CN107762135B - Construction method of scaffold wall connecting piece of building outer wall - Google Patents

Construction method of scaffold wall connecting piece of building outer wall Download PDF

Info

Publication number
CN107762135B
CN107762135B CN201610698483.6A CN201610698483A CN107762135B CN 107762135 B CN107762135 B CN 107762135B CN 201610698483 A CN201610698483 A CN 201610698483A CN 107762135 B CN107762135 B CN 107762135B
Authority
CN
China
Prior art keywords
wall
building
embedded section
scaffolding
exterior wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610698483.6A
Other languages
Chinese (zh)
Other versions
CN107762135A (en
Inventor
黄杰
陈士红
丁雪林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201610698483.6A priority Critical patent/CN107762135B/en
Publication of CN107762135A publication Critical patent/CN107762135A/en
Application granted granted Critical
Publication of CN107762135B publication Critical patent/CN107762135B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • E04G5/046Means for fastening, supporting, or bracing scaffolds on or against building constructions for fastening scaffoldings on walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种建筑物外墙脚手架连墙件的施工方法,本方法首先确定建筑物外墙模板需预埋连墙件的位置,在该位置开设与连墙件螺纹预埋段直径匹配的洞口;建筑物外墙梁板钢筋绑扎完成后,将预埋段拧入螺栓紧固件后插入洞口至建筑物外墙边缘梁构件内,预埋段通过螺栓紧固件固定在模板上,并且固定预埋段;浇筑建筑物外墙混凝土,并防止预埋段脱落、移位;待混凝土保养至建筑物外墙侧模可拆除时,将螺栓紧固件拆除,继而拆除侧模,将外部钢管通过螺纹连接预埋段,外部钢管连接建筑物外墙脚手架的锚固端。本方法确保脚手架连墙件可按照规范均匀等距布置,避免了脚手架搭建的安全隐患,解决了因脚手眼封堵而产生的墙面漏水问题,提高了施工质量。

The invention discloses a construction method of a building exterior wall scaffolding connecting wall piece. The method firstly determines the position where the building exterior wall formwork needs to be pre-embedded with the connecting wall piece, and the diameter of the pre-embedded section of the thread of the connecting wall piece is set at the position. After the reinforcement of the beams and slabs of the building exterior wall is completed, the embedded section is screwed into the bolt fasteners and inserted into the opening into the beam member at the edge of the building exterior wall. The embedded section is fixed on the formwork by the bolt fasteners. And fix the embedded section; pour concrete on the exterior wall of the building, and prevent the embedded section from falling off and shifting; when the concrete is maintained until the side formwork of the exterior wall of the building can be removed, the bolt fasteners are removed, and then the side formwork is removed, and the The external steel pipe is connected to the embedded section through the thread, and the external steel pipe is connected to the anchoring end of the scaffolding on the external wall of the building. The method ensures that the scaffolding and wall parts can be arranged evenly and equidistantly according to the specification, avoids the hidden safety hazards of scaffolding construction, solves the problem of water leakage on the wall surface caused by the blocking of the scaffolding and eyes, and improves the construction quality.

Description

建筑物外墙脚手架连墙件的施工方法Construction method of building external wall scaffolding connecting wall parts

技术领域technical field

本发明涉及一种建筑物外墙脚手架连墙件的施工方法。The invention relates to a construction method of a building outer wall scaffolding connecting wall piece.

背景技术Background technique

随着基础建设的发展,高层建筑越来越多,由于绝大部分高层建筑采用的是框架剪力墙结构,使得建筑物外墙脚手架连墙件因外部剪力墙的存在而无法按照规范均匀等距布置,脚手架的搭建存在安全隐患。在建筑工程中连墙件是用于将脚手架架体与建筑主体结构连接、能够传递拉力和压力的构件,采用连墙件实现脚手架的附壁联结,对于加强脚手架的整体稳定性,提高其稳定承载能力和避免出现倾倒或坍塌等重大事故具有很重要的作用。并且传统连墙件在砌筑时必须留下脚手眼,后期封堵易造成墙体漏水,所以解决此问题刻不容缓。With the development of infrastructure construction, there are more and more high-rise buildings. Since most high-rise buildings use frame shear wall structure, the scaffolding and connecting wall parts of the building exterior wall cannot be uniform in accordance with the specification due to the existence of the external shear wall. Equidistant arrangement, the construction of scaffolding poses a safety hazard. In the construction project, the connecting wall is a component used to connect the scaffold body with the main structure of the building and can transmit tension and pressure. The connecting wall is used to realize the attachment of the scaffolding, which can strengthen the overall stability of the scaffold and improve its stability. Bearing capacity and avoidance of major accidents such as tipping or collapse play an important role. In addition, the traditional wall joints must be left with scaffolding during the masonry, and the later blocking will easily cause the wall to leak, so it is urgent to solve this problem.

发明内容SUMMARY OF THE INVENTION

本发明所要解决的技术问题是提供一种建筑物外墙脚手架连墙件的施工方法,本方法确保脚手架连墙件可按照规范均匀等距布置,避免了脚手架搭建的安全隐患,解决了因脚手眼封堵而产生的墙面漏水问题,提高了施工质量。The technical problem to be solved by the present invention is to provide a construction method of scaffolding and wall-connecting parts for building exterior walls. This method ensures that the scaffolding-connecting wall parts can be arranged evenly and equidistantly according to the specification, avoids the potential safety hazards of scaffolding construction, and solves the problem of The problem of water leakage on the wall caused by hand-eye blocking improves the construction quality.

为解决上述技术问题,本发明建筑物外墙脚手架连墙件的施工方法包括如下步骤:In order to solve the above-mentioned technical problems, the construction method of the building outer wall scaffolding connecting wall piece of the present invention comprises the following steps:

步骤一、根据建筑物外墙脚手架的设计图纸确定建筑物外墙模板需预埋连墙件的位置,并且在该位置开设与连墙件螺纹预埋段直径匹配的洞口;Step 1: According to the design drawings of the building exterior wall scaffolding, determine the position where the building exterior wall formwork needs to embed the connecting wall piece, and open a hole matching the diameter of the thread embedded section of the connecting wall piece at this position;

步骤二、在建筑物外墙梁板钢筋绑扎完成后,将连墙件的预埋段拧入螺栓紧固件后插入洞口至建筑物外墙边缘梁构件内,预埋段通过螺栓紧固件固定在模板上,并且预埋段采用扎丝与钢筋固定;Step 2. After the reinforcement of the beams and slabs of the building exterior wall is completed, screw the pre-embedded section of the connecting wall into the bolt fastener and insert the hole into the beam member at the edge of the building exterior wall, and the pre-embedded section passes through the bolt fastener. It is fixed on the formwork, and the embedded section is fixed with wire ties and steel bars;

步骤三、建筑物外墙浇筑混凝土,浇筑时防止预埋段脱落、移位;Step 3. Concrete is poured on the outer wall of the building to prevent the pre-embedded section from falling off and shifting during pouring;

步骤四、待混凝土保养至建筑物外墙侧模可拆除时,将螺栓紧固件拆除,继而拆除侧模,将外部钢管通过螺纹连接连墙件的预埋段,外部钢管连接建筑物外墙脚手架的锚固端。Step 4. When the concrete is maintained until the side formwork of the exterior wall of the building can be removed, the bolt fasteners are removed, and then the side formwork is removed, the external steel pipe is connected to the embedded section of the connecting wall through the thread, and the external steel pipe is connected to the external wall of the building. The anchored end of the scaffolding.

由于本发明建筑物外墙脚手架连墙件的施工方法采用了上述技术方案,即本方法首先确定建筑物外墙模板需预埋连墙件的位置,在该位置开设与连墙件螺纹预埋段直径匹配的洞口;建筑物外墙梁板钢筋绑扎完成后,将预埋段拧入螺栓紧固件后插入洞口至建筑物外墙边缘梁构件内,预埋段通过螺栓紧固件固定在模板上,并且固定预埋段;浇筑建筑物外墙混凝土,并防止预埋段脱落、移位;待混凝土保养至建筑物外墙侧模可拆除时,将螺栓紧固件拆除,继而拆除侧模,将外部钢管通过螺纹连接预埋段,外部钢管连接建筑物外墙脚手架的锚固端。本方法确保脚手架连墙件可按照规范均匀等距布置,避免了脚手架搭建的安全隐患,解决了因脚手眼封堵而产生的墙面漏水问题,提高了施工质量。Because the construction method of the building exterior wall scaffolding connecting wall piece of the present invention adopts the above technical scheme, that is, the method first determines the position where the building exterior wall formwork needs to be pre-embedded with the connecting wall piece, and at this position, the thread pre-embedded with the connecting wall piece is opened. The hole with the matching diameter of the section; after the reinforcement of the beams and slabs of the building exterior wall is bound, screw the embedded section into the bolt fasteners and insert the hole into the beam member at the edge of the building exterior wall. On the formwork, and fix the embedded section; pour concrete on the exterior wall of the building, and prevent the embedded section from falling off and shifting; when the concrete is maintained until the side formwork of the exterior wall of the building can be removed, remove the bolt fasteners, and then remove the side formwork. The external steel pipe is connected to the embedded section through the thread, and the external steel pipe is connected to the anchoring end of the outer wall scaffolding of the building. The method ensures that the scaffolding and wall parts can be arranged evenly and equidistantly according to the specification, avoids the hidden safety hazards of scaffolding construction, solves the problem of water leakage on the wall surface caused by the blocking of the scaffolding and eyes, and improves the construction quality.

附图说明Description of drawings

下面结合附图和实施方式对本发明作进一步的详细说明:Below in conjunction with accompanying drawing and embodiment, the present invention is described in further detail:

图1为本方法中连墙件的预埋段和螺栓紧固件的设置示意图;Figure 1 is a schematic diagram of the arrangement of the embedded section of the connecting wall piece and the bolt fastener in this method;

图2为本方法中连墙件的预埋段与外部钢管的连接示意图。FIG. 2 is a schematic diagram of the connection between the embedded section of the connecting wall piece and the external steel pipe in the method.

具体实施方式Detailed ways

实施例如图1和图2所示,本发明建筑物外墙脚手架连墙件的施工方法包括如下步骤:Embodiment As shown in Fig. 1 and Fig. 2, the construction method of building exterior wall scaffold connecting wall piece of the present invention comprises the following steps:

步骤一、根据建筑物外墙1脚手架的设计图纸确定建筑物外墙模板2需预埋连墙件的位置,并且在该位置开设与连墙件螺纹预埋段3直径匹配的洞口;Step 1, determine the position where the building exterior wall formwork 2 needs to embed the wall fittings according to the design drawings of the scaffolding of the building exterior wall 1, and open a hole matching the diameter of the thread embedded section 3 of the connecting wall fittings at this position;

步骤二、在建筑物外墙1梁板钢筋绑扎完成后,将连墙件的预埋段3拧入螺栓紧固件4后插入洞口至建筑物外墙边缘梁构件内,预埋段3通过螺栓紧固件4固定在模板1上,并且预埋段3采用扎丝5与钢筋固定;Step 2. After the building exterior wall 1 beams and slabs are bound with steel bars, the embedded section 3 of the connecting wall is screwed into the bolt fasteners 4 and then inserted into the hole into the building exterior wall edge beam member, and the embedded section 3 passes through. The bolt fastener 4 is fixed on the formwork 1, and the embedded section 3 is fixed with the wire 5 and the steel bar;

步骤三、建筑物外墙1浇筑混凝土,浇筑时防止预埋段3脱落、移位;Step 3. Concrete is poured on the outer wall 1 of the building to prevent the pre-embedded section 3 from falling off and shifting during pouring;

步骤四、待混凝土保养至建筑物外墙1侧模可拆除时,将螺栓紧固件4拆除,继而拆除侧模,将外部钢管6通过螺纹连接连墙件的预埋段3,外部钢管6连接建筑物外墙脚手架的锚固端。Step 4. When the concrete is maintained until the side formwork of the building exterior wall 1 can be removed, the bolt fasteners 4 are removed, and then the side formwork is removed, and the external steel pipe 6 is connected to the embedded section 3 of the connecting wall piece by thread, and the external steel pipe 6 Connecting the anchoring end of the scaffolding on the exterior wall of the building.

本方法可使连墙件均匀预埋在建筑物的主体结构内,解决了建筑物外部剪力墙等构件影响并阻碍脚手架连墙件等距均匀预埋的问题;且后期砌筑时不会留下脚手眼,解决了因脚手眼封堵而产生的墙面漏水问题,克服了传统脚手架连墙件所带来的问题。The method can make the connecting wall parts evenly embedded in the main structure of the building, and solve the problem that the external shear walls and other components of the building affect and hinder the equidistant and evenly pre-buried scaffolding connecting wall parts; Leaving the scaffolding eyes solves the problem of water leakage on the wall caused by the blocking of the scaffolding and eyes, and overcomes the problems caused by the traditional scaffolding connected to the wall.

本方法的连墙件预埋方式简单,易拆除,省去后期拆除脚手架外架切割连墙件钢管的繁琐步骤,不受剪力墙等构件影响预埋,实现连墙件按规范预设,避免了传统连墙件影响木工搭设高一层内架的麻烦,解决了施工现场总存在的木工为搭设内架拆除连墙件而不恢复的问题,从而提高了施工质量。The method of pre-embedding the connecting wall parts is simple and easy to dismantle, eliminating the tedious steps of later dismantling the outer frame of the scaffold and cutting the steel pipes of the connecting wall parts, and is not affected by the shear wall and other components. It avoids the trouble that the traditional connecting wall piece affects the carpenter to set up a high-level inner frame, and solves the problem that the carpenter always removes the connecting wall piece for setting up the inner frame and does not restore it at the construction site, thereby improving the construction quality.

Claims (1)

1. A construction method of a scaffold wall connecting piece of an external wall of a building is characterized by comprising the following steps:
determining the position of a building outer wall template, which needs to embed a wall connecting piece in advance, according to a design drawing of a scaffold of the building outer wall, and forming a hole matched with the diameter of a thread embedded section of the wall connecting piece at the position;
step two, after the reinforcement of the beam plate of the outer wall of the building is bound, the embedded section of the wall connecting piece is screwed into the bolt fastener and then inserted into the opening to the edge beam member of the outer wall of the building, the embedded section is fixed on the template through the bolt fastener, and the embedded section is fixed with the reinforcement through the binding wire;
step three, concrete is poured on the outer wall of the building, and the embedded section is prevented from falling off and shifting during pouring;
and step four, when the concrete is maintained until the side mold of the outer wall of the building can be disassembled, disassembling the bolt fastener, then disassembling the side mold, connecting an external steel pipe with the embedded section of the wall connecting piece through threads, and connecting the external steel pipe with the anchoring end of the scaffold of the outer wall of the building.
CN201610698483.6A 2016-08-22 2016-08-22 Construction method of scaffold wall connecting piece of building outer wall Expired - Fee Related CN107762135B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610698483.6A CN107762135B (en) 2016-08-22 2016-08-22 Construction method of scaffold wall connecting piece of building outer wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610698483.6A CN107762135B (en) 2016-08-22 2016-08-22 Construction method of scaffold wall connecting piece of building outer wall

Publications (2)

Publication Number Publication Date
CN107762135A CN107762135A (en) 2018-03-06
CN107762135B true CN107762135B (en) 2020-01-14

Family

ID=61262354

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610698483.6A Expired - Fee Related CN107762135B (en) 2016-08-22 2016-08-22 Construction method of scaffold wall connecting piece of building outer wall

Country Status (1)

Country Link
CN (1) CN107762135B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110439124A (en) * 2019-09-05 2019-11-12 湖南中力建筑设备租赁有限公司 A kind of pre-embedded device
CN110952767A (en) * 2019-11-06 2020-04-03 上海建工七建集团有限公司 Assembled bolt connection scaffold wall connecting piece and mounting method
CN111364752A (en) * 2020-03-27 2020-07-03 中铁二局集团有限公司 Wall scaffold mounting method and embedded bolt wall connecting piece device
CN112554544B (en) * 2020-12-04 2025-09-16 国网黑龙江省电力有限公司牡丹江水力发电总厂 Built-in part, built-in tool, built-in fixing structure and pre-buried construction method for scaffold connection
CN115095134A (en) * 2022-07-19 2022-09-23 中铁一局集团(广州)建设工程有限公司 Novel outer frame wall connecting device and construction method thereof
CN117230981A (en) * 2023-08-24 2023-12-15 中国五冶集团有限公司 Wall connecting piece and wall connecting structure and method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201826517U (en) * 2010-10-21 2011-05-11 锦宸集团有限公司 Scaffold-wall connecting component in construction
CN203129564U (en) * 2013-03-07 2013-08-14 中国十七冶集团有限公司 Simple wall connection device for scaffold in silo slip-form construction
CN203654710U (en) * 2014-01-15 2014-06-18 南通四建集团有限公司 Instrumental connecting tube for external wall scaffold shearing wall portion
CN203669332U (en) * 2013-12-31 2014-06-25 武汉建工股份有限公司 Straight thread connection combined type steel pipe scaffold wall connecting component
CN204139576U (en) * 2014-08-19 2015-02-04 上海建工五建集团有限公司 For the external scaffolding drawknot structure of preset assembling plate

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201826517U (en) * 2010-10-21 2011-05-11 锦宸集团有限公司 Scaffold-wall connecting component in construction
CN203129564U (en) * 2013-03-07 2013-08-14 中国十七冶集团有限公司 Simple wall connection device for scaffold in silo slip-form construction
CN203669332U (en) * 2013-12-31 2014-06-25 武汉建工股份有限公司 Straight thread connection combined type steel pipe scaffold wall connecting component
CN203654710U (en) * 2014-01-15 2014-06-18 南通四建集团有限公司 Instrumental connecting tube for external wall scaffold shearing wall portion
CN204139576U (en) * 2014-08-19 2015-02-04 上海建工五建集团有限公司 For the external scaffolding drawknot structure of preset assembling plate

Also Published As

Publication number Publication date
CN107762135A (en) 2018-03-06

Similar Documents

Publication Publication Date Title
CN107762135B (en) Construction method of scaffold wall connecting piece of building outer wall
CN101949213B (en) Special support system of building structure deformed seam template
CN201443203U (en) A mold with reserved holes for cast-in-place reinforced concrete floor slabs
CN104358360A (en) Full-grouting sleeve for connection of construction reinforcing steel bars
CN207553314U (en) A kind of concrete postposition beam anchor bar constructing structure
US9169635B2 (en) Apparatus to tie forms to existing structures
CN204186002U (en) Screw shear wall protective layer thickness control device
CN206625428U (en) Pipe shaft post-cast floor slab closed system
CN203669368U (en) Split type split bolt
CN104453226B (en) Secondary structure constructional column formwork erection positioner
CN204299044U (en) A kind of building iron connects uses full grout sleeve
CN103556825B (en) The construction method of preserved pipeline sleeve pipe in a kind of high building structure layer concrete
CN217053788U (en) Large-tonnage embedded part
CN106499180B (en) A kind of novel exterior sheathing is reinforced and external scaffolding drawknot device and its construction method
CN105714985A (en) Steel bar connecting sleeve for concrete construction and construction process of steel bar connecting sleeve
CN214941092U (en) A detachable flower basket pull rod type cantilever scaffold embedded part
CN107152161B (en) The drawknot construction method of external scaffolding and wall interconnecting piece
CN104499712A (en) Building Formwork Tie Rod
CN205637571U (en) Do not have outside secret building wall who is detained pipe and pour template
CN209179465U (en) Pull-type screw-to-wall fittings
CN205206299U (en) Outer wall body concrete placement template fixing device in upper strata of crossing department of floor
CN207776413U (en) A kind of scaffold outrigger wall-connecting piece
CN115095134A (en) Novel outer frame wall connecting device and construction method thereof
CN203080926U (en) Reserved hole device of concrete floor slab
CN208594744U (en) Reinforcing device for inner formwork of concrete circular opening

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200114