CN103898812A - Ballastless track split type base - Google Patents

Ballastless track split type base Download PDF

Info

Publication number
CN103898812A
CN103898812A CN201210570816.9A CN201210570816A CN103898812A CN 103898812 A CN103898812 A CN 103898812A CN 201210570816 A CN201210570816 A CN 201210570816A CN 103898812 A CN103898812 A CN 103898812A
Authority
CN
China
Prior art keywords
boss
base
groove
type base
ballastless track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210570816.9A
Other languages
Chinese (zh)
Inventor
孙立
陈潇
王森荣
杨艳丽
张珍珍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201210570816.9A priority Critical patent/CN103898812A/en
Publication of CN103898812A publication Critical patent/CN103898812A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Railway Tracks (AREA)

Abstract

The invention belongs to a railway ballastless track structure system and particularly relates to a ballastless track split type base. The ballastless track split type base comprises base bodies longitudinally arranged along a railway in a mutually-matched mode. Gaps are reversed in connection portions between the adjacent base bodies. The corresponding mating faces between every two adjacent base bodies are provided with a first boss and a first groove in the horizontal direction respectively, wherein the first boss and the first groove are matched with each other. The corresponding mating faces between every two adjacent base bodies are provided with a second boss and a second groove in the perpendicular direction respectively, and the second boss and the second groove are matched with each other. According to the ballastless track split type base, through cooperation use of the bosses and the grooves, displacement of adjacent unit base bodies in the longitudinal direction, the horizontal direction and the vertical direction can be limited at the same time, the ballastless track split type base is high in adaptability to the longitudinal and horizontal deformation and differential settlement, overlarge longitudinal and horizontal deformation of the base can be avoided, slow settlement transition can be achieved under the condition of the differential settlement, and step-type settlement of the base can be avoided.

Description

Non-fragment orbit sectional type base
Technical field
The invention belongs to railway ballastless track structural system, be specifically related to a kind of non-fragment orbit sectional type base.
Background technology
At present, engineering is applied more non-fragment orbit base or supporting bed structure, mostly be continous way understructure, as CRTS I type double-block type ballastless track roadbed location supporting bed, CRTS II plate-type ballastless track roadbed and location, tunnel supporting bed, it is continous way understructure, on described base, cuts a horizontal precracking every certain length.This continuous structure is affected greatly by TEMPERATURE FORCE, and supporting bed or base may form crack because of external factor generation longitudinal strain, strong not to the differential settlement compliance on basis under line.
In CRTS III plate-type non-fragment orbit, roadbed location base is unit fraction block structure, and its unit base length is generally longer, for 3-5 piece track plates/road bed board long.Base adopts shearing rod to be connected or only adopts cystosepiment to separate with base.Shearing rod connected mode is difficult to ensure that in work progress all shearing rods of card are in the same plane, if under line there is very large differential settlement in basis, and along base horizontal direction differential settlement amount not etc., shearing rod is again in different planes, can cause along each row's shearing rod of base lateral aspects all stressed not etc., because the general rigidity of shearing rod is larger, may form the horizontal departure that left and right rail level is larger, cause that vehicle rocks inhomogeneous stressed with two strands of rail, causes rail irregular wear; Separate mode if only adopt cystosepiment, once under line there is differential settlement distortion in basis, also there is without restriction corresponding sedimentation in adjacent pans, may cause susceptor surface to form the discrepancy in elevation, even may cause the formation of the rail level step discrepancy in elevation, the irregularity of this kind of step rail level is also unfavorable to driving a vehicle.
Summary of the invention
Object of the present invention is exactly for above-mentioned defect, and it had been both unit partitioned organization that one is provided, and length is shorter, can limit again the non-fragment orbit sectional type base of base upper and lower displacement.
The technical solution used in the present invention is: a kind of non-fragment orbit sectional type base, comprise along railway longitudinally cooperatively interact arrange base, gap is left in adjacent pans junction, and between described adjacent pans, on the fitting face of correspondence, along continuous straight runs is respectively equipped with the first boss and the first groove that cooperatively interact; Between described adjacent pans, on the fitting face of correspondence, be vertically respectively equipped with the second boss and the second groove that cooperatively interact.
Preferably, the boss of described adjacent pans and the border of groove are all within the scope of the profile of base separately.
Preferably, the element length of described base can be one or the length of track plates how soon.
Preferably, the number of described boss and groove is one or more.
Preferably, the boss cooperatively interacting in described adjacent pans and the side of groove can arrange elastomeric material.
Preferably, packing material not in described gap, also can filling flexible material.
Beneficial effect of the present invention is:
1, because understructure of the present invention is unit sectional type understructure, its length can shorten to the length of a track plates, can reduce to a greater degree the impact of TEMPERATURE FORCE on base, ensures that base is difficult for occurring longitudinal large deformation.
2, base two ends are equipped with boss or groove in plane and short transverse, coordinate with adjacent pans, can limit displacement longitudinal and transverse, vertical direction simultaneously, to the strong adaptability of vertical lateral deformation and differential settlement, can avoid base that excessive vertical lateral deformation occurs, also can be by mild sedimentation transition under differential settlement condition, avoid the sedimentation of base generation step.
3, the present invention is without increasing special material and construction equipment in base construction, and construction is simple, easy to maintenance, can meet the high ride requirement of high-speed railway, passenger dedicated railway line, inter-city passenger rail.
Brief description of the drawings
Fig. 1 and Fig. 2 are the embodiment of the present invention 1 front view and skiagraph.
Fig. 1 and Fig. 3 are the embodiment of the present invention 2 front views and skiagraph.
Fig. 1 and Fig. 4 are the embodiment of the present invention 3 front views and skiagraph.
Fig. 1 and Fig. 5 are the embodiment of the present invention 4 front views and skiagraph.
Fig. 1 and Fig. 6 are the embodiment of the present invention 5 front views and skiagraph.
Fig. 7 and Fig. 8 are the embodiment of the present invention 6 front views and skiagraph.
Fig. 7 and Fig. 9 are the embodiment of the present invention 7 front views and skiagraph.
Fig. 7 and Figure 10 are the embodiment of the present invention 8 front views and skiagraph.
Fig. 7 and Figure 11 are the embodiment of the present invention 9 front views and skiagraph.
Fig. 7 and Figure 12 are the embodiment of the present invention 10 front views and skiagraph.
Detailed description of the invention
Below in conjunction with accompanying drawing, the present invention is described in further detail:
Embodiment 1: as shown in Figure 1, the present invention includes along railway longitudinally cooperatively interact arrange base, the length of base shortens to the length of a track plates, can reduce to a greater degree the impact of TEMPERATURE FORCE on base, ensure base be difficult for occur longitudinal large deformation.Gap 3 is left in junction between adjacent pans 1,2, between adjacent pans 1,2, on the fitting face of correspondence, along continuous straight runs is respectively equipped with the first boss 4 and the first groove 5 that cooperatively interact, and the boss cooperatively interacting and groove can limit the vertical, horizontal displacement between base.
As shown in Figure 2, between adjacent pans 1,2, on the fitting face of correspondence, be vertically respectively equipped with the second boss 6 and the second groove 7 that cooperatively interact.Boss and groove on base 1,2 coordinate the displacement that can limit the vertical direction between base in vertical direction.In adjacent pans 1,2 boss and the border of groove all within the scope of the profile of base separately.The boss cooperatively interacting in adjacent pans 1,2 and the side of groove can arrange elastomeric material, and the interior not packing material in gap 3 of boss and groove fit, also can filling flexible material.
Embodiment 2-5, as shown in Fig. 1, Fig. 3-6, these embodiment are substantially the same manner as Example 1, all establish first boss 3 and first groove 4 on adjacent pans 1,2 along continuous straight runs.Difference is, adjacent pans 1,2 is established one or more the second boss 6 and the second groove 7 in the vertical direction.As shown in Figure 3, base 1 boss is in the vertical direction contrary with Fig. 2, is that left end concave and downward convex, right-hand member epirelief are recessed, the boss corresponding with adjacent pans 2 and groove fit.As shown in Figure 4, base 1 right-hand member the second boss 6 is located at the middle part of base, and fovea superior convexity is recessed, and left end arranges groove at middle part, with boss and the groove fit of adjacent pans 2 in middle part setting.As shown in Figure 5, the second groove 7 is all established at base 1 middle part, two ends, and the second boss 6 of establishing with adjacent pans 2 two ends coordinates.As shown in Figure 6, be equipped with two the second boss 6 and the second groove 7 in the end of base 1 and adjacent pans 2.
Embodiment 6, as shown in Figure 7, Figure 8, establishes two the first boss 4 on base 1 two ends along continuous straight runs, two the first grooves 5 are established at adjacent pans 2 two ends, and boss and groove cooperatively interact, and leave gap.Base 1 and adjacent pans 2 are established respectively second boss 6 and second groove 7 in the vertical direction.
Embodiment 7-10, as shown in Fig. 7, Fig. 9-12, establishes multiple the first boss 4 and the first groove 5 on adjacent pans 1,2 two ends along continuous straight runs, establish in the vertical direction one or more the second boss 6 and the second groove 7.
Base should carry out the examination on basis under line before construction, and clean, prewet etc., first lay base steel mesh reinforcement by the definite position dimension of design drawing, installation form is built, in gap 3, should have homologue to cover to prevent concrete slag and other foreign material from falling into gap, construction should ensure substructure height, base convex platform and groove size precision.Then seat concrete is carried out to maintenance, that treats that concrete strength reaches design strength more than 75% just can carry out stripping, then carries out the construction of follow-up track structure.The foreign material such as scum silica frost and other mounds of finally removing in seam 3 gaps can carry out the filling of gap material.
The above, be only preferred embodiment of the present invention, not structure of the present invention done to any pro forma restriction.Any simple modification, equivalent variations and modification that every foundation technical spirit of the present invention is done above embodiment, all still belong in the scope of technical scheme of the present invention, as the second boss on base being arranged on to the longitudinal end of the first boss, corresponding the second groove is arranged on the inner face of the first groove, the first boss and the second boss have difference in height, the first groove and the second groove have difference in height, can reach equally the object that restriction base deforms.

Claims (6)

1. a non-fragment orbit sectional type base, comprise along railway longitudinally cooperatively interact arrange base, gap is left in adjacent pans junction, it is characterized in that: between described adjacent pans, on the fitting face of correspondence, along continuous straight runs is respectively equipped with the first boss and the first groove that cooperatively interact; Between described adjacent pans, on the fitting face of correspondence, be vertically respectively equipped with the second boss and the second groove that cooperatively interact.
2. non-fragment orbit sectional type base according to claim 1, is characterized in that: the boss of described adjacent pans and the border of groove are all within the scope of the profile of base separately.
3. non-fragment orbit sectional type base according to claim 1, is characterized in that: the element length of described base can be the length of one or more track plates.
4. non-fragment orbit sectional type base according to claim 1, is characterized in that: the number of described boss and groove is one or more.
5. non-fragment orbit sectional type base according to claim 1, is characterized in that: the boss cooperatively interacting in described adjacent pans and the side of groove can arrange elastomeric material.
6. non-fragment orbit sectional type base according to claim 1, is characterized in that: packing material not in described gap, and also can filling flexible material.
CN201210570816.9A 2012-12-25 2012-12-25 Ballastless track split type base Pending CN103898812A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210570816.9A CN103898812A (en) 2012-12-25 2012-12-25 Ballastless track split type base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210570816.9A CN103898812A (en) 2012-12-25 2012-12-25 Ballastless track split type base

Publications (1)

Publication Number Publication Date
CN103898812A true CN103898812A (en) 2014-07-02

Family

ID=50990369

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210570816.9A Pending CN103898812A (en) 2012-12-25 2012-12-25 Ballastless track split type base

Country Status (1)

Country Link
CN (1) CN103898812A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105200868A (en) * 2015-09-14 2015-12-30 中国铁道科学研究院金属及化学研究所 Novel slab ballastless track structure
CN105714626A (en) * 2016-01-21 2016-06-29 中铁第四勘察设计院集团有限公司 Joggle joint type bearing rail beam structure for middle and low-speed magnetic suspension traffic engineering low line
CN107227659A (en) * 2017-07-10 2017-10-03 中铁第四勘察设计院集团有限公司 A kind of assembled non-fragment orbit
CN107858868A (en) * 2017-10-31 2018-03-30 天津银龙预应力材料股份有限公司 A kind of railcar track plates
CN108774922A (en) * 2018-08-13 2018-11-09 中铁二院工程集团有限责任公司 A kind of assembled ballastless track system
CN108774921A (en) * 2018-08-13 2018-11-09 中铁二院工程集团有限责任公司 A kind of assembled fragment-free track slab
CN113550176A (en) * 2021-07-07 2021-10-26 高速铁路建造技术国家工程实验室 External spacing module pin-connected panel track structure
CN113737575A (en) * 2021-09-02 2021-12-03 中铁二院工程集团有限责任公司 Ballastless track plate end damping clamping groove device

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105200868A (en) * 2015-09-14 2015-12-30 中国铁道科学研究院金属及化学研究所 Novel slab ballastless track structure
CN105714626A (en) * 2016-01-21 2016-06-29 中铁第四勘察设计院集团有限公司 Joggle joint type bearing rail beam structure for middle and low-speed magnetic suspension traffic engineering low line
CN105714626B (en) * 2016-01-21 2017-05-10 中铁第四勘察设计院集团有限公司 Joggle joint type bearing rail beam structure for middle and low-speed magnetic suspension traffic engineering low line
WO2017125029A1 (en) * 2016-01-21 2017-07-27 中铁第四勘察设计院集团有限公司 Joggle joint type rail support beam structure for middle and low-speed magnetic suspension traffic engineering low line
CN107227659A (en) * 2017-07-10 2017-10-03 中铁第四勘察设计院集团有限公司 A kind of assembled non-fragment orbit
CN107858868A (en) * 2017-10-31 2018-03-30 天津银龙预应力材料股份有限公司 A kind of railcar track plates
CN108774922A (en) * 2018-08-13 2018-11-09 中铁二院工程集团有限责任公司 A kind of assembled ballastless track system
CN108774921A (en) * 2018-08-13 2018-11-09 中铁二院工程集团有限责任公司 A kind of assembled fragment-free track slab
CN113550176A (en) * 2021-07-07 2021-10-26 高速铁路建造技术国家工程实验室 External spacing module pin-connected panel track structure
CN113737575A (en) * 2021-09-02 2021-12-03 中铁二院工程集团有限责任公司 Ballastless track plate end damping clamping groove device

Similar Documents

Publication Publication Date Title
CN103898812A (en) Ballastless track split type base
CN206538637U (en) A kind of track strengthening device for existing railway
CN203487475U (en) Line suspending and reinforcing structure for existing line jacking bridge and culvert construction
CN204644799U (en) A kind of four line ballastless track roadbed pile slab structure
CN104562863B (en) A kind of dual-purpose railway two-orbit
CN106049209B (en) A kind of interim rail support meanss changed for railway ballastless track supporting layer
CN109868691B (en) Deformation-adjustable high-speed railway roadbed structure, construction method and settlement deformation adjustment method
CN103437254A (en) Reinforcing device for railway turnout area circuit during jacking for frame bridge
CN101798785A (en) Ballastless track structure
CN104480805A (en) Framed sleeper unit
CN107938438A (en) High-speed railway box road structure and construction method
CN103243619A (en) Slab-type replaceable combined ballast bed system and construction process
CN106192620B (en) A kind of railway ballastless track supporting layer and substructure change method
CN205223847U (en) Bridge expansion joint device
CN106400613A (en) Ballastless track
CN101699450B (en) Seamless turnout structural system on bridge and dynamic analysis method thereof
CN105178171B (en) Chain type butt strap structure based on seamless bridge
CN203007734U (en) Partitioned base of ballastless track
CN107805977A (en) Elastic shoe and resilient sleeper-bearing component and non-fragment orbit for non-fragment orbit
CN105421160B (en) A kind of concrete bedding top surface line type control method
KR20140028846A (en) Embedded rail track system and method for constructing the system
CN102535260A (en) Low frequency floating slab track
CN204162955U (en) Soft clay area modern tram subgrade stiffness transition structure
CN210737257U (en) Road tunnel transition structure and traffic line
CN208072217U (en) A kind of portable paves track

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140702