CN103896521A - Preparation method of anti-seepage water delivery tank of channel - Google Patents

Preparation method of anti-seepage water delivery tank of channel Download PDF

Info

Publication number
CN103896521A
CN103896521A CN201410076812.4A CN201410076812A CN103896521A CN 103896521 A CN103896521 A CN 103896521A CN 201410076812 A CN201410076812 A CN 201410076812A CN 103896521 A CN103896521 A CN 103896521A
Authority
CN
China
Prior art keywords
water delivery
preparation
tank
concrete
seepage control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410076812.4A
Other languages
Chinese (zh)
Other versions
CN103896521B (en
Inventor
张守杰
孙景路
张滨
司振江
刘丽佳
陶琦
钟华
刘建明
徐丽丽
李兆宇
吴志琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang Sanbei Water Conservancy Technology Development Co ltd
Original Assignee
HEILONGJIANG PROV WATER CONSERVANCY SCIENCE INST
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HEILONGJIANG PROV WATER CONSERVANCY SCIENCE INST filed Critical HEILONGJIANG PROV WATER CONSERVANCY SCIENCE INST
Priority to CN201410076812.4A priority Critical patent/CN103896521B/en
Publication of CN103896521A publication Critical patent/CN103896521A/en
Application granted granted Critical
Publication of CN103896521B publication Critical patent/CN103896521B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a preparation method of an anti-seepage delivery water of a channel, relates to the preparation method of a U-shaped/rectangular water tank for water delivery in irrigation and water conservancy, and is used for solving the problems of rough surface, poor freezing resistance and poor durability of a U-shaped tank and a trapezoid tank which are obtained by the existing preparation method. The preparation method provided by the invention comprises the following steps: 1, preparing raw materials; 2, evenly stirring the raw materials in a stirrer and then pouring into a mould; vibrating the mould of the anti-seepage water delivery tank on a suspension-type vibration platform for finishing the material distribution vibration moulding of the concrete raw materials; 3, transporting the mould carried with a concrete water tank into a curing kiln for steam curing and then transferring the mould from the curing kiln; and 4, demoulding the anti-seepage water delivery tank, thus finishing the preparation of the anti-seepage water delivery tank of a channel. According to the method, the overall vibration treatment of the concrete raw materials in the mould is carried out by adopting the vibration platform, so that the concrete has the advantages of uniform quality, smooth surface and good structural mechanical property and the concrete parameter of the concrete can reach a C50F300 level.

Description

A kind of preparation method of canal seepage control water delivery tank
Technical field
The present invention relates to a kind of for farmland water conservancy water delivery U(square) preparation method of type tank.
Background technology
China, to account for the Freshwater resources in the world 6%, 9% arable land, solves the food problem of the Liao Zhan world 21% population, and vital effect has been brought into play in farmland water conservancy.
In recent years, central authorities adhere to using construction of water conservancy works as the important foundation that ensures agriculture steady progression and national food safety, constantly perfect policies support system, and increasing work in every dynamics, promotes farmland water conservancy and enters new developmental stage.Within 2012, start four provinces and regions, northeast " it is moving that water saving increases wholesale grain store ", but branch canal is below to field, this " last kilometer " is the weakest link of farmland water conservancy, the problems such as ubiquity standard is low, supporting poor, aging in bad repair, benefit decay, farm field irrigation drainage " last kilometer " problem becomes increasingly conspicuous.
The lining canal of farmland water conservancy water delivery mainly contains U-lag and dovetail groove, existing U-lag and dovetail groove two side and bottom size uniform thickness, and waste of material, cost is high, and monolithic length only has 500mm, and section floor space is large.Existing production technique generally adopts low slump concrete vibration or compression moulding, existing water tank die divides that inner membrance adventitia is vertical to be laid, inner membrance base plate place installs vibrator additional, entirety is placed under pressing machine, and when production, the vibration of low slump concrete limit is filled on limit, fills after certain altitude, push with pressing machine, then take mould adventitia apart, goods are shifted out to mould and deliver to the maintenance of maintenance district, this auto-processes level and efficiency are low.Simultaneously because goods adopt low slump concrete, receptor site vibration source and fill time effects, goods are suffered exciting force and asynchronism(-nization) everywhere, easily causing that regional area concrete is crossed shakes, owes to shake, and extrudate density is inhomogeneous, surface irregularity, freeze proof, poor durability, quality causes anxiety and poor performance.
Summary of the invention
The object of the invention is the U-lag and the dovetail groove surface irregularity that obtain in order to solve existing preparation method, the problem of freeze proof, poor durability, and the preparation method of a kind of U (square) type canal seepage control water delivery tank is provided.
The preparation method of canal seepage control water delivery tank of the present invention realizes according to the following steps:
One, take the medium sand of water, the 600~720kg of breeze, the 178~198kg of flyash, the 25~30kg of cement, the 70~80kg of 390~420kg, rubble that 677~718kg specification is 1-2, rubble, the steel fiber of 5~8kg and the admixture of 9.5~10.5kg that 400~450kg specification is 0.5 as raw material;
Two, the raw material taking is joined to stirrer, after stirring, transfer in material distributing machine by heater car, antiseepage water delivery water tank die is placed on shaking table, by the deflector chute in material distributing machine, raw material is poured in antiseepage water delivery water tank die, shaking table drives the frequency vibration 2~3min of antiseepage water delivery water tank die with 1000~1500Hz simultaneously, completes the cloth vibratory compaction of concrete material;
Three, the antiseepage water delivery water tank die that is loaded with vibratory compaction concrete water tank is transported in curing kilns, first the at room temperature quiet 1.8~2.2h that stops, then pass through vapour passage, be warming up to 60~68 ℃ with the temperature rise rate of 13~16 ℃/h, keep being cooled to room temperature with the rate of temperature fall of 13~18 ℃/h again after 2.5h, the antiseepage water delivery water tank die that is loaded with maintenance formation of concrete sends out curing kilns;
Four, the antiseepage water delivery water tank die that is loaded with maintenance formation of concrete that sends out curing kilns is carried out to demoulding processing, complete the preparation of canal seepage control water delivery tank.
The present invention adopts floated shaking table to carry out body vibration processing to the concrete material in mould, in order to the exhaust of concrete materials, closely knit and moulding, shaking table is floated shaking table, vibration efficiency energy maximum effect is on water delivery tank goods, make the quality of canal seepage control water delivery tank product even, closely knit, smooth surface, structural mechanical property be good, more than ultimate compression strength reaches 50MPa, concrete parameters reaches C50F300 level, can be according to the size of product in preparation process, regulation and control vibrational frequency and time.Avoid the generation of existing technique because of the vibration uneven phenomenon of localized vibration initiation, the long U of 2000mm (square) the tank weather resistance and the frost resistance that prepare are greatly improved.
Accompanying drawing explanation
Fig. 1 is the one-piece construction schematic diagram of the canal seepage control water delivery tank for preparing of step 4 of the present invention;
Fig. 2 is the end view of the canal seepage control water delivery tank for preparing of step 4 of the present invention.
Embodiment
Embodiment one: the preparation method of present embodiment canal seepage control water delivery tank implements according to the following steps:
One, take the medium sand of water, the 600~720kg of breeze, the 178~198kg of flyash, the 25~30kg of cement, the 70~80kg of 390~420kg, rubble that 677~718kg specification is 1-2, rubble, the steel fiber of 5~8kg and the admixture of 9.5~10.5kg that 400~450kg specification is 0.5 as raw material;
Two, the raw material taking is joined to stirrer, after stirring, transfer in material distributing machine by heater car, antiseepage water delivery water tank die is placed on shaking table, by the deflector chute in material distributing machine, raw material is poured in antiseepage water delivery water tank die, shaking table drives the frequency vibration 2~3min of antiseepage water delivery water tank die with 1000~1500Hz simultaneously, completes the cloth vibratory compaction of concrete material;
Three, the antiseepage water delivery water tank die that is loaded with vibratory compaction concrete water tank is transported in curing kilns, first the at room temperature quiet 1.8~2.2h that stops, then pass through vapour passage, be warming up to 60~68 ℃ with the temperature rise rate of 13~16 ℃/h, keep being cooled to room temperature with the rate of temperature fall of 13~18 ℃/h again after 2.5h, the antiseepage water delivery water tank die that is loaded with maintenance formation of concrete sends out curing kilns;
Four, the antiseepage water delivery water tank die that is loaded with maintenance formation of concrete that sends out curing kilns is carried out to demoulding processing, complete the preparation of canal seepage control water delivery tank.
Room temperature described in the production technique of present embodiment canal seepage control water delivery tank is 20 ℃.
The production technique of present embodiment canal seepage control water delivery tank mainly by batching stirring system, cloth vibrational system, curing system, modular system is returned in the demoulding and electrical control system forms; wherein in maintenance passage, adopt vapor cure; maintenance passage is divided into four regions; in Ji Jingting district, quiet stopping processed; adopt steam heating at heating zone; keep the homo(io)thermism heating up while end in flat-temperature zone, finally in cooling area, be down to room temperature.In the passage of maintenance simultaneously, is furnished with Monitoring systems, can automatically control temperature and humidity in maintenance passage, due to the special construction design of punching block, when concrete water tank goods pass through the maintenance passage of temperature variation in specific time, can guarantee that mould can fully contact with steam, optimize maintenance effect, to guarantee to meet the requirements of demoulding strength.
Embodiment two: described in step 1 that what present embodiment was different from embodiment one is, the label of cement is 425.Other step and parameter are identical with embodiment one.
Embodiment three: the rank of what present embodiment was different from embodiment one or two the is flyash described in step 1 is one-level.Other step and parameter are identical with embodiment one or two.
Embodiment four: the length of what present embodiment was different from one of embodiment one to three the is steel fiber described in step 1 is 1~2cm.Other step and parameter are identical with one of embodiment one to three.
Embodiment five: what present embodiment was different from one of embodiment one to four is that the admixture described in step 1 is made up of water reducer, air entrapment agent and adjustable solidification agent.Other step and parameter are identical with one of embodiment one to four.
Embodiment six: what present embodiment was different from one of embodiment one to five is that step 3 is warming up to 65 ℃ with the temperature rise rate of 15 ℃/h.Other step and parameter are identical with one of embodiment one to five.
Embodiment seven: what present embodiment was different from one of embodiment one to six is that step 3 is cooled to room temperature with the rate of temperature fall of 15 ℃/h again.Other step and parameter are identical with one of embodiment one to six.
Embodiment eight: what present embodiment was different from embodiment one is that the canal seepage control water delivery tank that step 4 obtains is linked into an integrated entity by two side 1 and bottom land 2, the outer 1-2 of two side 1 is perpendicular to horizontal plane, the interior of two side is tilted to lower formation U-shaped cross section along 1-1, the bottom in U-shaped cross section is parallel to horizontal plane, be equipped with U-shaped watertight rubber groove 3 at the end face at canal seepage control water delivery tank two ends, and the length of canal seepage control water delivery tank is 2000mm.
The interior of present embodiment two side is tilted to lower formation U-shaped cross section along 1-1, and wherein the interior angle α along 1-1 and vertical of sidewall is 2.3 °.
Embodiment mono-: the preparation method of the present embodiment canal seepage control water delivery tank realizes according to the following steps:
One, take the medium sand of water, the 720kg of breeze, the 180kg of first level flour coal ash, the 30kg of 425 cement, the 80kg of 420kg, rubble that 700kg specification is 1-2, rubble, the steel fiber of 6kg and the admixture of 10kg that 420kg specification is 0.5 as raw material;
Two, the raw material taking is joined to planetary vertical-shaft stirrer, after stirring, transfer in material distributing machine by heater car, antiseepage water delivery water tank die is placed on floated shaking table, by the deflector chute in material distributing machine, raw material is poured in antiseepage water delivery water tank die, shaking table drives the frequency vibration 2.5min of antiseepage water delivery water tank die with 1200Hz simultaneously, completes the cloth vibratory compaction of concrete material;
Three, the antiseepage water delivery water tank die that is loaded with vibratory compaction concrete water tank is transported in curing kilns, first the at room temperature quiet 2h that stops, then pass through vapour passage, be warming up to 65 ℃ with the temperature rise rate of 15 ℃/h, keep being cooled to room temperature with the rate of temperature fall of 15 ℃/h again after 2.5h, the antiseepage water delivery water tank die that is loaded with maintenance formation of concrete sends out curing kilns;
Four, the antiseepage water delivery water tank die that is loaded with maintenance formation of concrete that sends out curing kilns is carried out to Pneumatic demould processing, complete the preparation of canal seepage control water delivery tank.
The selected antiseepage water delivery water tank die of the present embodiment is of a size of 400*400*2000mm, the length of mould is 2000mm, the canal seepage control water delivery tank that the demoulding obtains transports finished product district piling and deposits after quality inspection, packing, more than the ultimate compression strength of product canal seepage control water delivery tank reaches 50MPa, concrete parameters reaches C50F300 level (SL352-2006 concrete for hydraulic structure testing regulation).Because step 2 is placed in antiseepage water delivery water tank die on floated shaking table, make its body vibration, concrete anti-seepage water delivery U (square) the type flume surface obtaining is smoothly closely knit, not because of the bubble cavity of rigid concrete localized vibration compression moulding generation, improve the mechanical property of the antiseepage water delivery tank obtaining.

Claims (8)

1. a preparation method for canal seepage control water delivery tank, is characterized in that the preparation method of canal seepage control water delivery tank realizes according to the following steps:
One, take the medium sand of water, the 600~720kg of breeze, the 178~198kg of flyash, the 25~30kg of cement, the 70~80kg of 390~420kg, rubble that 677~718kg specification is 1-2, rubble, the steel fiber of 5~8kg and the admixture of 9.5~10.5kg that 400~450kg specification is 0.5 as raw material;
Two, the raw material taking is joined to stirrer, after stirring, transfer in material distributing machine by heater car, antiseepage water delivery water tank die is placed on shaking table, by the deflector chute in material distributing machine, raw material is poured in antiseepage water delivery water tank die, shaking table drives the frequency vibration 2~3min of antiseepage water delivery water tank die with 1000~1500Hz simultaneously, completes the cloth vibratory compaction of concrete material;
Three, the antiseepage water delivery water tank die that is loaded with vibratory compaction concrete water tank is transported in curing kilns, first the at room temperature quiet 1.8~2.2h that stops, then pass through vapour passage, be warming up to 60~68 ℃ with the temperature rise rate of 13~16 ℃/h, keep being cooled to room temperature with the rate of temperature fall of 13~18 ℃/h again after 2.5h, the antiseepage water delivery water tank die that is loaded with maintenance formation of concrete sends out curing kilns;
Four, the antiseepage water delivery water tank die that is loaded with maintenance formation of concrete that sends out curing kilns is carried out to demoulding processing, complete the preparation of canal seepage control water delivery tank.
2. the preparation method of a kind of canal seepage control water delivery tank according to claim 1, is characterized in that the label of cement is 425 described in step 1.
3. the preparation method of a kind of canal seepage control water delivery tank according to claim 1, the rank that it is characterized in that the flyash described in step 1 is one-level.
4. the preparation method of a kind of canal seepage control water delivery tank according to claim 1, the length that it is characterized in that the steel fiber described in step 1 is 1~2cm.
5. the preparation method of a kind of canal seepage control water delivery tank according to claim 1, is characterized in that the admixture described in step 1 is made up of water reducer, air entrapment agent and adjustable solidification agent.
6. the preparation method of a kind of canal seepage control water delivery tank according to claim 1, is characterized in that step 3 is warming up to 65 ℃ with the temperature rise rate of 15 ℃/h.
7. the preparation method of a kind of canal seepage control water delivery tank according to claim 1, is characterized in that step 3 is cooled to room temperature with the rate of temperature fall of 15 ℃/h again.
8. the preparation method of a kind of canal seepage control water delivery tank according to claim 1, it is characterized in that the canal seepage control water delivery tank that step 4 obtains is linked into an integrated entity by two side (1) and bottom land (2), the outer (1-2) of two side (1) is perpendicular to horizontal plane, the interior edge (1-1) of two side is tilted to lower formation U-shaped cross section, the bottom in U-shaped cross section is parallel to horizontal plane, be equipped with U-shaped watertight rubber groove (3) at the end face at canal seepage control water delivery tank two ends, and the length of canal seepage control water delivery tank is 2000mm.
CN201410076812.4A 2014-03-04 2014-03-04 A kind of preparation method of canal seepage control water delivery tank Active CN103896521B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410076812.4A CN103896521B (en) 2014-03-04 2014-03-04 A kind of preparation method of canal seepage control water delivery tank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410076812.4A CN103896521B (en) 2014-03-04 2014-03-04 A kind of preparation method of canal seepage control water delivery tank

Publications (2)

Publication Number Publication Date
CN103896521A true CN103896521A (en) 2014-07-02
CN103896521B CN103896521B (en) 2015-10-28

Family

ID=50988152

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410076812.4A Active CN103896521B (en) 2014-03-04 2014-03-04 A kind of preparation method of canal seepage control water delivery tank

Country Status (1)

Country Link
CN (1) CN103896521B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105016662A (en) * 2015-08-04 2015-11-04 常州市鼎日环保科技有限公司 Preparation method of anti-seepage concrete
CN106045424A (en) * 2016-05-25 2016-10-26 象州县科学技术局 Method for producing prefabricated member of concrete ditch by using construction waste
CN106759123A (en) * 2017-01-06 2017-05-31 石河子大学 The method for eliminating the canal for water conveyance frost heaving failure effect that Frozen Area winter is run without ice sheet, high water level
CN110395947A (en) * 2019-07-29 2019-11-01 安徽省交通规划设计研究总院股份有限公司 A kind of embankment gutter fiber reinforcement high performance concrete

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101274829A (en) * 2008-05-08 2008-10-01 同济大学 High-early-strength high-slump-retaining shrinkage-compensating self-compaction C60 concrete
CN102869633A (en) * 2010-03-01 2013-01-09 电气化学工业株式会社 Calcium ferroaluminate compound, cement admixture and process for producing same, and cement composition
CN103224356A (en) * 2013-02-07 2013-07-31 黄贺明 Green environmentally-friendly powder reinforced concrete water delivery pipe

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101274829A (en) * 2008-05-08 2008-10-01 同济大学 High-early-strength high-slump-retaining shrinkage-compensating self-compaction C60 concrete
CN102869633A (en) * 2010-03-01 2013-01-09 电气化学工业株式会社 Calcium ferroaluminate compound, cement admixture and process for producing same, and cement composition
CN103224356A (en) * 2013-02-07 2013-07-31 黄贺明 Green environmentally-friendly powder reinforced concrete water delivery pipe

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105016662A (en) * 2015-08-04 2015-11-04 常州市鼎日环保科技有限公司 Preparation method of anti-seepage concrete
CN105016662B (en) * 2015-08-04 2017-01-18 广州市盈坚混凝土有限公司 Preparation method of anti-seepage concrete
CN106045424A (en) * 2016-05-25 2016-10-26 象州县科学技术局 Method for producing prefabricated member of concrete ditch by using construction waste
CN106759123A (en) * 2017-01-06 2017-05-31 石河子大学 The method for eliminating the canal for water conveyance frost heaving failure effect that Frozen Area winter is run without ice sheet, high water level
CN106759123B (en) * 2017-01-06 2018-11-20 石河子大学 The method for eliminating the canal for water conveyance frost heaving failure effect that Frozen Area winter runs without ice sheet, high water level
CN110395947A (en) * 2019-07-29 2019-11-01 安徽省交通规划设计研究总院股份有限公司 A kind of embankment gutter fiber reinforcement high performance concrete

Also Published As

Publication number Publication date
CN103896521B (en) 2015-10-28

Similar Documents

Publication Publication Date Title
CN104723449B (en) A kind of automatic assembly line of building industrialization concrete prefabricated element
CN103896521B (en) A kind of preparation method of canal seepage control water delivery tank
CN103979872A (en) Preparation method of 2-meter lightweight prefabricated concrete U-shaped channel
CN102632547B (en) Semi-automatic production method of novel composite heat insulation building block
CN103541289A (en) Colored high-titanium heavy slag permeable pavement brick and production method thereof
CN103819154A (en) Recycled concrete using waste porcelain tiles as coarse and fine aggregates and preparation method thereof
CN103572966B (en) The construction method of silo funnel liner
CN105110767A (en) Method for preparing water permeable pavement bricks by means of waste ceramic bricks
CN104230256A (en) Self-compaction concrete and production technique of prefabricated municipal quadrate culvert component
CN104692714A (en) Self compact concrete and environmentally friendly slope protection member production technology
CN107139320A (en) A kind of high-performance foam concrete process units
CN104290171A (en) Automatic production line for concrete water tank
CN101712180A (en) Totally-enclosed type clay hollow brick and manufacture method thereof
CN104002374A (en) Plaster concrete building block forming machine
CN103290973B (en) Manufacturing process for concrete compound self-heat-preservation building block
CN105693162A (en) Half-dry concrete and method for prefabricating hollow floor slab cut according to length
CN104821534A (en) Side channel cable trough combined body, preparation method and side channel cable trough combined structure
CN106217584A (en) The device of mechanization clay molding
CN213005823U (en) Die for manufacturing multilayer sand fixing plate with holes and sand fixing plate with holes
CN208577911U (en) It is a kind of movable type curb stone concrete backrest pour trolley
CN104892026A (en) Concrete closed hydrothermal synthesis hardening process
CN206855727U (en) Foam concrete process units
CN104803637A (en) Preparation method of centrifugal concrete water supply-drainage pipe capable of reducing using amount of binding material
CN104817307A (en) Tunnel central ditch, single body thereof and method for manufacturing single body
TWI821690B (en) A production method and equipment of energy saving and environmental protection with lightweight insulated hive precast concrete

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190822

Address after: 150080 No. 12 Yanxing Road, Nangang District, Harbin City, Heilongjiang Province

Patentee after: Heilongjiang Sanbei Water Conservancy Science and Technology Development Co.

Address before: 150080 Heilongjiang City, Harbin Province, Nangang District Road No. 78

Patentee before: HEILONGJIANG PROVINCIAL HYDRAULIC Research Institute

TR01 Transfer of patent right
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Sun Jinglu

Inventor after: Li Zhaoyu

Inventor after: Wu Zhiqin

Inventor after: Zhang Shoujie

Inventor after: Zhang Bin

Inventor after: Si Zhenjiang

Inventor after: Liu Lijia

Inventor after: Tao Qi

Inventor after: Zhong Hua

Inventor after: Liu Jianming

Inventor after: Xu Lili

Inventor before: Zhang Shoujie

Inventor before: Li Zhaoyu

Inventor before: Wu Zhiqin

Inventor before: Sun Jinglu

Inventor before: Zhang Bin

Inventor before: Si Zhenjiang

Inventor before: Liu Lijia

Inventor before: Tao Qi

Inventor before: Zhong Hua

Inventor before: Liu Jianming

Inventor before: Xu Lili

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No. 78-10, Yanxing Road, Nangang District, Harbin City, Heilongjiang Province, 150080

Patentee after: Heilongjiang Sanbei Water Conservancy Technology Development Co.,Ltd.

Address before: 150080 No. 12 Xing Xing Road, Nangang District, Heilongjiang, Harbin

Patentee before: Heilongjiang Sanbei Water Conservancy Science and Technology Development Co.

EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20140702

Assignee: XINJIANG JINTUDI CEMENT PRODUCTS CO.,LTD.

Assignor: Heilongjiang Sanbei Water Conservancy Technology Development Co.,Ltd.

Contract record no.: X2023650000002

Denomination of invention: A preparation method of canal anti-seepage water conveyance trough

Granted publication date: 20151028

License type: Exclusive License

Record date: 20230302