CN104117412A - Modularized ball mill base and making method thereof - Google Patents
Modularized ball mill base and making method thereof Download PDFInfo
- Publication number
- CN104117412A CN104117412A CN201310147983.7A CN201310147983A CN104117412A CN 104117412 A CN104117412 A CN 104117412A CN 201310147983 A CN201310147983 A CN 201310147983A CN 104117412 A CN104117412 A CN 104117412A
- Authority
- CN
- China
- Prior art keywords
- supporting
- ball mill
- power source
- mill
- feed area
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Crushing And Grinding (AREA)
Abstract
Relating to the field of metallurgical mine equipment installation, the invention specifically provides a modularized ball mill base and a making method thereof. The modularized ball mill base comprises a bottom plate, a ball mill support, a mill feed area support, a transmission part support and a power source support. The modularized ball mill base is characterized in that: the bottom plate includes at least one daughter board; and the ball mill support, the mill feed area support, the transmission part support and the power source support are all disposed on the bottom plate and are connected to the bottom plate by bolts. The whole ball mill base is decomposed into two major functional modules, i.e. a foundation slab meeting the foundation bearing capacity and counterweight requirements and a pedestal of the mill and accessory equipment, and can realize in-situ concrete pouring. By adopting the design, the traditional ball mill base is divided into several modules, thus facilitating positioning and installation of the base, and finally bringing convenience to installation of the ball mill.
Description
Technical field
The present invention relates to metallurgical and mining equipment installing area, be specially a kind of modular Ball Mill Foundation and preparation method thereof.
Background technology
In metallurgical mine Process of Engineering Construction, the grinding machine basis of conventional method design adopts reinforced concrete structure, and the extensive works such as the colligation of reinforcing bar, basic preformed hole, built-in fitting setting, pouring concrete and equipment installation all need complete at building-site.Due to grinding machine basis preformed hole and built-in fitting One's name is legion and its absolute altitude positioning relation quite complicated.The contradiction that reinforcement foundation colligation is difficult, equipment installation is loaded down with trivial details, installation accuracy is poor is particularly outstanding.
Summary of the invention
The object of the present invention is to provide a kind of convenience to transport, improve installation accuracy and guarantee the modularization Ball Mill Foundation of installation quality.
In order to achieve the above object, the present invention is achieved in that
A modular Ball Mill Foundation, it comprises base plate, ball mill supporting, mill feed area supporting, driving member supporting, power source supporting, base plate comprises at least one daughter board; Ball mill supporting, mill feed area supporting, driving member supporting, power source supporting are all located on base plate and with base plate and are connected with bolt.
Described modularization Ball Mill Foundation; Base plate comprises six daughter boards, and ball mill supporting, mill feed area supporting, driving member supporting, power source supporting are located at respectively on described six daughter boards, and these six daughter boards are connected to each other and form base plate.
A preparation method for modular Ball Mill Foundation, it comprises:
Step 1, by design drawing, of steel section, make respectively the framework of daughter board, ball mill supporting, mill feed area supporting, driving member supporting, power source supporting;
Step 2, the framework that daughter board, ball mill supporting, mill feed area supporting, driving member supporting, power source are supported are transported to the job site of Ball Mill Foundation;
Step 3, by the design drawing requirement of Ball Mill Foundation, each daughter board connected with bolt and form base plate, build for the first time to an absolute altitude, more respectively the framework of ball mill supporting, mill feed area supporting, driving member supporting, power source supporting is connected on base plate with bolt by drawing;
Step 4, the framework that grinding machine supporting, ball mill feed area supporting, driving member supporting, power source are supported are implemented pouring concrete operation makes it form Ball Mill Foundation.
The present invention adopts above-mentioned design, and it is divided into some modules by traditional Ball Mill Foundation, thereby has facilitated basic location, installment work, finally for the installation of ball mill offers convenience.
Accompanying drawing explanation
Fig. 1 is the top view of base plate of the present invention.
Fig. 2 is structural representation of the present invention.
The specific embodiment
By specific embodiment, further illustrate the present invention below.
As shown in Figure 1 and Figure 2, a kind of modular Ball Mill Foundation, it comprises base plate 1, ball mill supporting 4, mill feed area supporting 3, driving member supporting 2, power source supporting 6, base plate 1 consists of six daughter boards 12,13,14,15,16,17; Ball mill supporting 4, mill feed area supporting 3, driving member supporting 2, power source supporting 6 are located at respectively on daughter board 12,13,14,15,16,17 and with daughter board and are connected with bolt.
A preparation method for modular Ball Mill Foundation, it comprises:
Step 1, by design drawing, of steel section, make respectively the framework of daughter board 12,13,14,15,16,17, ball mill supporting 4, mill feed area supporting 3, driving member supporting 2, power source supporting 6;
Step 2, the framework of daughter board 12,13,14,15,16,17, ball mill supporting 4, mill feed area supporting 3, driving member supporting 2, power source supporting 6 is transported to the job site of Ball Mill Foundation;
Step 3, by the design drawing requirement of Ball Mill Foundation, each daughter board 12,13,14,15,16,17 use bolts connected and form base plate 1, build for the first time to an absolute altitude, more respectively the framework of ball mill supporting 4, mill feed area supporting 3, driving member supporting 2, power source supporting 6 is connected on base plate 1 with bolt by drawing;
Thereby step 4, with concrete, the framework of ball mill supporting 4, mill feed area supporting 3, driving member supporting 2, power source supporting 6 is implemented to pouring concrete operation for the second time and make its final Ball Mill Foundation that forms.
The present invention adopts above-mentioned design, and it is divided into some modules by traditional Ball Mill Foundation, thereby has facilitated basic location, installment work, finally for the installation of ball mill offers convenience.
Claims (3)
1. a modular Ball Mill Foundation, it comprises base plate, ball mill supporting, mill feed area supporting, driving member supporting, power source supporting, it is characterized in that: ball mill supporting, mill feed area supporting, driving member supporting, power source supporting are all located on base plate and with base plate and are connected with bolt.
2. modularization Ball Mill Foundation according to claim 1; It is characterized in that: base plate comprises six daughter boards, ball mill supporting, mill feed area supporting, driving member supporting, power source supporting are located at respectively on described six daughter boards, and these six daughter boards are connected to each other and form base plate.
3. a preparation method for modular Ball Mill Foundation, it comprises:
Step 1, by design drawing, of steel section, make respectively the framework of daughter board, ball mill supporting, mill feed area supporting, driving member supporting, power source supporting;
Step 2, the framework that daughter board, ball mill supporting, mill feed area supporting, driving member supporting, power source are supported are transported to the job site of Ball Mill Foundation;
Step 3, by the design drawing requirement of Ball Mill Foundation, each daughter board connected with bolt and form base plate, build for the first time to an absolute altitude, more respectively the framework of ball mill supporting, mill feed area supporting, driving member supporting, power source supporting is connected on base plate with bolt by drawing;
Step 4, the framework that ball mill supporting, mill feed area supporting, driving member supporting, power source are supported make it form Ball Mill Foundation with the pouring practice of concrete enforcement second coagulation soil respectively.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310147983.7A CN104117412B (en) | 2013-04-26 | 2013-04-26 | A kind of modular Ball Mill Foundation and preparation method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310147983.7A CN104117412B (en) | 2013-04-26 | 2013-04-26 | A kind of modular Ball Mill Foundation and preparation method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104117412A true CN104117412A (en) | 2014-10-29 |
CN104117412B CN104117412B (en) | 2016-09-28 |
Family
ID=51763179
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310147983.7A Active CN104117412B (en) | 2013-04-26 | 2013-04-26 | A kind of modular Ball Mill Foundation and preparation method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104117412B (en) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2152640Y (en) * | 1993-04-02 | 1994-01-12 | 李才恩 | Rubber roller ball mill |
CN2366175Y (en) * | 1999-04-26 | 2000-03-01 | 李成斌 | Circular cone type ball mill |
JP2003181316A (en) * | 2001-12-17 | 2003-07-02 | Nippon Airitsuhi Kk | Medium agitation and crushing device and crushing treatment system having the device |
CN202238195U (en) * | 2011-09-19 | 2012-05-30 | 鞍钢集团矿业公司 | Various automatic spherical ball feeders for ball mill |
CN202273826U (en) * | 2011-08-28 | 2012-06-13 | 山东科瑞压缩机有限公司 | Separated-type base of large-scale compressor set |
CN202274242U (en) * | 2011-09-28 | 2012-06-13 | 安徽省宿州市龙华机械制造有限公司 | Split type base of transportation winch |
CN202343262U (en) * | 2011-12-01 | 2012-07-25 | 李志宏 | Sand-making ball grinder |
-
2013
- 2013-04-26 CN CN201310147983.7A patent/CN104117412B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2152640Y (en) * | 1993-04-02 | 1994-01-12 | 李才恩 | Rubber roller ball mill |
CN2366175Y (en) * | 1999-04-26 | 2000-03-01 | 李成斌 | Circular cone type ball mill |
JP2003181316A (en) * | 2001-12-17 | 2003-07-02 | Nippon Airitsuhi Kk | Medium agitation and crushing device and crushing treatment system having the device |
CN202273826U (en) * | 2011-08-28 | 2012-06-13 | 山东科瑞压缩机有限公司 | Separated-type base of large-scale compressor set |
CN202238195U (en) * | 2011-09-19 | 2012-05-30 | 鞍钢集团矿业公司 | Various automatic spherical ball feeders for ball mill |
CN202274242U (en) * | 2011-09-28 | 2012-06-13 | 安徽省宿州市龙华机械制造有限公司 | Split type base of transportation winch |
CN202343262U (en) * | 2011-12-01 | 2012-07-25 | 李志宏 | Sand-making ball grinder |
Also Published As
Publication number | Publication date |
---|---|
CN104117412B (en) | 2016-09-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204054323U (en) | Steel construction assembled beam making bench | |
CN109505609B (en) | Bracket-free construction method for underground comprehensive pipe rack of shallow-buried underground excavation city and comprehensive pipe rack | |
CN201901879U (en) | Nonstandard foundation used for fixing tower crane | |
CN202117341U (en) | Template for embedding foundation bolts of steel structures of buildings | |
CN203474271U (en) | Special assembly type rail base for portal crane | |
CN105544605A (en) | Modular assembly type comprehensive pipe gallery | |
CN101659088B (en) | Steel structure mixing station base and implementation method thereof | |
CN204212442U (en) | A kind of hi-Fix guiding device | |
CN103031892A (en) | Steel truss brace and manufacturing method for steel truss platform | |
CN202097833U (en) | Steel-concrete girder fabricating pedestal with small independent concrete foundations | |
CN104117412A (en) | Modularized ball mill base and making method thereof | |
CN104074275A (en) | Prefabricated concrete column connecting joint structure | |
CN203756190U (en) | Trolley device for herringbone forked tunnel | |
CN204173804U (en) | A kind of inside-climbing tower crane of structural beams bearing-type is installed and climbing structure | |
CN203253489U (en) | Modular ball mill foundation | |
CN104314318A (en) | High-precision positioning guide device and use method thereof | |
CN104234258A (en) | Building block and reinforced concrete laminated wall and construction method thereof | |
CN204199323U (en) | For the positioning screw hole mould of pre-embedded bolt quick position | |
CN204185966U (en) | Building block and reinforced concrete sandwich body of wall | |
CN203359339U (en) | Unit-type detachable steel bar raw material stacking platform | |
CN110748155B (en) | Support device for large-diameter silo conical hopper concrete construction template and construction method thereof | |
CN105715055B (en) | A kind of nuclear power station large size penetration piece adjustable tool and adjusting method | |
CN103225312A (en) | Prefabricated assembled foundation of tower mast structure | |
CN202787300U (en) | Control form for positions of foundation bolts of fixed tower crane | |
CN203008232U (en) | Steel truss strut |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder | ||
CP01 | Change in the name or title of a patent holder |
Address after: 330031 No. 888, Qian Hu Road, Hongjiao Island, Nanchang, Jiangxi. Patentee after: CHINA NERIN ENGINEERING Co.,Ltd. Patentee after: China 20th Metallurgical Group Co., Ltd Address before: 330031 No. 888, Qian Hu Road, Hongjiao Island, Nanchang, Jiangxi. Patentee before: CHINA NERIN ENGINEERING Co.,Ltd. Patentee before: China 20th Metallurgical Group Co., Ltd |