CN103979872B - A kind of preparation method of the U-shaped channel of the long lightweight precast concrete of 2m - Google Patents

A kind of preparation method of the U-shaped channel of the long lightweight precast concrete of 2m Download PDF

Info

Publication number
CN103979872B
CN103979872B CN201410198526.5A CN201410198526A CN103979872B CN 103979872 B CN103979872 B CN 103979872B CN 201410198526 A CN201410198526 A CN 201410198526A CN 103979872 B CN103979872 B CN 103979872B
Authority
CN
China
Prior art keywords
shaped channel
precast concrete
preparation
long
maintenance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201410198526.5A
Other languages
Chinese (zh)
Other versions
CN103979872A (en
Inventor
陶琦
卢健
刘丽佳
孙景路
张滨
司振江
李芳花
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HEILONGJIANG PROV WATER CONSERVANCY SCIENCE INST
Original Assignee
HEILONGJIANG PROV WATER CONSERVANCY SCIENCE INST
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HEILONGJIANG PROV WATER CONSERVANCY SCIENCE INST filed Critical HEILONGJIANG PROV WATER CONSERVANCY SCIENCE INST
Priority to CN201410198526.5A priority Critical patent/CN103979872B/en
Publication of CN103979872A publication Critical patent/CN103979872A/en
Application granted granted Critical
Publication of CN103979872B publication Critical patent/CN103979872B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Curing Cements, Concrete, And Artificial Stone (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

A kind of preparation method of the U-shaped channel of the long lightweight precast concrete of 2m, the preparation method that the present invention relates to a kind of 2m U-shaped channel of long lightweight precast concrete, it to solve that the precast concrete U-shaped channel comprcssive strength that existing preparation method obtains is low, anti-freezing property is poor, sound pollution is serious and can only the problem that produces of fixed-point type. Preparation method: one, preparation raw material; Two, the agitated uniform after-pouring of raw material is to being placed in the U-shaped channel mould on level ground, obtains the U-shaped channel of molding; Three, the U-shaped channel mould being loaded with the U-shaped channel of molding is transported in maintenance place, completes maintenance; Four, the U-shaped channel completing maintenance is carried out demoulding process, complete U-shaped channel and prepare. The present invention adopts reactive powder self-compacting concrete, has mould, the feature of without vibration of being automatically full of, decreases sound pollution during production and the channel smooth surface produced, and bubble is few, without honeycomb, hole etc. The present invention is for the preparation of the 2m U-shaped channel of long lightweight precast concrete.

Description

A kind of preparation method of the U-shaped channel of the long lightweight precast concrete of 2m
Technical field
The preparation method that the present invention relates to a kind of 2m U-shaped channel of long lightweight precast concrete.
Background technology
China with account for the freshwater resources in the world 6%, 9% arable land, solve the food problem accounting for the world 21% population, irrigation and water conservancy has played vital effect.
In recent years, central authorities adhere to using construction of water conservancy works as the important foundation ensureing agricultural stable development and national food security, continuous perfect policies support system, strengthen work in every dynamics, promote irrigation and water conservancy to enter new developmental stage. Within 2012, start provinces and regions, northeast four " water saving increases wholesale grain store and moves ", but to field, this " last one kilometer " is the weakest link of irrigation and water conservancy below branch canal, the problems such as ubiquity standard difference low, supporting, aging in bad repair and benefit decay, farm field irrigation drainage " last one kilometer " problem becomes increasingly conspicuous.
Along with country's attention to irrigation and water conservancy, construction of water conservancy works engineering gets more and more; The existing mode of production adopts the production technology of normal concrete vibratory compaction to prepare the U-shaped channel of precast concrete, product comprcssive strength is only 25MPa, frost resistance is only 100 times, and in production process, noise is big, and can only produce by fixed-point type, therefore, need a kind of preparation method, it is ensured that product quality, reduce sound pollution, portable production, meets engineering demand.
Summary of the invention
The invention aims to solve the precast concrete U-shaped channel comprcssive strength that existing preparation method obtains is low, anti-freezing property is poor, sound pollution is serious and can only the problem that produces of fixed-point type, and provide a kind of 2m preparation method of the U-shaped channel of long lightweight precast concrete.
The preparation method of the U-shaped channel of the long lightweight precast concrete of a kind of 2m of the present invention realizes according to the following steps:
One, 37%~40% stone, 33%~35% sand, 13%~15% cement, 5%~6% flyash, 2%~2.5% breeze, 0.2%~0.3% silica flour, 0.4%~0.5% additive, 0.2%~0.3% steel fibre and 7%~8% water are weighed by mass percentage as raw material;
Two, the raw material that step one weighs is joined in blender, be directly poured in the U-shaped channel mould being placed on level ground after stirring 2 minutes, obtain the 2m U-shaped channel of long light concrete of molding;
Three, the U-shaped channel mould of long for the 2m the being loaded with molding U-shaped channel of light concrete is transported in maintenance place, put into airtight maintenance space, pass into steam to airtight maintenance interior volume and carry out maintenance, maintenance processes is: first at room temperature quiet stop 4h, then pass to steam, the time passing into steam is 6h, the temperature in maintenance space that keeps for the 1st hour passing into steam is 45 DEG C, the temperature in maintenance space that keeps for the 2nd hour passing into steam is 60 DEG C, and keeping temperature in maintenance space after passing into the 3rd hour of steam is 75 DEG C; Open airtight maintenance space after stopping logical steam for 0.5 hour one jiao, then fully open airtight maintenance space after waiting 0.5 hour, complete whole maintenance processes, obtain the 2m U-shaped channel of long light concrete of maintenance;
Four, the 2m the completing maintenance U-shaped channel of long light concrete is carried out demoulding process, complete the preparation of the 2m U-shaped channel of long lightweight precast concrete.
Beneficial effects of the present invention:
1, adopting the U-shaped channel comprcssive strength of the long lightweight precast concrete of 2m prepared by the present invention more than 50MPa, frost resistance is more than 300 times. The durability index of the U-shaped channel of common precast concrete is 25MPa, frost resistance 100 times,
2, the reactive powder self-compacting concrete that the present invention uses when producing the U-shaped channel of the long lightweight precast concrete of 2m, has mould, the feature of without vibration of being automatically full of, decrease sound pollution during production, and the channel smooth surface produced, bubble is few, without honeycomb, hole etc.
3, the present invention is not by the restriction of production site, can follow project site at any time and convert, it is achieved the portable mode of production, can improve at any time or reduce yield, improve production efficiency, reduce waste.
Accompanying drawing explanation
Fig. 1 is the overall structure schematic diagram of the 2m U-shaped channel of long lightweight precast concrete that step 4 of the present invention prepares;
Fig. 2 is the end view of the 2m U-shaped channel of long lightweight precast concrete that step 4 of the present invention prepares.
Detailed description of the invention
Detailed description of the invention one: the preparation method of the U-shaped channel of the long lightweight precast concrete of a kind of 2m of present embodiment realizes according to the following steps:
One, 37%~40% stone, 33%~35% sand, 13%~15% cement, 5%~6% flyash, 2%~2.5% breeze, 0.2%~0.3% silica flour, 0.4%~0.5% additive, 0.2%~0.3% steel fibre and 7%~8% water are weighed by mass percentage as raw material;
Two, the raw material that step one weighs is joined in blender, be directly poured in the U-shaped channel mould being placed on level ground after stirring 2 minutes, obtain the 2m U-shaped channel of long light concrete of molding;
Three, the U-shaped channel mould of long for the 2m the being loaded with molding U-shaped channel of light concrete is transported in maintenance place, put into airtight maintenance space, pass into steam to airtight maintenance interior volume and carry out maintenance, maintenance processes is: first at room temperature quiet stop 4h, then passing to steam, the time passing into steam is 6h, and wherein within the 1st hour, keeping temperature in maintenance space is 45 DEG C, within 2nd hour, keeping temperature in maintenance space is 60 DEG C, and keeping temperature in maintenance space after the 3rd hour is 75 DEG C;Open airtight maintenance space after stopping logical steam for 0.5 hour one jiao, then fully open airtight maintenance space after waiting 0.5 hour, complete whole maintenance processes, obtain the 2m U-shaped channel of long light concrete of maintenance;
Four, the 2m the completing maintenance U-shaped channel of long light concrete is carried out demoulding process, complete the preparation of the 2m U-shaped channel of long lightweight precast concrete;
Described stone is 5mm~20mm continuous grading, and the modulus of fineness of described sand is 2.1.
The room temperature described in production technology of the U-shaped channel of the long lightweight precast concrete of present embodiment 2m is 20 DEG C.
The production technology of the U-shaped channel of the long lightweight precast concrete of present embodiment 2m mainly through choosing applicable raw material, dispensing stirring, build to steps such as mould, steam curing, dismounting moulds and complete, the mix-design of reactive powder self-compacting concrete is carried out after wherein choosing applicable raw material, according to raw-material Mass adjust-ment match ratio, thus reaching to ensure that production is smoothed out, product quality meets the target of design standard.
Adopting the U-shaped channel comprcssive strength of the long lightweight precast concrete of 2m prepared by present embodiment more than 50MPa, frost resistance is more than 300 times. The durability index of the U-shaped channel of common precast concrete is 25MPa, frost resistance 100 times,
The reactive powder self-compacting concrete that present embodiment uses when producing the U-shaped channel of the long lightweight precast concrete of 2m, has mould, the feature of without vibration of being automatically full of, decrease sound pollution during production, and the channel smooth surface produced, bubble is few, without honeycomb, hole etc.
Present embodiment by the restriction of production site, can not followed project site at any time and convert, it is achieved the portable mode of production, can improve at any time or reduce yield, improve production efficiency, reduce waste.
Detailed description of the invention two: present embodiment and detailed description of the invention one are numbered PO425 the difference is that cement described in step one. Other step and parameter and detailed description of the invention one are identical.
Detailed description of the invention three: present embodiment and detailed description of the invention one or two are I grade the difference is that the rank of the flyash described in step one. Other step and parameter and detailed description of the invention one or two are identical.
Detailed description of the invention four: one of present embodiment and detailed description of the invention one to three are 10mm~12mm the difference is that the length of the steel fibre described in step one. Other step and one of parameter and detailed description of the invention one to three are identical.
Detailed description of the invention five: one of present embodiment and detailed description of the invention one to four are made up of water reducer, air entraining agent, suspending agent and thickening agent the difference is that the additive described in step one. Other step and one of parameter and detailed description of the invention one to four are identical.
Detailed description of the invention six: the 2m U-shaped channel of long lightweight precast concrete that present embodiment and detailed description of the invention one obtain the difference is that step 4 is linked into an integrated entity by two side 1 and bottom land 2, the outer 1-2 of two side 1 is perpendicular to horizontal plane, the interior of two side forms U-shaped cross section diagonally downward along 1-1, the bottom in U-shaped cross section is parallel to horizontal plane, end face at the U-shaped channel two ends of the long lightweight precast concrete of 2m is equipped with U-shaped watertight rubber groove 3, and the length of the U-shaped channel of the long lightweight precast concrete of 2m is 2000mm.
The interior of present embodiment two side forms U-shaped cross section diagonally downward along 1-1, and wherein the interior angle α along 1-1 Yu vertical of sidewall is 2.3 °.
Embodiment one: the preparation method of the U-shaped channel of the long lightweight precast concrete of a kind of 2m of this enforcement realizes according to the following steps:
One, 906KG stone, 819KG sand, 325KG cement 125KG flyash, 50KG breeze, 5KG silica flour, 10KG additive, 5KG steel fibre and 175KG water are weighed as raw material;
Two, the raw material that step one weighs is joined in blender, be directly poured in the U-shaped channel mould being placed on level ground after stirring 2 minutes, obtain the 2m U-shaped channel of long light concrete of molding;
Three, the U-shaped channel mould of long for the 2m the being loaded with molding U-shaped channel of light concrete is transported in maintenance place, put into airtight maintenance space, pass into steam to airtight maintenance interior volume and carry out maintenance, maintenance processes is: first at room temperature quiet stop 4h, then passing to steam, the time passing into steam is 6h, and wherein within the 1st hour, keeping temperature in maintenance space is 45 DEG C, within 2nd hour, keeping temperature in maintenance space is 60 DEG C, and keeping temperature in maintenance space after the 3rd hour is 75 DEG C; Open airtight maintenance space after stopping logical steam for 0.5 hour one jiao, then fully open airtight maintenance space after waiting 0.5 hour, complete whole maintenance processes, obtain the 2m U-shaped channel of long light concrete of maintenance;
Four, the 2m the completing maintenance U-shaped channel of long light concrete is carried out demoulding process, complete the preparation of the 2m U-shaped channel of long lightweight precast concrete.
U-shaped channel mould selected by the present embodiment is of a size of 400*400*2000mm, the length of mould is 2000mm, the 2m U-shaped channel of long lightweight precast concrete that the demoulding obtains transports finished product district piling after quality inspection, packing and deposits, the comprcssive strength of the U-shaped channel of the long lightweight precast concrete of product 2m reaches more than 50MPa, and concrete parameters reaches C50F300 level (SL352-2006 concrete for hydraulic structure testing regulations).

Claims (5)

1. the preparation method of the 2m U-shaped channel of long lightweight precast concrete, it is characterised in that the preparation method of the U-shaped channel of the long lightweight precast concrete of 2m realizes according to the following steps:
One, 37%~40% stone, 33%~35% sand, 13%~15% cement, 5%~6% flyash, 2%~2.5% breeze, 0.2%~0.3% silica flour, 0.4%~0.5% additive, 0.2%~0.3% steel fibre and 7%~8% water are weighed by mass percentage as raw material;
Two, the raw material that step one weighs is joined in blender, be directly poured in the U-shaped channel mould being placed on level ground after stirring 2 minutes, obtain the 2m U-shaped channel of long light concrete of molding;
Three, the U-shaped channel mould of long for the 2m the being loaded with molding U-shaped channel of light concrete is transported in maintenance place, put into airtight maintenance space, pass into steam to airtight maintenance interior volume and carry out maintenance, maintenance processes is: first at room temperature quiet stop 4h, then pass to steam, the time passing into steam is 6h, the temperature in maintenance space that keeps for the 1st hour passing into steam is 45 DEG C, the temperature in maintenance space that keeps for the 2nd hour passing into steam is 60 DEG C, and keeping temperature in maintenance space after passing into the 3rd hour of steam is 75 DEG C; Open airtight maintenance space after stopping logical steam for 0.5 hour one jiao, then fully open airtight maintenance space after waiting 0.5 hour, complete whole maintenance processes, obtain the 2m U-shaped channel of long light concrete of maintenance;
Four, the 2m the completing maintenance U-shaped channel of long light concrete is carried out demoulding process, complete the preparation of the 2m U-shaped channel of long lightweight precast concrete;
The 2m U-shaped channel of long lightweight precast concrete that step 4 obtains is linked into an integrated entity by two side (1) and bottom land (2), the outer (1-2) of two side (1) is perpendicular to horizontal plane, the interior edge (1-1) of two side forms U-shaped cross section diagonally downward, the bottom in U-shaped cross section is parallel to horizontal plane, end face at the U-shaped channel two ends of the long lightweight precast concrete of 2m is equipped with U-shaped watertight rubber groove (3), and the length of the U-shaped channel of the long lightweight precast concrete of 2m is 2000mm; The interior edge (1-1) of the long lightweight precast concrete of the 2m U-shaped channel two side that described step 4 obtains forms U-shaped cross section diagonally downward, and wherein the interior edge (1-1) of sidewall and the angle α of vertical are 2.3 °.
2. the preparation method of a kind of 2m according to claim 1 U-shaped channel of long lightweight precast concrete, it is characterised in that cement described in step one be numbered PO42.5.
3. the preparation method of a kind of 2m according to claim 1 U-shaped channel of long lightweight precast concrete, it is characterised in that the rank of the flyash described in step one is I grade.
4. the preparation method of a kind of 2m according to claim 1 U-shaped channel of long lightweight precast concrete, it is characterised in that the length of the steel fibre described in step one is 10mm~12mm.
5. the preparation method of a kind of 2m according to claim 1 U-shaped channel of long lightweight precast concrete, it is characterised in that the additive described in step one is made up of water reducer, air entraining agent, suspending agent and thickening agent.
CN201410198526.5A 2014-05-12 2014-05-12 A kind of preparation method of the U-shaped channel of the long lightweight precast concrete of 2m Expired - Fee Related CN103979872B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410198526.5A CN103979872B (en) 2014-05-12 2014-05-12 A kind of preparation method of the U-shaped channel of the long lightweight precast concrete of 2m

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410198526.5A CN103979872B (en) 2014-05-12 2014-05-12 A kind of preparation method of the U-shaped channel of the long lightweight precast concrete of 2m

Publications (2)

Publication Number Publication Date
CN103979872A CN103979872A (en) 2014-08-13
CN103979872B true CN103979872B (en) 2016-06-15

Family

ID=51272077

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410198526.5A Expired - Fee Related CN103979872B (en) 2014-05-12 2014-05-12 A kind of preparation method of the U-shaped channel of the long lightweight precast concrete of 2m

Country Status (1)

Country Link
CN (1) CN103979872B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106045424A (en) * 2016-05-25 2016-10-26 象州县科学技术局 Method for producing prefabricated member of concrete ditch by using construction waste
CN106007530B (en) * 2016-05-25 2018-08-10 句容联众科技开发有限公司 Frost-resistant concrete
CN106087908A (en) * 2016-06-17 2016-11-09 新疆金土地水泥制品有限公司 Assembled channel precast segment
CN106495580B (en) * 2016-10-21 2019-05-28 长江宜昌航道工程局 A kind of steel fiber reinforced concrete structure water-permeable frame method for prefabricating
CN108503299A (en) * 2017-02-28 2018-09-07 北京城泰混凝土制品有限公司 Strong intensity steel fiber reinforced concrete
CN107471426A (en) * 2017-08-22 2017-12-15 潘春光 A kind of production method of water channel corner prefabricated component
CN110468685A (en) * 2019-09-06 2019-11-19 张进辉 The joint seal device of U-shaped Prefabricated aqueduct
CN110468684A (en) * 2019-09-06 2019-11-19 张进辉 The joint seal device of U-shaped Prefabricated aqueduct
CN116572374B (en) * 2023-06-01 2024-04-23 广东省水利水电第三工程局有限公司 Preparation method of hydraulic concrete prefabricated sill assembled component

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2154870Y (en) * 1992-03-09 1994-02-02 梁觉明 U-shape section concrete channel prefabricated components
CN1451626A (en) * 2002-04-17 2003-10-29 杨果林 High strength steel fibre concrete and making method thereof
CN101818504A (en) * 2009-11-06 2010-09-01 长江大学 The manufacture method of a kind of manhole cover or water drain grid cover
CN103224356A (en) * 2013-02-07 2013-07-31 黄贺明 Green environmentally-friendly powder reinforced concrete water delivery pipe

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56149361A (en) * 1980-04-15 1981-11-19 Matsushita Electric Works Ltd Manufacture of fiber reinforced cement product
CZ2010855A3 (en) * 2010-11-23 2012-05-30 Rázl@Ivan Cement composites resistant to acids and high temperature values and process for preparing thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2154870Y (en) * 1992-03-09 1994-02-02 梁觉明 U-shape section concrete channel prefabricated components
CN1451626A (en) * 2002-04-17 2003-10-29 杨果林 High strength steel fibre concrete and making method thereof
CN101818504A (en) * 2009-11-06 2010-09-01 长江大学 The manufacture method of a kind of manhole cover or water drain grid cover
CN103224356A (en) * 2013-02-07 2013-07-31 黄贺明 Green environmentally-friendly powder reinforced concrete water delivery pipe

Also Published As

Publication number Publication date
CN103979872A (en) 2014-08-13

Similar Documents

Publication Publication Date Title
CN103979872B (en) A kind of preparation method of the U-shaped channel of the long lightweight precast concrete of 2m
CN105041336A (en) Ultra-high performance hybrid fiber concrete shield segment and preparation method thereof
CN102010160A (en) Crack-resistant abrasion-resistant hydraulic concrete and preparation method thereof
CN102153321B (en) High-titanium slag well cover and production method thereof
US9296125B2 (en) Systems and methods of concrete apparatus with incorporated lifter
CN103541289A (en) Colored high-titanium heavy slag permeable pavement brick and production method thereof
CN103358387A (en) Production technology of anti-corrosion prefabricated reinforced concrete inspection well
CN102503307A (en) Novel high-strength expansive concrete
CN104230256A (en) Self-compaction concrete and production technique of prefabricated municipal quadrate culvert component
CN101775878A (en) Cement tile and manufacturing method thereof
CN105174836A (en) Ultra-high strength active powder concrete and preparation method therefor
CN102674759A (en) EPS (Expandable Polystyrene) light aggregate concrete thermal insulation hollow block and construction method thereof
CN104909643A (en) Assembly type lightweight thin wall integrated pipe gallery and production method thereof
CN103896521B (en) A kind of preparation method of canal seepage control water delivery tank
CN106187270A (en) A kind of polymer pervious concrete for building sponge city
CN108409201B (en) Concrete with low thermal expansion coefficient
CN104803637A (en) Preparation method of centrifugal concrete water supply-drainage pipe capable of reducing using amount of binding material
CN102139506B (en) Production technique of large-size artificial culture stone
CN103896531A (en) High-strength concrete tubular pile doped with levigated rice hull ash and production method of tubular pile
CN208293723U (en) A kind of big component of drainage inspection well precast assembly and its production mold
CN102765901B (en) High-performance hydrofluoric acid-resistance artificial functional composite plate and preparation method thereof
CN207874530U (en) Mix the system of remaining slurry production sand autoclave aerated concrete building block
CN206220130U (en) A kind of manhole cover
CN106316328A (en) Method for producing autoclaved aerated concrete building blocks
CN204590395U (en) A kind of heat-insulating wall block

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Tao Qi

Inventor after: Lu Jian

Inventor after: Liu Lijia

Inventor after: Sun Jinglu

Inventor after: Zhang Bin

Inventor after: Si Zhenjiang

Inventor after: Li Fanghua

Inventor before: Tao Qi

Inventor before: Zhang Bin

Inventor before: Si Zhenjiang

Inventor before: Li Fanghua

Inventor before: Liu Lijia

Inventor before: Sun Jinglu

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160615

Termination date: 20170512