CN104047621B - Based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition - Google Patents

Based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition Download PDF

Info

Publication number
CN104047621B
CN104047621B CN201310080820.1A CN201310080820A CN104047621B CN 104047621 B CN104047621 B CN 104047621B CN 201310080820 A CN201310080820 A CN 201310080820A CN 104047621 B CN104047621 B CN 104047621B
Authority
CN
China
Prior art keywords
way
transverse passage
lining
passenger flow
maximum section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310080820.1A
Other languages
Chinese (zh)
Other versions
CN104047621A (en
Inventor
黄爱军
徐正良
田海波
张向霞
张增峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Group Co Ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Co ltd filed Critical Shanghai Urban Construction Design Research Institute Co ltd
Priority to CN201310080820.1A priority Critical patent/CN104047621B/en
Publication of CN104047621A publication Critical patent/CN104047621A/en
Application granted granted Critical
Publication of CN104047621B publication Critical patent/CN104047621B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of maximum section of passenger flow adit construction method based on top small interval basement excavation condition, comprise the following steps: step one, construction shaft, and open ingate in described vertical shaft bottom side direction, simultaneously along described ingate excavation transverse passage-way; Step 2, two lining structures are set in described transverse passage-way to the crown arch springing place of described transverse passage-way, have been horizontally disposed with two lining top boards at described crown arch springing place, serve as a contrast fill concrete in vault cavity that top boards and described vault enclose formation toward described two; Step 3, according to designing requirement, the implementation condition of the space enclosing structure of reserved upper cover property foundation ditch above described two lining top boards; Step 4, complete other interval construction workings of described transverse passage-way.The present invention can interval structure under construction ground in advance, and need not limit by the engineering method and duration of building upper cover property in advance, and effectively strengthens its anti-floating ability, can construct the transverse passage-way of maximum section of passenger flow under the small interval basement excavation condition of top.

Description

Based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition
Technical field
The present invention relates to underground structure technical field of construction, particularly relate to a kind of maximum section of passenger flow adit construction method based on top small interval basement excavation condition.
Background technology
City underground is positioned at transport hub mostly, and ground is built maybe by intensive for the building of exploitation, and especially in recent years, along with the increase of subway line, the situation of building upper cover property above subway station or interval in advance increases gradually.At present conventional construction is that underground building combines with surface structures, Synchronization Design, synchronous construction, and this just causes both construction period and construction and influences each other and mutually restrict.And simultaneously because interval is buried underground comparatively dark, adopt top board between cut and cover tunneling back zone to be flat-top, in the thicker situation of earthing, top board structure is thicker, uneconomical.Therefore the interval construction of the existing big cross section building upper cover property in advance mostly need to coordinate both construction period and construction method, and due to interval buried depth comparatively dark, adopt top plate earth-covering between cut and cover tunneling back zone thicker, cause top board thicker, backfill earthing is many.
Therefore, those skilled in the art is devoted to develop a kind of maximum section of passenger flow adit construction method based on top small interval basement excavation condition, overcome above deficiency, and be, under the condition of small interval, meet the requirement of the opposing buoyancy of upper cover property bottom the transverse passage-way top of construction complete with the upper cover property of building in advance.
Summary of the invention
Because the above-mentioned deficiency of prior art, the present invention proposes one can interval structure under construction ground in advance, and need not by the maximum section of passenger flow adit construction method based on top small interval basement excavation condition of the engineering method and duration restriction of building upper cover property in advance.
For achieving the above object, the invention provides a kind of maximum section of passenger flow adit construction method based on top small interval basement excavation condition, comprise the following steps:
Step one, construction shaft, and open ingate in described vertical shaft bottom side direction, simultaneously along described ingate excavation transverse passage-way.
Step 2, two lining structures are set in described transverse passage-way to the crown arch springing place of described transverse passage-way, have been horizontally disposed with two lining top boards at described crown arch springing place, serve as a contrast fill concrete in vault cavity that top boards and described vault enclose formation toward described two.
Step 3, according to designing requirement, the implementation condition of the space enclosing structure of reserved upper cover property foundation ditch above described two lining top boards.
Step 4, complete other interval construction workings of described transverse passage-way.
Preferably, described transverse passage-way is provided with just lining structure, abolishes described just lining structure by local after the top radial grouting of the inner implementation condition towards reserved described space enclosing structure of described transverse passage-way.
Preferably, the positions be in described transverse passage-way below described two lining top boards have also been horizontally disposed with two lining dividing plates, after completing steps four, then fill element soil in the cavity enclosing formation toward described two lining top boards, described two lining dividing plates and transverse passage-way inside wall.
Preferably, the implementation condition of space enclosing structure described in step 3 is above described two lining top boards, remain for the wide mounting groove of 0.8-1.0m that described space enclosing structure plugs in advance.
Beneficial effect of the present invention is as follows:
1) the present invention adopts shallow mining method, constructs respectively with upper cover property, need not limit by the engineering method and duration of building upper cover property in advance, and after Underground Construction completes, the upper cover property of building in advance can row construction more on schedule.
2) the present invention be especially applicable to being applied in construct between transverse passage-way top and upper cover property (basement) bottom surface, clear distance is little when, and the requirement of upper cover property opposing buoyancy can well be met by construction method of the present invention, the present invention, by effectively strengthening its anti-floating ability at the vault partially filled concrete of transverse passage-way, can construct the transverse passage-way of maximum section of passenger flow under the small interval basement excavation condition of top.
3) the present invention is also for space enclosing structure has reserved implementation condition, is conducive to constructing of later stage space enclosing structure, realizes space enclosing structure and is connected with the ingenious of transverse passage-way, effectively raise the security reliability of space enclosing structure.
4) the present invention has added two lining dividing plates, and serve as a contrast at two lining dividing plates and two and to fill plain native between top board, further increases the anti-floating ability of transverse passage-way.
Be described further below with reference to the technique effect of accompanying drawing to design of the present invention, concrete structure and generation, to understand object of the present invention, characteristic sum effect fully.
Accompanying drawing explanation
Fig. 1 is the maximum section of passenger flow adit construction method flow diagram of the present embodiment based on top small interval basement excavation condition.
The structural representation of the maximum section of passenger flow transverse passage-way of Fig. 2 constructed by step S1.
The structural representation of the maximum section of passenger flow transverse passage-way of Fig. 3 constructed by step S2.
The structural representation of the maximum section of passenger flow transverse passage-way of Fig. 4 constructed by step S3.
The structural representation of the maximum section of passenger flow transverse passage-way of Fig. 5 constructed by step S4.
Fig. 6 is the A-A sectional schematic diagram of Fig. 4.
Fig. 7 is the B place partial enlarged drawing of Fig. 4.
Fig. 8 is the further structural representation implementing the maximum section of passenger flow transverse passage-way formed of the present embodiment.
Detailed description of the invention
As shown in Figure 1, a kind of maximum section of passenger flow adit construction method based on top small interval basement excavation condition of the present embodiment, comprises the following steps:
Shown in step S1, composition graphs 2, construction shaft 1, and open ingate 2 in vertical shaft 1 bottom side direction, excavate transverse passage-way 3 along ingate 2 simultaneously.
Shown in step S2, composition graphs 3, the crown arch springing place of two lining structures to transverse passage-way 3 is set in transverse passage-way 3, has been horizontally disposed with two lining top boards 5 at described crown arch springing place, fill concrete in the vault cavity 6 enclosing formation toward two lining top boards 5 and described vault.Exemplary, two lining structures of the present embodiment are arranged on the transverse passage-way inside wall below described crown, the concrete that the present embodiment backfills in vault cavity 6 adopts plain concrete filling crown cavity 6 rearward end to act on the part (as shown in Figure 4) of upper cover property, of coursing, also can be all fill in other embodiments.
Shown in step S3, composition graphs 4, Fig. 6 and Fig. 7, according to designing requirement, the implementation condition of the space enclosing structure 7 of reserved upper cover property foundation ditch above two lining top boards 5.Exemplary, as shown in the figure, the upper cover property 4 that will construct of later stage is positioned at the rearward end of transverse passage-way 3, therefore the space enclosing structure 7 that will construct of later stage also only local be arranged on the vault cavity 6 of transverse passage-way, above two lining top boards 5, corresponding position remains for the wide mounting groove of 1.0m that space enclosing structure 7 plugs in advance.Of course, in other specific embodiments, the width of mounting groove can also be that 0.8m is wide or according to designing requirement other sizes adaptive, this peripheral structure also can be that whole space enclosing structure is all plugged on cavity.
Shown in step S4, composition graphs 5, complete other interval construction workings of transverse passage-way 3.Concrete, the space of anterior for vault cavity non-fill concrete is adopted plain soil to carry out backfilling and retains mounting groove in relevant position, simultaneously on the two side of transverse passage-way 3, offers positive hole ingate, to the construction of interval, both sides.
As the further detailed description of the invention of the present embodiment, transverse passage-way 3 is provided with just lining structure, shown in composition graphs 6 and Fig. 7, abolishes described just lining structure by local after the top radial grouting of the implementation condition of reserved space enclosing structure 7, transverse passage-way 3 inside.Exemplary, the present embodiment is when excavating transverse passage-way, namely construct just lining structure and two lining structures simultaneously, and in follow-up step S3, according to designing requirement, the reserved first lining structure plugging the crown position of space enclosing structure 7 is carried out local abolish, and then grouting and reinforcing is carried out to space enclosing structure form reinforcing area 8, as shown in Fig. 7 reinforcing area by transverse passage-way inner radial.
As the further detailed description of the invention of the present embodiment, shown in composition graphs 8, the position be in transverse passage-way 3 below two lining top boards 5 has also been horizontally disposed with two lining dividing plates 9, after completing steps S4, then serve as a contrast in cavity that dividing plates 9 and transverse passage-way 3 inside wall enclose formation toward two lining top boards 5, two and fill element soil.Concrete, can according to the designing requirement of transverse passage-way, tunnel upper limit positions of driving a vehicle in transverse passage-way arranges two lining dividing plates and fills element soil, meets current requirement on the one hand, strengthens the requirement of transverse passage-way opposing upper cover property buoyancy on the one hand.
By the maximum section of passenger flow adit construction method based on top small interval basement excavation condition of the present embodiment, can independently construct underground building structure, be not subject to the restriction of surface structures structure duration and affect, and be also well positioned to meet the construction requirement of later stage earth construction, maximum section of passenger flow transverse passage-way of constructing under being particluarly suitable for top small interval situation.
More than describe preferred embodiment of the present invention in detail.Should be appreciated that those of ordinary skill in the art just design according to the present invention can make many modifications and variations without the need to creative work.Therefore, all technician in the art, all should by the determined protection domain of claims under this invention's idea on the basis of existing technology by the available technical scheme of logical analysis, reasoning, or a limited experiment.

Claims (4)

1., based on a maximum section of passenger flow adit construction method for top small interval basement excavation condition, it is characterized in that, comprise the following steps:
Step one, construction shaft, and open ingate in described vertical shaft bottom side direction, simultaneously along described ingate excavation transverse passage-way;
Step 2, two lining structures are set in described transverse passage-way to the crown arch springing place of described transverse passage-way, have been horizontally disposed with two lining top boards at described crown arch springing place, serve as a contrast fill concrete in vault cavity that top boards and vault enclose formation toward described two;
Step 3, according to designing requirement, the implementation condition of the space enclosing structure of reserved upper cover property foundation ditch above described two lining top boards;
Step 4, complete other interval construction workings of described transverse passage-way.
2. as claimed in claim 1 based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition, it is characterized in that: described transverse passage-way is provided with just lining structure, abolish described just lining structure by local after the top radial grouting of the inner implementation condition towards reserved described space enclosing structure of described transverse passage-way.
3. as claimed in claim 1 based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition, it is characterized in that: the position be in described transverse passage-way below described two lining top boards has also been horizontally disposed with two lining dividing plates, after completing steps four, then fill element soil in the cavity enclosing formation toward described two lining top boards, described two lining dividing plates and transverse passage-way inside wall.
4. as claimed in claim 1 or 2 based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition, it is characterized in that: the implementation condition of space enclosing structure described in step 3 is above described two lining top boards, remain for the wide mounting groove of 0.8-1.0m that described space enclosing structure plugs in advance.
CN201310080820.1A 2013-03-14 2013-03-14 Based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition Active CN104047621B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310080820.1A CN104047621B (en) 2013-03-14 2013-03-14 Based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310080820.1A CN104047621B (en) 2013-03-14 2013-03-14 Based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition

Publications (2)

Publication Number Publication Date
CN104047621A CN104047621A (en) 2014-09-17
CN104047621B true CN104047621B (en) 2015-12-23

Family

ID=51500972

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310080820.1A Active CN104047621B (en) 2013-03-14 2013-03-14 Based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition

Country Status (1)

Country Link
CN (1) CN104047621B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104632228B (en) * 2014-12-19 2017-04-12 中国建筑第四工程局有限公司 Main track entering construction method for cross aisle and cross aisle
CN106567717B (en) * 2015-10-10 2019-03-05 中铁第六勘察设计院集团有限公司 It is a kind of to double as construction access ramp structure and construction method using subway entrance
CN108930537B (en) * 2018-06-12 2019-04-23 济南城建集团有限公司 A kind of integrating tunnel main tunnel is excavated and the method for traffic above-ground leading setting vertical shaft
CN110778341B (en) * 2019-11-01 2021-07-13 中建八局轨道交通建设有限公司 Backfill construction method for construction vertical shaft and construction transverse passage
CN111577292B (en) * 2020-04-29 2022-02-18 中铁十二局集团有限公司 Double-branch road construction method for underground excavation station of local water-rich sand layer
CN113106982B (en) * 2021-04-13 2023-03-07 中铁十四局集团有限公司 Construction method of building enclosure without embedding
CN113106979B (en) * 2021-04-13 2023-08-04 中铁十四局集团有限公司 Excavation method of upper cover foundation pit and construction method for upper cover storey addition

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03103600A (en) * 1989-09-14 1991-04-30 Takenaka Komuten Co Ltd Construction of large space of building in extremely deep underground
JPH04309694A (en) * 1991-04-05 1992-11-02 Toda Constr Co Ltd Underground space construction method
JPH06346698A (en) * 1993-06-08 1994-12-20 Kajima Corp Construction method of underground space
CN1587643A (en) * 2004-09-02 2005-03-02 同济大学 Digging method for shallow underground hole
CN101280568A (en) * 2008-05-28 2008-10-08 上海隧道工程股份有限公司 Station pit construction method forming protection for neighboring operated subway interval tunnel

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03103600A (en) * 1989-09-14 1991-04-30 Takenaka Komuten Co Ltd Construction of large space of building in extremely deep underground
JPH04309694A (en) * 1991-04-05 1992-11-02 Toda Constr Co Ltd Underground space construction method
JPH06346698A (en) * 1993-06-08 1994-12-20 Kajima Corp Construction method of underground space
CN1587643A (en) * 2004-09-02 2005-03-02 同济大学 Digging method for shallow underground hole
CN101280568A (en) * 2008-05-28 2008-10-08 上海隧道工程股份有限公司 Station pit construction method forming protection for neighboring operated subway interval tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《浅埋暗挖隧道小净距下穿市政设施的施工技术》;吕亮等;《市政技术 规划设计篇》;20101130;第28卷;第32-34、51页 *

Also Published As

Publication number Publication date
CN104047621A (en) 2014-09-17

Similar Documents

Publication Publication Date Title
CN104047621B (en) Based on the maximum section of passenger flow adit construction method of top small interval basement excavation condition
CN104047623B (en) A kind of big across cavern excavation construction method
CN105298507B (en) A kind of underground pipe gallery construction method of top open cut bottom tunneler construction
CN103032097B (en) Be applicable to tunnel drainage structure and the construction method thereof of bias voltage water rich strata
CN104404974B (en) The thick sand-pebble layer deep basal pit of high artesian slip casting back cover structure and construction technology thereof
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN103195455B (en) Weak geological environment large cross-section tunnel construction supporting system and construction method
CN104763433A (en) Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN105003270A (en) Underwater tunnel construction method suitable for ultra-shallow earthing conditions
CN104165056A (en) Construction method for excavating water-rich shallow underground excavation tunnel
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN103225306B (en) Method of preventing foundation pit leakage during excavation of foundation pit close to water source
CN102660955B (en) Quick construction method for foundation pit slope support
CN209195427U (en) The open cut tunnel for passing through half Packing character solution cavity adds the tunnel bottom stake hardened structure of raft
CN102913249B (en) Inclined shaft transverse through positive hole single-horn lifting construction method
CN103306682A (en) Long-span and high-side-wall underground space building and excavation support method thereof
CN106812156A (en) A kind of assembled hypogee and its construction method
CN202865850U (en) Near-end shield tunnel foundation pit excavation supporting structure
CN103527204B (en) A kind of method for tunnel construction of first wall rear arch intersection median septum
CN205894027U (en) Structure is oozed in cutting of power station underground factory building
CN104088296B (en) Soft clay area basement adds a layer construction method
CN203613544U (en) Envelop enclosure for deep foundation pit partition simultaneous excavation
CN203050779U (en) Tunnel drainage structure suitable for bias pressure rich water strata
CN204252148U (en) High artesian thick sand-pebble layer deep foundation ditch slip casting back cover structure
CN103966981B (en) Force transferring structure and the construction method thereof of arch dam is built on weathering rock mass

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 200011 Tibet South Road, Shanghai, No. 1170, No.

Patentee after: Shanghai urban construction design & Research Institute (Group) Co., Ltd.

Address before: 200125 Dongfang Road, Shanghai, Pudong New Area, No. 3447

Patentee before: Shanghai Urban Construction Design & Research Institute