CN103867215A - Expressway tunnel groove integral lining trolley - Google Patents

Expressway tunnel groove integral lining trolley Download PDF

Info

Publication number
CN103867215A
CN103867215A CN201410076127.1A CN201410076127A CN103867215A CN 103867215 A CN103867215 A CN 103867215A CN 201410076127 A CN201410076127 A CN 201410076127A CN 103867215 A CN103867215 A CN 103867215A
Authority
CN
China
Prior art keywords
door frame
assembly
limit mould
lining trolley
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410076127.1A
Other languages
Chinese (zh)
Other versions
CN103867215B (en
Inventor
张进军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cai Mao Sheng
Zhang Jin Jun
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410076127.1A priority Critical patent/CN103867215B/en
Publication of CN103867215A publication Critical patent/CN103867215A/en
Application granted granted Critical
Publication of CN103867215B publication Critical patent/CN103867215B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention relates to tunnel construction machinery, and discloses an expressway tunnel groove integral lining trolley, which comprises a top mold assembly, a side mold assembly, a hydraulic system, a walking system and an electric system, wherein the walking system is driven by the hydraulic system to move on a steel rail, and the top mold assembly is erected on a gantry table beam through a top mold upright post frame and is driven by a jacking oil cylinder arranged on a gantry cross beam; the gantry table beam is arranged on the gantry cross beam through a middle jack frame, a plurality of side mold lead screws and reinforced lead screws are hinged between the side mold assembly and the gantry upright posts arranged at the two ends of the gantry cross beam; the lower side of the side mold assembly is hinged to side mold support feet, and a groove bottom plate and a filling mold used for integrally forming the tunnel bottom surface are arranged under a pad plate. The invention aims at providing the expressway tunnel groove integral lining trolley with the advantages that the integral construction between the tunnel wall and the tunnel bottom surface is realized, the construction period is shortened, the material and labor waste is avoided, in addition, the structural performance is stable, and the integral performance is good.

Description

A kind of freeway tunnel groove entirety lining trolley
Technical field
The present invention relates to a kind of tunnel construction machinery, relate in particular to a kind of freeway tunnel groove entirety lining trolley.
Background technology
Along with expanding economy, expressway construction is more and more, and these are built to people's life and produce and brought very big facility; In these are built, the tunnel that need to excavate or build is more, has a kind of construction method lining cutting in constructing tunnel.Lining cutting refers to as preventing surrouding rock deformation or caving in, the permanent supporting and protection structure of building with materials such as steel concrete along tunnel trunk periphery.Lining Technique is normally applied in construction of tunnel, water conservancy channel.Lining cutting be exactly in brief in tunnel, grotto carries out liner, a kind of way is to use building block lining cutting, another kind of way is prestressing force high pressure grouting concrete lining.
Lining cutting and preliminary bracing are comparatively speaking, refer to carry out under the condition of preliminary bracing in tunnel, the inner lining of building with materials such as concrete, reaching its support reinforcement, optimize route waterproof and water drainage system, beautify outward appearance, the effect of the facilities such as communication, illumination, monitoring be conveniently set, to adapt to the requirement of modernization super expressway tunnel construction.
For freeway tunnel lining construction, in the constructure scheme using now, what often adopt is to utilize lining trolley, first carry out the lining cutting of tunnel wall, Deng lower ditch, the wiring duct construction of carrying out again bottom surface, tunnel after having constructed, so not only extended construction period, and secondary construction can cause material and recruitment personnel waste, and globality is poor; And existing lining trolley structure is stable not, in use, easily breaks down.
Summary of the invention
The object of the invention is the problem existing for above prior art, a kind of freeway tunnel groove entirety lining trolley is provided, realize the integral construction of tunnel wall and bottom surface, tunnel, shorten the duration, avoid material and recruitment personnel waste, and structural performance is stable, good integrity.
For realizing above object, the technical solution used in the present invention is: a kind of freeway tunnel groove entirety lining trolley, and it comprises backform assembly (1), limit mould assembly (12), hydraulic system (31), running gear (26) and electrical system, wherein,
Described hydraulic system (31) is arranged on the door frame platform beam (4) of backform assembly (1) below setting; Described running gear (26) drives at rail (18) upper mobile by hydraulic system (31); Described electrical system comprises motor and by motor-operated oil pump;
Described backform assembly (1), by the support of backform column (2), middle longeron (3) and top very heavy (20), position-limited rack (21), is set up on door frame platform beam (4);
It is upper that described door frame platform beam (4) is set up in described door frame crossbeam (7) by middle part very heavy (5), and described door frame crossbeam (7) below bilateral symmetry has been set up two row's door frame columns (9); On described door frame crossbeam (7), be provided with the jacking cylinder (6) for driving backform assembly (1);
The periphery of described door frame column (9) is provided with scaffold (8) and side form oil cylinder (10), and described side form oil cylinder (10) is connected with limit mould assembly (12) by Bian Motong beam (14);
Between described door frame column (9) and described limit mould assembly (12), be provided with multiple side form screw mandrels (13) and strengthen screw mandrel (11), the two ends of described side form screw mandrel (13) are hinged with described door frame column (9) and described limit mould assembly (12) respectively, and described reinforcement screw mandrel (11) is angle setting with described side form screw mandrel (13);
Described door frame column (9) below is provided with bottom girder (15), and the below of described bottom girder (15) is provided with increases box (16), described in increase box (16) below and be provided with described rail (18); Described rail (18) below is provided with backing plate (19);
Described limit mould assembly (12) both sides, bottom are hinged with respectively limit mould feet (30), and described limit mould feet (30) passes through screw mandrel (17) over the ground and is connected with ground; Described backing plate (19) below is provided with groove base plate (28), is provided with and fills mould (29) in described groove base plate (28);
Described limit mould assembly (12) is fixed together by the diagonal member (23) being arranged on Bian Motong beam (14).
Further, described backform column (2) and described middle longeron (3) equi-spaced apart setting.
Further, described running gear (26) comprises running gear and rack winch composition, and described running gear is made up of four walking wheels, and the wheels of walking described in each comprise two road wheels.
Further, described backform assembly (1) is hinged with described limit mould assembly (12).
Further, described limit mould leg (30) down either side is equidistantly symmetrically arranged with bottom very heavy (27).
Further, in the rear and front end of device, be provided with working platform (24) on described door frame column (9), described working platform (24) top is connected with work ladder (22), and described working platform (24) is arranged with guardrail (25).
Beneficial effect of the present invention: adopt Integral molding device for insoles, realize the integral construction of tunnel wall and bottom surface, tunnel, shortened the duration, avoid secondary construction; Avoid material and recruitment personnel waste, and structural performance is stable, good integrity simultaneously.
Brief description of the drawings
Fig. 1 is the main TV structure schematic diagram of the present invention.
Fig. 2 is side-looking structural representation of the present invention.
Numerical reference described in figure is expressed as: 1, backform assembly; 2, backform column; 3, middle longeron; 4, door frame platform beam; 5, middle part is very heavy; 6, jacking cylinder; 7, door frame crossbeam; 8, scaffold; 9, door frame column; 10, side form oil cylinder; 11, strengthen screw mandrel; 12, limit mould assembly; 13, side form screw mandrel; 14, Bian Motong beam; 15, bottom girder; 16, increase box; 17, screw mandrel over the ground; 18, rail; 19, backing plate; 20, top is very heavy; 21, position-limited rack; 22, work ladder; 23, diagonal member; 24, working platform; 25, guardrail; 26, running gear; 27, bottom is very heavy; 28, groove base plate; 29, fill mould; 30, limit mould feet; 31, hydraulic system.
Detailed description of the invention
In order to make those skilled in the art understand better technical scheme of the present invention, describe the present invention below in conjunction with accompanying drawing, the description of this part is only exemplary and explanatory, should not have any restriction to protection scope of the present invention.
As shown in Figure 1-2, assembly relation of the present invention is: it comprises backform assembly 1, limit mould assembly 12, hydraulic system 31, running gear 26 and electrical system, wherein,
Described hydraulic system 31 is arranged on the door frame platform beam 4 of backform assembly 1 below setting; Described running gear 26 is driven on rail 18 and is moved by hydraulic system 31; Described electrical system comprises motor and by motor-operated oil pump;
Described backform assembly 1 is very heavy 20 by backform column 2, middle longeron 3 and top, the support of position-limited rack 21, is set up on door frame platform beam 4;
Described door frame platform beam 4 is set up on described door frame crossbeam 7 by middle part very heavy 5, and described door frame crossbeam 7 below bilateral symmetry have been set up two row's door frame columns 9; On described door frame crossbeam 7, be provided with the jacking cylinder 6 for driving backform assembly 1;
The periphery of described door frame column 9 is provided with scaffold 8 and side form oil cylinder 10, and described side form oil cylinder 10 is connected with limit mould assembly 12 by Bian Motong beam 14;
Between described door frame column 9 and described limit mould assembly 12, be provided with multiple side form screw mandrels 13 and strengthen screw mandrel 11, the two ends of described side form screw mandrel 13 are hinged with described door frame column 9 and described limit mould assembly 12 respectively, and described reinforcement screw mandrel 11 is angle setting with described side form screw mandrel 13;
Described door frame column 9 belows are provided with bottom girder 15, and the below of described bottom girder 15 is provided with increases box 16, described in increase box 16 belows and be provided with described rail 18; Described rail 18 belows are provided with backing plate 19;
Mould assembly 12 both sides, bottom in described limit are hinged with respectively limit mould feet 30, and described limit mould feet 30 passes through screw mandrel 17 over the ground and is connected with ground; Described backing plate 19 belows are provided with groove base plate 28, be provided with and fill mould 29 in described groove base plate 28;
Described limit mould assembly 12 is fixed together by the diagonal member 23 being arranged on Bian Motong beam 14.
Preferably, described backform column 2 and described middle longeron 3 equi-spaced apart settings.
Preferably, described running gear 26 comprises running gear and rack winch composition, and described running gear is made up of four walking wheels, and the wheels of walking described in each comprise two road wheels.
Preferably, described backform assembly 1 is hinged with described limit mould assembly 12.
Preferably, described limit mould leg 30 down either side are equidistantly symmetrically arranged with bottom very heavy 27.
Preferably, in the rear and front end of device, on described door frame column 9, be provided with working platform 24, described working platform 24 tops are connected with work ladder 22, and described working platform 24 is arranged with guardrail 25.
Described a kind of freeway tunnel groove entirety lining trolley is installed in the tunnel after excavation, is driven and is moved on rail 18 by running gear; Rail 18 belows are provided with backing plate 19, and there is groove base plate 28 backing plate below 19 and fills mould 29 with described chassis integrated connection; Described chassis adopts external 380V power supply as running gear main power source, is also the main power source that motor drives the work of oil pump drive hydraulic system principle; Device adopts hydraulic system transmission, makes simplified, weight saving, and the while has also been improved flexibility and the diversity of structure; Be designed to Overall Steel Formwork, the de-formwork erection of hydraulic jack, in construction, lean on the very heavy support of screw mandrel, motor is automatically walked or oil cylinder step-by-step movement is walked automatically, all adopt the perfusion of concrete transfer pump car, tunnel top, sidepiece and bottom integrated construction, be furnished with hydraulic lock on jacking cylinder 6, to ensure to hoist steadily, prevent jacking cylinder 6 automatic retracteds, when preventing oil pipe break or seriously leaking, have an accident; For convenience of operation, the main button of device is located on working platform, and is furnished with waterproof measure and safety measures for power consumption.
The present invention adopts the one-body molded chassis that arranges, and realizes the integral construction of tunnel wall and bottom surface, tunnel, has shortened the duration, avoids secondary construction; Avoid material and recruitment personnel waste, and structural performance is stable, good integrity simultaneously.
It should be noted that, in this article, term " comprises ", " comprising " or its any other variant are intended to contain comprising of nonexcludability, thereby which key element the process, method, article or the equipment that make to comprise a series of key elements not only comprise, but also comprise other key elements of clearly not listing, or be also included as the intrinsic key element of this process, method, article or equipment.
Applied specific case herein principle of the present invention and embodiment are set forth, the explanation of above example is just for helping to understand method of the present invention and core concept thereof.The above is only the preferred embodiment of the present invention, should be understood that, due to the finiteness of literal expression, and objectively there is unlimited concrete structure, for those skilled in the art, under the premise without departing from the principles of the invention, can also make some improvement, retouching or variation, also above-mentioned technical characterictic can be combined by rights; These improve retouching, change or combination, or without improving, the design of invention and technical scheme are directly applied to other occasion, all should be considered as protection scope of the present invention.

Claims (6)

1. a freeway tunnel groove entirety lining trolley, is characterized in that, it comprises backform assembly (1), limit mould assembly (12), hydraulic system (31), running gear (26) and electrical system, wherein,
Described hydraulic system (31) is arranged on the door frame platform beam (4) of backform assembly (1) below setting; Described running gear (26) drives at rail (18) upper mobile by hydraulic system (31); Described electrical system comprises motor and by motor-operated oil pump;
Described backform assembly (1), by the support of backform column (2), middle longeron (3) and top very heavy (20), position-limited rack (21), is set up on door frame platform beam (4);
It is upper that described door frame platform beam (4) is set up in described door frame crossbeam (7) by middle part very heavy (5), and described door frame crossbeam (7) below bilateral symmetry has been set up two row's door frame columns (9); On described door frame crossbeam (7), be provided with the jacking cylinder (6) for driving backform assembly (1);
The periphery of described door frame column (9) is provided with scaffold (8) and side form oil cylinder (10), and described side form oil cylinder (10) is connected with limit mould assembly (12) by Bian Motong beam (14);
Between described door frame column (9) and described limit mould assembly (12), be provided with multiple side form screw mandrels (13) and strengthen screw mandrel (11), the two ends of described side form screw mandrel (13) are hinged with described door frame column (9) and described limit mould assembly (12) respectively, and described reinforcement screw mandrel (11) is angle setting with described side form screw mandrel (13);
Described door frame column (9) below is provided with bottom girder (15), and the below of described bottom girder (15) is provided with increases box (16), described in increase box (16) below and be provided with described rail (18); Described rail (18) below is provided with backing plate (19);
Described limit mould assembly (12) both sides, bottom are hinged with respectively limit mould feet (30), and described limit mould feet (30) passes through screw mandrel (17) over the ground and is connected with ground; Described backing plate (19) below is provided with groove base plate (28), is provided with and fills mould (29) in described groove base plate (28);
Described limit mould assembly (12) is fixed together by the diagonal member (23) being arranged on Bian Motong beam (14).
2. a kind of freeway tunnel groove entirety lining trolley according to claim 1, is characterized in that described backform column (2) and described middle longeron (3) equi-spaced apart setting.
3. a kind of freeway tunnel groove entirety lining trolley according to claim 1, it is characterized in that, described running gear (26) comprises running gear and rack winch composition, and described running gear is made up of four walking wheels, and the wheels of walking described in each comprise two road wheels.
4. a kind of freeway tunnel groove entirety lining trolley according to claim 1, is characterized in that, described backform assembly (1) is hinged with described limit mould assembly (12).
5. a kind of freeway tunnel groove entirety lining trolley according to claim 1, is characterized in that, described limit mould leg (30) down either side is equidistantly symmetrically arranged with bottom very heavy (27).
6. a kind of freeway tunnel groove entirety lining trolley according to claim 1, it is characterized in that, in the rear and front end of device, on described door frame column (9), be provided with working platform (24), described working platform (24) top is connected with work ladder (22), and described working platform (24) is arranged with guardrail (25).
CN201410076127.1A 2014-03-04 2014-03-04 The overall lining trolley of a kind of freeway tunnel groove Active CN103867215B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410076127.1A CN103867215B (en) 2014-03-04 2014-03-04 The overall lining trolley of a kind of freeway tunnel groove

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410076127.1A CN103867215B (en) 2014-03-04 2014-03-04 The overall lining trolley of a kind of freeway tunnel groove

Publications (2)

Publication Number Publication Date
CN103867215A true CN103867215A (en) 2014-06-18
CN103867215B CN103867215B (en) 2016-03-16

Family

ID=50906176

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410076127.1A Active CN103867215B (en) 2014-03-04 2014-03-04 The overall lining trolley of a kind of freeway tunnel groove

Country Status (1)

Country Link
CN (1) CN103867215B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104747205A (en) * 2015-02-12 2015-07-01 中铁上海工程局集团有限公司 Formwork for preventing injuries in tunnel collapse accident and construction method thereof
CN104832194A (en) * 2015-04-14 2015-08-12 安徽岚岛重工科技股份有限公司 Full-automatic hydraulic concrete-lining steel-moulding-plate trolley
CN105350984A (en) * 2015-11-15 2016-02-24 贵阳鼎辉科技有限公司 Side mold assembly mechanism for tunnel lining trolley
CN107269297A (en) * 2017-07-17 2017-10-20 夏杰 Side and roof arch ditch cable duct tunneling boring one-shot forming two serves as a contrast concrete chassis
CN108301847A (en) * 2018-03-28 2018-07-20 中铁八局集团第三工程有限公司 A kind of Tunnel Second Lining trolley hydraulic end head mould and its construction method
CN108843353A (en) * 2018-07-18 2018-11-20 湖南进军隧道智能装备有限公司 A kind of excavation stand translation installing mechanism
CN109372547A (en) * 2018-11-02 2019-02-22 中铁工程装备集团有限公司 Narrow-bore tunnel rail-mounted lining trolley and lining methods
CN113062753A (en) * 2021-04-08 2021-07-02 贵州路桥集团有限公司 A slot lining cutting forming device for whole lining cutting platform truck of highway tunnel
CN114542125A (en) * 2022-03-28 2022-05-27 长安大学 Local arch changing device and method for highway soft rock tunnel

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020066835A (en) * 2001-02-14 2002-08-21 선산철강공업(주) Structure of sliding steel form which construct tunnel.
CN1851233A (en) * 2006-05-24 2006-10-25 杨秋利 Tunnel lining trolley
CN201196094Y (en) * 2008-05-22 2009-02-18 中铁十一局集团第一工程有限公司 Hydraulic template trolley for rail tunnel liner concrete
CN201526325U (en) * 2009-10-21 2010-07-14 北京中铁天瑞机械设备有限公司 Mold plate trolley for tunnel lining
CN103016028A (en) * 2012-12-06 2013-04-03 长沙进军机械有限公司 Hydraulic self-propelled steel form carrier for tunnel secondary lining operation
CN103089278A (en) * 2013-02-27 2013-05-08 中交隧道工程局有限公司 Continuous operation rolling over docking type tunnel lining formwork trolley
CN103541744A (en) * 2013-11-11 2014-01-29 中铁四局集团机电设备安装有限公司 Tire walking full-hydraulic lining trolley
CN203702181U (en) * 2014-03-04 2014-07-09 张进军 Expressway tunnel groove integral lining trolley

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020066835A (en) * 2001-02-14 2002-08-21 선산철강공업(주) Structure of sliding steel form which construct tunnel.
CN1851233A (en) * 2006-05-24 2006-10-25 杨秋利 Tunnel lining trolley
CN201196094Y (en) * 2008-05-22 2009-02-18 中铁十一局集团第一工程有限公司 Hydraulic template trolley for rail tunnel liner concrete
CN201526325U (en) * 2009-10-21 2010-07-14 北京中铁天瑞机械设备有限公司 Mold plate trolley for tunnel lining
CN103016028A (en) * 2012-12-06 2013-04-03 长沙进军机械有限公司 Hydraulic self-propelled steel form carrier for tunnel secondary lining operation
CN103089278A (en) * 2013-02-27 2013-05-08 中交隧道工程局有限公司 Continuous operation rolling over docking type tunnel lining formwork trolley
CN103541744A (en) * 2013-11-11 2014-01-29 中铁四局集团机电设备安装有限公司 Tire walking full-hydraulic lining trolley
CN203702181U (en) * 2014-03-04 2014-07-09 张进军 Expressway tunnel groove integral lining trolley

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104747205B (en) * 2015-02-12 2017-03-15 中铁上海工程局集团有限公司 The mould bases of anti-injury and its construction method in tunnel cave accident
CN104747205A (en) * 2015-02-12 2015-07-01 中铁上海工程局集团有限公司 Formwork for preventing injuries in tunnel collapse accident and construction method thereof
CN104832194A (en) * 2015-04-14 2015-08-12 安徽岚岛重工科技股份有限公司 Full-automatic hydraulic concrete-lining steel-moulding-plate trolley
CN105350984A (en) * 2015-11-15 2016-02-24 贵阳鼎辉科技有限公司 Side mold assembly mechanism for tunnel lining trolley
CN107269297B (en) * 2017-07-17 2023-06-02 夏杰 Two lining concrete platform trucks of full section one shot forming of limit roof arch ditch cable pit
CN107269297A (en) * 2017-07-17 2017-10-20 夏杰 Side and roof arch ditch cable duct tunneling boring one-shot forming two serves as a contrast concrete chassis
CN108301847A (en) * 2018-03-28 2018-07-20 中铁八局集团第三工程有限公司 A kind of Tunnel Second Lining trolley hydraulic end head mould and its construction method
CN108301847B (en) * 2018-03-28 2024-02-02 中铁八局集团第三工程有限公司 Hydraulic end mould of tunnel secondary lining trolley and construction method thereof
CN108843353A (en) * 2018-07-18 2018-11-20 湖南进军隧道智能装备有限公司 A kind of excavation stand translation installing mechanism
CN108843353B (en) * 2018-07-18 2023-08-15 湖南进军隧道智能装备有限公司 Excavation grudging post translation installation mechanism
CN109372547A (en) * 2018-11-02 2019-02-22 中铁工程装备集团有限公司 Narrow-bore tunnel rail-mounted lining trolley and lining methods
CN113062753A (en) * 2021-04-08 2021-07-02 贵州路桥集团有限公司 A slot lining cutting forming device for whole lining cutting platform truck of highway tunnel
CN113062753B (en) * 2021-04-08 2023-09-19 贵州路桥集团有限公司 Groove lining forming device for highway tunnel integral lining trolley
CN114542125A (en) * 2022-03-28 2022-05-27 长安大学 Local arch changing device and method for highway soft rock tunnel

Also Published As

Publication number Publication date
CN103867215B (en) 2016-03-16

Similar Documents

Publication Publication Date Title
CN103867215B (en) The overall lining trolley of a kind of freeway tunnel groove
CN203702179U (en) Single-track tunnel lining trolley with ventilating duct
CN109538238B (en) Tunnel arch prefabricated segment construction device and control method
CN104564104B (en) A kind of table system for tunnel-liner
CN109138483B (en) Device for alternatively jacking storey-increasing building by utilizing high-strength concrete columns and steel slide ways and construction method thereof
CN108033367B (en) Synchronous lifting device and lifting method for steel column and cylinder frame alternately supported steel platform and tower crane
CN204457802U (en) Formed by integrally casting formula formwork jumbo
CN104632251A (en) Integrally cast type mould plate trolley and construction method of concrete pouring of underground passage
CN104533460B (en) Support replacement formula formwork jumbo and the construction method of underpass concreting
CN103016028A (en) Hydraulic self-propelled steel form carrier for tunnel secondary lining operation
CN204662952U (en) A kind of self-propelled tool single side formwork formwork system
CN204402504U (en) A kind of tunnel steel form lining trolley
CN203702181U (en) Expressway tunnel groove integral lining trolley
CN203702178U (en) Bottom end supercharged type small-height tunnel lining trolley
CN205875162U (en) Unilateral formula rock -anchored beam concrete placement rebar installation platform truck
CN203702180U (en) Single-track railway outer mold tunnel trolley
CN203730015U (en) Groove lining forming device used for highway tunnel integral lining trolley
CN104929660B (en) Formation and construction set for continuous open-cut tunnel
CN104453951A (en) Combined lining formwork trolley for subway station
CN105887885A (en) Symmetric rock anchor beam concrete pouring trolley
CN201546323U (en) Steel angle concrete column steel box combined beam frame
CN203834370U (en) Arch ring steel formwork trolley for circular arch culvert
CN105887884A (en) Single-side type rock anchor beam concrete pouring trolley
CN203755173U (en) Formwork device used for hydraulic climbing of bridge high pier
CN203702176U (en) Side framework support structure of tunnel lining trolley

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180816

Address after: 471000 Pingle Town, Mengjin, Luoyang, Henan

Patentee after: Luoyang Zhongtie Strong Machinery Co., Ltd.

Address before: 410000 Chaoyang formation, Shuangfu village, shuangfupu Town, Ningxiang, Changsha, Hunan

Patentee before: Zhang Jinjun

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190114

Address after: 413100 Chaoyang Formation, Shuangfupu Town, Ningxiang County, Changsha City, Hunan Province

Patentee after: Zhang Jinjun

Address before: 471000 Pingle Town, Mengjin, Luoyang, Henan

Patentee before: Luoyang Zhongtie Strong Machinery Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190910

Address after: 410600 Xia duo Pu community, Xia duo Pu town, Ningxiang, Changsha, Hunan (Xia duo Pu Machinery Industrial Park)

Co-patentee after: Cai Mao Sheng

Patentee after: Zhang Jin Jun

Address before: 413100 Chaoyang Formation, Shuangfupu Town, Ningxiang County, Changsha City, Hunan Province

Patentee before: Zhang Jin Jun