CN103912013B - The immersion method of tunnel immersed tube - Google Patents

The immersion method of tunnel immersed tube Download PDF

Info

Publication number
CN103912013B
CN103912013B CN201310004844.9A CN201310004844A CN103912013B CN 103912013 B CN103912013 B CN 103912013B CN 201310004844 A CN201310004844 A CN 201310004844A CN 103912013 B CN103912013 B CN 103912013B
Authority
CN
China
Prior art keywords
barge
wireless communication
communication control
control terminal
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310004844.9A
Other languages
Chinese (zh)
Other versions
CN103912013A (en
Inventor
林鸣
尹海卿
苏乐平
翟世鸿
孙健
宿发强
王强
岳远征
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Zhenghua Heavy Industries Co Ltd
No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Original Assignee
Shanghai Zhenghua Heavy Industries Co Ltd
No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Zhenghua Heavy Industries Co Ltd, No 2 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd, CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd filed Critical Shanghai Zhenghua Heavy Industries Co Ltd
Priority to CN201310004844.9A priority Critical patent/CN103912013B/en
Publication of CN103912013A publication Critical patent/CN103912013A/en
Application granted granted Critical
Publication of CN103912013B publication Critical patent/CN103912013B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Mobile Radio Communication Systems (AREA)

Abstract

The invention provides the immersion method of a kind of tunnel immersed tube, particularly relate to a kind of by the two method of refuting the synchronous sinking immersed tube of thick stick of wireless communication control system realization; Described immersion method is included in fitting-out sinking equipment on major and minor barge; The control terminal of main barge to carry out Synchronization Control or secondary barge according to monitored data by wireless communication control system control terminal to secondary barge carries out Synchronization Control by wireless communication control system to main barge according to monitored data; TT&C system monitoring tube coupling sinking attitude also uploads monitored data in real time; The control terminal of main barge carries out Synchronization Control by wireless communication control system to secondary barge according to monitored data; After peace tube coupling installs, dismounting sinking equipment.

Description

The immersion method of tunnel immersed tube
Technical field
The present invention relates to the immersion method of a kind of tunnel immersed tube, particularly relate to a kind of by the two method of refuting the synchronous sinking immersed tube of thick stick of wireless communication control system realization.
Background technology
At present, the submerged tunnel for vehicle to run is formed by connecting by many immersed tube, and the volume and weight of immersed tube is quite large, and generally its length has 180 meters, and immersed tube is routed on the bedding that lays in advance.Mostly adopt when installing large gauge immersed tube and two refute thick stick lift-on/lift-off system and carry out sedimentation to it, namely have two to install barges, a barge is by vertically disposed hoist cable cable hanging immersed tube butt end; Another barge is by vertically disposed hoist cable cable hanging immersed tube tail end; Two barges across on beam, working platform is set, working platform is provided with sling system; Control system, by controlling the lifting of hoist cable cable, realizes the sinking of waiting to pacify tube coupling; Working platform is also provided with and can controls two barges and to move horizontally and immersed tube docks the anchorage system moved horizontally; But, this kind of method requires very high to immersed tube descent precision, the difficulty of corresponding control settlement is very large, not critical guarantee immersed tube two barges in the process of transportation by driving to installation region run and keep synchronous, also will keep the synchronism of two barge height when vertical sinking immersed tube and submerged level docking immersed tube, this just needs the control system arranged on two barges for coordinating immersed tube two ends synchronous vertical sinking and two barge level of synchronization displacements; The system being most commonly used to control synchronization in present stage this area is: main (hanging immersed tube butt end), secondary (hanging immersed tube tail end) barge are all installed and a whole set ofly installs system of refuting, anchorage system, ballast system, preliminary drawing system and sinking TT&C system, commanding respectively on two barges Real-Time Monitoring advance, sinking, first drawing process, commanding on two barges needs to transmit synchronically controlling information by artificial radio communication at any time, ensures to adjust in time, revise immersed tube sinking attitude; Because operation on the sea is affected by environment very large, commanding wants the many beyond thought situations of continuous fast processing, and this requires high to commanding, need the department that works in coordination and personnel amount many; Adopt this kind of synchronous method to make sinking process very complicated, the synchronism between two barges is difficult to ensure, is difficult to the synchronization accuracy reaching designing requirement; Very easily there is combination miss in Artificial Control, even great accident, and cause sinking construction speed slow, more serious even occurs property and personal casualty loss; Therefore, be badly in need of for the problems referred to above the immersion method that a kind of new tunnel immersed tube is provided.
Summary of the invention
The object of this invention is to provide the immersion method of a kind of tunnel immersed tube, this immersion method utilizes wireless communication control apparatus to realize the object of synchronous sinking between two barges.
The object of the invention is to be achieved through the following technical solutions: the immersion method of a kind of tunnel immersed tube, described immersion method comprises the following steps:
S1, on major and minor barge the step of fitting-out sinking equipment;
The control terminal of S2, main barge is by the step of the control terminal wireless connections of wireless communication control system and secondary barge;
S3, TT&C system monitoring tube coupling sinking attitude also uploads the step of monitored data in real time;
The control terminal of S4, main barge to carry out Synchronization Control or secondary barge according to monitored data by wireless communication control system control terminal to secondary barge carries out synchronous step by wireless communication control system with main ship according to monitored data;
S5, after until peace, tube coupling installs, the step of dismounting sinking equipment.
Described in described step S2, wireless communication control system comprises main wireless communication control apparatus and secondary wireless communication control apparatus; On the control terminal of main barge, commissioning installs main wireless communication control apparatus, and on the control terminal of secondary barge, commissioning installs the step of secondary wireless communication control apparatus.
Also comprise TT&C system monitoring tube coupling sinking attitude in described step S3, and monitored data is transferred to the step of main barge control terminal.
Also comprise the steps: in described step S4
Commanding is according to monitored data editor Synchronization Control instruction and inputted the step of main barge control terminal;
Main barge control terminal controls sinking equipment according to Synchronization Control instruction and treats the step that sinking is carried out in peace tube coupling butt end;
Synchronization Control instruction is transferred to the step of secondary wireless communication control apparatus by main barge control terminal by main wireless communication control apparatus;
Secondary wireless communication control apparatus by Synchronization Control command to the step of secondary barge control terminal;
Secondary barge control terminal automatically controls sinking equipment according to Synchronization Control instruction and treats the step that peace tube coupling tail end carries out sinking.
The step major and minor two cover wireless communication control apparatus being set to redundancy each other is also comprised in described step S2.
The step communication frequency of major and minor two cover wireless communication control apparatus being arranged respectively different frequency range is also comprised in described step S2.
The step major and minor two cover wireless communication control apparatus being all arranged to AFH pattern is also comprised in described step S2.
The step major and minor two cover wireless communication control apparatus being all arranged to IP65 degree of protection is also comprised in described step S2.
Described sinking equipment comprises the working platform, winch gear, electric device and the control terminal that are arranged on each barge.
Described winch gear comprises ponton manoeuvring winch for controlling installation ship horizontal movement, for the horizontal winch of tube coupling of control valve horizontal displacement, for controlling the hoisting gear of tube coupling vertical displacement and the cable for each winch.
The present invention compared with prior art has following advantage:
1, the present invention adopts the control terminal of main barge by the step of the control terminal wireless connections of wireless communication control system and secondary barge; Make to realize between two barges the data transmission of real-time synchronization, and the level being realized immersed tube to be installed by this wireless communication control system is to the synchronizing moving with Vertical dimension synchronous shift and two barges; The course of work of immersed tube sinking can be simplified, decrease commanding's quantity, make commanding on main barge, only just can complete alone the synchronous sinking process of two barges; Effectively ensure that the synchronism of two barge actions, improve synchronization accuracy; Decrease work mistake, avoid the appearance of major accident, improve operating efficiency.
2, the present invention adopts the step major and minor two cover wireless communication control apparatus being set to redundancy each other, can ensure after wherein a set of wireless communication control apparatus lost efficacy, can be cut at once in the wireless communications path of another set of wireless communication control apparatus, effectively ensure that the stability of wireless communication control system, reduce in synchronous sinking because of sync fail there is the probability of accident.
3, the present invention adopts the step communication frequency of major and minor two cover wireless communication control apparatus being arranged respectively different frequency range; The interference problem of single frequency band effectively can be avoided when radio communication to occur, greatly improve the communication reliability between two wireless communication control apparatus.
4, the present invention adopts the step major and minor two cover wireless communication control apparatus being all arranged to IP65 degree of protection; The fast roaming between two wireless communication control apparatus can be realized, ensure that communication quality, shorten the working time, improve operating efficiency.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described.
Fig. 1 is process chart of the present invention;
Fig. 2 is the butt end schematic diagram of installation ship of the present invention;
Fig. 3 is that schematic diagram (top view) laid by cable of the present invention.
Detailed description of the invention
Shown in Fig. 1, Fig. 2, the immersion method of a kind of tunnel of the present invention immersed tube, described immersion method comprises the following steps: the present invention applies and two refute thick stick system installation ship and realize immersion method, described installation ship comprises waits to pacify the main barge of tube coupling butt end for sinking and waits to pacify the secondary barge of tube coupling tail end for sinking, two barge order arrangements, connected by hoist cable cable between two barges and need to pacify tube coupling, described immersion method comprises the following steps:
1, fitting-out sinking equipment on major and minor barge; During secondary fitting-out, major and minor installation ship is transported to dock entrance, twists on immersed tube, is connected with hoist cable, debugs.
2, the control terminal that the control terminal of main barge to carry out Synchronization Control or secondary barge according to monitored data by wireless communication control system to secondary barge carries out synchronous by wireless communication control system with main ship according to monitored data; The technical scheme of the secondary barge of main barge Synchronization Control is adopted in the present embodiment, the present invention is described in detail to adopt this kind of technical scheme too with lower part, and in this kind of technical scheme, commanding only just can need operate major and minor barge on main barge simultaneously; The present invention is not only confined to this scheme, when a set of wireless telecommunications are broken down, can lead to the secondary ship of direct control and carry out synchronous with main ship; Wireless communication control system described in the present embodiment comprises main wireless communication control apparatus and secondary wireless communication control apparatus; On the control terminal of main barge, commissioning installs main wireless communication control apparatus, and on the control terminal of secondary barge, commissioning installs secondary wireless communication control apparatus; Major and minor two cover wireless communication control apparatus are set to redundancy each other, after a set of wireless communication control apparatus lost efficacy, can be cut at once in the wireless communications path of another set of wireless communication control apparatus; The communication frequency of major and minor two cover wireless communication control apparatus is arranged different frequency range respectively, avoids the interference problem of single frequency band when radio communication, greatly improve the communication reliability between two wireless communication control apparatus; Major and minor two cover wireless communication control apparatus are all arranged to AFH pattern; Major and minor two cover wireless communication control apparatus are all arranged to IP65 degree of protection, and realize the fast roaming between two wireless communication control apparatus with this, roaming time can reach 10ms the soonest, ensure that communication quality, shortens the working time, improves operating efficiency.。The present invention adopts the step major and minor two cover wireless communication control apparatus being set to redundancy each other, can ensure after wherein a set of wireless communication control apparatus lost efficacy, can be cut at once in the wireless communications path of another set of wireless communication control apparatus, effectively ensure that the stability of wireless communication control system, reduce in synchronous sinking because of sync fail there is the probability of accident.
3, by main wireless communication control apparatus and secondary wireless communication control apparatus wireless connections; Unobstructed to ensure the wireless signal path between two wireless communication control apparatus.
4, TT&C system monitoring tube coupling sinking attitude also uploads monitored data in real time; The attitude of TT&C system Real-Time Monitoring tube coupling sinking and installation ship movement locus, and monitored data is transferred to the control terminal of main barge; Described tube coupling sinking attitude comprises tube coupling level to displacement attitude, Vertical dimension displacement attitude, and described installation ship movement locus refers between two barges in the track that a word order arrangement drives tube coupling synchronously to advance.
5, control terminal described in the present embodiment comprises data processing unit, data display unit and the system control unit for controlling each sinking system; The control terminal of main barge carries out synchronous sinking control by wireless communication control system to secondary barge according to monitored data.
6, the monitored data gathered is calculated by data processing unit by the control terminal of main barge, by the adjustment data calculated, is shown by data display unit; Commanding is according to this adjustment data edition Synchronization Control instruction and inputted main barge control terminal; The instruction of Synchronization Control described in the present embodiment comprises the instruction of tube coupling butt end, the instruction of tube coupling tail end and installation ship and synchronously to advance instruction.
7, main barge control terminal according to butt end Synchronization Control instruction automatically control each sinking equipment according to adjustment data treat peace tube coupling butt end carry out sinking; Main barge control terminal controls direction that main barge advances, speed and attitude automatically according to barge instruction of advancing.
What 8, main barge control terminal was real-time advances instruction by main wireless communication control apparatus synchronous transfer to secondary wireless communication control apparatus by the instruction of tube coupling tail end and barge.
9, secondary wireless communication control apparatus command synchronization of the instruction of tube coupling tail end and barge being advanced transfers to secondary barge control terminal.
10, secondary barge control terminal automatically controls each sinking equipment according to the instruction of tail end Synchronization Control and treats peace tube coupling tail end according to adjustment data and carry out synchronous sinking; Secondary barge control terminal controls direction that secondary barge advances, speed and attitude automatically according to barge instruction of advancing, and makes itself and main barge keep synchronous.
11, after peace tube coupling installs, the step of dismounting sinking equipment.
The present invention adopts the control terminal of main barge by the step of the control terminal wireless connections of wireless communication control system and secondary barge; Make to realize between two barges the data transmission of real-time synchronization, and the level being realized immersed tube to be installed by this wireless communication control system is to the synchronizing moving with Vertical dimension synchronous shift and two barges; The course of work of immersed tube sinking can be simplified, decrease commanding's quantity, make commanding on main barge, only just can complete alone the synchronous sinking process of two barges; Effectively ensure that the synchronism of two barge actions, improve synchronization accuracy; Decrease work mistake, avoid the appearance of major accident, improve operating efficiency.
The WLAN Wireless Telecom Equipment that major and minor wireless communication control apparatus described in the present embodiment all adopts Phoenix Electric Co., Ltd to produce.Described in the present embodiment, the communication frequency of main wireless communication control apparatus is arranged on 2.4GHz frequency range; The communication frequency of secondary wireless communication control apparatus is arranged on 5GHz frequency range; Vice versa.
The equipment of sinking described in the present embodiment comprises the working platform, winch gear, electric device and the control terminal that are arranged on each barge.
Shown in Fig. 2, Fig. 3, winch gear described in the present embodiment comprises two groups of ponton manoeuvring winches for controlling installation ship horizontal movement, for one group of horizontal winch of tube coupling of control valve horizontal displacement, for controlling one group of hoisting gear of tube coupling vertical displacement and the cable for each winch.
Cable described in the present embodiment comprises the hoist cable cable be arranged on hoisting gear, the mooring line being arranged on the installation cable on the horizontal winch of tube coupling and being arranged on ponton manoeuvring winch.Hoist cable cable shown in Fig. 2, for controlling tube coupling vertical displacement; H1-H4 shown in Fig. 3 is installation cable, for the displacement of control valve horizontal; M1-M8 is mooring line, for controlling the horizontal movement of installation ship.
Control terminal described in the present embodiment realizes waiting pacifying moving integrally of the displacement of tube coupling in level, vertical direction and installation ship by controlling the hoist engine be arranged on each winch.When needs will in time pacifying tube coupling and vertically put down, control terminal hoist engine drives hoist cable cable under the two groups of hoisting gear Synchronous Radios being arranged on major and minor barge, thus realizes the vertical displacement of tube coupling; When needs will in time pacifying tube coupling horizontal movement, control terminal hoist engine drives the horizontal winch synchro-draw of the two groups of tube couplings be arranged on major and minor barge to install cable, thus realizes the horizontal movement of tube coupling; When needs are by two barge horizontal movements, control terminal hoist engine drives the four groups of ponton manoeuvring winch synchro-draw mooring lines be arranged on major and minor barge, thus realizes the level of synchronization displacement of two barges.
Winch gear described in the present embodiment comprises two groups of ponton manoeuvring winches for controlling installation ship horizontal movement, for one group of horizontal winch of tube coupling of control valve horizontal displacement, for controlling one group of hoisting gear of tube coupling vertical displacement and the cable for each winch, described cable is provided with the anchor be embedded on sea bed.
The system of sinking described in the present embodiment comprises the ballast water tank water remote console operating the ballasting system in tube coupling, underwater measurement system, video monitoring system and monitor; To the positioning anchor winch console that ponton manoeuvring winch, the horizontal winch of tube coupling and hoisting gear operate and control; Barge ballast console barge ballasting system being operated and controls; The preliminary drawing system control position preliminary drawing system operated and control and the measurement tower navigation system console that measurement tower navigation system is operated and monitored.
TT&C system described in the present embodiment comprises measures tower navigation system and observing and controlling navigation system under water; Described measurement tower navigation system comprises the measurement pylon be arranged on tube coupling butt end and tail end, be arranged on and wait to pacify the tilted instrument of pipe in tube coupling, be arranged on and measure tower top GPS on pylon and prism, land total powerstation.Barge is by cube transportation to sinking region and after starting sinking, tower top prism coordinate data (GPS real-time synchronization coordinate acquisition data) is measured by land total powerstation simultaneous observation, the data summarization that the tilted instrument synchronous acquisition of connecting pipe arrives is in control terminal, and calculated the spatial attitude of tube coupling in real time by computing, in order to instruct sinking and the docking of tube coupling.Described observing and controlling navigation system under water comprises and is located at promising device and being located on tube coupling two ends main barge working platform send by ripple device; This observing and controlling navigation system is under water mainly used in treating peace tube coupling and pacify tube coupling to carry out butt junction location.

Claims (7)

1. an immersion method for tunnel immersed tube, is characterized in that: described immersion method comprises the following steps:
S1, on major and minor barge the step of fitting-out sinking equipment;
The control terminal of S2, main barge is by the step of the control terminal wireless connections of wireless communication control system and secondary barge, wireless communication control system comprises main wireless communication control apparatus and secondary wireless communication control apparatus, wherein, major and minor two cover wireless communication control apparatus are set to the step of redundancy each other;
S3, TT&C system monitoring tube coupling sinking attitude also uploads monitored data in real time, and monitored data is transferred to the step of main barge control terminal;
The control terminal of S4, main barge to carry out Synchronization Control or secondary barge according to monitored data by wireless communication control system control terminal to secondary barge carries out synchronous step by wireless communication control system with main ship according to monitored data; Wherein, commanding is inputted the step of main barge control terminal according to monitored data editor Synchronization Control instruction; Main barge control terminal controls sinking equipment according to Synchronization Control instruction and treats the step that sinking is carried out in peace tube coupling butt end; Synchronization Control instruction is transferred to the step of secondary wireless communication control apparatus by main barge control terminal by main wireless communication control apparatus; Secondary wireless communication control apparatus by Synchronization Control command to the step of secondary barge control terminal; Secondary barge control terminal automatically controls sinking equipment according to Synchronization Control instruction and treats the step that peace tube coupling tail end carries out sinking;
S5, after until peace, tube coupling installs, the step of dismounting sinking equipment.
2. the immersion method of tunnel according to claim 1 immersed tube, it is characterized in that: on the control terminal being also included in main barge in described step S2, commissioning installs main wireless communication control apparatus, and on the control terminal of secondary barge, commissioning installs the step of secondary wireless communication control apparatus.
3. the immersion method of tunnel according to claim 2 immersed tube, is characterized in that: also comprise the step communication frequency of major and minor two cover wireless communication control apparatus being arranged respectively different frequency range in described step S2.
4. the immersion method of tunnel according to claim 3 immersed tube, is characterized in that: also comprise the step major and minor two cover wireless communication control apparatus being all arranged to AFH pattern in described step S2.
5. the immersion method of tunnel according to claim 4 immersed tube, is characterized in that: also comprise the step major and minor two cover wireless communication control apparatus being all arranged to IP65 degree of protection in described step S2.
6. the immersion method of tunnel according to claim 5 immersed tube, is characterized in that: described sinking equipment comprises the working platform, winch gear, electric device and the control terminal that are arranged on each barge.
7. the immersion method of tunnel according to claim 6 immersed tube, is characterized in that: described winch gear comprises ponton manoeuvring winch for controlling installation ship horizontal movement, for the horizontal winch of tube coupling of control valve horizontal displacement, for controlling the hoisting gear of tube coupling vertical displacement and the cable for each winch.
CN201310004844.9A 2013-01-07 2013-01-07 The immersion method of tunnel immersed tube Active CN103912013B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310004844.9A CN103912013B (en) 2013-01-07 2013-01-07 The immersion method of tunnel immersed tube

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310004844.9A CN103912013B (en) 2013-01-07 2013-01-07 The immersion method of tunnel immersed tube

Publications (2)

Publication Number Publication Date
CN103912013A CN103912013A (en) 2014-07-09
CN103912013B true CN103912013B (en) 2016-03-30

Family

ID=51037984

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310004844.9A Active CN103912013B (en) 2013-01-07 2013-01-07 The immersion method of tunnel immersed tube

Country Status (1)

Country Link
CN (1) CN103912013B (en)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104652480B (en) * 2015-02-16 2017-03-01 中交一航局第二工程有限公司 A kind of method of adjustment of immersed tube axis
CN105297774A (en) * 2015-11-06 2016-02-03 王燏斌 Sinking-pipe construction device used for constructing tunnels
CN105625484B (en) * 2015-12-31 2018-01-30 中交第一航务工程局有限公司 A kind of large item deep water TT&C system and method
CN105604093A (en) * 2016-03-18 2016-05-25 中铁隧道集团二处有限公司 Floating transportation construction method of immersed tube method tunnel pipe joint along foundation trench under high-flow-speed condition
CN105780811B (en) * 2016-03-24 2018-10-02 中铁隧道集团二处有限公司 A kind of immersed tunnelling method tunnel tube coupling suitable under big flow conditions reverses end for end construction method
CN106516021B (en) * 2016-11-17 2021-06-11 中交第一航务工程局有限公司 Self-propelled underwater tunnel immersed tube carrying and mounting integrated ship
US10836459B2 (en) 2016-11-17 2020-11-17 Cccc First Harbor Engineering Co., Ltd. Self-propelled integrated ship for transporting and installing immersed tubes of underwater tunnel and construction process
CN106628018B (en) * 2016-11-17 2021-03-23 中交第一航务工程局有限公司 Self-propelled large-scale component transportation and installation integrated ship and construction process
CN106940445A (en) * 2017-03-22 2017-07-11 中交第航务工程局有限公司 A kind of water surface floading condition tube coupling scaling method
CN107044137B (en) * 2017-04-18 2019-06-07 中交一航局第二工程有限公司 A kind of immersed tube sinking interconnection method
CN107574844A (en) * 2017-08-31 2018-01-12 中交航局第二工程有限公司 A kind of posture TT&C system and method for the installation of immersed tube tunnel final joint
CN107401540A (en) * 2017-08-31 2017-11-28 中交二航局第二工程有限公司 Remote hydraulic control system for FS final spice installation
CN107642106A (en) * 2017-09-01 2018-01-30 中交第航务工程局有限公司 A kind of ship method for arranging for immersed tube installation
WO2022135606A1 (en) 2021-04-23 2022-06-30 中交第一航务工程局有限公司 Semi-submersible-type immersed tube transportation and mounting integrated ship and construction process
CN113879487B (en) * 2021-10-12 2023-02-24 中交第四航务工程局有限公司 Non-self-floating immersed tube discharging method
CN114215109B (en) * 2021-11-29 2023-02-21 中交第四航务工程局有限公司 Discharge and barge system and discharge and barge method of negative buoyancy immersed tube

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85106195A (en) * 1985-08-17 1987-03-04 麦克德莫特国际公司 The method of variable load carrying ability barge and increase barge load carrying ability
CN86100433A (en) * 1985-09-11 1987-11-25 默克德莫特国际公司 The articulated barge that ocean structure haul and following water are used
CN201856886U (en) * 2010-11-15 2011-06-08 中交一航局第二工程有限公司 Remote monitoring system for leveling ship
KR101181971B1 (en) * 2009-11-24 2012-09-11 주식회사 케이엔티 Sinking pontoon for a construction of a submarine tunnel and a contructuion method of a submarine tunnel using the same

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN85106195A (en) * 1985-08-17 1987-03-04 麦克德莫特国际公司 The method of variable load carrying ability barge and increase barge load carrying ability
CN86100433A (en) * 1985-09-11 1987-11-25 默克德莫特国际公司 The articulated barge that ocean structure haul and following water are used
KR101181971B1 (en) * 2009-11-24 2012-09-11 주식회사 케이엔티 Sinking pontoon for a construction of a submarine tunnel and a contructuion method of a submarine tunnel using the same
CN201856886U (en) * 2010-11-15 2011-06-08 中交一航局第二工程有限公司 Remote monitoring system for leveling ship

Also Published As

Publication number Publication date
CN103912013A (en) 2014-07-09

Similar Documents

Publication Publication Date Title
CN103912013B (en) The immersion method of tunnel immersed tube
EP2776359B1 (en) Vessel and crane with full dynamic compensation for vessel and wave motions and a control method thereof
CN106405662A (en) Underwater pipeline detector based on underwater robot
CN103661801B (en) The installation ancillary system of ocean engineering underwater propeller and installation method
CN204257002U (en) A kind of boats and ships are by the safety navigation backup system of ship lock
CN104875867A (en) Deep-sea cable laying system of manned submersible
EP3036154B1 (en) Offset installation systems
CN208815567U (en) A kind of immersed tube mooring installation pre- tensioning system of anchor system
CN105484267A (en) Deep-water high-flow-speed fixed-point accurate throwing and filling device and construction method
GB1478165A (en) Method and apparatus for connecting an offshore wellhead to a gathering platform
CN102832574A (en) Method for dynamically monitoring power cable in real time by three-synchronization underwater robot
CN103910041A (en) High-precision offshore wind turbine hoisting and mounting ship
CN105464049A (en) Real-time testing-controlling acceptance system for deepwater dumping ship and construction method
CN101786496B (en) Deep-water directional drilling and steel-cable back-dragging device
RU2672362C2 (en) Mounting and dismounting of flexible line
CN210370634U (en) Deep sea underwater unmanned mining system
CN111271513B (en) Visualized positioning and guiding method for submarine cable management
CN209567062U (en) Support system in the vertical underwater base station of Free Station
CN217813464U (en) Deep sea mining positioning navigation operation system
CN108879491B (en) Offshore cable laying method and cable laying system
JP2009055661A (en) Method and arrangement for laying elongated object such as cable on seabed
CN105160506A (en) Crude oil output security protection system of FPSO device
CN104659704A (en) Integrated marine laying construction method for submarine observation network system junction box
CN113443572A (en) Umbilical cable positioning control system and control method for underwater cleaning robot
CN203544345U (en) Underwater mounting and automatic positioning integrated device for cross beam of slide way

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant