CN104050541A - Maintenance cycle management system for grid equipment - Google Patents

Maintenance cycle management system for grid equipment Download PDF

Info

Publication number
CN104050541A
CN104050541A CN201410302590.3A CN201410302590A CN104050541A CN 104050541 A CN104050541 A CN 104050541A CN 201410302590 A CN201410302590 A CN 201410302590A CN 104050541 A CN104050541 A CN 104050541A
Authority
CN
China
Prior art keywords
equipment
maintenance
account
tbo
overhauls
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410302590.3A
Other languages
Chinese (zh)
Inventor
崔高颖
邵劭
郭雅娟
邓洁清
赵鹏飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Maintenance Branch of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Maintenance Branch of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd, Maintenance Branch of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410302590.3A priority Critical patent/CN104050541A/en
Publication of CN104050541A publication Critical patent/CN104050541A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

The invention discloses a maintenance cycle management system for grid equipment. The maintenance cycle management system comprises an equipment ledger maintenance module, a maintenance cycle management module and a configuration and authority management module, wherein the equipment ledger maintenance module quickly maintains ledger information and guarantees the correctness of the content of a ledger according to a page filling-in process or a page filling-in template; the related ledger of grid equipment is quickly maintained by operating an organizational equipment tree in combination with the sequencing function of a ledger record; the maintenance cycle management module makes equipment maintenance cycle related information be related to the specific equipment ledger, the self-checking rules of equipment super-cycle conditions are set, and early warning and warning are performed on equipment maintenance super-cycle conditions; the configuration and authority management module is related to a transformer station according to different grades and authorities, so that a data dictionary is managed by a user, and incidence relations between the equipment maintenance cycle related information and the specific equipment ledger are maintained. According to the maintenance cycle management system, the complexity of the maintenance cycle for maintaining the equipment by maintenance staff is lowered, the maintenance efficiency of the equipment is enhanced, and early warning and warning are performed on the equipment super-cycle conditions.

Description

A kind of grid equipment time between overhauls(TBO) management system
Technical field
The present invention relates to a kind of grid equipment time between overhauls(TBO) management system, belong to grid equipment Condition-Based Maintenance Technology field.
Background technology
Along with the growth of electricity needs and power grid construction speed, social electricity consumption requires progressively to improve, and traditional grid equipment maintenance mode has been proposed to new requirement.But along with the increase day by day of dissimilar number of devices, still take at present and manually as main equipment overhaul cycle management becomes, become increasingly complex, the unitarity of overhaul data and integrality are difficult to guarantee.
Overhauling project in existing production management system (management of equipment account) is not corresponding completely one by one with the routine test in the handing-over of national grid company standard < < power transmission and transforming equipment and State Overhaul Test rules > >, and number is numerous, cause effectively according to equipment state, confirming the time between overhauls(TBO), formulate turnaround plan.And, if equipment account and time between overhauls(TBO) by affiliated maintenance unit, safeguarded respectively, easily cause equipment account and cycle information fall into disarray, maintainer is difficult to formulate turnaround plan according to the order of importance and emergency.Meanwhile, in primary equipment maintenance, may relate to the distinct device of Yi Ge transformer station different circuit, at this moment, if the order of equipment account and periodic maintenance is patrolled and examined custom with maintainer, not be inconsistent, likely cause the complexity of service work even to lead to errors.And for supraperiodic grid equipment, maintainer does not have the good approach supercycle situation of can both taking a panoramic view of the situation, and can grasp again the supraperiodic details of equipment.
Summary of the invention
The deficiency existing for prior art, the object of the invention is to provide a kind of grid equipment time between overhauls(TBO) management system, equipment account and time between overhauls(TBO) correctness maintenance issues have been solved, account, cyclic scheduling have been realized, and to equipment supercycle situation do in advance, alarm, user can be according to access configuration device account and Periodic correlation information associated, greatly reduce the complexity of maintainer's service equipment time between overhauls(TBO), improved the efficiency of overhaul of the equipments.
To achieve these goals, the present invention realizes by the following technical solutions:
A kind of grid equipment time between overhauls(TBO) management system of the present invention, comprises equipment account maintenance module, and described equipment account maintenance module is used for guaranteeing account content correctness according to page fill flow path or template Fast-Maintenance account information; The ranking function recording in conjunction with account by manipulation of tissue device tree is for the relevant grid equipment account of Fast-Maintenance; Time between overhauls(TBO) administration module, described time between overhauls(TBO) administration module is associated with concrete equipment account by equipment overhaul cycle relevant information, for avoiding secondary operation and inconsistency; Set device supercycle situation self check rule, to device entry mark different colours, carries out early warning and alarm to overhaul of the equipments supercycle situation; With configuration and authority management module, described configuration and authority management module are associated with transformer station according to user's different stage and authority, realize the management of user to data dictionary, thus service equipment time between overhauls(TBO) relevant information and concrete equipment account incidence relation.
The said equipment account maintenance module is used for guaranteeing that the method for account content correctness is as follows according to page fill flow path or template Fast-Maintenance account information:
During newly-increased account, in system, limit user's operation, must first in the title of system typing, search and treat recording device or transformer station's title, as existed, select existing title, if do not existed, the more newly-increased typing title for the treatment of, for avoiding same equipment or transformer station to produce the problem of a plurality of accounts because of title;
While newly putting into operation transformer station, if whole substation equipment account is over 100, can fill in by download the Excel template of account, and fill in after relevant device account information according to the hierarchical sequence of transformer station-> loop-> equipment, property imports again, realizes the Fast-Maintenance of account.
While filling in equipment account, the same page is according to the selection of transmission of electricity, the dissimilar equipment of power transformation, and corresponding different account fill substance is correct for guaranteeing the hierarchical sequence of equipment account;
When selecting converting equipment, must fill in order transformer station's title, loop title, device name, electric pressure, device type (because trip service teams and groups likely exist different personnel to safeguard same substation equipment, during typing, likely there is the typing different names to same transformer station, the possibility that causes Yi Ge transformer station two cover accounts, loop and device name in like manner, occur and occurred in other management software systems and this situation is very possible in real work.For avoiding this situation, must guarantee to fill according to the upper and lower hierarchical relationship of transformer station, guarantee the uniqueness of title simultaneously.The transformer station's title typing of take is example, must in the page, inquire about the current typing transformer station that needs according to prompting, if any, in the results list, directly select existing title, support fuzzy query, as nothing, the new transformer station of typing title is preserved.Whole process only need be clicked according to the sequential operation of page prompts, succinctly quick, does not have ambiguity, greatly improves account efficiency of inputting);
When selecting transmission facility, skip transformer station's title, loop title typing, directly fill in device name, electric pressure, circuit types, put into operation the date.
Above-mentioned as follows for the method for the relevant grid equipment account of Fast-Maintenance in conjunction with the ranking function of account record by manipulation of tissue device tree:
For selected wall scroll equipment account, can within the scope of transformer station's the same circuit, move up and down order; For equipment loop and higher level, other is sequentially adjusted, can by organize device tree node move up and down realize, make final account order consistent with actual maintenance order.Can, to equipment account by patrolling and examining custom sequence, improve overhaul efficiency.
The said equipment time between overhauls(TBO) relevant information method associated with concrete equipment account is as follows:
Overhauling project type in described time between overhauls(TBO) administration module, benchmark time between overhauls(TBO) is associated with device type, electric pressure in equipment account, and operate in described configuration and authority management module, the result that realization is adjusted equipment account, sort, is reacted directly in described time between overhauls(TBO) administration module.
Above-mentioned set device supercycle situation self check rule, to device entry mark different colours, carries out early warning and alarm to overhaul of the equipments supercycle situation, and concrete grammar is as follows:
Equipment periodic information in described time between overhauls(TBO) administration module is carried out to self check, take current date as the cut-off date, supraperiodic equipment is carried out to alarm with red sign;
Next time, the date of survey equipment that is month after next carried out early warning with orange;
The equipment that next time, date of survey was the second half year carries out early warning with yellow sign;
The equipment that next time, date of survey was succeeding year carries out early warning with green sign;
When information is not completely without the method judgment device maintenance supercycle during situation, data show blue, represent that maintenance of information is incomplete.
The user of above-mentioned different stage and authority comprises keeper, economizes maintenance and districts and cities' maintenance, and wherein, districts and cities maintenance user need be associated with the concrete transformer station in area under one's jurisdiction;
Districts and cities' maintenance is divided into different maintenance teams and groups, and each teams and groups area under one's jurisdiction is different, and each area under one's jurisdiction maintenance group is not paid close attention to the power transmission and transforming equipment maintenance situation outside area under one's jurisdiction, so user need be associated with concrete transformer station, the shielding of realization to irrelevant transformer station.
Realize described user as follows to the method for the management of data dictionary:
In data dictionary inediting electric pressure, time between overhauls(TBO), device type, circuit types, overhauling project, state evaluation result, result is directly reflected into the relevant account of all devices;
Set up the incidence relation of different pieces of information item, for equipment, if device type is definite, overhauling project type is just determined so;
If equipment electric pressure is definite, the benchmark time between overhauls(TBO) is also corresponding definite so.
The invention has the beneficial effects as follows: user can be according to existing template introducing equipment account information or manual typing account, system generates corresponding time between overhauls(TBO) maintenance information automatically, avoid equipment account and corresponding cycle inconsistent, reduced equipment account typing error rate; Maintainer can be associated with concrete transformer station, and according to patrolling and examining custom adjustment equipment account and cycle information order, improve the efficiency of maintenance of information and overhaul of the equipments; According to equipment supercycle self check rule, realize early warning and prompting to grid equipment different stage supercycle situation.
Accompanying drawing explanation
Fig. 1 is system chart of the present invention.
Embodiment
For technological means, creation characteristic that the present invention is realized, reach object and effect is easy to understand, below in conjunction with embodiment, further set forth the present invention.
A kind of grid equipment time between overhauls(TBO) management system of the present invention, the in the situation that of existing equipment component account or complete newly added equipment, grid equipment account is associated with time between overhauls(TBO) related content, can patrol and examine custom sequence flexibly according to maintainer simultaneously, realize efficient typing and the maintenance of grid equipment account and time between overhauls(TBO) information, and can to equipment supercycle situation, point out to prioritize according to supercycle self check rule, from multiple angles and dynamics, equipment supercycle information and rectification situation are added up, according to user class, set the associated of user and transformer station, and the management to data dictionary by user, realize the flexible management of equipment overhaul cycle information.Specific features comprises:
Equipment account maintenance module, time between overhauls(TBO) administration module, configuration and authority management module.
Equipment account maintenance module, can guarantee equipment account content correctness according to page fill flow path flexibly; The relevant grid equipment account of ranking function Fast-Maintenance that can record in conjunction with account by manipulation of tissue device tree; Can fill in the mode Fast-Maintenance equipment account that equipment account information uploads again and guarantee account content correctness by downloads template document.
Above-described according to page fill flow path assurance equipment account content correctness, while increasing account newly, in system, limit user's operation, must first in the title of system typing, search and treat recording device or transformer station's title, as existed, select existing title, if do not existed, more newly-increased treat typing title, avoid same equipment or transformer station to produce the problem of a plurality of accounts because of title; Can be defeated according to equipment during account maintenance of information, uncorrelated of the selection shielding of power transformation classification set and fill in order, the item of filling in that can not stride across above is directly filled in content below, guarantee equipment account to articulate hierarchical sequence correct.
The above-described relevant grid equipment account of ranking function Fast-Maintenance recording in conjunction with account by manipulation of tissue device tree for selected wall scroll equipment account, can move up and down order within the scope of transformer station's the same circuit; For equipment loop and higher level, other is sequentially adjusted, can by for organize device tree node move up and down realize; If newly-increased quantity is large (while newly putting into operation transformer station, whole substation equipment account is over 100) equipment account, can select to download Excel template that account fills in and by specifying requirements to fill in to be correlated with disposable importing after account, realize the Fast-Maintenance of account.
Time between overhauls(TBO) administration module, equipment overhaul cycle relevant information is associated with concrete equipment account, avoids secondary operation and inconsistency; Set device supercycle situation self check rule, to device entry mark different colours, carries out early warning and alarm to overhaul of the equipments supercycle situation.
Above-described equipment overhaul cycle relevant information is associated with concrete equipment account, be overhauling project type in time between overhauls(TBO) administration module, benchmark time between overhauls(TBO) etc. with equipment account in the field direct correlation such as device type, electric pressure, and operate in configuration and authority management module, realized the result that equipment account is adjusted, revised and sort, be reacted directly in time between overhauls(TBO) administration module.
Above-described locking equipment supercycle situation self check rule, to device entry mark different colours, overhaul of the equipments supercycle situation is carried out to early warning and alarm, for the equipment periodic information in time between overhauls(TBO) administration module, carry out self check, take current date as the cut-off date, supraperiodic equipment is carried out to alarm with red sign; Next time, the date of survey equipment that is month after next carried out early warning with orange; The equipment that next time, date of survey was the second half year carries out early warning with yellow sign; The equipment that next time, date of survey was succeeding year carries out early warning with green sign; When information is not completely without the method judgment device maintenance supercycle during situation, data show blue, represent that maintenance of information is incomplete.
Configure and authority management module, the user of different stage and authority is set: keeper, province's maintenance, districts and cities' maintenance, wherein districts and cities' maintenance user need be associated with the concrete transformer station in area under one's jurisdiction; Realize the management of user to data dictionary, the incidence relation of the field such as the device type in Maintenance and Repair item types, benchmark time between overhauls(TBO) etc. and equipment account, electric pressure.
Above-described districts and cities maintenance user need be associated with the concrete transformer station in area under one's jurisdiction, be that districts and cities' maintenance may be divided into different maintenance teams and groups, each teams and groups area under one's jurisdiction is different, each area under one's jurisdiction maintenance group is not paid close attention to the power transmission and transforming equipment maintenance situation outside area under one's jurisdiction, therefore user need be associated with concrete transformer station, realizes the shielding to irrelevant transformer station.
Above-describedly realize the management of user to data dictionary, for equipment, if device type determine, overhauling project type is just determined so; If equipment electric pressure is definite, the benchmark time between overhauls(TBO) is also corresponding definite so.Therefore, for these incidence relations that exist in maintenance, in data dictionary, safeguard, reduce time between overhauls(TBO) management complexity and uncertainty.
The invention has the beneficial effects as follows: user can be according to existing template introducing equipment account information or manual typing account, system generates corresponding time between overhauls(TBO) maintenance information automatically, avoid equipment account and corresponding cycle inconsistent, reduced equipment account typing error rate; Maintainer can be associated with concrete transformer station, and according to patrolling and examining custom adjustment equipment account and cycle information order, improve the efficiency of maintenance of information and overhaul of the equipments; According to equipment supercycle self check rule, realize early warning and prompting to grid equipment different stage supercycle situation, and can point out making a report on mistake.
Shown in Fig. 1, the present invention proposes a kind of grid equipment time between overhauls(TBO) management system, and available following steps represent:
Step 1: construct the tables of data such as equipment account information table, equipment overhaul cycle table, user message table, customer substation contingency table, data dictionary incidence relation table in database, wherein, equipment account information table is deposited all devices account information: comprise the fields such as device id, device name, device type, electric pressure, the time of putting into operation, equipment state, loop ID, the ID of transformer station; Relevant device id of equipment overhaul cycle table storage equipment time between overhauls(TBO), repair the fields such as examination project, reference period, performance period, state evaluation time, state evaluation result, date of last survey, next date of survey; The fields such as whether user message table is deposited user name, password that user right is relevant, come into force, region within the jurisdiction ID; Customer substation contingency table is deposited user and transformer station's corresponding relation, and for example, user user1 is associated with the Qin Huai of 220kV transformer station change within the scope of Nanjing, the change of yellow lane, Xi Du change, only pays close attention to this three substation equipments maintenance supercycle situations; Data dictionary incidence relation table is deposited the project that account and time between overhauls(TBO) are associated, and for example, the corresponding time between overhauls(TBO) of electric pressure 500kV is 36 months, and device type is that the corresponding overhauling project of isolating switch is for repairing examination project.
Step 2: by foreground equipment account maintenance module recording device account, during typing, by page restriction, must be filled according to the hierarchical sequence of transformer station-> loop-> equipment, simultaneously, the title such as transformer station, loop is filled in also and according to first searching, is had transformer station's title by page restriction, if do not exist, the order that creates again newname generates, and the equipment account of avoiding is filled in mistakes and omissions, repetition; Newly-increased account is positioned at last loop of last transformer station, but reference sequence may be inconsistent while overhauling with reality, therefore can realize final account order and reality maintenance sequence consensus by the adjustment that moves up and down and organize transformer station's node in device tree and loop node sequence of loop internal unit account order.When account is revised, also can select import or directly choose entry to be modified to modify by template, fill in order and fill in sequentially and be consistent with newly-increased account.
Step 3: owing to there being data dictionary incidence relation, in time between overhauls(TBO) administration module, only need Maintenance and Repair date, state evaluation result and state evaluation time, other fields directly generate by data dictionary mapping relations, equipment overhaul cycle information display order and account sequence consensus; According to date of last survey, judgement generates respective color prompting to the maintenance supercycle early warning information of each equipment.
Step 4: to configuration and authority management module in leading subscriber authority, and can increase and revise transformer station newly to user's incidence relation, for example, the 30Zuo transformer station that user can the appointment of associated this area, can other transformer stations of associated local area with another user in area under one's jurisdiction; , can increase newly and Update Table dictionary incidence relation meanwhile, as, editor's electric pressure and the incidence relation of time between overhauls(TBO).
More than show and described ultimate principle of the present invention and principal character and advantage of the present invention.The technician of the industry should understand; the present invention is not restricted to the described embodiments; that in above-described embodiment and instructions, describes just illustrates principle of the present invention; without departing from the spirit and scope of the present invention; the present invention also has various changes and modifications, and these changes and improvements all fall in the claimed scope of the invention.The claimed scope of the present invention is defined by appending claims and equivalent thereof.

Claims (8)

1. a grid equipment time between overhauls(TBO) management system, is characterized in that, comprises
Equipment account maintenance module, described equipment account maintenance module is used for guaranteeing account content correctness according to page fill flow path or template Fast-Maintenance account information; The ranking function recording in conjunction with account by manipulation of tissue device tree is for the relevant grid equipment account of Fast-Maintenance;
Time between overhauls(TBO) administration module, described time between overhauls(TBO) administration module is associated with concrete equipment account by equipment overhaul cycle relevant information, for avoiding secondary operation and inconsistency; Set device supercycle situation self check rule, to device entry mark different colours, carries out early warning and alarm to overhaul of the equipments supercycle situation;
With configuration and authority management module, described configuration and authority management module are associated with transformer station according to user's different stage and authority, realize the management of user to data dictionary, thus service equipment time between overhauls(TBO) relevant information and concrete equipment account incidence relation.
2. grid equipment time between overhauls(TBO) management system according to claim 1, is characterized in that,
Described equipment account maintenance module is used for guaranteeing that the method for account content correctness is as follows according to page fill flow path or template Fast-Maintenance account information:
During newly-increased account, in system, limit user's operation, must first in the title of system typing, search and treat recording device or transformer station's title, as existed, select existing title, if do not existed, the more newly-increased typing title for the treatment of, for avoiding same equipment or transformer station to produce the problem of a plurality of accounts because of title;
While newly putting into operation transformer station, if whole substation equipment account is over 100, can fill in by download the Excel template of account, and fill in after relevant device account information according to the hierarchical sequence of transformer station-> loop-> equipment, property imports again, realizes the Fast-Maintenance of account.
3. grid equipment time between overhauls(TBO) management system according to claim 2, is characterized in that,
While filling in equipment account, the same page is according to the selection of transmission of electricity, the dissimilar equipment of power transformation, and corresponding different account fill substance is correct for guaranteeing the hierarchical sequence of equipment account;
When selecting converting equipment, must fill in order transformer station's title, loop title, device name, electric pressure, device type;
When selecting transmission facility, skip transformer station's title, loop title typing, directly fill in device name, electric pressure, circuit types, put into operation the date.
4. grid equipment time between overhauls(TBO) management system according to claim 1, is characterized in that,
Described as follows for the method for the relevant grid equipment account of Fast-Maintenance in conjunction with the ranking function of account record by manipulation of tissue device tree:
For selected wall scroll equipment account, can within the scope of transformer station's the same circuit, move up and down order; For equipment loop and higher level, other is sequentially adjusted, can by organize device tree node move up and down realize, make final account order consistent with actual maintenance order.
5. grid equipment time between overhauls(TBO) management system according to claim 1, is characterized in that,
The described equipment overhaul cycle relevant information method associated with concrete equipment account is as follows:
Overhauling project type in described time between overhauls(TBO) administration module, benchmark time between overhauls(TBO) is associated with device type, electric pressure in equipment account, and operate in described configuration and authority management module, the result that realization is adjusted equipment account, sort, is reacted directly in described time between overhauls(TBO) administration module.
6. grid equipment time between overhauls(TBO) management system according to claim 1, is characterized in that,
Described set device supercycle situation self check rule, to device entry mark different colours, carries out early warning and alarm to overhaul of the equipments supercycle situation, and concrete grammar is as follows:
Equipment periodic information in described time between overhauls(TBO) administration module is carried out to self check, take current date as the cut-off date, supraperiodic equipment is carried out to alarm with red sign;
Next time, the date of survey equipment that is month after next carried out early warning with orange;
The equipment that next time, date of survey was the second half year carries out early warning with yellow sign;
The equipment that next time, date of survey was succeeding year carries out early warning with green sign;
When information is not completely without the method judgment device maintenance supercycle during situation, data show blue, represent that maintenance of information is incomplete.
7. grid equipment time between overhauls(TBO) management system according to claim 1, is characterized in that,
The user of described different stage and authority comprises keeper, economizes maintenance and districts and cities' maintenance, and wherein, districts and cities maintenance user need be associated with the concrete transformer station in area under one's jurisdiction;
Districts and cities' maintenance is divided into different maintenance teams and groups, and each teams and groups area under one's jurisdiction is different, and each area under one's jurisdiction maintenance group is not paid close attention to the power transmission and transforming equipment maintenance situation outside area under one's jurisdiction, so user need be associated with concrete transformer station, the shielding of realization to irrelevant transformer station.
8. grid equipment time between overhauls(TBO) management system according to claim 1, is characterized in that,
Realize described user as follows to the method for the management of data dictionary:
In data dictionary inediting electric pressure, time between overhauls(TBO), device type, circuit types, overhauling project, state evaluation result, result is directly reflected into the relevant account of all devices;
Set up the incidence relation of different pieces of information item, for equipment, if device type is definite, overhauling project type is just determined so;
If equipment electric pressure is definite, the benchmark time between overhauls(TBO) is also corresponding definite so.
CN201410302590.3A 2014-06-27 2014-06-27 Maintenance cycle management system for grid equipment Pending CN104050541A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410302590.3A CN104050541A (en) 2014-06-27 2014-06-27 Maintenance cycle management system for grid equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410302590.3A CN104050541A (en) 2014-06-27 2014-06-27 Maintenance cycle management system for grid equipment

Publications (1)

Publication Number Publication Date
CN104050541A true CN104050541A (en) 2014-09-17

Family

ID=51503350

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410302590.3A Pending CN104050541A (en) 2014-06-27 2014-06-27 Maintenance cycle management system for grid equipment

Country Status (1)

Country Link
CN (1) CN104050541A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104506528A (en) * 2014-12-23 2015-04-08 国家电网公司 Integrated network safety access method
CN105224517A (en) * 2015-11-04 2016-01-06 国家电网公司 A kind of mobile terminal
CN105956751A (en) * 2016-04-25 2016-09-21 邹平县供电公司 Power grid transformation equipment overhaul and evaluation management system
CN107153903A (en) * 2016-11-22 2017-09-12 国网江苏省电力公司盐城供电公司 A kind of rural power grids circuit high-low pressure equipment operation management system
CN107886210A (en) * 2017-07-18 2018-04-06 贵州电网有限责任公司信息中心 A kind of modularization automatic generation method of grid equipment account
CN108346001A (en) * 2018-02-10 2018-07-31 杭州后博科技有限公司 A kind of steel tower regular visit project order method of adjustment and system
CN110287935A (en) * 2019-07-02 2019-09-27 云南电网有限责任公司信息中心 A kind of power equipment data check method and system based on image recognition
CN110826939A (en) * 2019-11-29 2020-02-21 国网天津市电力公司电力科学研究院 Method for evaluating running state of distributed unattended substation
CN110852406A (en) * 2019-11-12 2020-02-28 国网天津市电力公司 Transformer substation protection equipment ledger management system based on mobile communication
CN110866216A (en) * 2019-10-22 2020-03-06 陕西省地方电力(集团)有限公司 Intelligent management method and system for overhaul of transformer substation equipment
CN111104446A (en) * 2019-12-09 2020-05-05 中国南方电网有限责任公司超高压输电公司贵阳局 Safety production subsystem equipment ledger entry method, device and equipment
CN113570110A (en) * 2021-06-25 2021-10-29 国网冀北电力有限公司电力科学研究院 Intelligent planning method for power line inspection tour
CN114284939A (en) * 2021-12-27 2022-04-05 国网北京市电力公司 Power distribution network operation and maintenance inspection method
CN116451910A (en) * 2023-06-16 2023-07-18 中国船舶集团有限公司第七一九研究所 Full life cycle management method and system for ship equipment

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102024188A (en) * 2009-09-17 2011-04-20 国电浙江北仑第三发电有限公司 Equipment accounting management module of EAM system of power plant
CN103366251A (en) * 2013-07-17 2013-10-23 嘉兴市恒光电力建设有限责任公司华创分公司 Power transmission patrolling management system

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102024188A (en) * 2009-09-17 2011-04-20 国电浙江北仑第三发电有限公司 Equipment accounting management module of EAM system of power plant
CN103366251A (en) * 2013-07-17 2013-10-23 嘉兴市恒光电力建设有限责任公司华创分公司 Power transmission patrolling management system

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104506528B (en) * 2014-12-23 2018-02-23 国家电网公司 A kind of integral network safety cut-in method
CN104506528A (en) * 2014-12-23 2015-04-08 国家电网公司 Integrated network safety access method
CN105224517A (en) * 2015-11-04 2016-01-06 国家电网公司 A kind of mobile terminal
CN105956751A (en) * 2016-04-25 2016-09-21 邹平县供电公司 Power grid transformation equipment overhaul and evaluation management system
CN107153903A (en) * 2016-11-22 2017-09-12 国网江苏省电力公司盐城供电公司 A kind of rural power grids circuit high-low pressure equipment operation management system
CN107886210A (en) * 2017-07-18 2018-04-06 贵州电网有限责任公司信息中心 A kind of modularization automatic generation method of grid equipment account
CN108346001A (en) * 2018-02-10 2018-07-31 杭州后博科技有限公司 A kind of steel tower regular visit project order method of adjustment and system
CN110287935A (en) * 2019-07-02 2019-09-27 云南电网有限责任公司信息中心 A kind of power equipment data check method and system based on image recognition
CN110866216A (en) * 2019-10-22 2020-03-06 陕西省地方电力(集团)有限公司 Intelligent management method and system for overhaul of transformer substation equipment
CN110852406A (en) * 2019-11-12 2020-02-28 国网天津市电力公司 Transformer substation protection equipment ledger management system based on mobile communication
CN110826939A (en) * 2019-11-29 2020-02-21 国网天津市电力公司电力科学研究院 Method for evaluating running state of distributed unattended substation
CN111104446A (en) * 2019-12-09 2020-05-05 中国南方电网有限责任公司超高压输电公司贵阳局 Safety production subsystem equipment ledger entry method, device and equipment
CN113570110A (en) * 2021-06-25 2021-10-29 国网冀北电力有限公司电力科学研究院 Intelligent planning method for power line inspection tour
CN114284939A (en) * 2021-12-27 2022-04-05 国网北京市电力公司 Power distribution network operation and maintenance inspection method
CN116451910A (en) * 2023-06-16 2023-07-18 中国船舶集团有限公司第七一九研究所 Full life cycle management method and system for ship equipment
CN116451910B (en) * 2023-06-16 2023-10-20 中国船舶集团有限公司第七一九研究所 Full life cycle management method and system for ship equipment

Similar Documents

Publication Publication Date Title
CN104050541A (en) Maintenance cycle management system for grid equipment
CN105022769B (en) A kind of City Underground Pipeline interactive system and its method
US7739138B2 (en) Automated utility supply management system integrating data sources including geographic information systems (GIS) data
CN104123271B (en) Intelligent substation secondary design system based on Excel
CN104133953B (en) Intelligent substation secondary design system
CN107167704B (en) Power distribution network fault diagnosis system and method based on CIM model
CN104318027B (en) The design method of model information table closed loop automatic interaction based on information table template
CN107346917A (en) Secondary device based on virtual machine integrates joint debugging method
CN112732924A (en) Power grid data asset management system and method based on knowledge graph
CN102455698B (en) Automatic control rate and stable rate monitoring system and monitoring method based on tree structure
CN110570101A (en) Intelligent OMS system for power grid distribution network
CN109685352A (en) A kind of device maintenance method and system of intelligence control linkage
CN104537573A (en) Power grid operation information panoramic visualized display system
CN101174208A (en) Method for implementing software assembly line platform
CN106446245A (en) Intelligent substation secondary device integrated drawing document system and managing and implementing method thereof
CN111585349B (en) Power grid model management and monitoring system
CN102117444A (en) System for comprehensive arrangement and execution management of production equipment maintenance plan
CN106651653A (en) Intelligent power distribution network project auxiliary management system
CN106355256A (en) Multivariate visualization overhaul management system
CN102857949B (en) A kind of method and apparatus that layout data consistency guarantees
CN106780153A (en) It is a kind of in real time multi-functional back brake, patrol and examine operation note system
CN107947356A (en) Electrified railway digital traction substation automated system
CN102646112A (en) Visual modeling method for capability description file of direct-current protection control device
CN104881739B (en) Data consistency verification method is matched somebody with somebody by a kind of battalion based on IEC61970/61968 CIM standards
CN107944659A (en) A kind of substation supervisory control system auto report completing method and apparatus

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140917

RJ01 Rejection of invention patent application after publication