CN104005415A - Efficient grooving construction method for underground diaphragm wall in micro-weathered granite - Google Patents

Efficient grooving construction method for underground diaphragm wall in micro-weathered granite Download PDF

Info

Publication number
CN104005415A
CN104005415A CN201410055023.2A CN201410055023A CN104005415A CN 104005415 A CN104005415 A CN 104005415A CN 201410055023 A CN201410055023 A CN 201410055023A CN 104005415 A CN104005415 A CN 104005415A
Authority
CN
China
Prior art keywords
rock
blasting
hole
drilling
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410055023.2A
Other languages
Chinese (zh)
Other versions
CN104005415B (en
Inventor
罗杰
高宪民
沈水龙
崔庆龙
巩宪忠
余大成
齐书峰
陈冲
房居旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 16th Bureau Group Co Ltd
Beijing Rail Transit Engineering Construction Co Ltd of China Railway 16th Bureau Group Co Ltd
Shanghai Jiao Tong University
Original Assignee
China Railway 16th Bureau Group Co Ltd
Beijing Rail Transit Engineering Construction Co Ltd of China Railway 16th Bureau Group Co Ltd
Shanghai Jiao Tong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 16th Bureau Group Co Ltd, Beijing Rail Transit Engineering Construction Co Ltd of China Railway 16th Bureau Group Co Ltd, Shanghai Jiao Tong University filed Critical China Railway 16th Bureau Group Co Ltd
Priority to CN201410055023.2A priority Critical patent/CN104005415B/en
Publication of CN104005415A publication Critical patent/CN104005415A/en
Application granted granted Critical
Publication of CN104005415B publication Critical patent/CN104005415B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

本发明提供了一种微风化花岗岩中地下连续墙的高效成槽施工方法,所述方法具体步骤包括:第一步、施工现场地质勘测;第二步、确定破岩方法;第三步、确定爆破参数;第四步、砂土层中成孔至岩层表面并出土;第五步、辨别岩样,确定钻进至中风化花岗岩;第六步、下PVC管,用于保护爆破导线;第七步、岩层中成孔至设计埋深下1m;第八步、装药爆破。本发明克服了现有施工方法在上覆砂土微风化花岗岩中施工困难或施工进度缓慢、成槽质量差等缺点和不足,实现微风化花岗岩中的高效、高精度、深嵌岩的成槽施工;本发明效果好,成槽速度快。

The invention provides a high-efficiency trough-forming construction method for an underground diaphragm wall in slightly weathered granite. The specific steps of the method include: the first step, geological survey at the construction site; the second step, determining the rock breaking method; the third step, determining Blasting parameters; the fourth step, forming a hole in the sand layer to the surface of the rock layer and unearthing; the fifth step, identifying the rock sample, and confirming that the drilled to the weathered granite; the sixth step, lowering the PVC pipe to protect the blasting wire; The seventh step is to form a hole in the rock formation to the design depth of 1m; the eighth step is to charge and blast. The invention overcomes the disadvantages and deficiencies of existing construction methods such as difficulty in construction or slow construction progress and poor trough-forming quality in overlying sandy soil micro-weathered granite, and realizes high-efficiency, high-precision, deep rock-socketed trough formation in slightly weathered granite Construction: the invention has good effect and fast groove forming speed.

Description

微风化花岗岩中地下连续墙的高效成槽施工方法High-efficiency groove-forming construction method for underground diaphragm wall in slightly weathered granite

技术领域technical field

本发明涉及一种建筑、水利、交通、环境等地下工程领域中的施工技术,具体地,涉及一种微风化花岗岩中地下连续墙的高效成槽施工方法。The invention relates to a construction technology in the fields of construction, water conservancy, transportation, environment and other underground engineering, in particular to an efficient groove-forming construction method for an underground continuous wall in slightly weathered granite.

背景技术Background technique

全国各大城市正在大规模地建设城市地下铁道以及各种地下空间。这些地下空间构筑物需要通过基坑开挖来建造,基坑开挖时需要用地下连续墙作为挡土与挡水的临时结构。由于各城市所处的地质条件和周围环境的不同,需要在各种地质条件下修筑地下连续墙。地下连续墙施工工艺已在我国天然沉积砂性土、粘性土等软土地层中得到了广泛应用。但在我国华南地区,一般在厚度不太大的砂性土层下面存在石灰岩、花岗岩等微风化岩层。在这种上覆砂土层的微风化花岗岩的上软下硬地层中建造地下连续墙,仍存在多方面的的技术困难。传统的适应于软土地层的成槽机具难于在上软下硬的复杂岩土层中抓挖微风化岩土,产生施工成槽困难或速度极为缓慢,施工效率低、工期长造价高的不利局面。Major cities across the country are building urban underground railways and various underground spaces on a large scale. These underground space structures need to be constructed by excavating foundation pits, and underground diaphragm walls are required as temporary structures for retaining soil and water during excavation of foundation pits. Due to the different geological conditions and surrounding environments of each city, it is necessary to build underground diaphragm walls under various geological conditions. The construction technology of underground diaphragm wall has been widely used in my country's natural sedimentary sandy soil, cohesive soil and other soft soil strata. However, in South my country, there are generally slightly weathered rock layers such as limestone and granite under the sandy soil layer that is not too thick. There are still various technical difficulties in building an underground diaphragm wall in the upper soft and lower hard stratum of slightly weathered granite overlying the sandy soil layer. Traditional trough-forming machines and tools adapted to soft soil strata are difficult to grasp and excavate slightly weathered rock and soil in complex rock-soil layers that are soft at the top and hard at the bottom, resulting in the disadvantages of difficult or extremely slow construction of troughs, low construction efficiency, long construction period and high cost. situation.

对现有的文献进行检索后发现两项相关专利的申请,实用新型专利“[申请号为201320455844.6],发明名称:一种地下连续墙成槽施工的有效冲岩装置”,与发明专利“[申请号为201310322485.1],发明名称:上覆砂土微风化石灰岩中地下连续墙的有效成槽施工方法”。这些文献虽然提出了下伏微风化石灰岩的岩面起伏变化、传统施工机械成槽垂直度无法保证等技术难题的解决方法,但是该文献提出的用重锤冲击破碎石灰岩的施工方法,对无侧限抗压强度为30MPa以下的石灰岩是有效的,而对于无侧限抗压强度为100MPa以上的微风化花岗岩,上述文献中提出的重锤冲击法难以产生高效的岩体破碎效应。特别是对于嵌岩深度在3~8m的地下连续墙,难以确保施工质量和施工工期。After searching the existing literature, two related patent applications were found, the utility model patent "[application number is 201320455844.6], the name of the invention: an effective rock flushing device for underground diaphragm wall trough construction", and the invention patent "[ The application number is 201310322485.1], and the name of the invention is: an effective groove-forming construction method for underground diaphragm walls in slightly weathered limestone overlying sandy soil". Although these documents proposed solutions to technical problems such as the undulation of the underlying micro-weathered limestone rock surface and the inability to guarantee the verticality of grooves formed by traditional construction machinery, the construction method proposed in this document using a heavy hammer to impact and break limestone is not suitable for non-side Limestone with an unconfined compressive strength of less than 30 MPa is effective, while for slightly weathered granite with an unconfined compressive strength of more than 100 MPa, it is difficult for the hammer impact method proposed in the above literature to produce an efficient rock mass crushing effect. Especially for underground diaphragm walls with a rock-socketed depth of 3-8m, it is difficult to ensure the construction quality and construction period.

发明内容Contents of the invention

针对现有技术中的缺陷,本发明的目的是提供一种微风化花岗岩中地下连续墙的高效成槽施工方法,该方法克服了现有技术中存在的施工质量差、施工工期长、甚至不能成槽等缺点和不足,实现微风化花岗岩中的高效成槽施工。Aiming at the defects in the prior art, the object of the present invention is to provide a highly efficient trench-forming construction method for underground diaphragm walls in slightly weathered granite, which overcomes the problems of poor construction quality, long construction period and even inability to Shortcomings and deficiencies such as trough forming can be realized, and efficient trough forming construction in slightly weathered granite can be realized.

为实现以上目的,本发明提供一种微风化花岗岩中地下连续墙的高效成槽施工方法,所述施工方法通过下列步骤实现:In order to achieve the above object, the present invention provides a kind of high-efficiency trough-forming construction method of underground diaphragm wall in slightly weathered granite, and the construction method is realized through the following steps:

第一步、施工现场地质勘测,具体的:The first step is the geological survey of the construction site, specifically:

通过钻孔取芯确定地下连续墙嵌岩深度范围内的微风化花岗岩的岩面性状、标准无侧限抗压强度的分布值;在此基础上根据地下连续墙的设计埋深确定地下连续墙的嵌岩深度;Determine the rock surface properties and standard unconfined compressive strength distribution values of the micro-weathered granite within the rock-socketed depth range of the underground diaphragm wall through drilling and coring; on this basis, determine the underground diaphragm wall according to the designed buried depth of the diaphragm wall rock-socketed depth;

第二步、确定破岩方法,具体的:The second step is to determine the rock breaking method, specifically:

由于传统成槽机难于在上软下硬的复杂岩土层中抓挖微风化岩土,而重锤冲击仅对无侧限抗压强度为30MPa以下的石灰岩有效,所以对于无侧限抗压强度为100MPa以上的微风化花岗岩,确定采用爆破的方式破岩;由于城市中地下连续墙施工要求对周围环境影响小,为了减弱在微风化花岗岩中爆破破岩对周围岩体的破坏,从而形成接近地下连续墙设计尺寸的平整轮廓面,所以确定采用微差预裂控制爆破方式;Because the traditional groove forming machine is difficult to excavate slightly weathered rock and soil in the complex rock and soil layer with soft top and hard bottom, and the impact of heavy hammer is only effective for limestone with unconfined compressive strength below 30MPa, so for unconfined compressive For micro-weathered granite with a strength above 100MPa, it is determined to use blasting to break the rock; since the construction of the underground diaphragm wall in the city requires little impact on the surrounding environment, in order to reduce the damage to the surrounding rock mass by blasting in the slightly weathered granite, a The flat profile surface is close to the design dimension of the underground diaphragm wall, so it is determined to adopt the micro-differential pre-splitting control blasting method;

第三步、确定爆破参数,具体的:The third step is to determine the blasting parameters, specifically:

1)根据地下连续墙的设计槽幅宽度、设计埋深、一次爆破施工的槽幅长度和微差预裂控制爆破的设计原理,先预估炮孔参数,再通过第三步5)确定炮孔参数;1) According to the designed groove width of the underground diaphragm wall, the designed buried depth, the groove length of the primary blasting construction and the design principle of differential pre-splitting controlled blasting, first estimate the parameters of the blast hole, and then determine the blast hole through the third step 5). Hole parameters;

2)由于所要爆破的岩石为微风化花岗岩,微风化花岗岩的无侧限抗压强度分布值为100~180MPa,确定选用2#岩石乳化炸药,炸药具有防水性能;2) Since the rock to be blasted is slightly weathered granite, and the unconfined compressive strength distribution value of the slightly weathered granite is 100-180MPa, it is determined to choose 2# rock emulsion explosive, which has waterproof performance;

3)根据第二步中所述的微差预裂控制爆破原理,起爆器选用微差毫秒电雷管;3) According to the micro-differential pre-splitting control blasting principle described in the second step, the detonator selects micro-secondary millisecond electric detonator;

4)根据岩石的无侧限抗压强度分布值并结合第三步5)确定炸药的线装药密度;线装药密度取值范围为1.0~1.5kg/m;可按如下公式计算线装药量密度:4) According to the unconfined compressive strength distribution value of the rock and combined with the third step 5), determine the line charge density of the explosive; the line charge density ranges from 1.0 to 1.5kg/m; the line charge density can be calculated according to the following formula Dose density:

Q=AaBσC Q=Aa B σ C

式中:Q为线装药密度;In the formula: Q is the linear charge density;

a为钻孔间距;a is the drilling distance;

σ为岩石无侧限抗压强度;σ is the unconfined compressive strength of rock;

A、B、C为待定系数,通过第三步5)现场试爆后再回归分析的方法确定;A, B, and C are undetermined coefficients, which are determined by regression analysis after the third step 5) field test;

5)爆破施工时需进行槽段试爆,在地下连续墙施工的场地内选取试验槽段,按经验选取第三步1)到4)中的爆破参数进行爆破施工,然后对试爆槽段钻孔取芯抽样,并根据抽样破碎情况调整爆破参数;重复上述槽段试爆步骤,直至岩石碎块可以被成槽机抓取,确定地下连续墙施工的钻孔直径、钻孔间距、不耦合系数、孔深、堵塞长度、线装药密度(通过回归分析确定A、B、C)和钻孔间距;5) During the blasting construction, it is necessary to carry out the test blasting of the groove section. Select the test groove section in the construction site of the underground diaphragm wall, and select the blasting parameters in the third step 1) to 4) according to experience for blasting construction, and then blast the test groove section Drill and take core samples, and adjust the blasting parameters according to the sample fragmentation; repeat the above-mentioned test blasting steps of the groove section until the rock fragments can be captured by the groove forming machine, and determine the diameter of the drill holes, the distance between the drill holes, and the Coupling coefficient, hole depth, plugging length, linear charge density (A, B, C determined by regression analysis) and drilling spacing;

第四步、砂土层中成孔至岩层表面并出土,具体的:The fourth step is to form holes in the sand layer to the surface of the rock layer and unearth, specifically:

1)平整场地,清除地面障碍物;1) Level the site and remove ground obstacles;

2)根据现场平面和高程控制点、地下连续墙设计图、爆破参数和现场情况,确定钻孔位置;2) Determine the drilling location according to the site plane and elevation control points, the design drawing of the underground diaphragm wall, the blasting parameters and the site conditions;

3)安装有砂土层钻头的潜孔钻机在已确定的钻孔位置钻进,同时进行钢套筒护壁,边接钻杆边接钢套筒,直至钻进至中风化花岗岩岩面;3) The down-the-hole drilling rig equipped with a sand layer drill bit drills at the determined drilling position, and at the same time protects the wall with a steel sleeve, and connects the steel sleeve while connecting the drill pipe until it reaches the moderately weathered granite rock face;

4)螺旋取土机取出钻孔内土体;4) The auger earth taker takes out the soil in the borehole;

第五步、辨别岩样,确定钻进至中风化花岗岩,具体的:The fifth step is to identify the rock sample and determine that the drilled to medium weathered granite, specifically:

1)将砂土层钻头换成取芯钻头,下伸至钻孔底部并向下钻进0.5m,取出中风化岩样0.5m且经现场确认为中风化花岗岩后,继续向下取芯0.5m,岩样无变化后,停止取芯钻孔;1) Replace the drill bit in the sand layer with a coring bit, extend down to the bottom of the borehole and drill down 0.5m, take out a moderately weathered rock sample of 0.5m and confirm that it is moderately weathered granite on site, and continue to drill down for 0.5m m, stop the core drilling after there is no change in the rock sample;

2)取出取芯钻头;2) Take out the core bit;

第六步、下PVC管,用于保护爆破导线,具体的:The sixth step is to lower the PVC pipe to protect the blasting wire, specifically:

1)向钢套管内插入PVC管,边插入边接长;待PVC管底部下至钻孔底部时,向PVC管内注水;1) Insert the PVC pipe into the steel casing, and extend it while inserting; when the bottom of the PVC pipe reaches the bottom of the drill hole, inject water into the PVC pipe;

2)PVC管接长至地面后,用钢锯将过长部分锯掉,控制PVC管比地面高100mm左右;2) After the PVC pipe is extended to the ground, use a hacksaw to cut off the overlong part, and control the PVC pipe to be about 100mm higher than the ground;

3)向PVC管底部插入注浆管,水下注水泥浆,用于固定PVC管,防止砂土层中的水土流入PVC管和第七步中的岩层钻孔;3) Insert the grouting pipe to the bottom of the PVC pipe, and inject grout underwater to fix the PVC pipe to prevent water and soil in the sand layer from flowing into the PVC pipe and the rock formation drilling in the seventh step;

4)待水泥浆硬化后,用水泵将PVC管内水全部抽出,同时用千斤顶将钢套管拔出;4) After the cement slurry is hardened, use a water pump to pump out all the water in the PVC pipe, and at the same time use a jack to pull out the steel casing;

第七步、岩层中成孔至设计埋深下1m,具体的:The seventh step is to form holes in the rock formation to 1m below the designed buried depth, specifically:

1)将潜孔钻机的取芯钻头换成岩层钻头,再次下伸钻头至PVC管底水泥浆表面处,钻进至设计槽壁下1m,边钻边施加高压风将石渣粉末吹出;1) Replace the core drill bit of the down-the-hole drilling rig with a rock formation drill bit, extend the drill bit down again to the surface of the cement slurry at the bottom of the PVC pipe, drill to 1m below the designed groove wall, and apply high-pressure wind while drilling to blow out the gravel powder;

2)潜孔钻机拔出钻头,更换钨钢合金钻头为土层钻头,在下一钻孔处钻进,按上述步骤循环作业,直到全部钻孔钻进完毕,撤出潜孔钻机;2) Pull out the drill bit from the down-the-hole drilling rig, replace the tungsten-steel alloy drill bit with the soil layer drill bit, and drill in the next hole. Follow the above-mentioned steps to cycle until all the holes are drilled, and then withdraw the down-the-hole drilling rig;

第八步、装药爆破,具体的:The eighth step, charge blasting, specifically:

1)根据设计装药量和钻孔深度,将乳化炸药药包和引线绑在竹竿上并将其下伸至钻孔孔底,完成单孔装药,待全部钻孔装药完毕后,检查每个孔的装药和引线;1) According to the designed charge amount and the drilling depth, tie the emulsion explosive charge and the lead wire to the bamboo pole and extend it down to the bottom of the drill hole to complete the single hole charge. After all the drill holes are charged, check charges and leads for each hole;

2)待全部钻孔装药完毕,检查无误后,用起爆器将所有引线连接,准备起爆;2) After all the drilling and charging are completed and the inspection is correct, use the detonator to connect all the lead wires and prepare for detonation;

3)做好爆破前准备工作,启动爆破;3) Prepare well before blasting and start blasting;

4)待该槽幅爆破施工完毕后,进行下一槽幅的钻孔爆破;4) After the blasting construction of the slot width is completed, the drilling and blasting of the next slot width is carried out;

第九步、导墙施工,成槽施工完成。The ninth step is the construction of the guide wall, and the construction of the groove is completed.

优选地,第一步1)中:Preferably, in the first step 1):

所述标准无侧限抗压强度的分布值是遵循土工试验规程,在无侧限条件下,施加轴向压力直至试样破坏所确定的土体抗压强度分布值;The distribution value of the standard unconfined compressive strength is the distribution value of the soil compressive strength determined by applying axial pressure until the sample is destroyed under the unconfined condition in accordance with the geotechnical test regulations;

所述钻孔取芯确定微风化花岗岩的岩面性状通过如下步骤获得:The rock face properties of the micro-weathered granite are obtained by taking cores from the boreholes as follows:

①根据待成槽区域大小布设地质勘测孔的位置与数量,分别钻探至成槽施工所需的深度取出岩芯,并根据成槽区域大小和范围确定钻孔的数量和间距,测试孔位沿地下连续墙中轴线的两侧交错布置;① Arrange the position and number of geological survey holes according to the size of the trough-forming area, respectively drill to the depth required for trough-forming construction to take out cores, and determine the number and spacing of drilled holes according to the size and scope of the trough-forming area. The two sides of the central axis of the underground diaphragm wall are staggered;

②通过钻孔取芯确定成槽施工区域的岩面深度与待挖厚度,确定岩石结构面与钻孔弯曲方向或地球磁北方向之间关系,所述岩石结构面是具有一定形态而且普遍存在的地质构造迹象的岩石平面或曲面,按力学性质不同分为挤压面、张裂面、扭裂面、压扭面、张扭面五种结构面性状;② Determine the rock surface depth and the thickness to be excavated in the trenching construction area by drilling and coring, and determine the relationship between the rock structural plane and the bending direction of the drilling hole or the earth's magnetic north direction. The rock structural plane has a certain shape and is ubiquitous According to different mechanical properties, the rock plane or curved surface with geological structure signs can be divided into five structural surface properties: extrusion surface, tension crack surface, torsion crack surface, compression torsion surface, and tension torsion surface;

③利用地球重力场,以铅垂线为基准,采用液面水平、悬锤的方法测定测点处倾斜方向的垂直平面上偏离铅垂线的角度,即顶角;③ Utilize the earth's gravity field, take the plumb line as the benchmark, and use the method of liquid level and pendent to measure the angle of the vertical plane in the inclined direction of the measuring point, that is, the top angle;

④利用地球磁场,以地球磁子午线为定向基准,用磁罗盘测量水平面上的钻孔轴线上某点切线方向与地球磁北方向的夹角,即方位角;④ Utilize the earth's magnetic field, take the earth's magnetic meridian as the orientation reference, and use a magnetic compass to measure the angle between the tangent direction of a point on the borehole axis on the horizontal plane and the earth's magnetic north direction, that is, the azimuth;

⑤利用扫描电子显微镜进行矿物微区测试,对取出岩芯进行微量元素和同位素测试,分析岩体的矿物组成,从而得到岩层的类别、温度、应力状态和结构面产状;⑤ Use the scanning electron microscope to conduct mineral micro-area testing, conduct trace element and isotope testing on the cores taken out, and analyze the mineral composition of the rock mass, so as to obtain the type, temperature, stress state and structural plane occurrence of the rock formation;

⑥根据顶角、方位角、矿物微区测试测试结果、受应力作用岩石的组构类型或干涉色对比和产生的应力矿物特征,推测出结构面的应力性质,确定岩石的岩面性状。⑥ According to the top angle, azimuth angle, mineral micro-region test results, the fabric type or interference color contrast of the rock subjected to stress, and the stress mineral characteristics generated, the stress nature of the structural plane is inferred, and the rock surface properties of the rock are determined.

优选地,第一步2)中,所述无量纲水的渗透系数指标由下式计算得到:Preferably, in the first step 2), the permeability index of the dimensionless water is calculated by the following formula:

KK DD. == 11 BB qq QQ tt

式中:Bq=为无量纲的空隙水压力系数,Qt=为无量纲的锥尖阻力,由下两式计算:In the formula: B q = dimensionless pore water pressure coefficient, Q t = dimensionless cone tip resistance, calculated by the following two formulas:

BB qq == uu aa -- uu sthe s qq tt -- σσ vv 00

QQ tt == qq tt -- σσ vv 00 σσ vv 00 ′′

式中:ua=绝对孔隙压力,where: u a = absolute pore pressure,

us=初始静孔隙水压,u s = initial static pore water pressure,

qt=修正的锥尖阻力,q t = modified cone tip resistance,

σv0=初始总的竖向应力。σ v0 = initial total vertical stress.

优选地,第二步中,所述微差预裂控制爆破方式是除开挖区内按设计正常钻孔装药外,还沿设计开挖线周边钻一排孔并装药;起爆时,周边孔先爆,开挖区后爆;先爆的周边钻孔产生一条1-4cm的裂缝;后爆的开挖区爆破时,其冲击波的能量被周边缝所削弱,可以减少对周边缝外的区域的爆炸冲击,这样可使设计线上的开凿边界平整。Preferably, in the second step, the micro-differential pre-splitting control blasting method is to drill a row of holes and charge along the periphery of the designed excavation line in addition to the normal drilling and charge of the design in the excavation area; The hole is blasted first, and the excavation area is blasted later; the peripheral drilling of the blasting first produces a 1-4cm crack; when the excavation area of the blasting is blasted later, the energy of the shock wave is weakened by the peripheral seams, which can reduce the impact on the surrounding seams. Blast impact in the zone, which smooths the excavation boundary on the design line.

优选地,第三步1)中,所述炮孔参数包括钻孔直径、钻孔间距、不耦合系数、孔深和堵塞长度,其中:Preferably, in the third step 1), the blasthole parameters include borehole diameter, borehole spacing, uncoupling coefficient, hole depth and plugging length, wherein:

所述钻孔直径是根据设计槽幅宽度和一次爆破施工的槽幅长度确定,当设计槽幅宽度为600~1000mm、一次爆破施工的槽幅长度为12m时,钻孔直径的范围为50~150mm;质量要求高的工程,采用小的钻孔;The borehole diameter is determined according to the designed slot width and the slot length of the primary blasting construction. When the designed slot width is 600-1000mm and the slot length of the primary blasting construction is 12m, the range of the drilling diameter is 50-100mm. 150mm; For projects with high quality requirements, use small drilling holes;

所述钻孔间距取钻孔直径的5~7倍,钻孔直径大于100mm时取小值,小于100mm时取大值,软弱破碎的岩石取小值,坚硬的岩石取大值,质量要求高的取小值,要求不高的取大值;The borehole spacing is 5 to 7 times the borehole diameter. When the borehole diameter is greater than 100mm, take a small value, and when it is less than 100mm, take a large value. For weak and broken rocks, take a small value, and for hard rocks, take a large value. High quality requirements Take a small value for those with low requirements, and take a large value for those with low requirements;

所述不耦合系数为炮孔内径与药包直径的比值,对于设计槽幅宽度为600~1000mm地下连续墙不耦合系数取1.5~2.5,不耦合系数值大时,表示药包与孔壁之间的间隙大,爆破后对孔壁的破坏小,反之对孔壁的破坏大;The non-coupling coefficient is the ratio of the inner diameter of the blast hole to the diameter of the cartridge. For the designed groove width of 600-1000 mm, the non-coupling coefficient of the underground diaphragm wall is 1.5-2.5. The gap between them is large, and the damage to the hole wall after blasting is small, otherwise the damage to the hole wall is large;

所述孔深是根据地下连续墙的设计埋深确定,孔深取地面至地下连续墙的设计埋深以下0.5m~1.5m;The hole depth is determined according to the design buried depth of the underground diaphragm wall, and the hole depth is taken from the ground to 0.5m to 1.5m below the designed buried depth of the underground diaphragm wall;

所述堵塞长度取炮孔直径的12~20倍。The plugging length is 12 to 20 times the diameter of the blast hole.

优选地,第三步3)中,所述微差毫秒电雷管是段间隔为十几毫秒至数百毫秒的延期电雷管。Preferably, in the third step 3), the differential millisecond electric detonator is a delay electric detonator with a segment interval of more than ten milliseconds to hundreds of milliseconds.

优选地,所述第四步3)中:Preferably, in the fourth step 3):

所述砂土层钻头为金刚石偏心钻头,钻头直径大于岩层爆破钻孔直径5~10mm,用于砂土层中钻孔;The sand layer drill bit is a diamond eccentric drill bit, the diameter of the drill bit is 5-10 mm larger than the diameter of the blasting hole in the rock layer, and is used for drilling in the sand layer;

所述潜孔钻机为用钻杆带动风动冲击器和钻头旋转破岩的钻孔设备;在凿岩过程中使冲击器潜入孔内,以减小由于钎杆传递冲击功所造成的能量损失,从而减小孔深对凿岩效率的影响;对于无侧限抗压强度分布值为100~180MPa的微风化花岗岩,能获得较高的凿岩速度;The down-the-hole drilling rig is a drilling equipment that uses a drill rod to drive a pneumatic impactor and a drill bit to rotate and break rock; during the rock drilling process, the impactor is submerged into the hole to reduce the energy loss caused by the impact energy transmitted by the drill rod , so as to reduce the influence of hole depth on rock drilling efficiency; for slightly weathered granite with unconfined compressive strength distribution value of 100-180MPa, higher rock drilling speed can be obtained;

所述的钻杆为一种圆形冲击钻杆;上端有锥形外螺纹、下端有锥形内螺纹用以连接钻头;钻杆的两端开有扳手切口和打捞时用的环形槽以方便拧卸;The drill rod is a circular percussion drill rod; the upper end has a tapered external thread and the lower end has a tapered internal thread for connecting the drill bit; both ends of the drill rod are provided with a wrench cut and an annular groove for fishing. Unscrew;

所述钢套筒为直径比金刚石偏心钻头小5~10mm的薄壁钢筒,用以防止钻孔在砂土中塌孔;上端有锥形外螺纹、下端有锥形内螺纹用以连接;钢套筒的两端开有扳手切口和环形槽用以取出。The steel sleeve is a thin-walled steel cylinder with a diameter 5-10 mm smaller than that of the diamond eccentric drill bit, to prevent the drill hole from collapsing in the sand; the upper end has a tapered external thread, and the lower end has a tapered internal thread for connection; the steel sleeve Both ends of the barrel have wrench cutouts and annular grooves for removal.

优选地,所述第四步4)中,所述螺旋取土机是安装有长螺旋状钻头的取土设备;将长螺旋状钻头插入钻孔,通过旋转叶片将孔内土体取出;长螺旋状钻头的外径小于钢套筒的内径。Preferably, in the fourth step 4), the auger soil removal machine is a soil removal device equipped with a long helical drill bit; the long helical drill bit is inserted into the borehole, and the soil in the hole is taken out by rotating blades; The outer diameter of the helical bit is smaller than the inner diameter of the steel sleeve.

优选地,第五步1)中,所述取芯钻头为中空金刚石取芯钻头,钻头直径和砂土层中钻头相同。Preferably, in the fifth step 1), the core bit is a hollow diamond core bit, and the diameter of the bit is the same as that of the bit in the sand layer.

优选地,第六步1)中,Preferably, in the sixth step 1),

所述PVC管的直径比钢套管小,两根PVC管通过内径与其外径相等的接头PVC管搭接接长,并用胶水粘贴牢固;The diameter of the PVC pipe is smaller than that of the steel sleeve, and the two PVC pipes are overlapped by a joint PVC pipe whose inner diameter is equal to its outer diameter, and are bonded firmly with glue;

注水量可按下述公式粗略估计:The amount of water injection can be roughly estimated according to the following formula:

GG == πkdhtπkdht ++ πdπd 22 hh 44

式中:G=注水量,In the formula: G = water injection volume,

k=第一步2)得到的砂土层渗透系数平均值,k = the average value of the permeability coefficient of the sand layer obtained in the first step 2),

d=第四步所述钢套筒的直径,d=the diameter of the steel sleeve mentioned in the fourth step,

h=注水液面到中风化花岗岩岩面的高差,h=height difference from water injection level to medium weathered granite rock surface,

t=注水开始到第六步3)注水泥浆结束的总时间。t = the total time from the start of water injection to the end of step 3) grout injection.

优选地,第六步3)中,所述水泥浆水灰质量配比为0.8:1,水泥浆拌制采用32.5级普通硅酸盐水泥,注浆压力控制在0.1-0.4MPa,注浆速度为3-7L/min;注浆量为使PVC管底部封口防止钢套管拔出时发生塌孔的用量,可根据钢套管直径和PVC管直径粗略估计,并根据钻孔时岩石破裂情况调整实际注浆量。Preferably, in the sixth step 3), the water-cement mass ratio of the cement slurry is 0.8:1, the cement slurry is mixed with 32.5 grade ordinary Portland cement, the grouting pressure is controlled at 0.1-0.4MPa, and the grouting speed It is 3-7L/min; the amount of grouting is the amount used to seal the bottom of the PVC pipe to prevent the hole from collapsing when the steel casing is pulled out. It can be roughly estimated according to the diameter of the steel casing and the diameter of the PVC pipe, and according to the rock fracture during drilling. Adjust the actual grouting volume.

优选地,第六步4)中,所述水泵为利用动力机传给并排出水体的机械。Preferably, in the sixth step 4), the water pump is a machine that uses a power machine to transmit and discharge water.

优选地,所述第七步1)中,所述岩层钻头为钨钢合金钻头,钻头直径等于药包直径和不耦合系数的乘积,用于岩层钻孔;所述高压风通过风压机提供。Preferably, in the seventh step 1), the rock formation drill bit is a tungsten steel alloy drill bit, and the diameter of the drill bit is equal to the product of the cartridge diameter and the uncoupling coefficient, which is used for drilling in the rock formation; the high-pressure air is provided by a wind compressor .

优选地,第八步3)中,所述爆破前准备工作即为对爆区顶面覆盖钢板加冲孔锤,以防止个别飞石泥浆造成周围保护物的损害;爆破时实施严格的安全警戒;爆破时人员全部撤至安全地点后方可起爆,爆破警戒距离不小于100m。Preferably, in the eighth step 3), the preparatory work before the blasting is to add a punching hammer to the steel plate covering the top surface of the blasting area to prevent damage to the surrounding protection caused by individual flying stone mud; strict safety precautions are implemented during blasting ; During the blasting, all personnel are evacuated to a safe place before detonating, and the blasting warning distance is not less than 100m.

优选地,第九步1)中,所述导墙施工具体包括:开挖导墙沟槽,钢筋笼绑扎并下放,然后树立模板,待钢筋笼与模板验收合格后浇捣混凝土;所述导墙施工分段进行,分段长度根据模板长度和规范确定控制在30~50m的范围内。Preferably, in the ninth step 1), the construction of the guide wall specifically includes: excavating a groove for the guide wall, binding and lowering the reinforcement cage, then setting up a formwork, and pouring concrete after the reinforcement cage and the formwork are accepted; The wall construction is carried out in sections, and the section length is determined and controlled within the range of 30-50m according to the formwork length and specifications.

优选地,第九步2)中,所述泥浆为化学泥浆,配浆材料为水、膨润土和碳酸钠,取不同质量配比的水、膨润土、碳酸钠做渗透试验,测得渗透系数为第一步2)测得砂土层渗透系数的百分之一时的配比即为施工配比;作业时,保持泥浆液面高度低于地面标高0.5m,以形成足够的泥浆柱压力平衡地下连续墙范围内的侧向土压力,即泥浆柱压力(σn)大于等于侧向土压力(σt),并随时向孔内补充泥浆。Preferably, in the ninth step 2), the mud is chemical mud, and the slurry preparation material is water, bentonite and sodium carbonate, and water, bentonite and sodium carbonate of different mass ratios are used for penetration tests, and the permeability coefficient is recorded as Step 2) The ratio when the permeability coefficient of the sand layer is measured to be 1% is the construction ratio; during operation, the height of the mud liquid level is kept below the ground level by 0.5m to form a sufficient mud column pressure to balance the underground The lateral earth pressure within the diaphragm wall, that is, the mud column pressure (σ n ) is greater than or equal to the lateral earth pressure (σ t ), and mud is added to the hole at any time.

更优选的,所述渗透试验即《土工试验规程》(SL237-1999)渗透试验SL237-014-1999所述试验方法。More preferably, the penetration test is the test method described in the "Geotechnical Test Regulations" (SL237-1999) penetration test SL237-014-1999.

更优选的,所述侧向土压力是指地下连续墙设计埋深范围内的土体对泥浆柱产生的侧向土压,可按下列公式估算:More preferably, the lateral earth pressure refers to the lateral earth pressure generated by the soil within the design depth of the underground diaphragm wall on the mud column, which can be estimated according to the following formula:

σh=K0σv0 σ h =K 0 σ v0

式中σh=侧向土压力,σv0=初始总的竖向应力,K0=侧向土压力系数,由下式计算:where σ h = lateral earth pressure, σ v0 = initial total vertical stress, K 0 = coefficient of lateral earth pressure, calculated by the following formula:

K0=1-sinθK 0 =1-sinθ

式中θ=砂土层的内摩擦角,通过《土工试验规程》(SL237-1999)三轴压缩试验SL237-017-1999确定。In the formula, θ = internal friction angle of the sandy soil layer, which is determined by the triaxial compression test SL237-017-1999 in the "Geotechnical Test Regulations" (SL237-1999).

更优选的,所述泥浆柱压力可按下列公式计算:More preferably, the mud column pressure can be calculated according to the following formula:

σnnhn σ nn h n

式中:σn=泥浆柱压力,where: σ n = mud column pressure,

γn=泥浆重度,γ n = mud weight,

hn=泥浆柱的埋深,设计埋深下0.5m。h n = buried depth of the mud column, 0.5m below the designed buried depth.

优选地,第九步3)中,所述重锤的锤身为十字圆台体,锤底设置合金齿,合金齿按十字雪花状分布;重锤的详细构造可参见实用新型专利“[申请号为201320455844.6],发明名称:一种地下连续墙成槽施工的有效冲岩装置”。Preferably, in the ninth step 3), the hammer body of the heavy hammer is a cross circular truncated body, the bottom of the hammer is provided with alloy teeth, and the alloy teeth are distributed in a cross snowflake shape; the detailed structure of the heavy hammer can be found in the utility model patent "[Application No. 201320455844.6], title of invention: an effective rock flushing device for underground diaphragm wall trenching construction".

与现有技术相比,本发明具有如下的有益效果:Compared with the prior art, the present invention has the following beneficial effects:

本发明的施工方法克服了现有施工方法在上覆砂土微风化花岗岩中施工困难或施工进度缓慢、成槽质量差等缺点和不足,实现微风化花岗岩中的高效、高精度、深嵌岩的成槽施工;本发明效果好,钻孔成功率100%;成槽速度快,工程周期缩减为传统的重锤夯击成槽工法的十分之一。The construction method of the present invention overcomes the disadvantages and deficiencies of existing construction methods such as difficult construction or slow construction progress and poor groove quality in the overlying sandy slightly weathered granite, and realizes high-efficiency, high-precision, deep rock-socketing in the slightly weathered granite trough forming construction; the invention has good effect, and the drilling success rate is 100%; the trough forming speed is fast, and the engineering period is reduced to one-tenth of the traditional heavy hammer ramming trough forming method.

附图说明Description of drawings

通过阅读参照以下附图对非限制性实施例所作的详细描述,本发明的其它特征、目的和优点将会变得更明显:Other characteristics, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:

图1为本发明地下连续墙槽壁的爆破孔位置及装药示意图;Fig. 1 is the position of the blast hole and the schematic diagram of charge of underground diaphragm wall groove wall of the present invention;

图2为本发明一个展开的药包加工示意图;Fig. 2 is a schematic diagram of the processing of an expanded drug pack of the present invention;

图3为本发明上覆砂土微风化花岗岩中成槽施工步骤示意图。Fig. 3 is a schematic diagram of the trenching construction steps in the overlying sandy slightly weathered granite of the present invention.

具体实施方式Detailed ways

下面结合具体实施例对本发明进行详细说明。以下实施例将有助于本领域的技术人员进一步理解本发明,但不以任何形式限制本发明。应当指出的是,对本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进。这些都属于本发明的保护范围。The present invention will be described in detail below in conjunction with specific embodiments. The following examples will help those skilled in the art to further understand the present invention, but do not limit the present invention in any form. It should be noted that those skilled in the art can make several modifications and improvements without departing from the concept of the present invention. These all belong to the protection scope of the present invention.

本实施例提供一种微风化花岗岩中地下连续墙的高效成槽施工方法,用于某场地拟建一地铁车站,车站外包总长度为236.4m,区域内土层类型为上覆砂土的微风化花岗岩层,拟采用钻孔爆破的方式进行地下连续墙的成槽施工,成槽深度为18m,设计宽度800mm;施工步骤如图3所示。This embodiment provides an efficient trench-forming construction method for an underground diaphragm wall in slightly weathered granite, which is used in a site where a subway station is proposed to be built. The total length of the station outsourcing is 236.4m, and the soil layer in the area is a breeze covered with sandy soil. It is planned to use drilling and blasting to construct trenches for the underground diaphragm wall, with a trench depth of 18m and a design width of 800mm; the construction steps are shown in Figure 3.

本实施例所述施工方法的具体施工步骤如下:The concrete construction steps of construction method described in the present embodiment are as follows:

步骤一、施工现场地质勘测,具体:Step 1. Construction site geological survey, specifically:

每隔50m布设钻探孔位,钻至22m深,然后取出岩芯,依据钻孔弯曲参数,确定待施工区域内岩面的埋深为11~15m,成槽入岩深度为3~7m,岩面性状是倾斜方向复杂,倾斜角为10°~25°,微风化花岗岩层的无侧限抗压强度的分布值在100~180MPa之间。Drilling holes are arranged every 50m, drilled to a depth of 22m, and then the core is taken out. According to the drilling bending parameters, the buried depth of the rock surface in the area to be constructed is determined to be 11-15m, and the depth of the groove into the rock is 3-7m. The surface properties are complex inclination direction, the inclination angle is 10°-25°, and the unconfined compressive strength distribution value of the slightly weathered granite layer is between 100-180MPa.

采用带孔隙水压力的静力触探法确定拟建基坑区域砂土层的性状,静力触探的测试深度为地表至中风化花岗岩岩面,沿基坑纵向每50m布置一个检验孔,且数量不少于3个;利用静力触探测出土体的贯入阻力和孔隙水压力与深度的关系曲线,并画出以孔隙水压力与贯入阻力之比为横轴,以贯入阻力与初始地层应力之比为纵轴的关系图,并将该图划分若干不同土性特征区以此代表不同土的类型;将实测的静力触探曲线的数据标于该图以判断场地土层的类型,并按下列公式确定砂土层的渗透系数:Use the static sounding method with pore water pressure to determine the properties of the sandy soil layer in the proposed foundation pit area. The test depth of the static sounding sounding is from the surface to the weathered granite rock surface, and an inspection hole is arranged every 50m along the longitudinal direction of the foundation pit. And the number is not less than 3; use static contact to detect the relationship curve between the penetration resistance of the soil and the pore water pressure and depth, and draw the ratio of the pore water pressure to the penetration resistance as the horizontal axis, and the penetration resistance The ratio of the initial stratum stress to the vertical axis is the relationship diagram, and the diagram is divided into several different soil characteristic areas to represent different soil types; the data of the measured static penetration curve is marked on the diagram to judge the site soil The type of layer, and determine the permeability coefficient of the sand layer according to the following formula:

kk == KK DD. UaUa γγ ww 22 σσ vv 00 ′′

式中:k=渗透系数,In the formula: k = permeability coefficient,

KD=无量纲水的渗透系数,K D = Dimensionless permeability coefficient of water,

U=锥入速率,U=cone penetration rate,

a=孔压静力触探探头横截圆面的半径,a = the radius of the cross-sectional circular surface of the piezostatic penetration probe,

γw=土体容重,γ w = soil bulk density,

σv0=初始总的竖向应力;σ v0 = initial total vertical stress;

本实施例中,采用带孔隙水压力的静力触探法获取含隧道在内的浅层土的土层划分信息,由上至下依次为:上覆第四系全新统人工堆积层(Q4ml)、冲洪积层(Q4al+pl)、花岗岩及混合花岗岩残积层(Qel),下伏燕山期花岗岩(γ53)、加里东期混合花岗岩(Mγ3);4个检测孔的砂土层渗透系数依次为:1.56、1.86、2.16、1.99m/d。In this embodiment, the static penetration method with pore water pressure is used to obtain the soil layer division information of the shallow soil including the tunnel. 4ml ), alluvium-diluvium (Q 4al+pl ), granite and migmatite residual layer (Q el ), underlying Yanshanian granite (γ 53 ), Caledonian migmatite (M γ3 ); The permeability coefficients of sandy soil layer are: 1.56, 1.86, 2.16, 1.99m/d.

步骤二、确定采用微差预裂控制爆破方式破岩施工地下连续墙Step 2. Determine the use of differential pre-splitting control blasting method to break rocks and construct underground diaphragm walls

本实施例中,所述的微差预裂控制爆破方式是除开挖区内按设计正常钻孔装药外,还沿设计开挖线周边钻一排孔并装药;起爆时,周边孔先爆,开挖区后爆;先爆的周边钻孔产生一条1-4cm的裂缝;后爆的开挖区爆破时,其冲击波的能量被周边缝所削弱,可以减少对周边缝外的区域的爆炸冲击,这样可使设计线上的开凿边界平整。In this embodiment, the micro-differential pre-splitting control blasting method is to drill a row of holes along the periphery of the designed excavation line and charge the explosives in addition to the normal drilling and charging in the excavation area according to the design; Explosion, blasting after the excavation area; the peripheral drilling of the blasting first produces a 1-4cm crack; when the excavation area of the post-explosion is blasted, the energy of the shock wave is weakened by the peripheral seam, which can reduce the impact on the area outside the peripheral seam Blast impact, which smooths the excavation boundary on the design line.

步骤三、确定爆破参数,具体的:Step 3, determine the blasting parameters, specifically:

按入微风化花岗岩5m、一次爆破施工的槽幅长度12m,在施工场地内选取试验段进行爆破施工,确定爆破参数为:砂土层钻孔直径150mm,岩层钻孔直径76mm,钻孔间距650mm,不耦合系数1.8,钻孔深度19m,间隔装药段堵塞长度0.6m,选用2#岩石乳化炸药,选用两发瞬发电雷管进行现场试爆确定相关参数为A=0.7,B=0.8,C=0.9,炸药单耗取值取1.3kg/m。如图1所示为本实施例的地下连续墙槽壁的爆破孔位置及装药示意图,如图2所示为本实施例的药包加工示意图。According to the slightly weathered granite 5m, the length of the groove width of the blasting construction is 12m, select the test section in the construction site for blasting construction, and determine the blasting parameters: the diameter of the sand layer drilling hole is 150mm, the rock formation drilling diameter is 76mm, and the drilling distance is 650mm , the non-coupling coefficient is 1.8, the drilling depth is 19m, and the plugging length of the interval charging section is 0.6m. 2# rock emulsion explosive is selected, and two instantaneous detonators are selected for field test blasting. The relevant parameters are A=0.7, B=0.8, C =0.9, the unit consumption of explosives is 1.3kg/m. Figure 1 is a schematic diagram of the position of the blast hole and charge of the trench wall of the underground diaphragm wall in this embodiment, and Figure 2 is a schematic diagram of the processing of the charge bag in this embodiment.

步骤四、砂土层中成孔至岩层表面并出土,具体的:Step 4, forming holes in the sand layer to the surface of the rock layer and unearthed, specifically:

平整场地,清除地面障碍物;根据现场平面和高程控制点、地下连续墙设计图、爆破参数及现场情况,确定钻孔位置;如图3(1)所示,潜孔钻机安装直径150mm的金刚石偏心钻头,钻头外设置钢套管护壁,潜孔钻机在已确定的钻孔位置钻进,边钻孔边接长套管,直至钻进中风化花岗岩岩面;如图3(2)所示,用外径130mm的螺旋取土机取出钻孔内土体。Level the site and remove ground obstacles; determine the drilling position according to the site plane and elevation control points, underground diaphragm wall design drawings, blasting parameters and site conditions; as shown in Figure 3 (1), the DTH drilling rig is installed with a diamond The eccentric drill bit is equipped with a steel casing protection wall outside the drill bit. The down-the-hole drilling machine drills at the determined drilling position, and connects long casings while drilling until it drills into the weathered granite rock surface; as shown in Figure 3 (2) As shown, take out the soil in the borehole with an auger with an outer diameter of 130mm.

本实施例中,所述的钻杆为圆形冲击钻杆,上端有锥形外螺纹,下端有锥形内螺纹,钻杆的两端开有扳手切口和打捞时用的环形槽以方便拧卸。In this embodiment, the drill rod is a circular percussion drill rod with a tapered external thread at the upper end and a tapered internal thread at the lower end. The two ends of the drill rod are provided with a wrench notch and an annular groove for fishing to facilitate screwing. Unload.

本实施例中,所述的钢套筒为直径146mm的薄壁钢筒;上端有锥形外螺纹,下端有锥形内螺纹,钢套筒的两端开有扳手切口和环形槽用以取出。In this embodiment, the steel sleeve is a thin-walled steel cylinder with a diameter of 146mm; the upper end has a tapered external thread, the lower end has a tapered internal thread, and both ends of the steel sleeve are provided with wrench cuts and annular grooves for removal.

步骤五、辨别岩样,确定钻进至中风化花岗岩,具体的:Step 5. Identify the rock sample and determine that the drilled to medium weathered granite, specifically:

将砂土层钻头换成直径110mm的中空金刚石取芯钻头进行取芯,下伸至钻孔底部并向下钻进0.5m,取出中风化岩样0.5m且经现场施工员辨别岩样确认后,继续取芯0.5m,岩样无变化后,停止取芯钻孔;取出取芯钻头。Replace the drill bit in the sand layer with a hollow diamond core bit with a diameter of 110mm for coring, extend down to the bottom of the borehole and drill down 0.5m, take out 0.5m of moderately weathered rock samples and confirm the identification of the rock samples by the on-site construction workers , continue to take coring for 0.5m, and stop coring drilling after the rock sample has no change; take out the coring bit.

步骤六、下PVC管,用于保护爆破导线,具体的:Step 6. Lower the PVC pipe to protect the blasting wire, specifically:

如图3(3)所示,向钢套管内插入PVC管,边插入边接长,待PVC管底部下至钻孔底部时,向PVC管内注水,注水时间为30min;PVC管接长至地面后,用钢锯将过长部分锯掉,控制PVC管比地面高100mm左右;如图3(4)所示,向PVC管底部插入注浆管,水下注水泥浆,用于固定PVC管,防止砂土层中的水土流入PVC管和第七步中的岩层钻孔;如图3(5)所示,待水泥浆硬化后,用水泵将PVC管内水全部抽出,同时用千斤顶将钢套管拔出。As shown in Figure 3 (3), insert the PVC pipe into the steel casing and extend it while inserting it. When the bottom of the PVC pipe reaches the bottom of the drill hole, inject water into the PVC pipe for 30 minutes; the PVC pipe is extended to the ground Finally, cut off the overlong part with a hacksaw, and control the PVC pipe to be about 100mm higher than the ground; as shown in Figure 3 (4), insert the grouting pipe to the bottom of the PVC pipe, and inject grout underwater to fix the PVC pipe. Prevent the water and soil in the sand layer from flowing into the PVC pipe and the rock formation drilling in the seventh step; as shown in Figure 3 (5), after the cement slurry hardens, use a pump to pump out all the water in the PVC pipe, and at the same time use a jack to lift the steel sleeve The tube is pulled out.

本实施例中,所述的PVC管外径90mm,管底用内径90mm堵头封堵,每节PVC管长4m,将PVC管插入内径与该管外径相等的PVC管内搭接接长,胶水粘贴牢固。In the present embodiment, the outer diameter of the PVC pipe is 90mm, and the bottom of the pipe is blocked with a plug with an inner diameter of 90mm. The length of each PVC pipe is 4m. The glue sticks firmly.

本实施例中,所述的注水量为350L。In this embodiment, the water injection volume is 350L.

本实施例中,所述的水泥浆水灰质量配比为0.8:1,水泥浆拌制采用32.5级普通硅酸盐水泥,注浆压力控制在0.3MPa,注浆速度为5L/min,注浆时间为10min。In this example, the water-cement mass ratio of the cement slurry is 0.8:1, the cement slurry is mixed with 32.5 grade ordinary Portland cement, the grouting pressure is controlled at 0.3MPa, and the grouting speed is 5L/min. Slurry time is 10min.

步骤七、岩层中成孔至设计埋深下1m,具体的:Step 7. Form holes in the rock formation to 1m below the designed buried depth, specifically:

如图3(6)所示,将潜孔钻机的取芯钻头换成直径76mm钨钢合金钻头,再次下伸钻头至PVC管底水泥浆表面处,钻进至设计槽壁下1m,边钻边施加高压风将石渣粉末吹出;如图3(7)所示,潜孔钻机拔出钻头,更换钨钢合金钻头为金刚石偏心钻头,在下一钻孔处钻进,按上述步骤循环作业,直至22个钻孔施工完毕,撤出潜孔钻机。As shown in Figure 3 (6), replace the core drill bit of the down-the-hole drilling rig with a tungsten steel alloy drill bit with a diameter of 76mm, extend the drill bit down to the surface of the cement slurry at the bottom of the PVC pipe, and drill to 1m below the designed groove wall, while drilling While applying high-pressure air to blow out the gravel powder; as shown in Figure 3 (7), the down-the-hole drilling rig pulls out the drill bit, replaces the tungsten steel alloy drill bit with a diamond eccentric drill bit, and drills in the next hole. The down-the-hole drilling rig was withdrawn until the construction of 22 drilling holes was completed.

步骤八、装药爆破,如图3(8)所示,具体的:Step eight, charge blasting, as shown in Figure 3 (8), specifically:

根据设计装药量和钻孔深度,将加工好的药包和引线绑在竹竿上并将其下伸至钻孔孔底,完成单孔装药,待全部钻孔装药完毕后,检查每个孔的装药和引线;待全部钻孔装药完毕,检查无误后,用起爆器将所有引线连接,准备起爆;做好爆破前准备工作,对爆区顶面覆盖钢板加冲孔锤,以防止个别飞石泥浆造成周围保护物的损害;设置安全警戒线,人员全部撤至安全地点;用起爆器将所有引线连接,由爆破工程师启动爆破;待该槽幅爆破施工完毕后,进行下一槽幅的钻孔爆破。According to the designed charge amount and drilling depth, tie the processed charge pack and lead wire to the bamboo pole and extend it down to the bottom of the drilled hole to complete the single hole charge. After all the drill holes are charged, check each charge and lead wires for each hole; after all the holes are drilled and charged, and after the inspection is correct, connect all the lead wires with the detonator and prepare for detonation; do the preparation work before blasting, and add a punching hammer to the top surface of the blasting area covering the steel plate, In order to prevent individual flying rocks and mud from causing damage to the surrounding protection; set up a safety warning line, and evacuate all personnel to a safe place; connect all lead wires with a detonator, and the blasting engineer will start the blasting; after the blasting construction of the slot width is completed, proceed to the next Drilling and blasting of a slot width.

本实施例中,所述的药包为2#岩石乳化炸药,药卷直径为60mm,单孔装药量4kg,一副地下连续墙用量56kg;采用56个非电雷管;堵塞材料为粗砂。In the present embodiment, the charge pack is 2# rock emulsion explosive, the charge roll diameter is 60mm, the single-hole charge is 4kg, and the amount of a pair of underground diaphragm walls is 56kg; 56 non-electric detonators are used; the plugging material is coarse sand .

本实施例中,炮孔采用正向装药起爆,起爆雷管选用两发瞬发电雷管,且分别属于两个非电起爆网路,两套网路并联后起爆。In this embodiment, the blast hole is detonated with positive charges, and the detonator is selected from two instantaneous detonators, which belong to two non-electric detonation networks respectively, and detonate after the two sets of networks are connected in parallel.

步骤九、施工导墙,如图3(9)所示;待一定范围内的地下连续墙成孔爆破施工完毕后,导墙施工,具体的:Step 9: Construction of the guide wall, as shown in Figure 3 (9); after the hole-forming blasting of the underground diaphragm wall within a certain range is completed, the guide wall is constructed, specifically:

如图3(10)所示,在泥浆护壁的条件下,用成槽机抓取上部砂土和碎岩;如图3(11)所示,在泥浆护壁的条件下,利用重锤冲孔、锤击岩面,每一锤击进尺施工完成后立即用成槽机挖出碎岩;用方锤清扫槽壁残余突出岩梗,连孔成槽;如图3(12)所示,用成槽机抓取槽底碎岩,成槽施工完成。As shown in Figure 3 (10), under the condition of the mud retaining wall, use the slotting machine to grab the upper sand and broken rock; as shown in Figure 3 (11), under the condition of the mud retaining wall, use the heavy hammer to punch 1. Hammering the rock surface, immediately after the completion of each hammering footage construction, dig out the broken rock with a groove forming machine; use a square hammer to clean the remaining protruding rock stems on the groove wall, and connect the holes to form grooves; as shown in Figure 3 (12), use The trough forming machine grabs the broken rock at the bottom of the trough, and the trough forming construction is completed.

本实施例中,所述的导墙厚200mm、外放100mm、深度1.5m;采用混凝土现浇方式分段施工,每段长度为50m。In this embodiment, the guide wall is 200mm thick, 100mm outside, and 1.5m deep; it is constructed in sections by cast-in-place concrete, and the length of each section is 50m.

本实施例中,所述的泥浆配浆材料及配比为:水:膨润土:碳酸钠=1:0.04:0.0002。In this embodiment, the mud mixing material and its ratio are: water: bentonite: sodium carbonate = 1:0.04:0.0002.

本实施例中,所述的重锤质量为3t,轴心处为中空构造,轴心孔孔径120mm;重锤的锤身为十字圆台体,锤身中部用钢筋2捆扎;重锤的底面4上设置矽钢合金齿3,矽钢合金齿3按十字雪花状分布,相邻矽钢合金齿3通过钢筋2连接;重锤距离待冲岩面的提升高度为3m,锤击进尺为400mm;每一进尺施工完成后,立即用成槽机挖出碎岩;本步骤的施工顺序为由两侧向中间,先主冲孔后副冲孔。In this embodiment, the mass of the heavy hammer is 3t, the center of the shaft is hollow, and the hole diameter of the shaft center is 120mm; Silicon steel alloy teeth 3 are arranged on the top, and the silicon steel alloy teeth 3 are distributed in a cross snowflake shape, and the adjacent silicon steel alloy teeth 3 are connected by steel bars 2; the lifting height of the hammer from the rock surface to be washed is 3m, and the hammering footage is 400mm; Immediately after the construction of each footage is completed, the broken rock is dug out with a slotting machine; the construction sequence of this step is from both sides to the middle, first the main punching and then the auxiliary punching.

本实施例中,所述的方锤锤面长1600mm、宽800mm,锤面四周加焊60mm厚、400mm高的矽钢合金齿。In this embodiment, the hammer face of the square hammer is 1600 mm long and 800 mm wide, and silicon steel alloy teeth with a thickness of 60 mm and a height of 400 mm are welded around the hammer face.

本发明的施工方法克服了现有施工方法在上覆砂土微风化花岗岩中施工困难或施工进度缓慢、成槽质量差等缺点和不足,实现微风化花岗岩中的高效、高精度、深嵌岩的成槽施工;本发明效果好,钻孔成功率100%;成槽速度快,工程周期缩减为传统的重锤夯击成槽工法的十分之一。The construction method of the present invention overcomes the disadvantages and deficiencies of existing construction methods such as difficult construction or slow construction progress and poor groove quality in the overlying sandy slightly weathered granite, and realizes high-efficiency, high-precision, deep rock-socketing in the slightly weathered granite trough forming construction; the invention has good effect, and the drilling success rate is 100%; the trough forming speed is fast, and the engineering period is reduced to one-tenth of the traditional heavy hammer ramming trough forming method.

以上对本发明的具体实施例进行了描述。需要理解的是,本发明并不局限于上述特定实施方式,本领域技术人员可以在权利要求的范围内做出各种变形或修改,这并不影响本发明的实质内容。Specific embodiments of the present invention have been described above. It should be understood that the present invention is not limited to the specific embodiments described above, and those skilled in the art may make various changes or modifications within the scope of the claims, which do not affect the essence of the present invention.

Claims (10)

1.一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,所述施工方法通过下列步骤实现:1. a kind of high-efficiency trenching construction method of underground diaphragm wall in slightly weathered granite, it is characterized in that, described construction method realizes by following steps: 第一步、施工现场地质勘测:通过钻孔取芯确定地下连续墙嵌岩深度范围内的微风化花岗岩的岩面性状、标准无侧限抗压强度的分布值;在此基础上根据地下连续墙的设计埋深确定地下连续墙的嵌岩深度;The first step, geological survey at the construction site: determine the rock surface properties and the distribution value of the standard unconfined compressive strength of the micro-weathered granite within the depth range of the rock-socketed underground diaphragm wall through drilling and coring; on this basis, according to the underground continuous wall The designed buried depth of the wall determines the rock-socketed depth of the underground diaphragm wall; 第二步、确定破岩方法:对于无侧限抗压强度为100MPa以上的微风化花岗岩,采用微差预裂控制爆破方式;The second step is to determine the rock-breaking method: for slightly weathered granite with an unconfined compressive strength of 100 MPa or more, the micro-differential pre-splitting control blasting method is used; 第三步、确定爆破参数:The third step is to determine the blasting parameters: 1)根据地下连续墙的设计槽幅宽度、设计埋深、一次爆破施工的槽幅长度和微差预裂控制爆破的设计原理,先预估炮孔参数,再通过第三步5)确定炮孔参数;1) According to the designed groove width of the underground diaphragm wall, the designed buried depth, the groove length of the primary blasting construction and the design principle of differential pre-splitting controlled blasting, first estimate the parameters of the blast hole, and then determine the blast hole through the third step 5). Hole parameters; 2)微风化花岗岩的无侧限抗压强度分布值为100~180MPa,确定选用2#岩石乳化炸药,炸药具有防水性能;2) The unconfined compressive strength distribution value of slightly weathered granite is 100-180MPa, and it is determined to use 2# rock emulsion explosive, which has waterproof performance; 3)根据第二步中所述的微差预裂控制爆破方式,起爆器选用微差毫秒电雷管,即间隔为十几毫秒至数百毫秒的延期电雷管;3) According to the micro-differential pre-splitting control blasting method described in the second step, the detonator selects a micro-second electric detonator, that is, an electric detonator whose interval is more than ten milliseconds to hundreds of milliseconds; 4)根据岩石的无侧限抗压强度分布值并结合第三步5)确定炸药的线装药密度;线装药密度取值范围为1.0~1.5kg/m;按如下公式计算线装药量密度:Q=AaBσC;式中:Q为线装药密度;a为钻孔间距;σ为岩石无侧限抗压强度;A、B、C为待定系数,通过第三步5)现场试爆后再回归分析的方法确定;4) According to the unconfined compressive strength distribution value of the rock and combined with the third step 5), determine the line charge density of the explosive; the line charge density ranges from 1.0 to 1.5kg/m; calculate the line charge according to the following formula Quantity density: Q=Aa B σ C ; where: Q is the linear charge density; a is the drilling distance; σ is the unconfined compressive strength of rock; A, B, and C are undetermined coefficients. ) to determine the method of regression analysis after field test; 5)爆破施工时需进行槽段试爆,在地下连续墙施工的场地内选取试验槽段,按经验选取第三步1)到4)中的爆破参数进行爆破施工,然后对试爆槽段钻孔取芯抽样,并根据抽样破碎情况调整爆破参数;重复上述槽段试爆步骤,直至岩石碎块可以被成槽机抓取,确定地下连续墙施工的钻孔直径、钻孔间距、不耦合系数、孔深、堵塞长度、线装药密度和钻孔间距;5) During the blasting construction, it is necessary to carry out the test blasting of the groove section. Select the test groove section in the construction site of the underground diaphragm wall, and select the blasting parameters in the third step 1) to 4) according to experience for blasting construction, and then blast the test groove section Drill and take core samples, and adjust the blasting parameters according to the sample fragmentation; repeat the above-mentioned test blasting steps of the groove section until the rock fragments can be captured by the groove forming machine, and determine the diameter of the drill holes, the distance between the drill holes, and the Coupling coefficient, hole depth, plugging length, linear charge density and drilling spacing; 第四步、砂土层中成孔至岩层表面并出土:The fourth step is to form holes in the sand layer to the surface of the rock layer and unearth: 1)平整场地,清除地面障碍物;1) Level the site and remove ground obstacles; 2)根据现场平面和高程控制点、地下连续墙设计图、爆破参数和现场情况,确定钻孔位置;2) Determine the drilling location according to the site plane and elevation control points, the design drawing of the underground diaphragm wall, the blasting parameters and the site conditions; 3)安装有砂土层钻头的潜孔钻机在已确定的钻孔位置钻进,同时进行钢套筒护壁,边接钻杆边接钢套筒,直至钻进至中风化花岗岩岩面;3) The down-the-hole drilling rig equipped with a sand layer drill bit drills at the determined drilling position, and at the same time protects the wall with a steel sleeve, and connects the steel sleeve while connecting the drill pipe until it reaches the moderately weathered granite rock face; 4)螺旋取土机取出钻孔内土体;4) The auger earth taker takes out the soil in the borehole; 第五步、辨别岩样,确定钻进至中风化花岗岩:The fifth step is to identify the rock sample and determine that the drilled to medium weathered granite: 1)将砂土层钻头换成取芯钻头,下伸至钻孔底部并向下钻进0.5m,取出中风化岩样0.5m且经确认为中风化花岗岩后,继续向下取芯0.5m,岩样无变化后,停止取芯钻孔;1) Replace the drill bit in the sand layer with a core bit, extend down to the bottom of the borehole and drill down 0.5m, take out 0.5m of moderately weathered rock samples and confirm that it is moderately weathered granite, and continue to take 0.5m down the core , when there is no change in the rock sample, stop the core drilling; 2)取出取芯钻头;2) Take out the core bit; 第六步、下PVC管,用于保护爆破导线:The sixth step is to lower the PVC pipe to protect the blasting wire: 1)向钢套管内插入PVC管,边插入边接长;待PVC管底部下至钻孔底部时,向PVC管内注水;1) Insert the PVC pipe into the steel casing, and extend it while inserting; when the bottom of the PVC pipe reaches the bottom of the drill hole, inject water into the PVC pipe; 2)PVC管接长至地面后,用钢锯将过长部分锯掉,控制PVC管比地面高100mm;2) After the PVC pipe is extended to the ground, use a hacksaw to cut off the overlong part, and control the PVC pipe to be 100mm higher than the ground; 3)向PVC管底部插入注浆管,水下注水泥浆,用于固定PVC管,防止砂土层中的水土流入PVC管和第七步中的岩层钻孔;3) Insert the grouting pipe to the bottom of the PVC pipe, and inject grout underwater to fix the PVC pipe to prevent water and soil in the sand layer from flowing into the PVC pipe and the rock formation drilling in the seventh step; 4)待水泥浆硬化后,用水泵将PVC管内水全部抽出,同时用千斤顶将钢套管拔出;4) After the cement slurry is hardened, use a water pump to pump out all the water in the PVC pipe, and at the same time use a jack to pull out the steel casing; 第七步、岩层中成孔至设计埋深下1m:The seventh step is to form a hole in the rock formation to 1m below the designed buried depth: 1)将潜孔钻机的取芯钻头换成岩层钻头,再次下伸钻头至PVC管底水泥浆表面处,钻进至设计槽壁下1m,边钻边施加高压风将石渣粉末吹出;1) Replace the core drill bit of the down-the-hole drilling rig with a rock formation drill bit, extend the drill bit down again to the surface of the cement slurry at the bottom of the PVC pipe, drill to 1m below the designed groove wall, and apply high-pressure wind while drilling to blow out the gravel powder; 2)潜孔钻机拔出钻头,更换钨钢合金钻头为土层钻头,在下一钻孔处钻进,按上述步骤循环作业,直到全部钻孔钻进完毕,撤出潜孔钻机;2) Pull out the drill bit from the down-the-hole drilling rig, replace the tungsten-steel alloy drill bit with the soil layer drill bit, and drill in the next hole. Follow the above-mentioned steps to cycle until all the holes are drilled, and then withdraw the down-the-hole drilling rig; 第八步、装药爆破:The eighth step, charge blasting: 1)根据设计装药量和钻孔深度,将乳化炸药药包和引线绑在竹竿上并将其下伸至钻孔孔底,完成单孔装药,待全部钻孔装药完毕后,检查每个孔的装药和引线;1) According to the designed charge amount and the drilling depth, tie the emulsion explosive charge and the lead wire to the bamboo pole and extend it down to the bottom of the drill hole to complete the single hole charge. After all the drill holes are charged, check charges and leads for each hole; 2)待全部钻孔装药完毕,检查无误后,用起爆器将所有引线连接,准备起爆;2) After all the drilling and charging are completed and the inspection is correct, use the detonator to connect all the lead wires and prepare for detonation; 3)做好爆破前准备工作,启动爆破;3) Prepare well before blasting and start blasting; 4)待该槽幅爆破施工完毕后,进行下一槽幅的钻孔爆破;4) After the blasting construction of the slot width is completed, the drilling and blasting of the next slot width is carried out; 第九步、导墙施工,成槽施工完成。The ninth step is the construction of the guide wall, and the construction of the groove is completed. 2.根据权利要求1所述的一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,第一步1)中:所述标准无侧限抗压强度的分布值是遵循土工试验规程,在无侧限条件下,施加轴向压力直至试样破坏所确定的土体抗压强度分布值;2. the efficient groove-forming construction method of underground diaphragm wall in a kind of slightly weathered granite according to claim 1, is characterized in that, in the first step 1): the distribution value of described standard unconfined compressive strength follows Geotechnical test procedures, under unconfined conditions, apply axial pressure until the specimen fails to determine the soil compressive strength distribution value; 所述钻孔取芯确定微风化花岗岩的岩面性状通过如下步骤获得:The rock face properties of the micro-weathered granite are obtained by taking cores from the boreholes as follows: ①根据待成槽区域大小布设地质勘测孔的位置与数量,分别钻探至成槽施工所需的深度取出岩芯,并根据成槽区域大小和范围确定钻孔的数量和间距,测试孔位沿地下连续墙中轴线的两侧交错布置;① Arrange the position and number of geological survey holes according to the size of the trough-forming area, respectively drill to the depth required for trough-forming construction to take out cores, and determine the number and spacing of drilled holes according to the size and scope of the trough-forming area. The two sides of the central axis of the underground diaphragm wall are staggered; ②通过钻孔取芯确定成槽施工区域的岩面深度与待挖厚度,确定岩石结构面与钻孔弯曲方向或地球磁北方向之间关系,所述岩石结构面是具有一定形态而且普遍存在的地质构造迹象的岩石平面或曲面,按力学性质不同分为挤压面、张裂面、扭裂面、压扭面、张扭面五种结构面性状;② Determine the rock surface depth and the thickness to be excavated in the trenching construction area by drilling and coring, and determine the relationship between the rock structural plane and the bending direction of the drilling hole or the earth's magnetic north direction. The rock structural plane has a certain shape and is ubiquitous According to different mechanical properties, the rock plane or curved surface with geological structure signs can be divided into five structural surface properties: extrusion surface, tension crack surface, torsion crack surface, compression torsion surface, and tension torsion surface; ③利用地球重力场,以铅垂线为基准,采用液面水平、悬锤的方法测定测点处倾斜方向的垂直平面上偏离铅垂线的角度,即顶角;③ Utilize the earth's gravity field, take the plumb line as the benchmark, and use the method of liquid level and pendent to measure the angle of the vertical plane in the inclined direction of the measuring point, that is, the top angle; ④利用地球磁场,以地球磁子午线为定向基准,用磁罗盘测量水平面上的钻孔轴线上某点切线方向与地球磁北方向的夹角,即方位角;④ Utilize the earth's magnetic field, take the earth's magnetic meridian as the orientation reference, and use a magnetic compass to measure the angle between the tangent direction of a point on the borehole axis on the horizontal plane and the earth's magnetic north direction, that is, the azimuth; ⑤利用扫描电子显微镜进行矿物微区测试,对取出岩芯进行微量元素和同位素测试,分析岩体的矿物组成,从而得到岩层的类别、温度、应力状态和结构面产状;⑤ Use the scanning electron microscope to conduct mineral micro-area testing, conduct trace element and isotope testing on the cores taken out, and analyze the mineral composition of the rock mass, so as to obtain the type, temperature, stress state and structural plane occurrence of the rock formation; ⑥根据顶角、方位角、矿物微区测试测试结果、受应力作用岩石的组构类型或干涉色对比和产生的应力矿物特征,推测出结构面的应力性质,确定岩石的岩面性状。⑥ According to the top angle, azimuth angle, mineral micro-region test results, the fabric type or interference color contrast of the rock subjected to stress, and the stress mineral characteristics generated, the stress nature of the structural plane is inferred, and the rock surface properties of the rock are determined. 3.根据权利要求1所述的一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,第三步1)中,所述炮孔参数包括钻孔直径、钻孔间距、不耦合系数、孔深和堵塞长度,其中:所述钻孔直径是根据设计槽幅宽度和一次爆破施工的槽幅长度确定,当设计槽幅宽度为600~1000mm、一次爆破施工的槽幅长度为12m时,钻孔直径的范围为50~150mm;质量要求高的工程,采用小的钻孔;3. the efficient trough-forming construction method of underground diaphragm wall in a kind of slightly weathered granite according to claim 1, is characterized in that, in the 3rd step 1), described blasthole parameter comprises borehole diameter, borehole spacing, Uncoupling coefficient, hole depth and plugging length, wherein: the borehole diameter is determined according to the designed slot width and the slot length of one blasting construction, when the designed slot width is 600-1000 mm, the slot length of one blasting construction When the diameter is 12m, the drilling diameter ranges from 50 to 150mm; for projects with high quality requirements, use small drilling holes; 所述钻孔间距取钻孔直径的5~7倍,钻孔直径大于100mm时取小值,小于100mm时取大值,软弱破碎的岩石取小值,坚硬的岩石取大值,质量要求高的取小值,要求不高的取大值;The borehole spacing is 5 to 7 times the borehole diameter. When the borehole diameter is greater than 100mm, take a small value, and when it is less than 100mm, take a large value. For weak and broken rocks, take a small value, and for hard rocks, take a large value. High quality requirements Take a small value for those with low requirements, and take a large value for those with low requirements; 所述不耦合系数为炮孔内径与药包直径的比值,对于设计槽幅宽度为600~1000mm地下连续墙不耦合系数取1.5~2.5,不耦合系数值大时,表示药包与孔壁之间的间隙大,爆破后对孔壁的破坏小,反之对孔壁的破坏大;The non-coupling coefficient is the ratio of the inner diameter of the blast hole to the diameter of the cartridge. For the designed groove width of 600-1000 mm, the non-coupling coefficient of the underground diaphragm wall is 1.5-2.5. The gap between them is large, and the damage to the hole wall after blasting is small, otherwise the damage to the hole wall is large; 所述孔深是根据地下连续墙的设计埋深确定,孔深取地面至地下连续墙的设计埋深以下0.5m~1.5m;The hole depth is determined according to the design buried depth of the underground diaphragm wall, and the hole depth is taken from the ground to 0.5m to 1.5m below the designed buried depth of the underground diaphragm wall; 所述堵塞长度取炮孔直径的12~20倍。The plugging length is 12 to 20 times the diameter of the blast hole. 4.根据权利要求1所述的一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,所述第四步3)中:所述砂土层钻头为金刚石偏心钻头,钻头直径大于岩层爆破钻孔直径5~10mm,用于砂土层中钻孔;4. the efficient trough-forming construction method of underground diaphragm wall in a kind of slightly weathered granite according to claim 1, is characterized in that, in described 4th step 3): described sand layer drill bit is diamond eccentric drill bit, drill bit The diameter is 5-10mm larger than the diameter of the blasting hole in the rock formation, and it is used for drilling in the sandy soil layer; 所述潜孔钻机为用钻杆带动风动冲击器和钻头旋转破岩的钻孔设备;The down-the-hole drilling rig is a drilling equipment that uses a drill rod to drive a pneumatic impactor and a drill bit to rotate and break rocks; 所述的钻杆为一种圆形冲击钻杆;上端有锥形外螺纹、下端有锥形内螺纹用以连接钻头;钻杆的两端开有扳手切口和打捞时用的环形槽以方便拧卸;The drill rod is a circular percussion drill rod; the upper end has a tapered external thread and the lower end has a tapered internal thread for connecting the drill bit; both ends of the drill rod are provided with a wrench cut and an annular groove for fishing. Unscrew; 所述钢套筒为直径比金刚石偏心钻头小5~10mm的薄壁钢筒,用以防止钻孔在砂土中塌孔;上端有锥形外螺纹、下端有锥形内螺纹用以连接;钢套筒的两端开有扳手切口和环形槽用以取出。The steel sleeve is a thin-walled steel cylinder with a diameter 5-10 mm smaller than that of the diamond eccentric drill bit, to prevent the drill hole from collapsing in the sand; the upper end has a tapered external thread, and the lower end has a tapered internal thread for connection; the steel sleeve Both ends of the barrel have wrench cutouts and annular grooves for removal. 5.根据权利要求1所述的一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,所述第四步4)中,所述螺旋取土机是安装有长螺旋状钻头的取土设备;将长螺旋状钻头插入钻孔,通过旋转叶片将孔内土体取出;长螺旋状钻头的外径小于钢套筒的内径。5. The efficient trough-forming construction method of underground diaphragm wall in a kind of slightly weathered granite according to claim 1, is characterized in that, in described fourth step 4), described spiral earth-moving machine is installed with long spiral Soil removal equipment for the drill bit; insert the long helical drill bit into the borehole, and take out the soil in the hole through the rotating blade; the outer diameter of the long helical drill bit is smaller than the inner diameter of the steel sleeve. 6.根据权利要求1所述的一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,第五步1)中,所述取芯钻头为中空金刚石取芯钻头,钻头直径和砂土层中钻头相同。6. the efficient trough-forming construction method of underground diaphragm wall in a kind of slightly weathered granite according to claim 1, is characterized in that, in the 5th step 1), described coring bit is hollow diamond coring bit, and drill bit diameter It is the same as the drill bit in the sand layer. 7.根据权利要求1所述的一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,第六步1)中,所述PVC管的直径比钢套管小,两根PVC管通过内径与其外径相等的接头PVC管搭接接长,并用胶水粘贴牢固。7. the efficient trough-forming construction method of underground diaphragm wall in a kind of slightly weathered granite according to claim 1, is characterized in that, in the 6th step 1), the diameter of described PVC pipe is smaller than steel sleeve pipe, two The PVC pipe is lapped and lengthened by a joint PVC pipe whose inner diameter is equal to its outer diameter, and is firmly pasted with glue. 8.根据权利要求1所述的一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,第六步3)中,所述水泥浆水灰质量配比为0.8:1,水泥浆拌制采用32.5级普通硅酸盐水泥,注浆压力控制在0.1-0.4MPa,注浆速度为3-7L/min;注浆量为使PVC管底部封口防止钢套管拔出时发生塌孔的用量,可根据钢套管直径和PVC管直径粗略估计,并根据钻孔时岩石破裂情况调整实际注浆量。8. the efficient trough-forming construction method of underground diaphragm wall in a kind of slightly weathered granite according to claim 1, is characterized in that, in the 6th step 3), described cement slurry water-cement mass ratio is 0.8:1, The cement slurry is mixed with 32.5 grade ordinary Portland cement, the grouting pressure is controlled at 0.1-0.4MPa, and the grouting speed is 3-7L/min; The amount of hole collapse can be roughly estimated according to the diameter of the steel casing and the diameter of the PVC pipe, and the actual grouting amount should be adjusted according to the rock fracture during drilling. 9.根据权利要求1所述的一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,所述第七步1)中:所述岩层钻头为钨钢合金钻头,钻头直径等于药包直径和不耦合系数的乘积,用于岩层钻孔;所述高压风通过风压机提供。9. The efficient trough-forming construction method of underground diaphragm wall in a kind of slightly weathered granite according to claim 1, it is characterized in that, in the 7th step 1): the rock formation drill bit is a tungsten steel alloy drill bit, and the drill bit diameter It is equal to the product of the diameter of the charge pack and the uncoupling coefficient, and is used for rock formation drilling; the high-pressure air is provided by an air compressor. 10.根据权利要求1所述的一种微风化花岗岩中地下连续墙的高效成槽施工方法,其特征在于,第八步3)中,所述爆破前准备工作即为对爆区顶面覆盖钢板加冲孔锤,以防止个别飞石泥浆造成周围保护物的损害;爆破时实施严格的安全警戒;爆破时人员全部撤至安全地点后方可起爆,爆破警戒距离不小于100m。10. The efficient groove-forming construction method of underground diaphragm wall in a kind of slightly weathered granite according to claim 1, characterized in that, in the eighth step 3), the preparatory work before the blasting is to cover the top surface of the blasting area Steel plates and punching hammers are used to prevent individual flying rocks and mud from causing damage to surrounding protection; strict safety precautions are implemented during blasting; blasting can only be initiated after all personnel are evacuated to a safe place during blasting, and the blasting warning distance is not less than 100m.
CN201410055023.2A 2014-02-18 2014-02-18 The efficient forming construction method thereof of diaphram wall in light weathered granite Expired - Fee Related CN104005415B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410055023.2A CN104005415B (en) 2014-02-18 2014-02-18 The efficient forming construction method thereof of diaphram wall in light weathered granite

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410055023.2A CN104005415B (en) 2014-02-18 2014-02-18 The efficient forming construction method thereof of diaphram wall in light weathered granite

Publications (2)

Publication Number Publication Date
CN104005415A true CN104005415A (en) 2014-08-27
CN104005415B CN104005415B (en) 2015-12-02

Family

ID=51366304

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410055023.2A Expired - Fee Related CN104005415B (en) 2014-02-18 2014-02-18 The efficient forming construction method thereof of diaphram wall in light weathered granite

Country Status (1)

Country Link
CN (1) CN104005415B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104762989A (en) * 2015-04-07 2015-07-08 中国建筑第六工程局有限公司 Method for speeding up diaphragm retaining wall construction at hard rock strata
CN104947690A (en) * 2015-06-19 2015-09-30 深圳市工勘岩土集团有限公司 Grooving construction method for embedding underground continuous wall into rock
CN105588479A (en) * 2016-02-25 2016-05-18 中铁十八局集团有限公司 Three-times elementary error vibration reduction major blasting method using rock flour spaced loading in blasting holes
CN105926641A (en) * 2016-04-28 2016-09-07 中铁二十二局集团第工程有限公司 Subtle preprocessing construction process of decomposed rock of underground continuous wall
CN106382120A (en) * 2016-09-14 2017-02-08 中石化石油工程技术服务有限公司 Detonating tunneling pipe-jacking construction method
CN107339920A (en) * 2017-09-06 2017-11-10 中钢集团马鞍山矿山研究院有限公司 The method of superdeep holes presplit blasting
CN108643179A (en) * 2018-06-28 2018-10-12 中水电第十工程局(郑州)有限公司 A kind of anchor pole and construction method using the construction of hand air drill in loose media stratum
CN109026039A (en) * 2018-10-19 2018-12-18 深圳市工勘岩土集团有限公司 Subway tunnel shield tunnels boulder deep hole blasting and pre-processes construction method
CN109610439A (en) * 2018-12-24 2019-04-12 北京城建北方集团有限公司 The construction method of underground obstacle ultra-deep underground continuous wall grooving
CN109989409A (en) * 2019-03-22 2019-07-09 上海长凯岩土工程有限公司 Building enclosure soil layer underground cavity is removed obstacles method
CN111121575A (en) * 2019-12-30 2020-05-08 中国十九冶集团(防城港)设备结构有限公司 Construction Method of Shallow Loosening Controlled Blasting in Urban Deep Foundation Pit
CN111263839A (en) * 2017-12-06 2020-06-09 东京土壤研究株式会社 Land surveying method and cone with blades
CN115752127A (en) * 2022-12-10 2023-03-07 中铁广州工程局集团有限公司 Rock-through slag blasting method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR970002246B1 (en) * 1990-09-06 1997-02-26 하. 룬트베크 아크티에 셀스카브 Pharmaceutical composition for the treatment of cerebrovascular disorders
KR20030075643A (en) * 2002-03-20 2003-09-26 한국지질자원연구원 Two-face simultaneous cut blasting using air decking
CN102032844A (en) * 2009-11-17 2011-04-27 广东爆破工程有限公司 Method for blasting closed rock of shield tunnel in complex strata
CN102692164A (en) * 2012-06-14 2012-09-26 中国水电顾问集团华东勘测设计研究院 Stress unloading, water injecting and drilling and blasting method for longitudinal structure surface structural strong rockburst regions
CN102818485A (en) * 2012-08-17 2012-12-12 重庆市爆破工程建设有限责任公司 High slope sunken layered blasting relief method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR970002246B1 (en) * 1990-09-06 1997-02-26 하. 룬트베크 아크티에 셀스카브 Pharmaceutical composition for the treatment of cerebrovascular disorders
KR20030075643A (en) * 2002-03-20 2003-09-26 한국지질자원연구원 Two-face simultaneous cut blasting using air decking
CN102032844A (en) * 2009-11-17 2011-04-27 广东爆破工程有限公司 Method for blasting closed rock of shield tunnel in complex strata
CN102692164A (en) * 2012-06-14 2012-09-26 中国水电顾问集团华东勘测设计研究院 Stress unloading, water injecting and drilling and blasting method for longitudinal structure surface structural strong rockburst regions
CN102818485A (en) * 2012-08-17 2012-12-12 重庆市爆破工程建设有限责任公司 High slope sunken layered blasting relief method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
吴爱军: "地下连续墙基岩处理控制爆破技术", 《河南科技》, no. 21, 15 November 2013 (2013-11-15) *

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104762989A (en) * 2015-04-07 2015-07-08 中国建筑第六工程局有限公司 Method for speeding up diaphragm retaining wall construction at hard rock strata
CN104947690A (en) * 2015-06-19 2015-09-30 深圳市工勘岩土集团有限公司 Grooving construction method for embedding underground continuous wall into rock
CN105588479A (en) * 2016-02-25 2016-05-18 中铁十八局集团有限公司 Three-times elementary error vibration reduction major blasting method using rock flour spaced loading in blasting holes
CN105926641A (en) * 2016-04-28 2016-09-07 中铁二十二局集团第工程有限公司 Subtle preprocessing construction process of decomposed rock of underground continuous wall
CN106382120A (en) * 2016-09-14 2017-02-08 中石化石油工程技术服务有限公司 Detonating tunneling pipe-jacking construction method
CN107339920B (en) * 2017-09-06 2019-01-18 中钢集团马鞍山矿山研究院有限公司 The method of superdeep holes presplit blasting
CN107339920A (en) * 2017-09-06 2017-11-10 中钢集团马鞍山矿山研究院有限公司 The method of superdeep holes presplit blasting
CN111263839A (en) * 2017-12-06 2020-06-09 东京土壤研究株式会社 Land surveying method and cone with blades
CN108643179A (en) * 2018-06-28 2018-10-12 中水电第十工程局(郑州)有限公司 A kind of anchor pole and construction method using the construction of hand air drill in loose media stratum
CN109026039A (en) * 2018-10-19 2018-12-18 深圳市工勘岩土集团有限公司 Subway tunnel shield tunnels boulder deep hole blasting and pre-processes construction method
CN109610439A (en) * 2018-12-24 2019-04-12 北京城建北方集团有限公司 The construction method of underground obstacle ultra-deep underground continuous wall grooving
CN109989409A (en) * 2019-03-22 2019-07-09 上海长凯岩土工程有限公司 Building enclosure soil layer underground cavity is removed obstacles method
CN111121575A (en) * 2019-12-30 2020-05-08 中国十九冶集团(防城港)设备结构有限公司 Construction Method of Shallow Loosening Controlled Blasting in Urban Deep Foundation Pit
CN111121575B (en) * 2019-12-30 2022-04-19 中国十九冶集团(防城港)设备结构有限公司 Construction Method of Shallow Loosening Controlled Blasting in Urban Deep Foundation Pit
CN115752127A (en) * 2022-12-10 2023-03-07 中铁广州工程局集团有限公司 Rock-through slag blasting method

Also Published As

Publication number Publication date
CN104005415B (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN104005415B (en) The efficient forming construction method thereof of diaphram wall in light weathered granite
CN106524844B (en) Boulder reconnoitres the construction method with explosion treatment along a kind of shield tunnel
CN102071940B (en) Construction method for mine shaft through multilayer goaf
AU2020257049B2 (en) Construction method for forming water-proof grouting curtain in water-rich porous rock stratum by blasting
CN106245626A (en) A kind of hard formation churning driven enters method
CN105651132B (en) Directional static blasting construction method for foundation pit stratum and combined guiding device for directional static blasting construction method
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN104763428B (en) Method of Grading and Partitioning Grouting to Reinforce Collapsed Columns to Make Fully Mechanized Mining Face Straight Through Soft Collapsed Columns
CN101761346A (en) Method for constructing metamorphic rock confined water tunnel
CN107060760A (en) A kind of method that colliery withdraws tunnel presplit blasting caving release
CN102518442A (en) Method for processing isolated stone groups in shield excavation karren section
CN109737840B (en) Multi-tunnel construction method based on weak interlayer
CN106677786B (en) A kind of ultra-deep big cross section vertical shaft shaft formatting by one blasting method based on electric detonator
CN109322301B (en) Quincuncial pore-forming construction method for rotary excavating bored concrete pile of large-diameter ultra-deep and ultra-thick rock stratum
CN104929146B (en) A construction method for multi-layer karst developed foundation with piles
CN104748632A (en) Underwater rock plug blasting construction method
CN109252868A (en) Hard-soft heterogeneous ground shield-tunneling construction boulder and basement rock protrusion processing method
CN107339122B (en) Construction method for treating goaf by steel pipe column
CN105401946A (en) Reverse blasting excavation method of shaft and pilot shaft
CN107762399A (en) Explosion coordinates rotary drilling rig deep layer one-step pore-creating construction method
CN115539039A (en) Method for regionalizing and improving caving coal recovery rate based on up-down combined operation of well
CN107060800A (en) A kind of shield-tunneling construction huge stone handling construction method
CN110656947A (en) Method for tunneling raised section of seabed bedrock
CN107514266A (en) Shield export & import bolt anchorage soil body construction method
CN112983258A (en) Down-the-hole hammer rapid hole forming construction method for unconsolidated rock stratum geology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151202