Mounting correction tool for protection corner angle of frame column and manufacturing method thereof Download PDF

Info

Publication number
CN103967042B
CN103967042B CN201310034608.1A CN201310034608A CN103967042B CN 103967042 B CN103967042 B CN 103967042B CN 201310034608 A CN201310034608 A CN 201310034608A CN 103967042 B CN103967042 B CN 103967042B
Authority
CN
China
Prior art keywords
screw rod
frame column
flitch
length
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310034608.1A
Other languages
Chinese (zh)
Other versions
CN103967042A (en
Inventor
邱战武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201310034608.1A priority Critical patent/CN103967042B/en
Publication of CN103967042A publication Critical patent/CN103967042A/en
Application granted granted Critical
Publication of CN103967042B publication Critical patent/CN103967042B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a mounting correction tool for a protection corner angle of a frame column. The tool comprises a screw rod (1), a square pillar (2) and two clamping pieces (3). The tool is characterized in that the screw rod (1) is a screw rod with the diameter of 12 to 16mm, the screw rod is made of round steel, the length of the screw rod is 200mm longer than that of the sectional dimension of the mounted frame column, threads which are formed in both ends of the screw rod are matched with fixing nuts (4), and a plurality of small holes for allowing iron nails (6) to pass through are drilled in the middle part; the length of the square pillar (2) is 5mm longer than that of the sectional dimension of the mounted frame column, and the small holes of the screw rod (1),through which the iron nails (6) pass, are connected and fixed with the screw rod (1); the clamping pieces (3) comprise two pairs of parallel steel bars (7,8) which are mutually vertical to form a well-shaped fixing weld to be welded and fixed with a steel plate (9), and a through hole (10) is formed in the center of the steel plate; the two clamping pieces (3) are arranged at both ends of the screw rod (1) in a sleeving manner and are screwed tightly and fixed by the nuts (4).

Description

A kind of frame column edge-protecting angle iron installs aligning tool and preparation method thereof
Technical field
The present invention relates to a kind of aligning tool, specifically, be a kind of frame column edge-protecting angle iron install aligning tool and its Manufacture method.
Background technology
In building engineering construction, it is frequently encountered by large-scale long line scaoffold formula equipment Foundations, it is steel reinforced concrete frame Frame structure.Due to often having haulage vehicle to pass through on reinforced concrete frame structure side, it is that bearer bar trestle seamed edge is not subject to car Collsion damage, needs to add edge-protecting angle iron to scaoffold frame column corner.When frame column edge-protecting angle iron is installed, adopt one As correcting mode is installed, draw to resist stubbornly with manually life and adjust steel bar framework column dimension, this method is easy to operate, laborious, time-consuming Take a lot of trouble again, and be difficult to ensure installation quality.
Therefore known frame column edge-protecting angle iron is installed bearing calibration and be there is above-mentioned a variety of inconvenience and problem.
Content of the invention
The purpose of the present invention, is to propose a kind of make that edge-protecting angle iron is quick, be accurately installed in place and reduce workmen's The frame column edge-protecting angle iron of labor intensity installs aligning tool.
Edge-protecting angle iron is made quickly, to be accurately installed in place and reduce constructor it is another object of the present invention to proposing one kind The manufacture method that the frame column edge-protecting angle iron of the labor intensity of member installs aligning tool.
For achieving the above object, the technical solution of the present invention is:
A kind of frame column edge-protecting angle iron installs aligning tool, including a screw rod, a flitch and two intermediate plates it is characterised in that:
Described screw rod is the screw rod of the round steel making of a diameter 12~16mm, and its length is than the cross-section of frame column installed The long 200mm of size, the two ends of screw rod are provided with screw thread, and are furnished with fixing nut, be drilled with several iron nail can be allowed to pass through in the middle part of it Aperture;
The length 5mm longer than the cross-section of frame column size installed of described flitch, the aperture of its screw rod being passed through with iron nail It is connected with screw rod;
Described intermediate plate include two pairs of parallel rebar be mutually perpendicular to into groined type admittedly weld Zai Yu mono- center carry through hole steel plate It is welded and fixed;Described two intermediate plates are linked in the two ends of screw rod, then are fixed with nut screwing clamping.
The frame column edge-protecting angle iron of the present invention is installed aligning tool and can also be come further in fact using following technical measures Existing.
Aforesaid frame column edge-protecting angle iron installs aligning tool, and wherein said steel plate is weldingly fixed on two pairs of parallel rebar phases Mutually vertically become the center of groined type component.
A kind of frame column edge-protecting angle iron installs the manufacture method of aligning tool it is characterised in that comprising the following steps:
A, making screw rod
Using the round steel of a diameter 12~16mm, length 200mm longer than cross-section of frame column, two ends 100mm length model Enclose and mantle fiber is carried out using die head threading machine become screw thread, form a screw rod, screw rod two configures locking nut, and the drilled in middle in screw rod Several can allow the aperture that iron nail passes through;
B, making flitch
One flitch is provided, makes the length 5mm longer than the cross-section of frame column size installed of described flitch;
C, two intermediate plates of making
Described intermediate plate include two pairs of parallel rebar be mutually perpendicular to into groined type admittedly weld Zai Yu mono- center carry through hole steel plate It is welded and fixed, described steel plate is weldingly fixed on the center that two pairs of parallel rebar are mutually perpendicular to into groined type component;
D, assembling frame column edge-protecting angle iron install aligning tool
Some iron nails are provided, and bored from the middle part of screw rod several can allow and squeeze into the aperture that iron nail passes through, until Hammer into flitch to fix;Two intermediate plates made first are inserted in the two ends of screw rod by through hole, then are screwed into respective nut.
After technique scheme, the frame column edge-protecting angle iron of the present invention is installed aligning tool and is had advantages below:
1st, structure is simple, easy to make;
2nd, correct operation is directly perceived, easy, reduces operation sequence and the labor intensity of site operation personnel, improves and produce effect Rate;
3rd, workable, so that edge-protecting angle iron installation site is met the requirements, ensure frame column presentation quality;
4th, realize quick, precision installation, save the construction period, save construction cost.
Brief description
Fig. 1 is the structural representation of the frame column edge-protecting angle iron installation aligning tool of the present invention;
Fig. 2 is the enlarged front view of intermediate plate in Fig. 1;
Fig. 3 is the side view of Fig. 2;
Fig. 4 is the use state schematic diagram of the frame column edge-protecting angle iron installation aligning tool of the present invention.
In figure:1 screw rod, 2 flitches, 3 intermediate plates, 4 nuts, 5 screw threads, 6 iron nails, 7 first pairs of reinforcing bars, 8 second pairs of reinforcing bars, 9 steel Plate, 10 through holes, 11 edge-protecting angle irons, 12 edge-protecting angle irons fix reinforcing bar, 13 frame column reinforcing bars.
Specific embodiment
With reference to embodiments and its accompanying drawing illustrates further to the present invention.
Referring now to Fig. 1~Fig. 3, Fig. 1 is the structural representation of the frame column edge-protecting angle iron installation aligning tool of the present invention, Fig. 2 is the enlarged front view of intermediate plate in Fig. 1, and Fig. 3 is Fig. 2 side view.As illustrated, described screw rod 1 is a diameter 14mm The screw rod that round steel makes, its length 200mm longer than the cross-section of frame column size installed, the two ends of screw rod are provided with screw thread, and join There is fixing nut 4, in the middle part of it, be drilled with the aperture that several can allow iron nail 6 pass through;
The length 5mm longer than the cross-section of frame column size installed of described flitch 2, the screw rod 1 that it is passed through with iron nail 6 little Hole is connected with screw rod 1;
Described intermediate plate 3 include two pairs of parallel rebar 7,8 be mutually perpendicular to into groined type admittedly weld Zai Yu mono- center carry through hole 10 Steel plate 9 be welded and fixed, described steel plate 9 is weldingly fixed on the center that two pairs of parallel rebar 7,8 are mutually perpendicular to into groined type component; Described two intermediate plates 3 are linked in the two ends of screw rod 1, then tighten fixation with nut 4.
The frame column edge-protecting angle iron of the present invention installs aligning tool manufacture method:Using the round steel of a diameter 14mm, long Degree 200mm longer than cross-section of frame column, two ends 100mm length range carries out mantle fiber using die head threading machine and becomes screw thread, forms a spiral shell Bar, nut is worn at screw rod two, and bores three apertures in the middle.With two 150mm length, diameter 18mm reinforcing bar, and two straight Footpath 6mm, the reinforcing bar of long 80mm are welded into intermediate plate frame member, using one piece of 50mm × 50mm × 5mm steel plate, have in the middle of steel plate The circular hole of diameter 18mm, and it is welded on formation intermediate plate in the middle part of intermediate plate skeleton, intermediate plate is arranged on screw rod two ends for totally two.In round steel Nailed on by aperture in the middle part of round steel, fixed the hard lumps of wood with three iron nails in portion, lumps of wood length is slightly big than cross-section of frame column size 5mm, wide 100mm, thick 50mm, form strut and also serve as handle.
Fig. 4 is the use state schematic diagram of the frame column edge-protecting angle iron installation aligning tool of the present invention.The framework of the present invention Post edge-protecting angle iron installs aligning tool using method:Determine in-site installation position before edge-protecting angle iron is installed, then by safe edge Angle steel is placed on the outer 5mm of hookup wire, then adopts edge-protecting angle iron to install aligning tool, by edge-protecting angle iron card to two intermediate plates, adopts With spanner, aligning tool two ends nut is tightened respectively, during tightening nut, angle steel gradually moves, and using ribbon is When control angle steel positioning, after reaching requirement, stop tighten nut, carry out being welded and fixed angle steel.
In frame column edge-protecting angle iron installation, there is the universal suitability, there is extensive popularizing application prospect.
Above example is used for illustrative purposes only, rather than limitation of the present invention, about the technology people of technical field Member, without departing from the spirit and scope of the present invention, can also make various conversion or change.Therefore, all equivalent Technical scheme also should belong to scope of the invention, should be limited by each claim.

Claims (3)

1. a kind of frame column edge-protecting angle iron installs aligning tool, including a screw rod(1), a flitch(2)With two intermediate plates(3), it is special Levy and be:
Described screw rod(1)It is the screw rod that the round steel of a diameter 12~16mm makes, its length is than the cross-section of frame column installed The long 200mm of size, the two ends of screw rod are provided with screw thread, and are furnished with fixing nut(4), it is drilled with several in the middle part of it and can allow iron nail(6) The aperture passing through;
Described flitch(2)Length 5mm longer than the cross-section of frame column size installed, it uses iron nail(6)Through screw rod(1)Little Hole and screw rod(1)It is connected;
Described intermediate plate(3)Including two to parallel rebar(7,8)It is mutually perpendicular to into groined type and admittedly weld Zai Yu mono- center with through hole (10)Steel plate(9)It is welded and fixed;Described two intermediate plates(3)It is linked in screw rod(1)Two ends, then use nut(4)Tighten fixation.
2. frame column edge-protecting angle iron as claimed in claim 1 installs aligning tool it is characterised in that described steel plate(9)Welding It is fixed on two pairs of parallel rebar(7,8)It is mutually perpendicular to into the center of groined type component.
3. a kind of frame column edge-protecting angle iron installs the manufacture method of aligning tool it is characterised in that comprising the following steps:
A, making screw rod(1)
Using the round steel of a diameter 12~16mm, length 200mm longer than cross-section of frame column, two ends 100mm length range is adopted Carry out mantle fiber with die head threading machine and become screw thread, form a screw rod(1), screw rod two configures locking nut, and the drilled in middle in screw rod Several can allow iron nail(6)The aperture passing through;
B, making flitch(2)
One flitch is provided(2), make described flitch(2)Length 5mm longer than the cross-section of frame column size installed;
C, two intermediate plates of making(3)
Described intermediate plate(3)Including two to parallel rebar(7,8)It is mutually perpendicular to into groined type and admittedly weld Zai Yu mono- center with through hole (10)Steel plate(9)It is welded and fixed, described steel plate(9)It is weldingly fixed on two pairs of parallel rebar(7,8)It is mutually perpendicular to into groined type The center of component;
D, assembling frame column edge-protecting angle iron install aligning tool
Some iron nails are provided(6), and bored from the middle part of screw rod several can allow iron nail(6)Squeeze in the aperture passing through, directly To hammering into flitch(2)Fixing;Two intermediate plates made(3)By through hole(10)First it is inserted in screw rod(1)Two ends, then be screwed into Respective nut(4).
CN201310034608.1A 2013-01-30 2013-01-30 Mounting correction tool for protection corner angle of frame column and manufacturing method thereof Active CN103967042B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310034608.1A CN103967042B (en) 2013-01-30 2013-01-30 Mounting correction tool for protection corner angle of frame column and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310034608.1A CN103967042B (en) 2013-01-30 2013-01-30 Mounting correction tool for protection corner angle of frame column and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN103967042A CN103967042A (en) 2014-08-06
CN103967042B true CN103967042B (en) 2017-02-15

Family

ID=51237011

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310034608.1A Active CN103967042B (en) 2013-01-30 2013-01-30 Mounting correction tool for protection corner angle of frame column and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN103967042B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107524149B (en) * 2017-07-31 2020-02-11 北方工业大学 Assembled soil nailing wall and construction and dismantling method thereof
CN109955101B (en) * 2017-12-26 2021-08-17 河南森源重工有限公司 Pump truck turret and machining method thereof
CN110340555B (en) * 2019-07-12 2021-03-09 浙江东南网架股份有限公司 Welding construction method for linear multi-cavity steel plate and steel bar angle steel truss combined component
CN110340556B (en) * 2019-07-12 2021-03-19 浙江东南网架股份有限公司 Welding construction method for combined component of inverted-Y-shaped steel plate and steel bar angle steel truss

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU672314A1 (en) * 1975-03-31 1979-07-05 Semenets Aleksej N Jig for interim securing and checking out the elements of reinforced-concrete frameworks of buildings
CN101956458A (en) * 2010-11-05 2011-01-26 中国建筑第八工程局有限公司 Construction method of overlong and superhigh single-side fair-faced concrete wall
CN102409865A (en) * 2011-08-17 2012-04-11 安徽富煌钢构股份有限公司 Mounting and measurement-correcting structure for multi-storey steel structured column
CN202509786U (en) * 2011-12-26 2012-10-31 上海市机械施工有限公司 Temporary-connection tool piece with bidirectional regulation function
CN202644567U (en) * 2012-06-26 2013-01-02 华丰建设股份有限公司 Concrete foundation for fixing mechanical equipment

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU672314A1 (en) * 1975-03-31 1979-07-05 Semenets Aleksej N Jig for interim securing and checking out the elements of reinforced-concrete frameworks of buildings
CN101956458A (en) * 2010-11-05 2011-01-26 中国建筑第八工程局有限公司 Construction method of overlong and superhigh single-side fair-faced concrete wall
CN102409865A (en) * 2011-08-17 2012-04-11 安徽富煌钢构股份有限公司 Mounting and measurement-correcting structure for multi-storey steel structured column
CN202509786U (en) * 2011-12-26 2012-10-31 上海市机械施工有限公司 Temporary-connection tool piece with bidirectional regulation function
CN202644567U (en) * 2012-06-26 2013-01-02 华丰建设股份有限公司 Concrete foundation for fixing mechanical equipment

Also Published As

Publication number Publication date
CN103967042A (en) 2014-08-06

Similar Documents

Publication Publication Date Title
CN203452204U (en) Connecting node of prefabricated hollow steel-reinforced concrete column and steel girder
CN101538939B (en) Construction method for preset nut type steel-reinforced concrete compound pier template fixing device
CN103967042B (en) Mounting correction tool for protection corner angle of frame column and manufacturing method thereof
CN103437425A (en) Connecting joint of prefabricated hollow steel-reinforced concrete column and steel beam and construction method
CN202913420U (en) Reusable positioning device for installing foundation bolts
CN202248298U (en) Node of steel reinforced concrete framework
CN202081516U (en) Node structure for solid-web section steel concrete column and reinforced concrete beam
CN107503473A (en) A kind of tool-type rectangular column steel bar positioning fixture
CN112796514A (en) Masonry corner constructional column template shaping and reinforcing device and construction method
CN206917265U (en) A kind of adjustable small bore beam side reinforcement tools
CN110005073A (en) A kind of fixed built-in fitting of non-solder plate and its fixing means
CN113550431B (en) Annular steel plate type stirrup for beam column joint area of stiff structure and construction method of annular steel plate type stirrup
CN205444456U (en) Precast concrete lotus root roof beam rebar positioning board
CN106401179A (en) Novel adjustable beam clamp
CN201401010Y (en) Fixing device for preset nut type steel reinforced concrete combined column template
CN203603446U (en) Clamping-groove-type fixing device for H-section steel of cantilever
CN202209046U (en) Wall connecting rod for external scaffold
CN204001802U (en) A kind of fence assembly and adopt this fence assembly and the construction protection railing that forms
CN206752855U (en) A kind of adjustable frame post reinforcing bar spacer ferrule
CN102926536A (en) Template unilateral reinforcement combination tool and template unilateral reinforcement construction method
CN216195411U (en) Assembled steel frame structure
CN206220492U (en) A kind of new adjustable beam fixture
CN210421443U (en) Non-welding flat plate fixing embedded part
CN209704012U (en) The formwork erection device of steel column cornerite
CN104481127A (en) Rigidly-connected and high-strength die plate supporting system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant