CN104032946B - A kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof - Google Patents
A kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof Download PDFInfo
- Publication number
- CN104032946B CN104032946B CN201410257899.5A CN201410257899A CN104032946B CN 104032946 B CN104032946 B CN 104032946B CN 201410257899 A CN201410257899 A CN 201410257899A CN 104032946 B CN104032946 B CN 104032946B
- Authority
- CN
- China
- Prior art keywords
- screw rod
- scaffold
- connecting screw
- steel cable
- wire rope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The invention belongs to the realm of building construction, be specifically related to a kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof, this assembly is fixedly connected on outer choosing on girder steel by steel cable, be used for reinforcing outer outrigger scaffold, described assembly comprises the oblique plastic bushing in floor that is embedded in advance, in plastic bushing, be provided with a connecting screw rod, connecting screw rod is connected in steel cable near scaffold end, from inside to outside adjacent backing plate, bevel washer and the nut of being provided with successively of the connecting screw rod other end. The present invention can reinforce the outer scaffold of choosing, and makes scaffold safer, and installs simple and convenient, effective.
Description
Technical field
The invention belongs to the realm of building construction, be specifically related to a kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof.
Background technology
The device of auxiliary construction when scaffold is building structure construction, in prior art, when building structure construction due to scaffold is fixed or install not rationally, firmly, have again, because scaffold itself holds yielding design feature, easily there is security incident, especially the scaffold of skyscraper. In view of this, the applicant provides a kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof in conjunction with the experience of being engaged in for many years construction, and this case produces thus.
Summary of the invention
The object of the present invention is to provide a kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof, to reinforce scaffold, prevention scaffold is because fixing or installation not rationally, firmly occurs security incident.
For achieving the above object, the concrete technical scheme of the present invention is: the pre-buried steel wire rope drag hook component of a kind of outer outrigger scaffold, this assembly is fixedly connected on outer choosing on girder steel by steel cable, be used for reinforcing outer outrigger scaffold, described assembly comprises the oblique plastic bushing in floor that is embedded in advance, in plastic bushing, be provided with a connecting screw rod, connecting screw rod is connected in steel cable near scaffold end, from inside to outside adjacent backing plate, bevel washer and the nut of being provided with successively of the connecting screw rod other end.
Further, the adjacent nut end face of described bevel washer is inclined-plane.
Further, the screw that described backing plate is connected with connecting screw rod with bevel washer is skewed screw hole.
A construction installation method for the pre-buried steel wire rope drag hook component of outer outrigger scaffold, specifically comprises the steps: (1), sets assembly draw node and quantity when fixing according to outer outrigger scaffold code requirement; (2), with before concreting floor, plastic bushing being tiltedly embedded in floor in advance; (3), outer choosing on girder steel is fixed in one end of steel cable; (4), connecting screw rod penetrates in pre-buried plastic bushing, the crotch of connecting screw rod is down; (5), the other end of steel cable penetrates in the crotch of connecting screw rod, and fixes steel cable after definite steel cable length; (6), backing plate, bevel washer be inserted in to connecting screw rod successively towards upper end and tighten up steel cable with nut.
Beneficial effect of the present invention: the present invention chooses girder steel outside connecting by steel cable one end, and the other end is fixed on flooring, reinforces scaffold; Described assembly comprises the plastic bushing being embedded in advance in floor, in plastic bushing, be provided with a connecting screw rod, connecting screw rod is connected in steel cable near scaffold end, from inside to outside adjacent backing plate, bevel washer and the nut of being provided with successively of the connecting screw rod other end, this modular construction is simple and practical, easy for installation, and can regulate according to the actual requirements and tighten up steel cable.
Below in conjunction with drawings and the specific embodiments, the present invention is described in further detail.
Brief description of the drawings
Fig. 1 is structural representation of the present invention;
Fig. 2 is that the present invention uses state diagram and partial enlarged drawing;
Fig. 3 is the enlarged drawing that the present invention chooses girder steel and steel cable junction outward.
Detailed description of the invention
As shown in Figure 1, 2, 3, what the present invention disclosed is the pre-buried steel wire rope drag hook component of a kind of outer outrigger scaffold, this assembly is fixedly connected on outer choosing on girder steel 2 by steel cable 1, be used for reinforcing outer outrigger scaffold 3, described assembly comprises the oblique plastic bushing 4 in floor 9 that is embedded in advance, in plastic bushing 4, be provided with a connecting screw rod 5, connecting screw rod 5 is connected in steel cable 1 near scaffold end, connects from inside to outside adjacent backing plate 6, bevel washer 7 and the nut 8 of being provided with successively of the spiral shell 5 bar other ends.
Further, adjacent nut 8 end faces of described bevel washer 7 are inclined-plane; The screw that described backing plate 6 is connected with connecting screw rod 5 with bevel washer 7 is skewed screw hole.
A construction installation method for the pre-buried steel wire rope drag hook component of outer outrigger scaffold, specifically comprises the steps: (1), sets assembly draw node and quantity when fixing according to outer outrigger scaffold 3 code requirements; (2), plastic bushing 4 being tiltedly embedded in floor 9 in advance with concreting floor 9 is front; (3), outer choosing on girder steel 2 is fixed in one end of steel cable 1; (4), connecting screw rod 5 penetrates in pre-buried plastic bushing 4, the crotch of connecting screw rod 4 is down; (5), the other end of steel cable 1 penetrates in the crotch of connecting screw rod 5, and fixes steel cable 1 after definite steel cable 1 length; (6), backing plate 6, bevel washer 7 are inserted in successively to connecting screw rod 5 and also tighten up steel cable 1 with nut 8 towards upper end.
Shown in Fig. 2,3, its China and foreign countries choose girder steel 2 one end and are fixedly installed on flooring, the other end is fixed on scaffold 3, be used for fixing scaffold 3, the present invention connects the outer girder steel 2 of choosing by steel cable 1 indirectly to reinforce scaffold 3, steel cable 1 is to fix by pricking head with choosing girder steel 2 and connecting screw rod 5 junctions outward, and the present invention is assembly of each storey setting.
Plastic bushing 4 of the present invention is to be tiltedly embedded in advance near in scaffold 3 place's floors 9, when pre-buried, the two ends of plastic bushing 4 is exposed to floor, so that better installation component.
Another embodiment of the present invention, is that bevel washer 7 is cancelled, the adjacent backing plate 6 of nut 8, and backing plate 6 is inclined-plane with adjacent of nut 8 and agrees with nut 8 contact-making surfaces.
Above-described embodiment and graphic and non-limiting product form of the present invention and style, suitable variation or modification that any person of an ordinary skill in the technical field does it, all should be considered as not departing from patent category of the present invention.
Claims (3)
1. the pre-buried steel wire rope drag hook component of outer outrigger scaffold, it is characterized in that: this assembly is fixedly connected on outer choosing on girder steel by steel cable, be used for reinforcing outer outrigger scaffold, described assembly comprises the oblique plastic bushing in floor that is embedded in advance, in plastic bushing, be provided with a connecting screw rod, connecting screw rod is connected in steel cable near scaffold end, from inside to outside adjacent backing plate, bevel washer and the nut of being provided with successively of the connecting screw rod other end.
2. the outer pre-buried steel wire rope drag hook component of outrigger scaffold of one according to claim 1, is characterized in that: the adjacent nut end face of described bevel washer is inclined-plane.
3. the construction installation method of the pre-buried steel wire rope drag hook component of a kind of outer outrigger scaffold according to claim 1, is characterized in that: specifically comprise the steps: (1), set assembly draw node and quantity when fixing according to outer outrigger scaffold code requirement; (2), with before concreting floor, plastic bushing being tiltedly embedded in floor in advance; (3), outer choosing on girder steel is fixed in one end of steel cable; (4), connecting screw rod penetrates in pre-buried plastic bushing, the crotch of connecting screw rod is down; (5), the other end of steel cable penetrates in the crotch of connecting screw rod, and fixes steel cable after definite steel cable length; (6), backing plate, bevel washer be inserted in to connecting screw rod successively towards upper end and tighten up steel cable with nut.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410257899.5A CN104032946B (en) | 2014-06-11 | 2014-06-11 | A kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410257899.5A CN104032946B (en) | 2014-06-11 | 2014-06-11 | A kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104032946A CN104032946A (en) | 2014-09-10 |
CN104032946B true CN104032946B (en) | 2016-05-11 |
Family
ID=51463918
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410257899.5A Active CN104032946B (en) | 2014-06-11 | 2014-06-11 | A kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104032946B (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2136395A5 (en) * | 1972-04-10 | 1972-12-22 | Outinord Sa Ets | |
CN202248831U (en) * | 2011-09-15 | 2012-05-30 | 浙江城建建设集团有限公司 | Flying ring used for lacing diagonal steel wire rope and building structure |
CN103821333A (en) * | 2014-02-27 | 2014-05-28 | 中天建设集团有限公司 | Construction method for overhung scaffold with detachable triangular supports |
CN203977839U (en) * | 2014-06-11 | 2014-12-03 | 绍兴县明煌建材科技有限公司 | The pre-buried wire rope drag hook component of a kind of outer outrigger scaffold |
-
2014
- 2014-06-11 CN CN201410257899.5A patent/CN104032946B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2136395A5 (en) * | 1972-04-10 | 1972-12-22 | Outinord Sa Ets | |
CN202248831U (en) * | 2011-09-15 | 2012-05-30 | 浙江城建建设集团有限公司 | Flying ring used for lacing diagonal steel wire rope and building structure |
CN103821333A (en) * | 2014-02-27 | 2014-05-28 | 中天建设集团有限公司 | Construction method for overhung scaffold with detachable triangular supports |
CN203977839U (en) * | 2014-06-11 | 2014-12-03 | 绍兴县明煌建材科技有限公司 | The pre-buried wire rope drag hook component of a kind of outer outrigger scaffold |
Also Published As
Publication number | Publication date |
---|---|
CN104032946A (en) | 2014-09-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203977839U (en) | The pre-buried wire rope drag hook component of a kind of outer outrigger scaffold | |
CN101736893B (en) | Overhanging type scaffold supporting system | |
CN103206074B (en) | Elevator shaft template construction method, platform and support | |
CN204940556U (en) | A kind of steel structure girder of building in the style of the ancients and the syndeton of pin | |
CN102235034A (en) | Prefabricated part and construction method for connecting prefabricated part with main structure | |
CN203808484U (en) | Integrated cantilevered and attached external scaffolding | |
CN109555300A (en) | A kind of builder's jack | |
CN204919828U (en) | Archaize building's wooden frame and steel structure column's connection structure | |
CN104032946B (en) | A kind of pre-buried steel wire rope drag hook component of outer outrigger scaffold and construction installation method thereof | |
CN103255892A (en) | Installing device of veneers or stone curtain walls and construction method for dry hanging veneers or stone curtain walls | |
CN202745402U (en) | Hard protection structure for construction of high-rise elevator shaft | |
CN107762135B (en) | Construction method of scaffold wall connecting piece of building outer wall | |
CN209585576U (en) | A kind of builder's jack | |
CN204681011U (en) | Wire rack | |
CN204343642U (en) | Builder's jack corner support frame | |
CN203097310U (en) | Horizontal opening protective covering plate device of high-rise building face | |
CN202055509U (en) | Upright rod installation structure of directly-inserted scaffold | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN204139585U (en) | A kind of scaffold | |
CN204343647U (en) | A kind of the shaped steel suspension scaffolding bracing frame | |
CN203066500U (en) | Floor hole security protection device | |
CN203701559U (en) | Guiding device for external scaffold | |
CN204738522U (en) | Channel -section steel mounting of encorbelmenting | |
CN203684557U (en) | Fixed reinforcement device for handrail | |
CN205063318U (en) | Device for connecting scaffold and concrete wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |