CN103941713A - Hoisting monitoring analysis control system - Google Patents

Hoisting monitoring analysis control system Download PDF

Info

Publication number
CN103941713A
CN103941713A CN201410199920.0A CN201410199920A CN103941713A CN 103941713 A CN103941713 A CN 103941713A CN 201410199920 A CN201410199920 A CN 201410199920A CN 103941713 A CN103941713 A CN 103941713A
Authority
CN
China
Prior art keywords
hoisting
crane
control system
data
internet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410199920.0A
Other languages
Chinese (zh)
Inventor
陈延刚
李广庆
娄志年
司凯伦
冯敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410199920.0A priority Critical patent/CN103941713A/en
Publication of CN103941713A publication Critical patent/CN103941713A/en
Pending legal-status Critical Current

Links

Landscapes

  • Closed-Circuit Television Systems (AREA)

Abstract

A hoisting monitoring analysis control system is characterized by comprising a cloud vidicon, a crane computer, a data mixer and a 3(4)G network card. The cloud vidicon is located at the top of a crane head, the crane computer is located in a crane cab, and data are summarized through the data mixer and output to a controller or a displayer by utilizing an existing mobile 3G (4G) international internet network, a wired international internet network and video control software and through data analysis. The hoisting monitoring analysis control system has the advantages that when the system works, a technical director and a safety director of a construction company can supervise and execute an approved hoisting scheme and perform real-time monitoring analysis control on the hoisting site situations of various places, and the safety director can perform remote stopping or authorized operation according to operation against rules or hoisting operation unconformable to the scheme. Hoisting site video monitoring can be performed by remotely monitoring the cloud vidicon according to the constructions site satiation.

Description

Lifting monitors analysis and Control system
Technical field
The present invention relates to hoisting engineering safety management field, be specifically related to a kind of lifting and monitor analysis and Control system.
Background technology:
Hoisting engineering feature, preparatory period is long, short construction period, job location disperses, particularly professional construction company, may lift in multiple places, the person in charge of the technology aspect of construction company and safety director are very large to the lifting scheme implementation and supervision difficulty of approved simultaneously, carry out the pernicious industrial accident that easily causes fatal crass not according to scheme.
Hoisting and hanging is an important operational procedure of excessive risk in engineering construction.In general be all to adopt integral hoisting for main equipments such as tower, reactor, boiler-steam dome in bulk and oxygen-eliminating device, large scale structures, at ability and the quantitative aspects of hoisting machine tool equipment, generally adopt wheel crane, many coordinating operations of crawler crane.Before lifting operation construction, should work out special arrangement and method for construction, and implement after experts' evaluation, in construction, workmen should be in strict accordance with the special arrangement and method for construction of the hoisting engineering of having examined, as not in place in supervision and management, workmen does not carry out in strict accordance with Hoisting Program, by easily causing fatal crass's serious accident, according to the regulation of laws and regulations, should investigate major technique responsible official, safety manager's responsibility.Due to specialty lifting or Wei Duo place, installation company's operation place synchronous construction, supervision workmen is brought to great difficulty to the special scheme implementation status of hoisting engineering, therefore carrying out remote supervisory, Long-distance Control by company technique responsible official and safety manager to lifting scene, is the solution of avoiding because cause fatal crass's serious accident not according to the special scheme construction of hoisting engineering.
According to safety in production method: the 35 article of production and operation unit carries out the dangerous operations such as explosion, lifting, should arrange professional to carry out site safety management, guarantee observing of working specification and implementing of safety practice.
Article 85, production and operation unit has following line one of to be, is ordered to make correction within a time limit; Exceed the time limit unrectified, the rectification that orders to discontinue production or business operation, can and locate 20,000 yuan of above 100,000 yuan of following fine; Cause serious consequence, in the case which constitutes a crime, give criminal sanctions according to criminal law relevant regulations:
(3) carry out the dangerous operations such as explosion, lifting, do not arrange concrete management personnel to carry out site safety management.
Ordinance of Construction Engineering Safty Production Management:
Article 26 unit in charge of construction should work out technical safety measures and working-yard temporary electricity scheme in Design of Construction Organization, the following larger branch's kinds of construction of danger that reaches certain scale is worked out to special arrangement and method for construction, and attach safety check result, after the person in charge of the technology aspect of unit in charge of construction, chief supervision engineer's signature, implement, carry out scene supervision by full-time production safety management personnel.
(4) hoisting and hanging engineering;
Dangerous larger branch subitem engineering safety management method:
Article 16 unit in charge of construction should specify special messenger carry out scene supervision and be carried out in accordance with regulations monitoring special scheme implementation situation.Discovery is constructed not according to special scheme, should require it to rectify and improve immediately; Find that there is and jeopardize personal safety emergency condition, should organize immediately operating personnel to withdraw hazardous location.  
The person in charge of the technology aspect of the unit in charge of construction special scheme implementation situation of should regularly patrolling.
Summary of the invention:
The technical problem to be solved in the present invention is that a kind of person in charge of the technology aspect and safety director that solves construction company is very large to the lifting scheme implementation and supervision difficulty of approved, carries out the pernicious industrial accident that easily causes fatal crass not according to scheme.
A kind of lifting monitors analysis and Control system, and its feature is: this lifting supervision analysis and Control system is comprising monopod video camera, crane computer, data mixing device, 3(4) G network interface card.Described monopod video camera is positioned at headstock top, described crane computer is positioned at crane pilothouse, gather by described data mixing device, utilize existing mobile 3G (4G) Internet (internet) network, wired Internet (internet) and video control software, outputing to controller or display by data analysis.
Advantage of the present invention is: when the present invention is in the time working, monopod video camera starts shooting, collecting live video, when crane work, exported by crane computer real time data, gather by described data mixing device, utilize existing mobile 3G (4G) Internet (internet) network, the wired Internet in company guard station (internet) and video control software, outputing to controller or display by data analysis, the person in charge of the technology aspect of construction company and safety director can be to the lifting scheme implementation and supervision of approved, carry out various places lifting field condition is carried out to real time monitoring analysis and Control for operating against regulations or lifting not according to scheme by scheme, corporate security supervision can remote parking or au-thorization job.To the situation of working-yard, by Remote monopod video camera, can lift live video monitoring.
Brief description of the drawings
Fig. 1 is that the present invention lifts part-structure schematic diagram.
Fig. 2 is that the present invention uses running schematic diagram.
In accompanying drawing
1, monopod video camera 2, crane computer
Embodiment:
Below in conjunction with accompanying drawing and specific embodiment, the invention will be further described:
A kind of lifting monitors analysis and Control system, and as shown in Figure 1, 2, this lifting supervision analysis and Control system is comprising monopod video camera 1, crane computer 2, data mixing device, 3(4) G network interface card.Described monopod video camera is positioned at headstock top, described crane computer is positioned at crane pilothouse, gather by described data mixing device, utilize existing mobile 3G (4G) Internet (internet) network, wired Internet (internet) and video control software, outputing to controller or display by data analysis.
Beneficial effect of the present invention is:
When the present invention is in the time working, monopod video camera starts shooting, collecting live video, when crane work, exported by crane computer real time data, gather by described data mixing device, utilize existing mobile 3G (4G) Internet (internet) network, the wired Internet in company guard station (internet) and video control software, outputing to controller or display by data analysis, the person in charge of the technology aspect of construction company and safety director can be to the lifting scheme implementation and supervision of approved, carry out various places lifting field condition is carried out to real time monitoring analysis and Control for operating against regulations or lifting not according to scheme by scheme, corporate security supervision can remote parking or au-thorization job.To the situation of working-yard, by Remote monopod video camera, can lift live video monitoring.
Embodiment recited above is described the preferred embodiment of the present invention; not design of the present invention and protection domain are limited; do not departing under the prerequisite of design concept of the present invention; various modification and improvement that in this area, common engineering technical personnel make technical scheme of the present invention, all should fall into protection scope of the present invention.

Claims (1)

1. lifting monitors an analysis and Control system, and its feature is: this lifting supervision analysis and Control system is comprising monopod video camera (1), crane computer (2), data mixing device, 3G or 4G network interface card; Described monopod video camera is positioned at headstock top, described crane computer is positioned at crane pilothouse, gather by described data mixing device, utilize existing mobile 3G (4G) Internet (internet) network, wired Internet (internet) and video control software, outputing to controller or display by data analysis.
CN201410199920.0A 2014-05-13 2014-05-13 Hoisting monitoring analysis control system Pending CN103941713A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410199920.0A CN103941713A (en) 2014-05-13 2014-05-13 Hoisting monitoring analysis control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410199920.0A CN103941713A (en) 2014-05-13 2014-05-13 Hoisting monitoring analysis control system

Publications (1)

Publication Number Publication Date
CN103941713A true CN103941713A (en) 2014-07-23

Family

ID=51189421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410199920.0A Pending CN103941713A (en) 2014-05-13 2014-05-13 Hoisting monitoring analysis control system

Country Status (1)

Country Link
CN (1) CN103941713A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201473212U (en) * 2009-09-09 2010-05-19 中国石油化工集团公司 Monitoring system used for crane truck
CN101927959A (en) * 2009-06-18 2010-12-29 湖北二一三电气成套设备有限公司 Crane safety real-time centralized monitoring system based on 3G/4G communications
US20110191025A1 (en) * 2010-02-01 2011-08-04 Kurt Maynard Sensor unit system
CN202175511U (en) * 2011-07-13 2012-03-28 中海工业(江苏)有限公司 Long-distance wireless network safety monitoring management device for crane
CN103395694A (en) * 2013-08-13 2013-11-20 哈尔滨东建机械制造有限公司 Integral monitoring system for tower crane
CN204270110U (en) * 2014-05-13 2015-04-15 李广庆 Lifting monitors analysis and Control system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101927959A (en) * 2009-06-18 2010-12-29 湖北二一三电气成套设备有限公司 Crane safety real-time centralized monitoring system based on 3G/4G communications
CN201473212U (en) * 2009-09-09 2010-05-19 中国石油化工集团公司 Monitoring system used for crane truck
US20110191025A1 (en) * 2010-02-01 2011-08-04 Kurt Maynard Sensor unit system
CN202175511U (en) * 2011-07-13 2012-03-28 中海工业(江苏)有限公司 Long-distance wireless network safety monitoring management device for crane
CN103395694A (en) * 2013-08-13 2013-11-20 哈尔滨东建机械制造有限公司 Integral monitoring system for tower crane
CN204270110U (en) * 2014-05-13 2015-04-15 李广庆 Lifting monitors analysis and Control system

Similar Documents

Publication Publication Date Title
CN113033393B (en) Thermal power station personnel operation safety monitoring system and method based on machine vision
KR102534819B1 (en) Method, apparatus and system for providing platform service for providing manual and reporting results for safety monitoring of construction sites and industrial sites
CN204270110U (en) Lifting monitors analysis and Control system
CN112734355A (en) Wisdom building site management system
CN104340795B (en) Node-added safety protection control system, method and device and construction elevator
Guo et al. A BIM-RFID unsafe on-site behavior warning system
CN103941713A (en) Hoisting monitoring analysis control system
CN106241522A (en) The earthquake controlled operation control system of elevator and method thereof
CN110827508B (en) Intelligent operation permission system
Mansoor et al. Conceptual framework for safety improvement in mobile cranes
CN203644175U (en) Safety protection system for human-machine mixed working
CN103803411A (en) Cable crane video monitoring system for concrete construction
CN116527843A (en) Building site safety monitoring system and monitoring method based on building site core
CN116483007A (en) Safety belt control method and device, electronic equipment and storage medium
Vishwas et al. Hazards Identification and Risk Assessment in Metro Railway Line Construction Project at Hyderabad
CN206062255U (en) A kind of construction environment monitors safety helmet
CN210895105U (en) Intelligent monitoring system for fastening of mounting bolts of tower crane
CN208873402U (en) The dedicated nameplate of protection screen of transformer substation
CN202402926U (en) Monitoring and safety maintaining device for large hydraulic machine
CN113315952B (en) Power distribution network operation site safety monitoring method and system
CN104735398A (en) Monitoring and commanding device
CN206950481U (en) A kind of detachable safety belt hanging point device
CN204265216U (en) Large-scale component lifting special balancing suspender
Krishnamurthy Safety during steel erection
CN210351665U (en) Comprehensive security device for power plant dangerous area

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140723