracking outer wall putty
KR100765437B1 (en) * 2006-06-02 2007-10-09 (주)포산엔지니어링 Pretreatment method of wall painting for a building
CN101215916A (en) * 2008-01-17 2008-07-09 中设建工集团有限公司 Indoor wall surface putty construction process
CN101363269A (en) * 2008-08-13 2009-02-11 中建五局第三建设有限公司 Construction method of anti-plastering putty for concrete structure wall
CN101591485A (en) * 2009-06-10 2009-12-02 巨匠建设集团有限公司 A kind of anti-cracking putty for building and constructional method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1414196A (en) * 2001-10-25 2003-04-30 云南建工装饰工程有限公司 External wall magnetic surface whitewash technology
US20030136072A1 (en) * 2001-11-28 2003-07-24 Weiling Peng Panelized wall system utilizing adhesive-edge building panels
CN1532232A (en) * 2003-03-24 2004-09-29 深圳市海川实业股份有限公司 Double component anti-cracking outer wall putty
KR100765437B1 (en) * 2006-06-02 2007-10-09 (주)포산엔지니어링 Pretreatment method of wall painting for a building
CN101215916A (en) * 2008-01-17 2008-07-09 中设建工集团有限公司 Indoor wall surface putty construction process
CN101363269A (en) * 2008-08-13 2009-02-11 中建五局第三建设有限公司 Construction method of anti-plastering putty for concrete structure wall
CN101591485A (en) * 2009-06-10 2009-12-02 巨匠建设集团有限公司 A kind of anti-cracking putty for building and constructional method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105350729A (en) * 2015-11-23 2016-02-24 中国二十冶集团有限公司 Inner wall whitewash-free coating construction method
CN105619546A (en) * 2016-03-10 2016-06-01 广西南宁侨盛木业有限责任公司 System capable of achieving double-sided mechanical and automatic pouring and filling of spackling compound for laminated board
CN107304622A (en) * 2016-04-25 2017-10-31 李平远 A kind of integrated special putty construction technology of moistureproof anti-soil
CN107476514A (en) * 2016-06-08 2017-12-15 宜兴市周铁镇生力钻探机械厂 A kind of wall surface putty construction process
CN107130750A (en) * 2017-06-10 2017-09-05 东莞市华美乐建材超市有限公司 A kind of brushing method of pair of putty layer
CN112031341A (en) * 2020-08-07 2020-12-04 云南亚龙建筑工程有限公司 Construction method of building engineering beneficial to environmental protection

Also Published As

Publication number Publication date
CN104120847B (en) 2016-08-31

Similar Documents

Publication Publication Date Title
CN104120847A (en) Construction method for whitewashing-free puttying processing of concrete porous brick wall
CN104018598B (en) A kind of external wall structure and construction installation method
CN103321442A (en) Self-compensating repair structure and process for internal stress cracking of inner wall heat insulating wall surface
CN101565997A (en) Construction method for large-area irregular floor tile
CN103821296A (en) Wall plastering technique for aerated concrete block filler wall
CN101942905B (en) Method for treating assembly-type floorslab cracks
CN103643754B (en) The waterproof treatment structure of building wall body interface seam crossing and processing method
CN204826464U (en) Waterproof construction of parapet
CN108468413A (en) A kind of air-entrained concrete building block exempts from anti-hollowing construction method of plastering
CN112267628A (en) Construction method of plastering-free system for interior wall decoration of constructional engineering
CN106284998A (en) Plastering on inner walls completely spreads fiberglass gridding cloth construction method
CN106499066A (en) A kind of method that utilization FS101 mortar waterproof agents carry out building waterproof layer construction
CN103291024B (en) A kind of construction method of novel cement-based motar
CN104453011A (en) Light outer wall structure and construction method thereof
CN113550451A (en) Waterproof construction method for building outer wall
CN103774696A (en) Construction process of cement-based permeable-crystallization type waterproof material
CN102344278A (en) Permeable crystallization type cement-based waterproof mucilage
CN110005174A (en) Improve the construction method of Machine-blasting mortar plastering quality
CN101586367B (en) Method for preventing decorative surfaces of ceramic tiles in shower room from leaking water
CN203834826U (en) Novel staircase water drip tank
CN109853888A (en) A kind of historical building plucking wall surface construction technology
CN207553357U (en) Rubble plate, styrofoam and porous brick compound thermal-insulating decorative exterior wall
CN102182323A (en) Process for dry laying of autoclaved aerated concrete blocks in low-latitude plateaus
CN211949245U (en) Roof stone flashing structure
CN205296610U (en) Limit structure is received to waterproofing membrane facade flashing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant