CN104050527A CN201410224295.0A CN201410224295A CN104050527A CN 104050527 A CN104050527 A CN 104050527A CN 201410224295 A CN201410224295 A CN 201410224295A CN 104050527 A CN104050527 A CN 104050527A
Authority
CN
China
Prior art keywords
operation order
power grid
regional power
ticket
verification
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410224295.0A
Other languages
Chinese (zh)
Inventor
卢京祥
卢芳
刘祥波
任妍
韩邦东
刘斌
晋京
汉新宇
司政
金立峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Rizhao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
Rizhao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Rizhao Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical Rizhao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority to CN201410224295.0A priority Critical patent/CN104050527A/en
Publication of CN104050527A publication Critical patent/CN104050527A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

The invention relates to a regional power grid dispatching intelligent operation order system which comprises a supporting platform, a database, a configuration management module, an operation order generating module, a safety verification module, an operation order management module and an interface of a DTS system. By adopting the regional power grid dispatching intelligent operation order system, the problem that an interface between a traditional operation order system and an SCADA system is unstable is solved, and a real environment is provided for intelligent order generation. In addition, the regional power grid dispatching intelligent operation order system provides accurate and precise safety verification in the simulation process, ensures the operation order correctness and achieves pre-analysis and target pre-control before dispatching operation. The working intensity of dispatchers is reduced to great extent, the order generating speed and quality are improved, and the dispatching working efficiency and safety are greatly improved.

Description

Regional power grid scheduling Aptitude Operation Order Sheet System
Technical field
The present invention relates to a kind of operation ticket system, especially a kind of regional power grid scheduling Aptitude Operation Order Sheet System.
Background technology
Along with the fast development of area power grid, structure and the method for operation of electric system are increasingly sophisticated, and original various Computer aided generation operation ticket systems can not meet the needs that dispatching of power netwoks is made out an invoice and operated.Because management and running personnel are undertaking the task of commanding operation of power networks in electrical network, therefore, must be skillfully and grasp exactly power system operating mode and scheduling operation technical ability.
Existing scheduling operation bill system majority is the intelligent generating run ticket based on expert system development, artificial setting operation target mode, and the automatic generating run sequence of steps of system, long-term use will cause the degeneration of management and running personnel experience.And expert's operation ticket system majority is off-line billing system, and the environment of making out an invoice can not be corresponding with the actual electric network method of operation, thereby causes operations staff to lack the comprehensive assurance to dispatching of power netwoks safety.
In addition, existing scheduling operation bill system majority is all to carry out design and development for concrete electrical network, and versatility has much room for improvement, and cannot promote at regional power grid scheduling center.The reason that causes system to promote has: 1. can not obtain electrical network real time operation mode during graphics aided, power system operating mode need to be manually set, even by and SCADA system between interface, also cause the problems such as the data method of synchronization is unstable and complicated and changeable; 2. model, figure can not be accomplished to share with SCADA system easily, need a newly-built set of model and graph data, and line service amount is large; 3. in simulation preview generating run ticket process, lack accurately tight safety check; 4. cannot accomplish that the intelligence to secondary device is drawn a bill on primary system wiring diagram.
For the problems referred to above, be necessary to provide further improvement project.
Summary of the invention
The object of the present invention is to provide a kind of regional power grid scheduling Aptitude Operation Order Sheet System.
For achieving the above object, a kind of regional power grid scheduling Aptitude Operation Order Sheet System of the present invention, it comprises: the interface of support platform, database, Configuration Manager, operation order generation module, safety check module, operation order administration module and DTS system;
Based on SCADA system platform, construction forms described support platform;
The Data Source of described database comprises SCADA system and DTS system;
Described Configuration Manager comprises form customization unit, flow custom unit, authority customization units and rule base customization units;
Described operation order generation module comprises following operation order generating mode: point diagram becomes ticket, typical ticket to generate, historical ticket generates, off-line is write ticket;
Described safety check module comprises the anti-verification of system topological five and trend verification, and described safety check module is for carrying out verification to the result of system management module and database output;
Described operation order administration module manages for the result to through described safety check module verification.
As a further improvement on the present invention, described supporting platform is shared the public service function of described SCADA system, and described public service function comprises: model management, alerting service, system management.
As a further improvement on the present invention, described SCADA system provides primary equipment model data for described database, and described DTS system provides secondary device model data for described database.
As a further improvement on the present invention, described secondary device model data is transmitted by the interface of described DTS system.
As a further improvement on the present invention, the network topology structure of described system topological five anti-verifications be take whole network equipment as basis.
As a further improvement on the present invention, in described whole network equipment, the latching relation between each equipment be take described network topology structure as basis for estimation.
As a further improvement on the present invention, described trend verification comprises the verification of the whole network trend and local trend verification.
As a further improvement on the present invention, described operation order administration module for newly-built, the typical ticket management of ticket, the editor of ticket, preservation, printing, the workflow management of ticket, the statistics of the simulation of ticket and verification, ticket and inquiry.
As a further improvement on the present invention, the data transfer mode of the interface of described DTS system comprises: periodic transmission and irregularly transmission.
As a further improvement on the present invention, when changing appears in secondary device model data that described database receives, described regional power grid scheduling Aptitude Operation Order Sheet System sends the request instruction of synchronous variation model whether to operator.
Compared with prior art, the invention has the beneficial effects as follows: regional power grid scheduling Aptitude Operation Order Sheet System of the present invention has solved the unsettled problem of interface between traditional operation ticket system and SCADA system, for intelligence becomes tickets-raise up, supplied real environment.Meanwhile, regional power grid scheduling Aptitude Operation Order Sheet System of the present invention, by accurately tight safety check is provided in simulation process, is guaranteed the correctness of generating run ticket, reaches the front preanalysis of scheduling operation and pre-control target.And from having alleviated to a great extent yardman's working strength, improved invoicing speed and quality, greatly promoted despatching work efficiency and security.
Accompanying drawing explanation
Fig. 1 is the module diagram of an embodiment of regional power grid scheduling Aptitude Operation Order Sheet System of the present invention.
Embodiment
In conjunction with the accompanying drawings, the present invention is further detailed explanation.These accompanying drawings are the schematic diagram of simplification, basic structure of the present invention is only described in a schematic way, so it only show the formation relevant with the present invention.
Change as shown in Figure 1 and modification.The technical scope of this invention is not limited to the content on instructions, must determine its technical scope according to claim scope.
As shown in Figure 1, regional power grid scheduling Aptitude Operation Order Sheet System of the present invention comprises: the interface 70 of support platform, database 20, Configuration Manager 30, operation order generation module 40, safety check module 50, operation order administration module 60 and DTS system.
Wherein, based on SCADA system platform, construction forms described support platform, so SCSDA system has been carried out to sufficient utilization, has saved and has exploited natural resources.Particularly, described supporting platform 10 is shared the public service function of described SCADA system, and for example, described public service function comprises: model management, alerting service, system management etc.By above-mentioned service, reduced the design and development of system to public service demand.
The Data Source of described database 20 comprises SCADA system and DTS system.Particularly, described SCADA system provides primary equipment model data for described database, and described DTS system provides secondary device model data for described database.Described secondary device model data, by the interface 70 of DTS system, under secondary device working rule, is obtained by described database 20, realizes secondary device intelligence and draws a bill.Database 20 provides various basic datas for operation order generates.
Described Configuration Manager 30 comprises form customization unit, flow custom unit, authority customization units and rule base customization units.Wherein, form customization unit can arrange the form of operation order; Described flow custom unit can arrange the workflow management of operation order; Described authority customization units is for arranging different types of authority; Described rule base customization units is for arranging the dependency rule of operation order.
Described operation order generation module 40, under described operation order administration module 60 auxiliary, according to the data in database 20, has following operation order generating mode: point diagram becomes ticket, typical ticket to generate, historical ticket generates, off-line is write ticket.Wherein, the point diagram that regional power grid scheduling Aptitude Operation Order Sheet System of the present invention is secondary device by the interface with DTS with regular framework becomes the realization of ticket that condition is provided.
Described safety check module 50 comprises the anti-verification of system topological five and trend verification, and described safety check module is for carrying out verification to the result of system management module and database output.Wherein, the network topology structure of described system topological five anti-verifications be take whole network equipment as basis.Latching relation in described whole network equipment between each equipment be take described network topology structure as basis for estimation.Particularly, the anti-verification of system topological five in present embodiment can realize the non-maintaining of latching logic relation between equipment, thereby overcome in existing topological five anti-verifications, must the artificial drawback that defines the operation locking relation between each equipment and other equipment.In addition, described system topological five is anti-has also broken through anti-error boundary in the station of existing topological five anti-verifications, from the whole network angle, to operating, carries out anti-error verification and Analysis about Dangerous Point, has improved the safety coefficient of system.
Described trend verification comprises the verification of the whole network trend and local trend verification.The verification of above-mentioned the whole network trend and local trend verification can change regional electric network influencing according to equipment state, optionally carry out the verification of the whole network trend and local trend verification.So, improved the efficiency of trend verification.
Described operation order administration module 60 manages for the result to through described safety check module 50 verifications.Particularly, described operation order administration module can be used for ticket newly-built, typical ticket management, the editor of ticket, preservation, printing, the workflow management of ticket are, the statistics of the simulation of ticket and verification, ticket and inquiry etc.
The interface of described DTS system for by the data transmission of DTS system to database 20, thereby provide data source for database 20.The data transfer mode of the interface of DTS system comprises: periodic transmission and irregularly transmission.When changing appears in the secondary device model data receiving when described database 20, described regional power grid scheduling Aptitude Operation Order Sheet System sends the request instruction of synchronous variation model whether to operator, by the synchronous variation of manual mode implementation model.So, operation ticket system of the present invention combines operator's experience, has further improved the security of system data.
In sum, regional power grid scheduling Aptitude Operation Order Sheet System of the present invention has solved the unsettled problem of interface between traditional operation ticket system and SCADA system, for intelligence becomes tickets-raise up, has supplied real environment.Meanwhile, regional power grid scheduling Aptitude Operation Order Sheet System of the present invention, by accurately tight safety check is provided in simulation process, is guaranteed the correctness of generating run ticket, reaches the front preanalysis of scheduling operation and pre-control target.And from having alleviated to a great extent yardman's working strength, improved invoicing speed and quality, greatly promoted despatching work efficiency and security.
To those skilled in the art, obviously the invention is not restricted to the details of above-mentioned one exemplary embodiment, and in the situation that not deviating from spirit of the present invention or essential characteristic, can realize the present invention with other concrete form.Therefore, no matter from which point, all should regard embodiment as exemplary, and be nonrestrictive, scope of the present invention is limited by claims rather than above-mentioned explanation, is therefore intended to include in the present invention dropping on the implication that is equal to important document of claim and all changes in scope.Any Reference numeral in claim should be considered as limiting related claim.
In addition, be to be understood that, although this instructions is described according to embodiment, but not each embodiment only comprises an independently technical scheme, this narrating mode of instructions is only for clarity sake, those skilled in the art should make instructions as a whole, and the technical scheme in each embodiment also can, through appropriately combined, form other embodiments that it will be appreciated by those skilled in the art that.

Claims (10)

1. a regional power grid scheduling Aptitude Operation Order Sheet System, it is characterized in that, described regional power grid scheduling Aptitude Operation Order Sheet System comprises: the interface of support platform, database, Configuration Manager, operation order generation module, safety check module, operation order administration module and DTS system;
Based on SCADA system platform, construction forms described support platform;
The Data Source of described database comprises SCADA system and DTS system;
Described Configuration Manager comprises form customization unit, flow custom unit, authority customization units and rule base customization units;
Described operation order generation module comprises following operation order generating mode: point diagram becomes ticket, typical ticket to generate, historical ticket generates, off-line is write ticket;
Described safety check module comprises the anti-verification of system topological five and trend verification, and described safety check module is for carrying out verification to the result of system management module and database output;
Described operation order administration module manages for the result to through described safety check module verification.
2. regional power grid scheduling Aptitude Operation Order Sheet System according to claim 1, is characterized in that, described supporting platform is shared the public service function of described SCADA system, and described public service function comprises: model management, alerting service, system management.
3. regional power grid scheduling Aptitude Operation Order Sheet System according to claim 1, is characterized in that, described SCADA system provides primary equipment model data for described database, and described DTS system provides secondary device model data for described database.
4. regional power grid scheduling Aptitude Operation Order Sheet System according to claim 3, is characterized in that, described secondary device model data is transmitted by the interface of described DTS system.
5. regional power grid scheduling Aptitude Operation Order Sheet System according to claim 1, is characterized in that, the network topology structure of described system topological five anti-verifications be take whole network equipment as basis.
6. regional power grid scheduling Aptitude Operation Order Sheet System according to claim 5, is characterized in that, the latching relation in described whole network equipment between each equipment be take described network topology structure as basis for estimation.
7. regional power grid scheduling Aptitude Operation Order Sheet System according to claim 1, is characterized in that, described trend verification comprises the verification of the whole network trend and local trend verification.
8. regional power grid scheduling Aptitude Operation Order Sheet System according to claim 1, it is characterized in that, described operation order administration module for newly-built, the typical ticket management of ticket, the editor of ticket, preservation, printing, the workflow management of ticket, the statistics of the simulation of ticket and verification, ticket and inquiry.
9. regional power grid scheduling Aptitude Operation Order Sheet System according to claim 1, is characterized in that, the data transfer mode of the interface of described DTS system comprises: periodic transmission and irregularly transmission.
10. regional power grid scheduling Aptitude Operation Order Sheet System according to claim 1, it is characterized in that, when changing appears in secondary device model data that described database receives, described regional power grid scheduling Aptitude Operation Order Sheet System sends the request instruction of synchronous variation model whether to operator.
CN201410224295.0A 2014-05-24 2014-05-24 Regional power grid dispatching intelligent operation order system Pending CN104050527A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410224295.0A CN104050527A (en) 2014-05-24 2014-05-24 Regional power grid dispatching intelligent operation order system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410224295.0A CN104050527A (en) 2014-05-24 2014-05-24 Regional power grid dispatching intelligent operation order system

Publications (1)

Publication Number Publication Date
CN104050527A true CN104050527A (en) 2014-09-17

Family

ID=51503336

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410224295.0A Pending CN104050527A (en) 2014-05-24 2014-05-24 Regional power grid dispatching intelligent operation order system

Country Status (1)

Country Link
CN (1) CN104050527A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111009967A (en) * 2019-11-29 2020-04-14 广东电网有限责任公司 Programmed control system
CN113656532A (en) * 2021-08-16 2021-11-16 雅砻江流域水电开发有限公司 Intelligent retrieval system for work tickets and operation tickets

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
徐俊杰等: "基于SCADA 系统的地区电网调度操作票系统的设计", 《电力系统保护与控制》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111009967A (en) * 2019-11-29 2020-04-14 广东电网有限责任公司 Programmed control system
CN113656532A (en) * 2021-08-16 2021-11-16 雅砻江流域水电开发有限公司 Intelligent retrieval system for work tickets and operation tickets
CN113656532B (en) * 2021-08-16 2024-05-07 雅砻江流域水电开发有限公司 Intelligent retrieval system for work ticket and operation ticket

Similar Documents

Publication Publication Date Title
CN101436790B (en) On-line splicing and coalition method for electric network model containing complex T connection line
CN104133443A (en) Method for automatically generating power grid dispatching operation order through power grid overhaul application forms
CN102957205A (en) Method and system for establishing distribution network model
CN103886511A (en) Real-time command system for power distribution network fault repair
CN105447611A (en) OMS equipment transaction management and control information system supported by GID platform
CN104063765A (en) SCD file management method for intelligent substation
CN104252646A (en) Method for automatically formulating daily power grid maintenance plans
CN104504483B (en) Method for realizing province and local integration of anti-misoperation tickets
CN101895154B (en) Main and distribution network model splicing method and system in distribution network automation system
CN105262227A (en) Fool-proof lockout system
CN104953707A (en) Intelligent error prevention method and system for monitoring operation order
CN104915794A (en) Multi-time-state full-service unified modeling method based on model center
CN102916489A (en) Virtual terminal automatic wiring method based on primary system structure of regional power grid
CN105576832A (en) Sub-station simulation and transmission system and method of substation automation system
CN111798088A (en) Power grid dispatching method and system
CN104966137A (en) Smart power grid project optimizing method
CN104050527A (en) Regional power grid dispatching intelligent operation order system
CN103903103A (en) Online model parameter collection method based on process cross-region power grid running method
CN102169343A (en) Programmed remote operation system and method of grid centralized monitoring center
CN106096835A (en) Model center construction method between based on the isomery dispatching patcher of agency service
CN106022648A (en) Electric power scheduling report form coordination and generation method
US20130082524A1 (en) Methods and systems for branch encoding in an electric network
CN102479359A (en) Power grid overhauling plan compilation method based on graphic operations
CN104243218B (en) A kind of communication of power system mode list preparation method based on more schedule constraints
CN102708181A (en) Distributed data instancing method of charging station monitoring system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140917

WD01 Invention patent application deemed withdrawn after publication