CN103955815A CN201410194151.5A CN201410194151A CN103955815A CN 103955815 A CN103955815 A CN 103955815A CN 201410194151 A CN201410194151 A CN 201410194151A CN 103955815 A CN103955815 A CN 103955815A
Authority
CN
China
Prior art keywords
stock
transformer substation
goods
management system
portable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410194151.5A
Other languages
Chinese (zh)
Inventor
朱皆悦
殷志良
冷超
王和杰
闫全全
刘志龙
刘志英
刘斯佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Shanghai Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Shanghai Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Shanghai Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410194151.5A priority Critical patent/CN103955815A/en
Publication of CN103955815A publication Critical patent/CN103955815A/en
Pending legal-status Critical Current

Links

Landscapes

  • Warehouses Or Storage Devices (AREA)

Abstract

The invention relates to a portable transformer substation inventory material management system and method. The portable transformer substation inventory material management system comprises a portable scanning instrument (1), a server (2) and a printer (3). The portable scanning instrument (1) comprises a scanning unit (11), a wireless transmit-receive unit (12) and a control circuit (13), wherein the scanning unit (11) and the wireless transmit-receive unit (12) are both connected with the control circuit (13), the input end of the printer (3) is connected with the server (2), and the portable scanning instrument (1) is connected with the server (2) through the wireless transmit-receive unit (12) and a wireless network. After the portable scanning instrument (1) scans the personnel information and the object information and finishes corresponding operations, the data are sent to the server, the server records the data, and the printer prints related information. Compared with the prior art, the portable transformer substation inventory material management system and method have the advantages of being easy and convenient to use and the like.

Description

A kind of Portable transformer substation stock in storage management system and method
Technical field
The present invention relates to a kind of material Management System and method, especially relate to a kind of Portable transformer substation stock in storage management system and method.
Background technology
In transformer station, often there is no special stock in storage management system, no matter be that flow process is declared in buying, the warehouse-in of standby redundancy etc., borrow and to receive, outbound flow process or the warehouse-in of Work tool, verification, the flow process such as to scrap and all rely on manual amendment EXECL form to file even manually to fill in the form that minute book files to manage, not only inefficiency but also as easy as rolling off a log going wrong, cause the situation of goods and materials loss, managerial confusion to occur.And existing material Management System is not suitable for transformer station yet.
The Chinese patent that for example application number is 201310112270.7 discloses a kind of Power Material storage management method and system, and the attribute management system that the method builds based on AWT, identifies the attribute of all material equipments in Power Material warehouse; The attribute of all material equipments in the Power Material warehouse that material Management System provides according to attribute management system, call 3 d model library, reality scene in Power Material warehouse is reappeared in the virtual interface of the full-scale three-dimensional model in the Power Material warehouse based on RIA, for supvr, check.This management system is used three-dimensional model, when improving goods and materials statement, also increase the requirement to system hardware configuration, also increased virtually cost investment, although and show and can increase the intuitivism apprehension of outsider to electric goods and materials with three-dimensional model, but for insider, can disturb their memory on the contrary, impracticable.
For another example the Chinese patent that application number is 201310095473.X discloses a kind of Material Resource Management Systems, this management system comprises purchase order, receiving inspection list and storage bill, in purchase order, be provided with the first selection option, first selects option to be provided with supplier's shipment date, haulage time, proving time and dilivery date, be the shipment date dilivery date, haulage time, proving time sum, receiving inspection has set up the second selection option, second selects option to comprise proving time, storage bill comprises that the 3rd selects option, the 3rd selects option to comprise the warehouse-in date, the warehouse-in date is after proving time.By the way, Material Resource Management Systems of the present invention has made up the deficiency of original ERP system, and slip up still less dilivery date, can not cause the delay of production.But this invents most crucial problem, i.e. material management in routine use in also unresolved transformer station material management.
Summary of the invention
Object of the present invention is exactly that a kind of easy to use, scanner mobile portable transformer station stock in storage management system and method are provided in order to overcome the defect that above-mentioned prior art exists.
Object of the present invention can be achieved through the following technical solutions:
A kind of Portable transformer substation stock in storage management system, this management system comprises portable scanner, server and printer, described portable scanner comprises scanning element, wireless transmit/receive units and control circuit, described scanning element, wireless transmit/receive units are all connected with control circuit, the input end of described printer is connected with server, and described scanner is connected with server with wireless network by wireless transmit/receive units;
Described portable scanner, by after personal information, Item Information and the respective operations of scanning, sends the data to server, and server carries out record to data, and printer is printed relevant information.
Described scanner also comprises keyboard and display, and described scanning element, wireless transmit/receive units, keyboard and display are connected with control circuit respectively.
Described scanning element scanning recognition bar code and employee's identification card.
Described keyboard comprises numeric keyboard of mobile telephone and seven function keys of standard, and described seven function keys are corresponding respectively puts in storage, use, give back, receive, transfer, verification and scrap operation.
In described server, be provided with database, described database comprises declares goods and materials table, stock in storage form and operation sheet, described in to declare goods and materials table and stock in storage form associated by materiel code.
A Portable transformer substation stock in storage management method, the method comprises the following steps:
101) by after cargo number, by printer, print bar code;
102) by staff, bar code is attached on goods and materials;
103) by staff, goods and materials are put into warehouse;
104) carry out routine use operation.
Described 12 bit numbers that are encoded to, wherein, the classification of the 1st to 2 bit representation goods and materials, the 3rd to 6 bit representation producer information, the specifications and models of the 7th to 9 bit representation goods and materials, the 10th to 12 bit representation goods and materials sequence numbers.
The operation of described routine use comprise use, give back, receive, transfer, verification and scrap operation.
Compared with prior art, the present invention has the following advantages:
1) 12 codings that totally 5 parts form can comprise all goods and materials in transformer station completely, and principle is easily understood, and have realized with minimum figure place and have realized and maximize the function that contains material category.
2) scanner can be realized borrowing and receives separated with database manipulation.
3) workload that minimizing is to the full extent declared, goods and materials are borrowed generation while receiving, thereby save a large amount of time costs and human cost, reduce materials warehousing simultaneously, required time and efforts while getting, more can ensure at crucial moment putting in place rapidly of standby redundancy and special Work tool, instrument and meter.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is portable scanner high-level schematic functional block diagram;
Fig. 3 is the process flow diagram of the inventive method.
Embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in detail.The present embodiment be take technical solution of the present invention and is implemented as prerequisite, provided detailed embodiment and concrete operating process, but protection scope of the present invention is not limited to following embodiment.
As shown in Figure 1, a kind of Portable transformer substation stock in storage management system, this management system comprises portable scanner 1, server 2 and printer 3, as shown in Figure 2, portable scanner 1 comprises scanning element 11, wireless transmit/receive units 12 and control circuit 13, scanning element 11, wireless transmit/receive units 12 are all connected with control circuit 13, and the input end of printer 3 is connected with server 2, and scanner 1 is connected with server 2 with wireless network by wireless transmit/receive units 12;
Portable scanner 1, by after personal information, Item Information and the respective operations of scanning, sends the data to server, and server carries out record to data, and printer is printed relevant information.
As shown in Figure 2, scanner also comprises keyboard 14 and display 15, and scanning element 11, wireless transmit/receive units 12, keyboard 14 and display 15 are connected with control circuit 13.
Scanning element 12 scanning recognition bar codes and employee's identification card.
Keyboard 14 comprises numeric keyboard of mobile telephone and seven function keys of standard, and eight function keys are corresponding respectively puts in storage, use, give back, receive, transfer, verification and scrap operation.
In server 2, be provided with database 4, this database 4, based on SQL Server2005 database, is developed with C# language, supports LAN (Local Area Network) access services device, and hardware is equipped with printer 3 and portable scanner 1, forms the management platform of a whole set of software and hardware one.In database, set up three tables: first is shown as declaring goods and materials form, " the concentrated bid and purchase application of state's net the is detailed " table of take is basic, deletes after some inessential, with state's net coding and goods and materials name, is called most important two contents; Second table is stock in storage form, with state's net coding, self-editing coding and goods and materials name, is called most important three contents; The 3rd table is operation sheet.Wherein, declaring goods and materials form and stock in storage form, with state's net, to be encoded to key word interrelated.During design in database, according to actual service condition, whole flow of material is divided into and declares, put in storage, use, give back, receive, transfer, verification, scrap eight parts.
Goods and materials comprise standby redundancy, material, oversize vehicle, special tool utensil, safety appliance etc.
As shown in Figure 3, a kind of Portable transformer substation stock in storage management method, the method comprises the following steps:
101 by after cargo number, by printer 3, prints bar code;
102 are attached to bar code on goods and materials by staff;
103 put into warehouse by staff by goods and materials.
104 carry out routine use bookkeeping.
Be encoded to 12 bit numbers, wherein, the classification of the 1st to 2 bit representation goods and materials, the 3rd to 6 bit representation producer information, the specifications and models of the 7th to 9 bit representation goods and materials, the 10th to 12 bit representation goods and materials sequence numbers.
Routine use bookkeeping comprise use, give back, receive, transfer, verification and scrap operation.
Declare personnel and can generate one " procurement request detail list " by importer's net materiel code or goods and materials title, this table can directly be transferred to produce O&M portion and purchase, and carries out afterwards seven generic operations, is described as follows:
In-stockroom operation:
First the goods and materials that buy put in storage, and warehouse-in process is these goods and materials and encodes, determines the information such as deposit position, check-verifying period, annotation funds source.Determine warehouse-in materiel code is defined as to 12, be divided into 5 parts: be respectively " the large class " of the 1st, " group " of the 2nd, " the brand producer " of the 3rd to 6, " specifications and models " of the 7th to 9, the definition of the 10th to 12 is divided into two kinds.The first: these goods and materials are standby redundancy or this two large class of material, and these three remain 001, till coding is defined into model; The second: large piece article or the article that can distinguish with methods such as sequence numbers in standby redundancy and material can define at most 999, does not share this tri-bit encoding between different model.Inputted relevant information and clicked after definite warehouse-in, bar code printer starts the bar code that prints these article automatically, and bar code can be attached on these article.
Use, receive, give back operation:
Seemingly, by input materiel code, the automatic information such as goods and materials title, classification, quantity that show of system meeting, only need fill in borrower to these three class of operation and handler gets final product complete operation.
Jump operation:
Jump operation refers to the goods and materials transfer work of carrying out between the inner different warehouses of Yi Ge administrative office, and it does not relate to borrows, receives, and only need fill in and shifts quantity and be transferred to which warehouse.
Scrap operation:
Scrap operation as the term suggests for scrapping this goods and materials, only need fill in quantity and handler.
Verification operation:
Checking time is that the check-verifying period of filling in during according to warehouse-in is calculated, and starts " verification prompting ", until the day zero clearing of fetching to verification is from newly starting at when also having 30 days from Check Date with from last time checking time.

Claims (8)

1. a Portable transformer substation stock in storage management system, it is characterized in that, this management system comprises portable scanner (1), server (2) and printer (3), described portable scanner (1) comprises scanning element (11), wireless transmit/receive units (12) and control circuit (13), described scanning element (11), wireless transmit/receive units (12) are all connected with control circuit (13), the input end of described printer (3) is connected with server (2), and described scanner (1) is connected with server (2) with wireless network by wireless transmit/receive units (12);
Described portable scanner (1), by after personal information, Item Information and the respective operations of scanning, sends the data to server (2), and server (2) carries out record to data, and printer (3) is printed relevant information simultaneously.
2. a kind of Portable transformer substation stock in storage management system according to claim 1, it is characterized in that, described scanner also comprises keyboard (14) and display (15), and described scanning element (11), wireless transmit/receive units (12), keyboard (14) and display (15) are connected with control circuit (13) respectively.
3. a kind of Portable transformer substation stock in storage management system according to claim 2, is characterized in that described scanning element (12) scanning recognition bar code and employee's identification card.
4. a kind of Portable transformer substation stock in storage management system according to claim 2, it is characterized in that, described keyboard (14) comprises numeric keyboard of mobile telephone and seven function keys of standard, and described seven function keys are corresponding respectively puts in storage, use, give back, receive, transfer, verification and scrap operation.
5. a kind of Portable transformer substation stock in storage management system according to claim 1, it is characterized in that, in described server (2), be provided with database (4), described database (4) comprises declares goods and materials table (41), stock in storage form (42) and operation sheet (43), described in to declare goods and materials table (41) and stock in storage form (42) associated by materiel code.
6. implement the claims the Portable transformer substation stock in storage management method described in 1-5, it is characterized in that, the method comprises the following steps:
101), by after cargo number, by printer (3), print bar code;
102) by staff, bar code is attached on goods and materials;
103) by staff, goods and materials are put into warehouse.
104) carry out routine use bookkeeping.
7. a kind of Portable transformer substation stock in storage management method according to claim 6, it is characterized in that, described 12 bit numbers that are encoded to, wherein, the classification of the 1st to 2 bit representation goods and materials, the 3rd to 6 bit representation producer information, the specifications and models of the 7th to 9 bit representation goods and materials, the 10th to 12 bit representation goods and materials sequence numbers.
8. a kind of Portable transformer substation stock in storage management method according to claim 6, is characterized in that, described routine use bookkeeping comprise use, give back, receive, transfer, verification and scrap operation.
CN201410194151.5A 2014-05-09 2014-05-09 Portable transformer substation inventory material management system and method Pending CN103955815A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410194151.5A CN103955815A (en) 2014-05-09 2014-05-09 Portable transformer substation inventory material management system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410194151.5A CN103955815A (en) 2014-05-09 2014-05-09 Portable transformer substation inventory material management system and method

Publications (1)

Publication Number Publication Date
CN103955815A true CN103955815A (en) 2014-07-30

Family

ID=51333088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410194151.5A Pending CN103955815A (en) 2014-05-09 2014-05-09 Portable transformer substation inventory material management system and method

Country Status (1)

Country Link
CN (1) CN103955815A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104537452A (en) * 2014-11-04 2015-04-22 无锡鹰智科技有限公司 Electric power project computer management system
CN104700192A (en) * 2014-11-03 2015-06-10 国网浙江省电力公司嘉兴供电公司 Aided intelligent management and control system for power transmission and transformation project and management and control method thereof
CN106327040A (en) * 2015-06-29 2017-01-11 国网河南省电力公司周口供电公司 Electric power emergency material storage and calling platform in large-area disaster range
CN107730185A (en) * 2017-11-13 2018-02-23 广东电网有限责任公司江门供电局 One kind metering flow of material management system and its method
CN108171291A (en) * 2017-12-26 2018-06-15 深圳供电局有限公司 Inspection operation method and system based on unmanned aerial vehicle
CN109389345A (en) * 2018-09-26 2019-02-26 柳州钢铁股份有限公司 Base management system by machine
CN109572235A (en) * 2018-12-29 2019-04-05 国网山东省电力公司桓台县供电公司 Portable power service patch printer
CN112116287A (en) * 2020-08-11 2020-12-22 大亚湾核电运营管理有限责任公司 Multi-power station spare part borrowing method, system and medium based on heap clustering mode

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070219916A1 (en) * 2000-03-07 2007-09-20 Michael Lucas Systems and methods for tracking and verifying the authenticity of an item
CN101419689A (en) * 2008-12-10 2009-04-29 武汉奋进电力技术有限公司 Full lofe cycle management system of electric power tools
CN101894314A (en) * 2010-04-23 2010-11-24 南京邮电大学 Method for applying warehouse based on internet of things
CN201936342U (en) * 2010-10-29 2011-08-17 雷柏电子(深圳)有限公司 Product delivery tracking system
CN202854876U (en) * 2012-10-24 2013-04-03 天津市电力公司 Electric power communication device management system based on two-dimensional codes

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070219916A1 (en) * 2000-03-07 2007-09-20 Michael Lucas Systems and methods for tracking and verifying the authenticity of an item
CN101419689A (en) * 2008-12-10 2009-04-29 武汉奋进电力技术有限公司 Full lofe cycle management system of electric power tools
CN101894314A (en) * 2010-04-23 2010-11-24 南京邮电大学 Method for applying warehouse based on internet of things
CN201936342U (en) * 2010-10-29 2011-08-17 雷柏电子(深圳)有限公司 Product delivery tracking system
CN202854876U (en) * 2012-10-24 2013-04-03 天津市电力公司 Electric power communication device management system based on two-dimensional codes

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104700192A (en) * 2014-11-03 2015-06-10 国网浙江省电力公司嘉兴供电公司 Aided intelligent management and control system for power transmission and transformation project and management and control method thereof
CN104537452A (en) * 2014-11-04 2015-04-22 无锡鹰智科技有限公司 Electric power project computer management system
CN106327040A (en) * 2015-06-29 2017-01-11 国网河南省电力公司周口供电公司 Electric power emergency material storage and calling platform in large-area disaster range
CN107730185A (en) * 2017-11-13 2018-02-23 广东电网有限责任公司江门供电局 One kind metering flow of material management system and its method
CN108171291A (en) * 2017-12-26 2018-06-15 深圳供电局有限公司 Inspection operation method and system based on unmanned aerial vehicle
CN109389345A (en) * 2018-09-26 2019-02-26 柳州钢铁股份有限公司 Base management system by machine
CN109572235A (en) * 2018-12-29 2019-04-05 国网山东省电力公司桓台县供电公司 Portable power service patch printer
CN112116287A (en) * 2020-08-11 2020-12-22 大亚湾核电运营管理有限责任公司 Multi-power station spare part borrowing method, system and medium based on heap clustering mode

Similar Documents

Publication Publication Date Title
CN103955815A (en) Portable transformer substation inventory material management system and method
CN105096083B (en) Information system for warehouse
CN102214187A (en) Complex event processing method and device
Sahara et al. Real-time data integration of an internet-of-things-based smart warehouse: a case study
EP1866882A2 (en) Method and system for setup of, and communication with, an rfid middleware server from an enterprise resource planning system server
KR102192429B1 (en) Goods Receipt and Issue Management System using binary management user interface
CN106372694B (en) Information code generation method, information code material determination method and corresponding device
CN112214508A (en) Data processing method and device
CN104299157A (en) Fabric trading system and method
CN103295113A (en) Method for carrying out goods control by generating documents automatically through goods classification
Hehua Application of Passive Wireless RFID Asset Management in Warehousing of Cross‐Border E‐Commerce Enterprises
CN109559085B (en) Approval method based on BIM lightweight model and terminal equipment
CN114118849A (en) Workshop material flow tracking and control method and system based on RFID technology
KR20200104030A (en) Binary management user interface and product information management system
CN104199648A (en) General mobile information system adaptation method and device
US11587024B2 (en) Supply chain model generation system
CN101958893A (en) Pre-positioned business server and processing method thereof
KR20170055379A (en) Purchase price forecasting methods for new developments utilizing the ERP database
CN203070361U (en) Finance equipment information acquisition system based on hand-held terminal
Wang Design and Optimisation of an Enterprise Digital Management System Based on IoT Monitoring
CN104680269A (en) Novel cloud computing enviromental protection enterprise information movement computer management motherboard
CN208873177U (en) A kind of pharmaceutical information whole process information tracing system
US11176501B2 (en) Methods and systems to track relocation status
Curran et al. RFID in the production line for work flow improvement
Ahn et al. QR-Code Implementation to Reduce Unnecessary Procedures in Material Handling

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20140730