CN103938641A - 一种沙漠地质大型光伏电站的基础施工工艺 - Google Patents

一种沙漠地质大型光伏电站的基础施工工艺 Download PDF

Info

Publication number
CN103938641A
CN103938641A CN201410173614.XA CN201410173614A CN103938641A CN 103938641 A CN103938641 A CN 103938641A CN 201410173614 A CN201410173614 A CN 201410173614A CN 103938641 A CN103938641 A CN 103938641A
Authority
CN
China
Prior art keywords
square pile
sandy soil
square
circular hole
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410173614.XA
Other languages
English (en)
Inventor
刘洋
方文军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Realforce Power Co Ltd
Original Assignee
Realforce Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Realforce Power Co Ltd filed Critical Realforce Power Co Ltd
Priority to CN201410173614.XA priority Critical patent/CN103938641A/zh
Publication of CN103938641A publication Critical patent/CN103938641A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

一种沙漠地质大型光伏电站的基础施工工艺是针对解决于沙漠化地质的区域建设光伏电站所需的基础施工形式,其工艺步骤为:定点放线—预制孔—送桩—锤击—填充—浇水,通过最后附加的浇水工艺,使得增强基础的各项受力,从而达到基础的受力条件,本发明具有以下有益效果:有效能够满足抗倾覆力、以及抗风拔力的要求,并且有效避免开挖量增多、施工困难、环境破坏等问题,本发明结构简单、安装方便,特别适合于沙漠地形中的光伏电站的安装。

Description

一种沙漠地质大型光伏电站的基础施工工艺
技术领域
本发明属于光伏电站施工领域,具体涉及一种适用于沙漠地质、并且充分利用水与土的凝固作用简化施工工艺的光伏电站施工工艺。
背景技术
 众所周知,目前目前光伏电站的基础形式主要为以下方式:1、独立基础;2、条形基础;3、锚杆基础;光伏电站施工工艺主要为浇桩灌注工艺,但上述方式存在以下缺点:1、要求地面平整度过高; 2、对地质条件要求过高; 3、施工难度过大; 4、施工工期过长; 5、施工工艺复杂; 6、直面增加项目成本,并且其抗风较小并且施工量过大,容易造成环境的破坏。
发明内容
为解决上述缺陷,满足光伏支架在沙漠地质上的抗倾覆力以及抗风拔力、避免岩石开挖量增多从而增加成本、以及施工上的困难等缺点,本发明提供一种光伏电站基础施工工艺,该基础形式能够满足抗倾覆力、以及抗风拔力、避免岩石开挖量增多、施工困难,操作方面简单。
为实现上述目的,本发明采用以下技术方案:一种沙漠地质大型光伏电站的基础施工工艺,包括以下步骤:
a定点放线:根据测量控制方桩安装点,前后左右方桩之上的光伏组件之间不出现光线遮挡;
b预制方桩:方桩直径不低于5厘米,方桩顶部预制钢筋混泥土方框,钢筋混泥土方框上预制光伏组件安装孔,方桩本体顶部下方三分之一处预制支撑件固定座;
c预制方桩圆孔:根据测量的方桩安装点挖制方桩安装圆孔,方桩圆孔的深度大于30厘米;
d送桩锤击:将步骤b制作的方桩送入步骤c制作的方桩圆孔内,并锤击方桩,使方桩深入方桩圆孔内部;
d沙土填充:在方桩四周的方桩圆孔内填充沙土;
e浇水凝固:对所填充的沙土进行饱和浇水,利用水与土的下沉凝固作用使沙土凝固紧实;
f沙土填充:重复步骤d e直至方桩四周的沙土紧实平整,然后再对四周的沙土进行锤击进一步使沙土紧实,从而使方桩更加稳固。
作为优选,饱和浇水的沙土上可以种植生存能力较强并且低矮的草本植物,既能改善环境,又能进一步稳固桩基。
与现有技术相比,本发明具有以下有益效果:由于采用方桩采用钢筋混泥土结构并且深入地下,因此能够有效满足抗倾覆力、以及抗风拔力的要求,通过利用水与土的粘合凝固作用,全程无需混泥土浇筑,并通过进一步机械压实,因此有效避免开挖量增多、施工困难、破坏环境等问题,本发明工艺简单、施工方便,特别适合于沙漠地形中的光伏电站的安装。
附图说明
下面结合附图和实施例对本发明进一步说明。
图1一种沙漠地质大型光伏电站的基础施工工艺流程图。
具体实施方式
如图1所示,一种沙漠地质大型光伏电站的基础施工工艺,包括以下步骤:
a定点放线:根据测量控制方桩安装点,前后左右方桩之上的光伏组件之间不出现光线遮挡;
b预制方桩:方桩直径不低于5厘米,方桩顶部预制钢筋混泥土方框,钢筋混泥土方框上预制光伏组件安装孔,方桩本体顶部下方三分之一处预制支撑件固定座;
c预制方桩圆孔:根据测量的方桩安装点挖制方桩安装圆孔,方桩圆孔的深度大于30厘米;
d送桩锤击:将步骤b制作的方桩送入步骤c制作的方桩圆孔内,并锤击方桩,使方桩深入方桩圆孔内部;
e沙土填充:在方桩四周的方桩圆孔内填充沙土;
f浇水凝固:对所填充的沙土进行饱和浇水,利用水与土的下沉凝固作用使沙土凝固紧实;
g沙土填充:重复步骤d e直至方桩四周的沙土紧实平整,然后再对四周的沙土进行锤击进一步使沙土紧实,从而使方桩更加稳固,饱和浇水的沙土上可以种植生存能力较强并且低矮的草本植物,既能改善环境,又能进一步稳固桩基。
显而易见,上述实施方式仅为本发明的较佳实施方式,任何在此基础上的简单改进均属于本发明的保护范围。

Claims (1)

1.一种沙漠地质大型光伏电站的基础施工工艺,包括以下步骤:
a定点放线:根据测量控制方桩安装点,前后左右方桩之上的光伏组件之间不出现光线遮挡;
b预制方桩:方桩直径不低于5厘米,方桩顶部预制钢筋混泥土方框,钢筋混泥土方框上预制光伏组件安装孔,方桩本体顶部下方三分之一处预制支撑件固定座;
c预制方桩圆孔:根据测量的方桩安装点挖制方桩安装圆孔,方桩圆孔的深度大于30厘米;
d送桩锤击:将步骤b制作的方桩送入步骤c制作的方桩圆孔内,并锤击方桩,使方桩深入方桩圆孔内部;
d沙土填充:在方桩四周的方桩圆孔内填充沙土;
e浇水凝固:对所填充的沙土进行饱和浇水,利用水与土的下沉凝固作用使沙土凝固紧实;
f沙土填充:重复步骤d e直至方桩四周的沙土紧实平整,然后再对四周的沙土进行锤击进一步使沙土紧实,从而使方桩更加稳固。
CN201410173614.XA 2014-04-28 2014-04-28 一种沙漠地质大型光伏电站的基础施工工艺 Pending CN103938641A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410173614.XA CN103938641A (zh) 2014-04-28 2014-04-28 一种沙漠地质大型光伏电站的基础施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410173614.XA CN103938641A (zh) 2014-04-28 2014-04-28 一种沙漠地质大型光伏电站的基础施工工艺

Publications (1)

Publication Number Publication Date
CN103938641A true CN103938641A (zh) 2014-07-23

Family

ID=51186496

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410173614.XA Pending CN103938641A (zh) 2014-04-28 2014-04-28 一种沙漠地质大型光伏电站的基础施工工艺

Country Status (1)

Country Link
CN (1) CN103938641A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105984018A (zh) * 2015-02-09 2016-10-05 任丘市永基建筑安装工程有限公司 一种组合模具基础施工工法
CN108385712A (zh) * 2018-01-12 2018-08-10 江苏华源新能源科技有限公司 一种大型光伏电站的基础施工工艺
CN111719579A (zh) * 2020-06-02 2020-09-29 中国电建集团西北勘测设计研究院有限公司 一种沙漠光伏支架桩基础的后注水振密施工方法
CN115369912A (zh) * 2022-09-19 2022-11-22 陕西建工新能源有限公司 一种光伏支架基础下沉处理方法
CN116657643A (zh) * 2023-05-26 2023-08-29 中国电建集团西北勘测设计研究院有限公司 适用于沙漠地质的管桩类风机基础及施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1490467A (zh) * 2003-08-05 2004-04-21 胡柏英 一种复合摩擦桩的结构及其施工方法
US20070065233A1 (en) * 2003-09-24 2007-03-22 Vincenzo Collina Method of constructing a pile foundation
JP2009030338A (ja) * 2007-07-27 2009-02-12 Shusuke Ito 軟弱地盤の地耐力増強工法
CN203007967U (zh) * 2013-01-05 2013-06-19 葛洲坝集团电力有限责任公司 一种高原戈壁沙土地区光伏电站组件支架基础
CN203096750U (zh) * 2013-01-28 2013-07-31 中国水电顾问集团西北勘测设计研究院 滩涂流沙软弱地基风机基础护筒型混凝土灌注桩装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1490467A (zh) * 2003-08-05 2004-04-21 胡柏英 一种复合摩擦桩的结构及其施工方法
US20070065233A1 (en) * 2003-09-24 2007-03-22 Vincenzo Collina Method of constructing a pile foundation
JP2009030338A (ja) * 2007-07-27 2009-02-12 Shusuke Ito 軟弱地盤の地耐力増強工法
CN203007967U (zh) * 2013-01-05 2013-06-19 葛洲坝集团电力有限责任公司 一种高原戈壁沙土地区光伏电站组件支架基础
CN203096750U (zh) * 2013-01-28 2013-07-31 中国水电顾问集团西北勘测设计研究院 滩涂流沙软弱地基风机基础护筒型混凝土灌注桩装置

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105984018A (zh) * 2015-02-09 2016-10-05 任丘市永基建筑安装工程有限公司 一种组合模具基础施工工法
CN108385712A (zh) * 2018-01-12 2018-08-10 江苏华源新能源科技有限公司 一种大型光伏电站的基础施工工艺
CN111719579A (zh) * 2020-06-02 2020-09-29 中国电建集团西北勘测设计研究院有限公司 一种沙漠光伏支架桩基础的后注水振密施工方法
CN115369912A (zh) * 2022-09-19 2022-11-22 陕西建工新能源有限公司 一种光伏支架基础下沉处理方法
CN116657643A (zh) * 2023-05-26 2023-08-29 中国电建集团西北勘测设计研究院有限公司 适用于沙漠地质的管桩类风机基础及施工方法
CN116657643B (zh) * 2023-05-26 2024-02-06 中国电建集团西北勘测设计研究院有限公司 适用于沙漠地质的管桩类风机基础及施工方法

Similar Documents

Publication Publication Date Title
CN103774675B (zh) 组合双排桩联合竖向预应力锚杆支护体系的施工方法
CN103938641A (zh) 一种沙漠地质大型光伏电站的基础施工工艺
CN102155009A (zh) 用于极软土地基加固的碎石桩及其施工方法
CN204139197U (zh) 扩底预应力锚桩风力机基础
CN204098043U (zh) 留土后开挖结合内支撑双排桩支护结构
CN111910678A (zh) 海上风电新型基础结构及其施工方法
CN103410152B (zh) 一种用于狭长深基坑土方开挖的施工方法
CN102953392B (zh) 一种光伏电站的桩基础结构与桩基础施工工艺
CN106120822B (zh) 一种防止泥岩滑坡的支护方法及装置
CN101691760B (zh) 一种锚杆联合掏挖复合基础及其施工方法
CN103669383B (zh) 一种在海底地面上安装和调平沉箱的方法
CN203498860U (zh) 光伏组件支架带混凝土块的锚杆基础结构
CN102966109A (zh) 软土地基带状深基坑封底施工方法
CN209669900U (zh) 水底强透水砂性土层中隧道建设围堰结构
CN201502065U (zh) 一种锚杆联合开挖类复合基础
CN103195077B (zh) 一种坝基加固框架结构和坝基加固方法
CN206143783U (zh) 一种防止泥岩滑坡的支护装置
CN110259456A (zh) 一种隧道施工用的溶洞处理方法
CN103306290B (zh) 冻土区杆塔基础地基土快速回冻回填施工方法
CN105040723A (zh) 一种防砂土回填治理水泥杆上拔结构及其施工方法
CN211900659U (zh) 浅埋大跨度地下洞室开挖支护布置结构
CN202954373U (zh) 一种光伏电站的桩基础结构
CN203129163U (zh) 一种坝基加固框架结构
CN203174586U (zh) 加固铁路软土地基的混凝土管桩
CN103103985B (zh) 一种基于植桩过程的地源热泵管埋置方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140723