CN104091247A - Production plan management system and method - Google Patents

Production plan management system and method Download PDF

Info

Publication number
CN104091247A
CN104091247A CN201410372302.1A CN201410372302A CN104091247A CN 104091247 A CN104091247 A CN 104091247A CN 201410372302 A CN201410372302 A CN 201410372302A CN 104091247 A CN104091247 A CN 104091247A
Authority
CN
China
Prior art keywords
production
plan
management system
information
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410372302.1A
Other languages
Chinese (zh)
Inventor
巫乔顺
刘超
杨晓伟
陈子敏
熊添翼
杨雁杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Iron and Steel Group Kunming Iron and Steel Co Ltd
Original Assignee
Wuhan Iron and Steel Group Kunming Iron and Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Iron and Steel Group Kunming Iron and Steel Co Ltd filed Critical Wuhan Iron and Steel Group Kunming Iron and Steel Co Ltd
Priority to CN201410372302.1A priority Critical patent/CN104091247A/en
Publication of CN104091247A publication Critical patent/CN104091247A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

The invention discloses a production plan management system and method. The production plan management system comprises a compiling module, an adjusting module and an issuing module. The production plan management method comprises the following steps: establishing a steel plant production plan and saving the steel plant production plan into the production plan management system; providing basic data support for the compiling module; and processing the production plan in the production plan management system by the data compiling module and the data adjusting module through the data issuing module, and saving and issuing the processed production plan to a steel plant production execution system. According to the production plan management system and method, melt and cast information is automatically formed by a production planning department according to a scheduled output; and a network and a database resource are used for supporting the operation of the system, saving melt and cast data and tracing and realizing full-process track management by an operation log. A manual standing book is not needed, and the melt and cast data is accurately issued; the speed of information flow among all departments of iron and steel enterprises is increased.

Description

A kind of production planning management system and method
Technical field
The invention belongs to field of computer technology, be specifically related to a kind of production planning management system and method.
Background technology
At present between production schedule department of iron and steel enterprise and steelworks production management department, there is no specific heat, a casting plan, is all often that the dispatcher by steelworks Central Control Room follows the manual account making their own according to field condition.The major defect of this disposal route is: operation promptness can not be guaranteed, and operator can not guarantee to follow according to on-the-spot heat, water time condition of production makes plan adjustment in time; There is no system support, in steelworks the dispatcher of control room, relevant departments such as total adjusting, production schedule portion do not know to organize heat in this manufacturing program of a month completely, waters time production real-time condition, must from artificial account, go analysis, it is this that to have paper to do work mode extremely backward; Manual account data are inconvenient to manage, if heat, water and time occur error in data and File lose this all will cause very large loss, it is quite unfavorable that tissue is produced.Therefore developing a kind of management system that can address the above problem is very important.
Summary of the invention
The first object of the present invention is to provide a kind of production planning management system; The second object is to provide the using method of described production planning management system.
The first object of the present invention is achieved in that and comprises compiling module, adjusting module, issues module, wherein:
Compiling module: for according to the blank information with design according to group stove principle by the order formation plan that combines;
Adjusting module: for according to the timely plan for adjustment of production information;
Issue module: for the plan information weaving is confirmed one by one, and issue guidance production.
The second object of the present invention is achieved in that and comprises the following steps:
A, the manufacturing program of a month of setting up in ERP System according to production schedule portion, download plan information to be saved in production planning management system simultaneously, for compiling module provides data, reads support;
B, by read the steelworks production schedule information of this month from production planning management system, according to group stove standard establishment heat information, then heat plan is saved in production management system;
C, from production management system, read heat information, according to group, water the adjustment of principle standard and choose the casting plan that needs the heat information of inserting and form steelworks, and casting plan information is saved in production management system;
D, adjusting module, by read time information of watering from production management system, form this production according to production specification and water inferior cut-over plan, and cut-over plan information is saved in production management system;
E, steelworks are produced after casting plan and the confirmation of cut-over plan You Zongtiao department, instruct steelworks tissue to produce the data distributing after confirming in steelworks production executive system, complete the production planning management flow process of steelworks.
The present invention solve steelworks in organizing production run to heat, water time not in time, not rigorous and can chase after retrospective and the inadequate problem of continuity, provide a kind of production schedule portion of connecting to water method with automatic group of stove group in the production of steelworks tissue.The raw data that group stove group is watered by from SAP system downloads to MES, then resolves into batch plan by production schedule portion, after the data arrival database of a certain portion, triggers the operation that next step group stove group is watered after the processing such as judgement.Whole process can form heat in time, accurately, water secondary data, and has and can chase after retrospective and data continuity, triggers next step flow performing, has improved information flow transmission efficiency.The present invention makes production schedule portion automatically form heat, water time information according to scheduled production, utilize network and database resource come back-up system operation, preserve heat, water secondary data and the management of Operation Log all-the-way tracking.Without manual account, the data that issue heat, water time promptly and accurately, improve the interdepartmental information flow speed of iron and steel enterprise.
Accompanying drawing explanation
Fig. 1 is production planning management system schematic diagram of the present invention;
Fig. 2 is heat of the present invention, water time establishment schematic flow sheet;
Fig. 3 is heat of the present invention, water time changing process schematic diagram.
Embodiment
Below in conjunction with accompanying drawing, the present invention is further illustrated, but never in any form the present invention is limited, and any conversion or the replacement based on training centre of the present invention, done, all belong to protection scope of the present invention.
Production planning management system, is characterized in that comprising compiling module, adjusting module, issues module, wherein:
Compiling module: for according to the blank information with design according to group stove principle by the order formation plan that combines;
Adjusting module: for according to the timely plan for adjustment of production information;
Issue module: for the plan information weaving is confirmed one by one, and issue guidance production.
Blank information described in compiling module is the trade mark, specifications section, length, standard No. and remaining material whether.
Group stove principle described in compiling module is that section is identical, the trade mark is identical, stove is counted scope.
Order combination described in compiling module is that one or several condition of producing in line, product form or means of transportation according to delivery date, priority, Plant maintenance plan, production combines.
Plan described in compiling module be heat plan, batch time plan, casting plan and cut-over plan.
Production information described in adjusting module is inferior for watering, steel rolling will be expected situation, equipment operation situation, iron-smelter hot metal supply situation, alloy auxiliary material supply situation and energy management and control situation.
Plan described in adjusting module is casting plan, heat plan and cut-over plan.
Issuing the plan information described in module is casting plan information and cut-over plan information.
The using method of production planning management system of the present invention, is characterized in that comprising the following steps:
A, the manufacturing program of a month of setting up in ERP System according to production schedule portion, download plan information to be saved in production planning management system simultaneously, for compiling module provides data, reads support;
B, by read the steelworks production schedule information of this month from production planning management system, according to group stove standard establishment heat information, then heat plan is saved in production management system;
C, from production management system, read heat information, according to group, water the adjustment of principle standard and choose the casting plan that needs the heat information of inserting and form steelworks, and casting plan information is saved in production management system;
D, adjusting module, by read time information of watering from production management system, form this production according to production specification and water inferior cut-over plan, and cut-over plan information is saved in production management system;
E, steelworks are produced after casting plan and the confirmation of cut-over plan You Zongtiao department, instruct steelworks tissue to produce the data distributing after confirming in steelworks production executive system, complete the production planning management flow process of steelworks.
Production planning system of the present invention issues module by steel-making plan compiling module, steel-making plan adjusting module, steel-making plan.Steel-making plan compiling module: according to group stove principle, qualified order is got up to form a heat plan according to conditional combinations such as delivery date, priority according to the blank information having designed, simultaneity factor generates cut-over plan according to heat plan, again existing heat plan is watered to principle according to group and be combined into casting plan, finally casting plan is handed down to steelworks.Steel-making plan adjusting module: adjust and comprise casting plan, heat plan adjustment, watering of steelworks is inferior for issuing.According to equipment operation situation, steel rolling, to expect that situation adjusts steel-making plan in time.When watering can not delete while time having gone into operation, water time, can only carry out the change of heat quantity, insert or delete heat.Steel-making plan issues module: the casting plan information weaving is confirmed one by one, and be handed down to STEELMAKING PRODUCTION control and make steel operation scheduling, instruct steelworks tissue to produce.
Wherein organizing stove group waters the method for establishment and is:
1, producing order obtains: receive the production order of crossing through design of material;
2, production order volume statistics; Statistics is produced order and whether is met heat size and group stove standard;
3, group stove: follow according to group stove standard (trade mark is identical, section is identical, in heat size, remaining material minimizes) and organize stove;
4, heat obtains; First get and meet the heat that group is watered;
5, group is watered: a plurality of heats are watered to standard (section is identical, the trade mark is identical, stove count scope) by group and form one and water time tissue and produce;
Wherein organize stove group and water the method for adjustment:
1, casting plan obtains: choose the casting plan that needs adjustment;
2, water time lower whole heats cancellations; Cancel whole water time, first delete all heats under watering time;
3, water time cancellation: water time whole deletion;
4, need the heat of cancellation to choose; Choose the heat information that needs deletion;
5, heat is cancelled: delete the heat information under corresponding water time;
6, being inserted into heat information chooses: choose the heat information that will insert casting plan
7, heat inserts: follow according to metallurgic index code, group water standard again group water
8, steel-making plan adjustment finishes: adjust and finish
Method of the present invention is for automatically forming heat, casting plan between iron and steel enterprise's production planning management system and steelworks management system, when steelworks is handed down to heat, casting plan in production schedule department, by the mode automatically issuing, process, and all leave operation note in each operation.
Heat between production planning system and steelworks management system in the present invention, water the method that time information issues automatically, comprise that producing order chooses module 1, group oven module 2, group is watered module 3, water time adjusting module 4, water secondary data and issue module 5, as shown in Figure 1, production order module 1 is issued and is obtained data by production schedule portion, by group oven module 2, according to group stove standard, generate heat number, by group, watering module 3 generates and waters inferior number according to the group standard of watering, total tune by adjusting module 4 adjusted actual demand in steel refinery, finally by data distributing module 5, issue time information of watering, if success, just data mode is for issuing, steelworks is with organizing production according to watering time information.
Feature of the present invention:
1, the sequence information that need to produce is adopted the Ministry of worker by production and is issued and obtain from SAP automatic acquisition;
2, group stove, group is watered standard and is come according to producing trade mark maintenance of information by production technology chamber;
3, watering time information data transmits by intranet;
4, whole process is all followed and according to standard, is automatically organized stove, group and water need not manually participate in calculating and participate in:
As shown in Figure 2, this figure shows to organize stove group and waters working-flow and realize disposal route, and concrete methods of realizing is as follows:
1) select specification, sequence information that the trade mark is identical;
2) according to group stove standard, automatically generate the heat information of the trade mark;
3) according to group stove standard, automatically generate the heat information of the trade mark;
4) with watering information according to automatically organizing stove group, link up whether close production requirement with steelworks, not so adjust time information of watering;
5) water time information and be issued to steelworks;
6), when new order data arrives, repeat above-mentioned steps.

Claims (9)

1. a production planning management system, is characterized in that comprising compiling module, adjusting module, issues module, wherein:
Compiling module: for according to the blank information with design according to group stove principle by the order formation plan that combines;
Adjusting module: for according to the timely plan for adjustment of production information;
Issue module: for the plan information weaving is confirmed one by one, and issue guidance production.
2. production planning management system according to claim 1, is characterized in that the blank information described in compiling module is the trade mark, specifications section, length, standard No. and remaining material whether.
3. production planning management system according to claim 1, is characterized in that the group stove principle described in compiling module is that section is identical, the trade mark is identical, stove is counted scope.
4. production planning management system according to claim 1, is characterized in that the order combination described in compiling module is that one or several condition of producing in line, product form or means of transportation according to delivery date, priority, Plant maintenance plan, production combines.
5. production planning management system according to claim 1, is characterized in that the plan described in compiling module is heat plan, batch plan, casting plan and cut-over plan.
6. production planning management system according to claim 1, is characterized in that the production information described in adjusting module is inferior for watering, steel rolling will be expected situation, equipment operation situation, iron-smelter hot metal supply situation, alloy auxiliary material supply situation and energy management and control situation.
7. production planning management system according to claim 1, is characterized in that the plan described in adjusting module is casting plan, heat plan and cut-over plan.
8. production planning management system according to claim 1, it is characterized in that issuing the plan information described in module is casting plan information and cut-over plan information.
9. a using method for production planning management system claimed in claim 1, is characterized in that comprising the following steps:
A, the manufacturing program of a month of setting up in ERP System according to production schedule portion, download plan information to be saved in production planning management system simultaneously, for compiling module provides data, reads support;
B, by read the steelworks production schedule information of this month from production planning management system, according to group stove standard establishment heat information, then heat plan is saved in production management system;
C, from production management system, read heat information, according to group, water the adjustment of principle standard and choose the casting plan that needs the heat information of inserting and form steelworks, and casting plan information is saved in production management system;
D, adjusting module, by read time information of watering from production management system, form this production according to production specification and water inferior cut-over plan, and cut-over plan information is saved in production management system;
E, steelworks are produced after casting plan and the confirmation of cut-over plan You Zongtiao department, instruct steelworks tissue to produce the data distributing after confirming in steelworks production executive system, complete the production planning management flow process of steelworks.
CN201410372302.1A 2014-07-31 2014-07-31 Production plan management system and method Pending CN104091247A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410372302.1A CN104091247A (en) 2014-07-31 2014-07-31 Production plan management system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410372302.1A CN104091247A (en) 2014-07-31 2014-07-31 Production plan management system and method

Publications (1)

Publication Number Publication Date
CN104091247A true CN104091247A (en) 2014-10-08

Family

ID=51638962

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410372302.1A Pending CN104091247A (en) 2014-07-31 2014-07-31 Production plan management system and method

Country Status (1)

Country Link
CN (1) CN104091247A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106269894A (en) * 2015-05-27 2017-01-04 鞍钢股份有限公司 A kind of control method of the automatic predetermined slab plan of continuous casting
CN108182535A (en) * 2017-12-28 2018-06-19 鞍钢集团朝阳钢铁有限公司 A kind of material information management method
CN110322190A (en) * 2019-05-28 2019-10-11 唐山钢铁集团有限责任公司 The method that steel industry intrabranch service order based on SAP automatically creates
CN112712246A (en) * 2020-12-25 2021-04-27 包头钢铁(集团)有限责任公司 Method for centralized batch production of falling plate blanks
CN113245372A (en) * 2021-05-26 2021-08-13 重庆钢铁股份有限公司 Hot-rolled strip steel production control method and system
CN113627736A (en) * 2021-07-19 2021-11-09 常州皓鸣信息科技有限公司 Gantt chart-based plan scheduling system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090259331A1 (en) * 2008-04-15 2009-10-15 Honeywell International, Inc. Automated system for checking proposed human adjustments to operational or planning parameters at a plant
CN101770615A (en) * 2010-01-25 2010-07-07 重庆大学 Steelmaking-continuous casting production operation plan and real-time dispatching optimization method and system based on mixed intelligent optimization algorithm
CN101786146A (en) * 2009-12-30 2010-07-28 东北大学 Online steelmaking continuous casting control method
CN102496095A (en) * 2011-11-24 2012-06-13 北京首钢自动化信息技术有限公司 Hot-charging logistics tracking, monitoring and dynamic scheduling system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090259331A1 (en) * 2008-04-15 2009-10-15 Honeywell International, Inc. Automated system for checking proposed human adjustments to operational or planning parameters at a plant
CN101786146A (en) * 2009-12-30 2010-07-28 东北大学 Online steelmaking continuous casting control method
CN101770615A (en) * 2010-01-25 2010-07-07 重庆大学 Steelmaking-continuous casting production operation plan and real-time dispatching optimization method and system based on mixed intelligent optimization algorithm
CN102496095A (en) * 2011-11-24 2012-06-13 北京首钢自动化信息技术有限公司 Hot-charging logistics tracking, monitoring and dynamic scheduling system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
於春月: "钢铁一体化生产计划与调度优化问题研究", 《中国博士学位论文全文数据库 经济与管理科学辑》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106269894A (en) * 2015-05-27 2017-01-04 鞍钢股份有限公司 A kind of control method of the automatic predetermined slab plan of continuous casting
CN106269894B (en) * 2015-05-27 2017-12-05 鞍钢股份有限公司 A kind of control method of continuous casting predetermined slab plan automatically
CN108182535A (en) * 2017-12-28 2018-06-19 鞍钢集团朝阳钢铁有限公司 A kind of material information management method
CN108182535B (en) * 2017-12-28 2020-06-16 鞍钢集团朝阳钢铁有限公司 Material information management method
CN110322190A (en) * 2019-05-28 2019-10-11 唐山钢铁集团有限责任公司 The method that steel industry intrabranch service order based on SAP automatically creates
CN112712246A (en) * 2020-12-25 2021-04-27 包头钢铁(集团)有限责任公司 Method for centralized batch production of falling plate blanks
CN112712246B (en) * 2020-12-25 2023-02-21 包头钢铁(集团)有限责任公司 Method for centralized batch production of falling plate blanks
CN113245372A (en) * 2021-05-26 2021-08-13 重庆钢铁股份有限公司 Hot-rolled strip steel production control method and system
CN113245372B (en) * 2021-05-26 2023-01-31 重庆钢铁股份有限公司 Hot-rolled strip steel production control method and system
CN113627736A (en) * 2021-07-19 2021-11-09 常州皓鸣信息科技有限公司 Gantt chart-based plan scheduling system
CN113627736B (en) * 2021-07-19 2023-05-26 常州皓鸣信息科技有限公司 Gantt chart-based planning and scheduling system

Similar Documents

Publication Publication Date Title
CN104091247A (en) Production plan management system and method
CN101303588B (en) Method and system for automatically making sub batch plan for steel-smelting continuous casting furnace
CN1885328B (en) Steelmaking-continuous casting tundish batch plan method and system
CN111126748A (en) Dynamic production plan scheduling method for discrete manufacturing industry
CN103116813A (en) Method of intelligent navigation for manufacturing operations of real-time information-driven production equipment
CN109359884A (en) Aviation complex equipment structural member Production Scheduling Problem and rescheduling method
CN104483915A (en) Hot rolling multiple production line slab matching control method for improving steel enterprise material utilization rate
CN104835012A (en) Iron and steel enterprise production scheduling management system and production scheduling management method
CN113506081A (en) Production plan management system and production scheduling method thereof
Dombrowski et al. Industrie 4.0 in production ramp-up management
CN103824136A (en) MES (Manufacturing Execution System) dynamic workshop scheduling and manufacturing execution system
CN106779220A (en) A kind of steel-making continuous casting hot rolling integrated scheduling method and system
TW201714122A (en) Production scheduling method and automatically scheduling system
CN104635683B (en) A kind of smelter whole process unit Productivity Allocation control method
CN101944202A (en) Just-in-time-based parallel forward calculation programing method for steel-making production planned time
CN111523803A (en) Factory transparent management method
CN109615165A (en) A kind of Flexible Manufacture dispatching method based on ERP Yu MES data interaction technique
Gao et al. Construction of intelligent manufacturing workshop based on lean management
CN101344781B (en) Plate coil automatic scheduling method and system for cold rolling hot galvanizing units
JP2017068788A (en) Device for planning steel making and rolling, method and program for planning steel making and rolling
CN101833322A (en) Expert system and control method applied to blast furnace-converter sector production scheduling process control of steel enterprises
CN102419581A (en) HRCEA (hybrid of rules and compression-extensive algorithm)-based steel making-continuous casting production scheduling method for special steel mill
CN111459116B (en) Efficient tube intelligent production line digital management system
CN107516149B (en) Enterprise supply chain management system
CN104504484A (en) Coating production scheduling management system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20141008