CN104008194A - PDA-based electric energy meter rotation data processing system - Google Patents

PDA-based electric energy meter rotation data processing system Download PDF

Info

Publication number
CN104008194A
CN104008194A CN201410264307.2A CN201410264307A CN104008194A CN 104008194 A CN104008194 A CN 104008194A CN 201410264307 A CN201410264307 A CN 201410264307A CN 104008194 A CN104008194 A CN 104008194A
Authority
CN
China
Prior art keywords
module
electric energy
energy meter
pda
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410264307.2A
Other languages
Chinese (zh)
Other versions
CN104008194B (en
Inventor
曹袆
俞磊
黄锋
陈海宾
沈华
沈培刚
杜卫华
张雷
张垠
沈滢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Shanghai Electric Power Co Ltd
East China Power Test and Research Institute Co Ltd
Original Assignee
State Grid Shanghai Electric Power Co Ltd
East China Power Test and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Shanghai Electric Power Co Ltd, East China Power Test and Research Institute Co Ltd filed Critical State Grid Shanghai Electric Power Co Ltd
Priority to CN201410264307.2A priority Critical patent/CN104008194B/en
Publication of CN104008194A publication Critical patent/CN104008194A/en
Application granted granted Critical
Publication of CN104008194B publication Critical patent/CN104008194B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply

Abstract

The invention relates to a PDA-based electric energy meter rotation data processing system which comprises an electric energy meter marketing information server, an electric energy meter case adjustment management main station, a distributed substation and a PDA mounting and connecting handheld unit. The electric energy meter case adjustment management main station is connected with the electric energy meter marking information server through a network, the PDA mounting and connecting handheld unit is connected with the distributed substation through a data line, and the distributed substation is connected with the electric energy meter case adjustment management main station in a communication mode. Compared with the prior art, the PDA-based electric energy meter rotation data processing system has the advantages of guaranteeing accuracy of information of the electric energy meter rotation work and improving on-site exchanging efficiency, data entry efficiency and the like.

Description

A kind of electric energy meter rotation data handling system based on PDA
Technical field
The present invention relates to electric energy meter management data treatment technology, especially relate to a kind of electric energy meter rotation data handling system based on PDA.
Background technology
Along with the prolongation of service time, can there is the aging problem of mechanical wearing and tearing, electronic devices and components in intelligent electric energy meter, these problems often cause the metering of intelligent electric energy meter inaccurate.For ensureing the metering accuracy of intelligent electric energy meter, the whole nation " power supply and business rules " regulation " cycle verification, rotation charging electric meter that power supply enterprise must be in accordance with regulations; and charging electric meter is carried out to casual inspection ", be that power service enterprise needs the regular mounted intelligent electric energy meter of tearing open back to carry out periodic calibration, carry out the rotation of intelligent electric energy meter.
During traditional electric energy meter wheel changes jobs, field personnel has required electric energy meter to be assigned a new job according to dress work order, simultaneously in dress work order, record returns to, takes on electric energy meter information (comprise and take on table number, tear back meter reading open, take on meter reading etc.), finally dress work order is returned and information is entered in the marketing system server of electric energy meter by hand.Whole exchange process at the scene staff's link is all to carry out information transmission with the form of papery shop order, this has not only reduced the scene efficiency of being assigned a new job, greatly increase Data Enter work, and had the human error in information acquisition and Data Enter work.
Summary of the invention
Object of the present invention is exactly to provide a kind of electric energy meter rotation data handling system based on PDA in order to overcome the defect that above-mentioned prior art exists, and guarantees that technically electric energy meter take turns the information accuracy changing jobs, and improves on-the-spot exchange efficiency and data efficiency of inputting.
Object of the present invention can be achieved through the following technical solutions:
A kind of electric energy meter rotation data handling system based on PDA, comprise electric energy meter marketing message server, electric energy meter example tune management main website, distributed substation and PDA attaching palm machine, described electric energy meter example adjusts management main website to be connected by network with electric energy meter marketing message server, adjust management main website to send rotation information to electric energy meter example, described PDA attaching palm machine is connected with distributed substation by data line, described distributed substation adjusts management master station communication to be connected with electric energy meter example, adjusts management main website transmission completion information to electric energy meter example.
Described distributed substation and electric energy meter example adjust the exchanges data between management main website to realize by encrypted U disk.
Described electric energy meter example adjusts management main website to comprise main control module, rotation information receiver module, encrypt file generation module, encrypt file output module, completion information receiving module and data check module, described main control module connects respectively rotation information receiving module and completion information receiving module, described completion information receiving module connects respectively rotation information receiving module and encrypt file output module, and described completion information receiving module is connected with data check module;
Main control module judges current information, if rotation information starts rotation information receiving module and receives current information, generates task bag, and export to distributed substation by encrypt file output module by encrypt file generation module; If completion information, starts completion information receiving module and receive current information, and carry out verification by data check module, if generate warning message when verification is wrong, if verification is errorless, information is uploaded to electric energy meter marketing message server.
Described distributed substation is provided with multiple.
Described PDA attaching palm machine comprises:
CPU module;
Bar code scan module, is connected with CPU module, the information for the old table of automatically identifying, check rotation with new table, and check new and old table current specification and whether conform to;
Communication module, is connected with CPU module, for reading the reading of old table;
Voice cue module, is connected with CPU module, for sending operation prompt information or abnormal prompt information;
Display module, is connected with CPU module, for showing the information of old table or new table;
Memory module, is connected with CPU module, for preserving the information of old table and new table.
Described communication module comprises infrared communication module or 485 communication modules.
Compared with prior art, the present invention organically combines PDA technology and information-based means, PDA attaching palm facility are had been friends in the past to show to count and are checked, newly show the functions such as parameter judgement, new and old table corresponding relation coupling, abnormal conditions warning, the corresponding relation of guaranteeing reading at the bottom of the old table after electric energy meter rotation, Xin Biao and user is very accurate, reliability is high, reduce on-the-spot craft and made a copy of the error rate of data, improved the work efficiency of on-the-spot exchange, saved labour costs.
Brief description of the drawings
Fig. 1 is structural representation of the present invention;
Fig. 2 is the structured flowchart that electric energy meter example of the present invention is adjusted management main website.
Embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in detail.The present embodiment is implemented as prerequisite taking technical solution of the present invention, provided detailed embodiment and concrete operating process, but protection scope of the present invention is not limited to following embodiment.
As shown in Figure 1, a kind of electric energy meter rotation data handling system based on PDA, comprise electric energy meter marketing message server 1, electric energy meter example is adjusted management main website 2, distributed substation 3 and PDA attaching palm machine 4, described electric energy meter example adjusts management main website 2 to be connected by network with electric energy meter marketing message server 1, described PDA attaching palm machine 4 is connected with distributed substation 3 by data line, described distributed substation 3 is provided with multiple, multiple distributed substations 3 and electric energy meter example adjust the exchanges data between management main website 2 to realize by encrypted U disk, electric energy meter marketing message server 1 adjusts management main website 2 to send rotation information to electric energy meter example, distributed substation 3 adjusts management main website 2 to transmit completion information to electric energy meter example.
As shown in Figure 2, electric energy meter example adjusts management main website 2 to comprise main control module 21, rotation information receiver module 22, encrypt file generation module 23, encrypt file output module 24, completion information receiving module 25 and data check module 26, described main control module 21 connects respectively rotation information receiving module 22 and completion information receiving module 25, described completion information receiving module 25 connects respectively rotation information receiving module 22 and encrypt file output module 24, and described completion information receiving module 25 is connected with data check module 26; Main control module 21 judges current information, if rotation information starts rotation information receiving module 22 and receives current information, generates task bag by encrypt file generation module 23, and exports to distributed substation 3 by encrypt file output module 24; If completion information, starts completion information receiving module 25 and receive current information, and carry out verification by data check module 26, if generate warning message when verification is wrong, if verification is errorless, information is uploaded to electric energy meter marketing message server.
Described PDA attaching palm machine 4 comprises CPU module and the bar code scan module, communication module, voice cue module, display module and the memory module that are connected with CPU module respectively, can realize display module and memory module.Whether wherein, bar code scan module is the information with new table for the old table of automatically identifying, check rotation, and check new and old table current specification and conform to; Communication module comprises infrared communication module or 485 communication modules, for reading the reading of old table; Voice cue module, for sending operation prompt information or abnormal prompt information; Display module is for showing the information of old table or new table; Memory module is for preserving the information of old table and new table.On PDA attaching palm machine, be also provided with the function button that is respectively used to start bar code scan module, communication module and memory module.

Claims (6)

1. the electric energy meter rotation data handling system based on PDA, it is characterized in that, comprise electric energy meter marketing message server (1), electric energy meter example tune management main website (2), distributed substation (3) and PDA attaching palm machine (4), described electric energy meter example adjusts management main website (2) to be connected by network with electric energy meter marketing message server (1), described PDA attaching palm machine (4) is connected with distributed substation (3) by data line, and management main website (2) communication connection is adjusted with electric energy meter example in described distributed substation (3).
2. a kind of electric energy meter rotation data handling system based on PDA according to claim 1, is characterized in that, described distributed substation (3) and electric energy meter example adjust the exchanges data between management main website (2) to realize by encrypted U disk.
3. a kind of electric energy meter rotation data handling system based on PDA according to claim 1, it is characterized in that, described electric energy meter example adjusts management main website (2) to comprise main control module (21), rotation information receiver module (22), encrypt file generation module (23), encrypt file output module (24), completion information receiving module (25) and data check module (26), described main control module (21) connects respectively rotation information receiving module (22) and completion information receiving module (25), described completion information receiving module (25) connects respectively rotation information receiving module (22) and encrypt file output module (24), described completion information receiving module (25) is connected with data check module (26),
Main control module (21) judges current information, if rotation information, start rotation information receiving module (22) and receive current information, generate task bag by encrypt file generation module (23), and export to distributed substation (3) by encrypt file output module (24); If completion information, start completion information receiving module (25) and receive current information, and carry out verification by data check module (26), if generate warning message when verification is wrong, if verification is errorless, information is uploaded to electric energy meter marketing message server (1).
4. a kind of electric energy meter rotation data handling system based on PDA according to claim 1, is characterized in that, described distributed substation (3) is provided with multiple.
5. a kind of electric energy meter rotation data handling system based on PDA according to claim 1, is characterized in that, described PDA attaching palm machine (4) comprising:
CPU module;
Bar code scan module, is connected with CPU module, the information for the old table of automatically identifying, check rotation with new table, and check new and old table current specification and whether conform to;
Communication module, is connected with CPU module, for reading the reading of old table;
Voice cue module, is connected with CPU module, for sending operation prompt information or abnormal prompt information;
Display module, is connected with CPU module, for showing the information of old table or new table;
Memory module, is connected with CPU module, for preserving the information of old table and new table.
6. a kind of electric energy meter rotation data handling system based on PDA according to claim 5, is characterized in that, described communication module comprises infrared communication module or 485 communication modules.
CN201410264307.2A 2014-06-13 2014-06-13 A kind of electric energy meter rotation data handling system based on PDA Active CN104008194B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410264307.2A CN104008194B (en) 2014-06-13 2014-06-13 A kind of electric energy meter rotation data handling system based on PDA

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410264307.2A CN104008194B (en) 2014-06-13 2014-06-13 A kind of electric energy meter rotation data handling system based on PDA

Publications (2)

Publication Number Publication Date
CN104008194A true CN104008194A (en) 2014-08-27
CN104008194B CN104008194B (en) 2017-11-21

Family

ID=51368851

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410264307.2A Active CN104008194B (en) 2014-06-13 2014-06-13 A kind of electric energy meter rotation data handling system based on PDA

Country Status (1)

Country Link
CN (1) CN104008194B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106815543A (en) * 2016-12-16 2017-06-09 国网北京市电力公司 Data processing method and device
CN109242145A (en) * 2018-08-01 2019-01-18 深圳供电局有限公司 A kind of electric energy meter batch rotation field operation method, apparatus and system
CN110058067A (en) * 2019-04-24 2019-07-26 国网宁夏电力有限公司电力科学研究院 Information maintenance method and device when a kind of replacement electric energy meter

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201689440U (en) * 2010-04-29 2010-12-29 光一科技股份有限公司 Handheld bar-code meter reading machine
CN103354026A (en) * 2013-06-25 2013-10-16 国家电网公司 Meter reading instrument and method for replacing electric energy meter by virtue of meter reading instrument
CN203587795U (en) * 2013-11-18 2014-05-07 国家电网公司 Intelligent ammeter remained degree verification device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201689440U (en) * 2010-04-29 2010-12-29 光一科技股份有限公司 Handheld bar-code meter reading machine
CN103354026A (en) * 2013-06-25 2013-10-16 国家电网公司 Meter reading instrument and method for replacing electric energy meter by virtue of meter reading instrument
CN203587795U (en) * 2013-11-18 2014-05-07 国家电网公司 Intelligent ammeter remained degree verification device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
国网浙江省电力公司: "浙江绍兴电力局自主开发电能表智能调换掌机成功应用", 《HTTPS://WEB.ARCHIVE.ORG/WEB/20131105044659/HTTP://WWW.SGCC.COM.CN/XWZX/GSYW/YXFC/05/292300.SHTML》 *
姚青: "基于DLMS/COSEM的远程抄表系统研制", 《中国优秀硕士学位论文全文数据库 信息科技辑》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106815543A (en) * 2016-12-16 2017-06-09 国网北京市电力公司 Data processing method and device
CN109242145A (en) * 2018-08-01 2019-01-18 深圳供电局有限公司 A kind of electric energy meter batch rotation field operation method, apparatus and system
CN110058067A (en) * 2019-04-24 2019-07-26 国网宁夏电力有限公司电力科学研究院 Information maintenance method and device when a kind of replacement electric energy meter

Also Published As

Publication number Publication date
CN104008194B (en) 2017-11-21

Similar Documents

Publication Publication Date Title
CN101767452B (en) Electro-fusion welding machine realizing welding quality monitoring through wireless network and implementation method
CN103516507B (en) Electricity utilization information collecting system time synchronization method based on DLPTP clock synchronization
CN107390636A (en) A kind of numerical control device operational monitoring method and maintaining method and system
CN203055137U (en) On-site handheld comprehensive service terminal of intelligent electric meter
CN102496209A (en) Intelligent object network heat meter and management system thereof
CN102592364A (en) Encryption and decryption functions based field service terminal and application method thereof
CN102496259A (en) Internet of things based water meter and management system thereof
CN102496258A (en) Internet of things based intelligent electric energy meter and management system thereof
CN105448067A (en) Electric power collection and management system
Surajudeen-Bakinde et al. Development of an Internet based prepaid energy meter
CN104008194A (en) PDA-based electric energy meter rotation data processing system
CN103746337B (en) A kind of relay protection device constant value intelligence amendment and check system
CN104881729A (en) Electric power marketing system power failure information processing method, and electric power marketing system power failure information processing system
CN105427027A (en) Electricity charge automatic settlement system for power plant
CN109541338A (en) A kind of definite value comparison device obtaining definite value parameter by relay protection device printing port
CN202350878U (en) Automatic checking device for flow meter
CN104978635A (en) Production management information physical system and implementation method thereof
CN103020756B (en) Instrument management informatization platform system and control method
CN202534055U (en) Prepayment electric energy meter site detector
CN113570075A (en) Remote monitoring software system for water meter
CN205195432U (en) Energy station electric power direct -furnish management and control system for industrial park
CN202331644U (en) Intelligent water meter of Internet of things
CN104503415A (en) System for remotely checking and resetting running parameters of reactive compensation device
CN106849346A (en) A kind of system for testing power distribution automation equipment time adjustment function and timekeeping performance
CN203465753U (en) Management system of warehouse-returned electricity meter

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant