CN104074370B - 一种砖混结构建筑物整体过河平移方法及其专用托换装置 - Google Patents

一种砖混结构建筑物整体过河平移方法及其专用托换装置 Download PDF

Info

Publication number
CN104074370B
CN104074370B CN201410332708.7A CN201410332708A CN104074370B CN 104074370 B CN104074370 B CN 104074370B CN 201410332708 A CN201410332708 A CN 201410332708A CN 104074370 B CN104074370 B CN 104074370B
Authority
CN
China
Prior art keywords
building
steel
flitch
channel
river
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410332708.7A
Other languages
English (en)
Other versions
CN104074370A (zh
Inventor
陈�胜
祁红
李保亮
宋伟伟
陈辉
祁超
黄登楼
万华
张国栋
刘辕
宋建春
宋在云
胡爱明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huaian Boyan Civil Engineering Research Institute Co., Ltd.
Original Assignee
陈�胜
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 陈�胜 filed Critical 陈�胜
Priority to CN201410332708.7A priority Critical patent/CN104074370B/zh
Publication of CN104074370A publication Critical patent/CN104074370A/zh
Application granted granted Critical
Publication of CN104074370B publication Critical patent/CN104074370B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种砖混结构建筑物整体过河平移方法及其专用托换装置,一种砖混结构建筑物整体过河平移方法,其特征在于:包括如下步骤,基础处理、河道处理、建筑物托换、建筑物牵引、就位连接。本发明有效解决了现有建筑物整体平移过程中传统的平移托换装置,重复利用率低,导致工程造价高的问题,而且有效解决了传统平移方法若选择过桥平移则可能涉及平移路程较远、桥面标高与建筑标高不同,建筑物平移过程中涉及建筑物的整体升降,且影响桥梁的正常使用问题。

Description

一种砖混结构建筑物整体过河平移方法及其专用托换装置
技术领域
本发明涉及建筑物整体平移技术领域,具体涉及一种砖混结构建筑物整体过河平移方法及其专用托换装置。
背景技术
目前,我国经济发展和城市化进程的不断加速,大规模的城市再建设和旧城改造在全国各地正如火如茶地开展,在此过程中,有大量的建筑物面临着被强制拆除,其中包括一大部分建造时间不长,仍具有较大使用价值,但与城市发展规划相冲突的建筑物。建筑物拆迁为建设单位带了巨大经济损失,又带了建筑垃圾和噪声污染。因此,建筑物整体移位技术为城市建设提供了一条新思路。建筑物整体移位是指在保持房屋整体性和可用性不变的前提下,将上部建筑与基础分离,在机械动力作用下使上部建筑从原址移动到新址的过程。
在建筑物整体平移过程中,上轨道梁和上轨道梁一般都是临时性结构,重复性利用率低,但却是除新基础外造价最高的分项工程,平移距离较长时,则会远远超过一半平移费用。
另外,经检索目前国内未有建筑物整体过河平移案例,建筑物整体过河平移必须避免可能出现的不均匀沉降对建筑结构的不利影响,如果选择过桥平移则可能涉及平移路程较远、桥面标高与建筑标高不同,建筑物平移过程中涉及建筑物的整体升降,且影响桥梁的正常使用。
发明内容
本发明要解决的技术问题是提供一种砖混结构建筑物整体过河平移方法及其专用托换装置,本发明有效解决了现有建筑物整体平移过程中传统的平移托换装置,重复利用率低,导致工程造价高的问题,而且有效解决了传统平移方法若选择过桥平移则可能涉及平移路程较远、桥面标高与建筑标高不同,建筑物平移过程中涉及建筑物的整体升降,且影响桥梁的正常使用问题。
本发明通过以下技术方案实现:
1、一种砖混结构建筑物整体过河平移方法,其特征在于:包括如下步骤,
1)、基础处理:在新旧基础过渡段平移轴线上铺设1.6米宽12㎜厚钢板;
2)、河道处理:包括河道的围堰、抽水、清淤、回填,回填过程中采用废料钢渣或1:1砂石进行回填,回填高度同原基础基顶标高相同,回填过程中采用铁三轮压路机分层碾压,经静载荷检测承载力不低于原基础承载力;
3)、建筑物托换:采用托换装置以原地圈梁作为托盘,直接利用千斤顶和内衬木方槽钢简支梁完成上部结构和旧基础的分离及托换,以内衬木方的长槽钢作为上轨道梁和下轨道梁,基础顶面以横向排放500mm长木方作为枕木;
4)、建筑物牵引:施加牵引力的地圈梁平齐处外设一道工字钢刚性梁;
5)、就位连接:上部结构就位、托换、基础连接。
本发明通过以下技术方案实现:
一种用于如权利要求1所述砖混结构建筑物整体过河平移方法的专用托换装置,其特征在于:包括墙体(1)、地圈梁(2)以及原混凝土基础层(3),其特征在于:所述原混凝土基础层(3)上设置有找平层(4),地圈梁(2)下方设置有简支梁(5),简支梁(5)两端与找平层(4)之间设置有千斤顶(6),简支梁(5)中间位置与找平层(4)之间设置有滚轴(9),滚轴(9)与简支梁(5)之间设置有上轨道梁(10),滚轴(9)与找平层(4)之间依次设置有下轨道梁(8)以及枕木(7)。
本发明进一步解决的技术方案为:
所述简支梁(5)由槽钢(51)及内衬木方(52)构成。
本发明进一步解决的技术方案为:
所述上轨道梁(10)由两根平行设置的槽钢(101)组成,槽钢(101)内衬有木方(102),所述下轨道梁(8)由两根平行设置的槽钢(81)组成,槽钢(81)内衬有木方(82)。
本发明进一步解决的技术方案为:
所述滚轴(9)由中空钢管制成,钢管内填充有混凝土。
本发明进一步解决的技术方案为:
所述滚轴(9)直径为100~200mm,长度400~500mm。
本发明与现有技术相比,具有以下明显优点:
本发明利直接利用原地圈梁作为托换底盘,在牵引施力点处加装了工字钢刚性梁,利用纵向地圈梁下的枕木以及与之叠合的钢木结构的轨道梁加强了平移行走过程中的承载能力和整体稳定性;利用千斤顶加型钢简支梁直接完成上部结构与旧基础的分离托换;直接使用槽钢衬方木作为下轨道梁,并随着牵引平移的进度流水铺设,用量少、铺设快、无损耗,且可重复使用。以上施工方法,相比传统完全采用混凝土现浇托换梁、行走梁以及加固支撑的做法,大大地缩短了工期、节约了造价。
附图说明
图1为本发明实例基础平面图;
图2为本发明实例托换结构示意图。
具体实施方式
如图2所示,本发明包括墙体1、地圈梁2以及原混凝土基础层3,原混凝土基础层3上设置有找平层4,地圈梁2下方设置有简支梁5,简支梁5两端与找平层4之间设置有千斤顶6,简支梁5中间位置与找平层4之间设置有滚轴9,滚轴9与简支梁5之间设置有上轨道梁10,滚轴9与找平层4之间依次设置有下轨道梁8以及枕木7;简支梁5由槽钢51及内衬木方52构成;上轨道梁10由两根平行设置的槽钢101组成,槽钢101内衬有木方102;下轨道梁8由两根平行设置的槽钢81组成,槽钢81内衬有木方82;滚轴9由中空钢管制成,钢管内填充有混凝土,滚轴9直径为100~200mm,长度400~500mm;槽钢51、槽钢81、槽钢101均为18b槽钢,木方52、木方82、木方102、枕木7均为180*75mm木方。
结合图1、2简述本发明的施工过程:
某砖混结构建筑物,建筑面积1050㎡,长30.24m×宽14.24m,局部三层,砖混结构,7度抗震设防,纵横墙交接部位均设构造柱,设地圈梁、楼层楼盖圈梁,结构整体性强,施工质量好。原基础为墙下浅埋钢筋混凝土条形基础,埋深-1.000m,基础顶面标高-0.750m,纵墙基础宽度1.00m~1.40m,横墙基础宽度1.00m~1.10m,基础墙为实心粘土标准砖水泥砂浆砌筑,底下一皮370,其余240,所有一层墙下纵横方向贯通设置240×240地圈梁,纵横墙交接处从基底起均设构造柱。其过河平移具体过程如下:
1)、挖除原基础两侧全部土方至原垫层底标高,原地基为天然地基,持力层为二层粘土;
2)、在重新规划的地方放线、定位、满堂开挖至设计标高(同原位设计标高)。地基持力层与原位相同,仍为二层粘土,分布均匀,钎探无异常。
3)、在重新规划的地方,完全按照原基础复制新的钢筋混凝土条形基础。
4)、新旧基础之间均直接开挖至二层粘土。
5)、河道段处地基处理。本项工序的关键是要保证建筑物迁移过程中不得因此处的不均匀沉降造成结构开裂。处理的方法为围堰、抽水、清淤,采用附近钢厂的废料钢渣回填,同基顶标高。回填过程中采用铁三轮压路机分层碾压,经静载荷检测承载力不小于二层粘土承载力。
6)、整个过渡段,在新旧基础的A、B、C、D四轴连线平移轴线上均铺设1.6米宽12㎜厚钢板。
7)、以地圈梁2作为托盘,分段凿除纵横墙1地圈梁2下基础,构造柱钢筋预留一搭接长度,往外打弯确保不影响圈梁2托换施工。每凿除一段墙体,立即垂直于墙面安放开口向上内衬木方102的短槽钢101两道,并在该槽钢101两端分别安装千斤顶6顶紧,千斤顶坐落于原条形基础3找平层4上。
8)、在基础顶面横向排放500㎜长木方作为枕木7。
9)、在500㎜长枕木7上面通长并排两根安放开口向下内衬木方82的[18b的长槽钢81作为下轨道梁。其余使用随着建筑物平移而退出来的下轨道梁材料流水铺设。其中过渡段下轨道梁直接铺设于铁板上。
10)、在下轨道梁8上垂直于轨道梁8按300安装D=150㎜、L=450㎜的管内灌C60砼钢滚轴9(壁厚d=5mm)。
11)、在钢滚轴9上并排两根安装开口向上内衬木方102的[18b的长槽钢101作为上轨道梁10。
12)、在上轨道梁10上面,将千斤顶6简支梁5之间的空隙(未布简支梁的地方)铺满内衬木方52的500㎜长[18b槽钢51。
13)、撤走所有墙下千斤顶。至此,完成托换。
14)、牵引,在需施加牵引力的①轴地圈梁平齐处外侧设置一道45b工字钢刚性梁,在新基础一侧设4台卷扬机。用钢丝绳对托换底盘——地圈梁2进行牵引,实际上施加的相当于推力,亦即在A、B、C、D四轴地圈梁2内只产生压应力。
15)、监测、就位、托换、基础连接。
本发明方案所公开的技术手段不仅限于上述实施方式所公开的技术手段,还包括由以上技术特征任意组合所组成的技术方案。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也视为本发明的保护范围。

Claims (6)

1.一种砖混结构建筑物整体过河平移方法,其特征在于:包括如下步骤,
1)、基础处理:新旧基础处理及新旧基础过渡段平移轴线上铺设1.6米宽12㎜厚钢板;
2)、河道处理:包括河道的围堰、抽水、清淤、回填,回填过程中采用废料钢渣或1:1砂石进行回填,回填高度同原基础基顶标高相同,回填过程中采用铁三轮压路机分层碾压,经静载荷检测承载力不低于原基础承载力;
3)、建筑物托换:采用托换装置以原地圈梁作为托盘,直接利用千斤顶和内衬木方槽钢简支梁完成上部结构和旧基础的分离及托换,以内衬木方的长槽钢作为上轨道梁和下轨道梁,基础顶面以横向排放500mm长木方作为枕木;
4)、建筑物牵引:在施加牵引力的地圈梁平齐处外设一道工字钢刚性梁,在新基础一侧设置卷扬机,并用钢丝绳对地圈梁进行牵引;
5)、就位连接:上部结构就位、托换、基础连接。
2.一种用于如权利要求1所述砖混结构建筑物整体过河平移方法的专用托换装置,其特征在于:包括墙体(1)、地圈梁(2)以及原混凝土基础层(3),其特征在于:所述原混凝土基础层(3)上设置有找平层(4),地圈梁(2)下方设置有简支梁(5),简支梁(5)两端与找平层(4)之间设置有千斤顶(6),简支梁(5)中间位置与找平层(4)之间设置有滚轴(9),滚轴(9)与简支梁(5)之间设置有上轨道梁(10),滚轴(9)与找平层(4)之间依次设置有下轨道梁(8)以及枕木(7)。
3.根据权利要求2所述的专用托换装置,其特征在于:所述简支梁(5)由槽钢(51)及内衬木方(52)构成。
4.根据权利要求2所述的专用托换装置,其特征在于:所述上轨道梁(10)由两根平行设置的槽钢(101)组成,槽钢(101)内衬有木方(102),所述下轨道梁(8)由两根平行设置的槽钢(81)组成,槽钢(81)内衬有木方(82)。
5.根据权利要求2所述的专用托换装置,其特征在于:所述滚轴(9)由中空钢管制成,钢管内填充有混凝土。
6.根据权利要求5所述的专用托换装置,其特征在于:所述滚轴(9)直径为100~200mm,长度400~500mm。
CN201410332708.7A 2014-07-14 2014-07-14 一种砖混结构建筑物整体过河平移方法及其专用托换装置 Active CN104074370B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410332708.7A CN104074370B (zh) 2014-07-14 2014-07-14 一种砖混结构建筑物整体过河平移方法及其专用托换装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410332708.7A CN104074370B (zh) 2014-07-14 2014-07-14 一种砖混结构建筑物整体过河平移方法及其专用托换装置

Publications (2)

Publication Number Publication Date
CN104074370A CN104074370A (zh) 2014-10-01
CN104074370B true CN104074370B (zh) 2016-05-18

Family

ID=51595940

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410332708.7A Active CN104074370B (zh) 2014-07-14 2014-07-14 一种砖混结构建筑物整体过河平移方法及其专用托换装置

Country Status (1)

Country Link
CN (1) CN104074370B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104912125B (zh) * 2015-04-13 2016-09-28 步向义 一种条形基础的加固方法
CN108999427B (zh) * 2018-10-15 2023-10-24 北京建工四建工程建设有限公司 一种建筑物迁移就位时移动荷载的支撑结构及其施工方法
CN113914658B (zh) * 2021-10-29 2023-04-28 山东建筑大学 一种顶管托换装置及建筑物顶升托换方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2311564Y (zh) * 1997-11-10 1999-03-24 赵启 建筑物整体迁移滑动装置
CN1225965A (zh) * 1999-01-29 1999-08-18 孙炳法 楼房连基整体迁移装置与技术
CN2375704Y (zh) * 1999-01-18 2000-04-26 管春梅 高层建筑整体搬迁装置
WO2004065710A1 (en) * 2003-01-23 2004-08-05 The Mattamy Corporation Transporter for a house
JP5037301B2 (ja) * 2007-11-02 2012-09-26 孝師 西岡 既存建造物に対する免震構造施工方法および免震機構
CN103806674A (zh) * 2014-01-27 2014-05-21 中国矿业大学 一种砖混结构建筑物横向平移时横向行走梁的设计方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2311564Y (zh) * 1997-11-10 1999-03-24 赵启 建筑物整体迁移滑动装置
CN2375704Y (zh) * 1999-01-18 2000-04-26 管春梅 高层建筑整体搬迁装置
CN1225965A (zh) * 1999-01-29 1999-08-18 孙炳法 楼房连基整体迁移装置与技术
WO2004065710A1 (en) * 2003-01-23 2004-08-05 The Mattamy Corporation Transporter for a house
JP5037301B2 (ja) * 2007-11-02 2012-09-26 孝師 西岡 既存建造物に対する免震構造施工方法および免震機構
CN103806674A (zh) * 2014-01-27 2014-05-21 中国矿业大学 一种砖混结构建筑物横向平移时横向行走梁的设计方法

Also Published As

Publication number Publication date
CN104074370A (zh) 2014-10-01

Similar Documents

Publication Publication Date Title
CN108643231B (zh) 一种中心城区地铁车站半幅结构顶板盖挖施工方法
CN109235499B (zh) 一种明挖地下建筑结构装配式施工方法
CN100497841C (zh) 支腿式地下连续墙施工工法
CN106402490B (zh) 基于钢套头工具管的粉砂土地层顶管顶进施工方法
CN101509263A (zh) 钢盖板盖挖法基坑结构及其施工方法
CN103741714A (zh) 地下工程全盖挖逆作法施工方法
CN109797769B (zh) 一种湿陷性黄土地区地下综合管廊地基结构及其施工方法
CN112575670B (zh) 一种适用于隧道穿越巨型溶洞的t形刚构桥及其施工技术
CN111503368A (zh) 砂卵石地质条件下顶管施工方法
CN110593308A (zh) 一种上跨运营地铁地下综合管廊基坑明挖反压施工方法
CN113152185A (zh) 一种桩板路基支承预制路面的全装配式道路及其施工方法
CN104074370B (zh) 一种砖混结构建筑物整体过河平移方法及其专用托换装置
CN109706952A (zh) 大型沉井施工方法
CN108708290B (zh) 小半径铁路曲线单元的箱桥架空结构及现浇施工方法
CN112012763B (zh) 一种双层初期支护的多连拱隧道结构的施工方法
CN108316314A (zh) 一种可解决深浅基坑中坑偏压问题的内支撑结构
CN105926642B (zh) 一种城市地下综合管廊基坑支护与地下结构外模一体化结构及施工方法
CN111608435A (zh) 一种地铁车站与高架桥合建结构及其施工方法
CN207846471U (zh) 用于地下道路的半逆作地下结构
CN207862964U (zh) 一种陆上承台施工系统
CN112627002B (zh) 一种适用于隧道穿越巨型溶洞的连续梁桥及其施工技术方法
CN211815447U (zh) 过路管处沥青路面破损塌陷维修结构
CN209816896U (zh) 一种湿陷性黄土地区地下综合管廊地基结构
CN113389218A (zh) 一种地道桥出入口挡墙结构及其施工方法
CN109306712A (zh) 顶管工作井逆筑施工工法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Chen Sheng

Inventor after: Liu Yuan

Inventor after: Song Jianchun

Inventor after: Song Zaiyun

Inventor after: Hu Aiming

Inventor after: Qi Hong

Inventor after: Li Baoliang

Inventor after: Song Weiwei

Inventor after: Chen Hui

Inventor after: Qi Chao

Inventor after: Huang Denglou

Inventor after: Wan Hua

Inventor after: Zhang Guodong

Inventor before: Chen Sheng

Inventor before: Chen Hui

Inventor before: Li Baoliang

Inventor before: Zhang Guodong

Inventor before: Liu Yuan

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20160407

Address after: Huaian City, Jiangsu Province, 223000 Xiang Guan Cheng Cun Qingpu District No. 611 South four groups

Applicant after: Chen Sheng

Address before: 223001 No. 228 Huaihai West Road, Qinghe District, Jiangsu, Huaian

Applicant before: JIANGSU NANFANG URBAN CONSTRUCTION DESIGN CONSULTATION CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180412

Address after: 223001 Qingpu Industrial Park, Huaian, Jiangsu, 163-12 West Road.

Patentee after: Huaian construction machine safety scientific research Co., Ltd.

Address before: Huaian City, Jiangsu Province, 223000 Xiang Guan Cheng Cun Qingpu District No. 611 South four groups

Patentee before: Chen Sheng

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191212

Address after: 223001 Qingpu Industrial Park, Qingjiangpu District, Huaian City, Jiangsu Province, 118 Meizheng West Road

Patentee after: Huaian Boyan Civil Engineering Research Institute Co., Ltd.

Address before: 223001 Qingpu Industrial Park, Huaian, Jiangsu, 163-12 West Road.

Patentee before: Huaian construction machine safety scientific research Co., Ltd.