CN103924584B - The construction method of bored pile - Google Patents

The construction method of bored pile Download PDF

Info

Publication number
CN103924584B
CN103924584B CN201410093645.4A CN201410093645A CN103924584B CN 103924584 B CN103924584 B CN 103924584B CN 201410093645 A CN201410093645 A CN 201410093645A CN 103924584 B CN103924584 B CN 103924584B
Authority
CN
China
Prior art keywords
vertical duct
blocking
cement mortar
stake holes
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410093645.4A
Other languages
Chinese (zh)
Other versions
CN103924584A (en
Inventor
杨恩建
陈建新
高如月
吴温艳
朱建贤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG XINBANG CONSTRUCTION Co.,Ltd.
Original Assignee
ZHEJIANG XINBANG CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG XINBANG CONSTRUCTION CO Ltd filed Critical ZHEJIANG XINBANG CONSTRUCTION CO Ltd
Priority to CN201410093645.4A priority Critical patent/CN103924584B/en
Publication of CN103924584A publication Critical patent/CN103924584A/en
Application granted granted Critical
Publication of CN103924584B publication Critical patent/CN103924584B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The invention discloses a kind of construction method of bored pile, comprise the following steps: A, boring settle reinforcing cage, on reinforcing cage, vertical duct and the transverse circular pipe with vertical duct conducting are fixed in colligation, the sprue gate of described vertical duct and the exit of playpipe adopt blocking to close, and blocking adopts the material being dissolvable in water water; B, to fluid concrete in stake holes; C, employing super-pressure water filling device are to vertical duct water filling, and time the blocking in pipe exit to be sprayed dissolves, High-Pressure Water outwards sprays and washes the outer concrete solidified not yet completely open, and then goes out pit on stake holes sidewall; D, adopt high-pressure slip-casting device to inject cement mortar after 28 days again, multiple vertical duct finally can be adopted simultaneously to inject cement mortar, the cement mortar of injection fills the region the pit be deep on stake holes sidewall washed open by water under high pressure; E, cement mortar to be implanted solidify rear sealing of hole.The construction method of this bored pile can strengthen the frictional resistance between pile body and stake holes inwall.

Description

The construction method of bored pile
Technical field
The present invention relates to a kind of construction method of bored pile.
Background technology
The construction of conventional borehole castinplace pile comprises: 1, bore stake holes, 2, lifting reinforcing cage, 3, fluid concrete.But the earth contact surface on the concrete side walls of the bored pile that the cast of this method is formed and stake holes inwall vertically distributes, and therefore its frictional resistance is less, is unfavorable for the carrying of pile body, easily causes building posterior settlement.
Summary of the invention
In view of the deficiency of background technology, technical problem to be solved by this invention is to provide the construction method that a kind of structure can strengthen the bored pile of the frictional resistance between pile body and stake holes inwall.
For this reason, the construction method of bored pile provided by the invention, comprise the following steps: A, hole and settle reinforcing cage, on reinforcing cage, vertical duct and the transverse circular pipe with vertical duct conducting are fixed in colligation, vertical duct has two at least and all with the sprue gate of upper end open and lower end, described transverse circular pipe arranges along the vertical interval of reinforcing cage and is distributed in the length range of whole stake holes, transverse circular pipe racks has the playpipe of multiple lateral openings, playpipe and the conducting of transverse circular pipe, the sprue gate of described vertical duct and the exit of playpipe adopt blocking to close, blocking is made through the soluble material of certain hour after adopting and meeting water, B, to fluid concrete in stake holes, a 24 hours vertical duct water filling wherein after C, fluid concrete, after air emptying, close other vertical ducts, and adopt super-pressure water filling device to vertical duct water filling, time the blocking in pipe exit to be sprayed dissolves, High-Pressure Water outwards sprays and washes the outer coagulation solidified not yet completely open, and then goes out pit on stake holes sidewall, D, one of them vertical duct water filling backward in 28 days, after air emptying, adopt high-pressure slip-casting device to inject cement mortar again, multiple vertical duct finally can be adopted simultaneously to inject cement mortar, the cement mortar of injection fills the region the pit be deep on stake holes sidewall washed open by water under high pressure, E, cement mortar to be implanted solidify rear sealing of hole.
In the present invention, 24 hours after pouring concrete stake holes, concrete solidifies not yet completely, when now injecting water under high pressure, there are current and can't go out completely due to blocking, treat that blocking dissolves in a flash, gather the water flow jet of high pressure on the concrete of side, concrete can be washed open and brush out pit in stake holes sidewall upper punch, thus at the concrete of bored pile after 28 days solidify completely, can casting cement mortar again, this priming charge cement mortar can in side layer of concrete and the pit going deep into stake holes side earth shape all-in-one-piece cement mortar coagulation band, make the intensive side embedded structure that pile body and stake holes sidewall are formed, greatly can strengthen the frictional resistance of bored pile, and then promote its bearing capacity, prevent building posterior settlement.
Accompanying drawing explanation
Fig. 1 is the structure cross-sectional schematic of bored pile provided by the invention.
Fig. 2 is the structure enlarged diagram of the round tube in Fig. 1.
Detailed description of the invention
As Fig. 1, shown in Fig. 2, the construction method of bored pile provided by the invention, comprise the following steps: A, hole and settle reinforcing cage 1, on reinforcing cage 1, vertical duct 2 and the transverse circular pipe 3 with vertical duct 2 conducting are fixed in colligation, vertical duct 2 has two at least and all with the sprue gate 5 of upper end open 4 and lower end, in the present embodiment, vertical duct 2 only has two, described transverse circular pipe 3 arranges along the vertical interval of reinforcing cage 1 and is distributed in the length range of whole stake holes, transverse circular pipe 3 is with the playpipe 6 of multiple lateral openings, playpipe 6 and transverse circular pipe 3 conducting, the sprue gate 5 of described vertical duct 2 and the exit of playpipe 6 adopt blocking 7 to close, blocking 7 is made through the soluble material of certain hour after adopting and meeting water, B, to fluid concrete in stake holes, a 24 hours vertical duct 2 water filling wherein after C, fluid concrete, after air emptying, close other vertical ducts 2, and adopt super-pressure water filling device to vertical duct 2 water filling, super-pressure water filling device is actual is a high-pressure hydraulic pump, time the blocking 7 in pipe 6 exit to be sprayed dissolves, High-Pressure Water outwards sprays and washes the outer concrete solidified not yet completely open, and then goes out pit 8 on stake holes sidewall, D, one of them vertical duct 2 water filling backward in 28 days, after air emptying, high-pressure slip-casting device is adopted to inject cement mortar again, high-pressure slip-casting device is a high pressure slurry pump, multiple vertical duct 2 finally can be adopted to inject cement mortar, and the cement mortar of injection fills the region the pit 8 be deep on stake holes sidewall washed open by water under high pressure simultaneously, E, cement mortar to be implanted solidify rear sealing of hole.
In the above-described embodiments, described blocking 7 adopts starch to make, the thickness of blocking 7 reduces from bottom to top gradually, the starch material blocking 7 of different-thickness dissolves and to wash required basis of time thickness open different, the thickness that blocking of the present invention reduces from bottom to top is gradually arranged, the blocking of each height aspect can be made to be rushed to open in the roughly the same time, thus to avoid occurring that local blocking is rushed to open the situation that rear pressure cannot wash open not because of other blockings.

Claims (2)

1. the construction method of a bored pile, it is characterized in that: comprise the following steps: A, hole and settle reinforcing cage, on reinforcing cage, vertical duct and the transverse circular pipe with vertical duct conducting are fixed in colligation, vertical duct has two at least and all with the sprue gate of upper end open and lower end, described transverse circular pipe arranges along the vertical interval of reinforcing cage and is distributed in the length range of whole stake holes, transverse circular pipe racks has the playpipe of multiple lateral openings, playpipe and the conducting of transverse circular pipe, the sprue gate of described vertical duct and the exit of playpipe adopt blocking to close, blocking is made through the soluble material of certain hour after adopting and meeting water, B, to fluid concrete in stake holes, a vertical duct water filling wherein in 24 hours after C, fluid concrete, after air emptying, close other vertical ducts, and adopt super-pressure water filling device to vertical duct water filling, time the blocking in pipe exit to be sprayed dissolves, High-Pressure Water outwards sprays and washes the outer concrete solidified not yet completely open, and then goes out pit on stake holes sidewall, D, one of them vertical duct water filling backward in 28 days, after air emptying, adopt high-pressure slip-casting device to inject cement mortar again, multiple vertical duct finally can be adopted simultaneously to inject cement mortar, the cement mortar of injection fills the region the pit be deep on stake holes sidewall washed open by water under high pressure, E, cement mortar to be implanted solidify rear sealing of hole.
2. the construction method of bored pile according to claim 1, is characterized in that: described blocking adopts starch to make, and the thickness of blocking reduces from bottom to top gradually.
CN201410093645.4A 2014-03-14 2014-03-14 The construction method of bored pile Active CN103924584B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410093645.4A CN103924584B (en) 2014-03-14 2014-03-14 The construction method of bored pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410093645.4A CN103924584B (en) 2014-03-14 2014-03-14 The construction method of bored pile

Publications (2)

Publication Number Publication Date
CN103924584A CN103924584A (en) 2014-07-16
CN103924584B true CN103924584B (en) 2016-02-03

Family

ID=51142964

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410093645.4A Active CN103924584B (en) 2014-03-14 2014-03-14 The construction method of bored pile

Country Status (1)

Country Link
CN (1) CN103924584B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727305B (en) * 2015-01-27 2016-11-02 安徽同济建设集团有限责任公司 Boring high-pressure slip-casting uplift pile construction method
CN106116349B8 (en) * 2016-06-27 2020-06-30 辽阳鞍钢弓附建筑工程有限公司 Concrete material capable of shortening final setting time and preparation method and application thereof
CN106930289B (en) * 2017-03-10 2019-03-12 东南大学 A kind of noiseless broken pile device and broken pile method
CN110005872B (en) * 2019-04-23 2021-01-05 河海大学 Transportation and grouting integrated pipeline and operation method thereof
CN111287176A (en) * 2020-02-15 2020-06-16 广州市芳村建筑工程有限公司 Construction method of building pile foundation
CN112832235A (en) * 2021-01-08 2021-05-25 翟宇思 Construction method and construction device for precast pile post-grouting
CN113356255A (en) * 2021-06-25 2021-09-07 上海涵格建设工程有限公司 Weak geological building foundation reinforcement construction method
CN114775576B (en) * 2022-05-05 2024-02-23 交通运输部公路科学研究所 Low-disturbance rotary spraying solidification method and device for frozen soil active layer of Qinghai-Tibet plateau

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02296927A (en) * 1989-05-11 1990-12-07 Fujita Corp Method for treating pile head of establishment pile
JP2005180168A (en) * 2003-12-23 2005-07-07 Ujisu:Kk Replaceable columnar hardened formation device and formation method
CN201722685U (en) * 2010-02-05 2011-01-26 中国建筑第四工程局有限公司 No-adhesive prestress and pile side rear grouting punching pile structure
CN201770981U (en) * 2010-09-17 2011-03-23 广州市建筑科学研究院有限公司 Tube-side injection grouting apparatus for simultaneous drilling pipe pile
CN103334428A (en) * 2013-06-24 2013-10-02 河海大学 Disc type cast-in-place concrete pile and construction process for same
CN103469792A (en) * 2013-09-09 2013-12-25 广东省第二建筑工程公司 Method for conducting grouting construction at back of pile bottom of cast-in-place pile

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02296927A (en) * 1989-05-11 1990-12-07 Fujita Corp Method for treating pile head of establishment pile
JP2005180168A (en) * 2003-12-23 2005-07-07 Ujisu:Kk Replaceable columnar hardened formation device and formation method
CN201722685U (en) * 2010-02-05 2011-01-26 中国建筑第四工程局有限公司 No-adhesive prestress and pile side rear grouting punching pile structure
CN201770981U (en) * 2010-09-17 2011-03-23 广州市建筑科学研究院有限公司 Tube-side injection grouting apparatus for simultaneous drilling pipe pile
CN103334428A (en) * 2013-06-24 2013-10-02 河海大学 Disc type cast-in-place concrete pile and construction process for same
CN103469792A (en) * 2013-09-09 2013-12-25 广东省第二建筑工程公司 Method for conducting grouting construction at back of pile bottom of cast-in-place pile

Also Published As

Publication number Publication date
CN103924584A (en) 2014-07-16

Similar Documents

Publication Publication Date Title
CN103924584B (en) The construction method of bored pile
CN100387785C (en) Hydraulic sheeting and use method thereof
CN103924987B (en) A kind of SMW engineering method stake tunnel shielding portal seepage-proof structure and construction method thereof
CN103321215B (en) Construction technology of cast-in-situ concrete tubular pile applied to water area, as well as special hole-forming device of construction technology
CN108086342A (en) The construction method of karst strata pile foundation
CN113006117A (en) Karst cave stratum pile foundation structure and pile forming process
CN106638647A (en) Underwater sunk shaft sealing method and sunk shaft
CN203569555U (en) Water plugging and seepage proofing recharge well
CN105155472B (en) Dam foundation anti-seepage structure of deep overlying layer earth-rock dam and construction method of dam foundation anti-seepage structure
CN205875194U (en) Pouring jacket cofferdam bearing platform structure
CN105350575B (en) A kind of reversed construction method of diaphram wall
CN104294806B (en) Excavation, diversion and drainage method for inter-pile water above water-resisting layer of deep foundation pit
CN104895086A (en) Manual grouting layer method pile toe three-dimensional post-pressure grouting structure and pouring method
CN108798730A (en) A kind of mine worked-out section artificial ore pillar connects top method
CN211498905U (en) Pressure reduction well with well wall compensation
JP2011208484A (en) Method of injecting grout in soil improvement
CN204252119U (en) The special-shaped supporting pile structure of X
CN103452124A (en) Method and device for removing accumulated water in foundation pit
CN108487229A (en) Artificial pore-forming method after strong rock-soluble foundation pre-grouting treatment
CN106088086A (en) The pile body post-mud-jacking bored pile of karst area deep foundation pit fender post supporting
CN109555078A (en) A kind of Gravity Type Casisson Berth and its construction method
CN110805045B (en) Active defense construction method for deep foundation pit leakage
CN203782862U (en) Window type draining well
CN209100007U (en) A kind of drilling artesian water is synchronous to drain slip casting plugging device
CN203145020U (en) Secant pile oriented grouting structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 325000 4 buildings of Lu Xiang business center, Shuang Yu Street, Wenzhou, Zhejiang.

Patentee after: ZHEJIANG XINBANG CONSTRUCTION Co.,Ltd.

Address before: 325000, Zhejiang Wenzhou shoes three phase Lucheng District Economic headquarters B06 building

Patentee before: ZHEJIANG XINBANG CONSTRUCTION Co.,Ltd.