CN103821105A - 一种粉土充填土工织物袋筑堤的方法 - Google Patents

一种粉土充填土工织物袋筑堤的方法 Download PDF

Info

Publication number
CN103821105A
CN103821105A CN201410074144.1A CN201410074144A CN103821105A CN 103821105 A CN103821105 A CN 103821105A CN 201410074144 A CN201410074144 A CN 201410074144A CN 103821105 A CN103821105 A CN 103821105A
Authority
CN
China
Prior art keywords
silt
geotextile
dike
geotextile bag
hydraulic reclamation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410074144.1A
Other languages
English (en)
Other versions
CN103821105B (zh
Inventor
胡殿才
马兴华
盛懿洁
詹田进
任强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Waterway Engineering Design and Consulting Co Ltd
Original Assignee
Shanghai Waterway Engineering Design and Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Waterway Engineering Design and Consulting Co Ltd filed Critical Shanghai Waterway Engineering Design and Consulting Co Ltd
Priority to CN201410074144.1A priority Critical patent/CN103821105B/zh
Publication of CN103821105A publication Critical patent/CN103821105A/zh
Application granted granted Critical
Publication of CN103821105B publication Critical patent/CN103821105B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Revetment (AREA)

Abstract

一种粉土充填土工织物袋筑堤的方法,涉及筑堤工程。本发明用粉土、土工织物袋、塑料排水板和降水井构筑堤坝,其特征是粉土中粒径大于0.075mm的颗粒含量不超过总质量的50%;土工织物袋侧面用复合土工布,上下面用编织布制成;堤坝二侧为土工织物袋充填粉土棱体,堤坝中间吹填粉土堤心,在充填粉土的土工织物袋之间埋设水平向塑料排水板,形成横向排水通道;施工时,采用水力吹填工艺从取土区取粉土吹填至堤心,然后从堤心取粉土充灌土工织物袋形成袋装粉土棱体;吹填粉土堤心后,采用降水井和低能级强夯法,加快吹填粉土堤心的排水固结,提高堤心的密实度和承载力。本发明适用于围堤、围堰、护岸、引堤、防波堤、海堤、路堤堤坝工程。

Description

一种粉土充填土工织物袋筑堤的方法
技术领域
本发明涉及利用粉土充填土工织物袋筑堤形成堤坝的工程。
背景技术
目前在港口、水利、岩土、市政、公路专业领域,已完成和正在进行的土工织物充填袋筑堤形成堤坝工程中,现行规范要求充填料宜选用砂性土,粒径大于0.075mm的颗粒含量应大于50%,这对于砂源丰富的地区比较容易实现,具有较好的应用价值。但对于砂性土缺乏,而粉土资源丰富的地区,由于粉土颗粒更细,排水性和保土性差,堤坝土体固结慢,国内目前鲜有采用粉土充填土工织物袋筑堤的成功案例。
发明内容
本发明需要解决的问题是在砂性土缺乏而粉土资源丰富的条件下,研发粉土替代砂性土充填土工织物袋筑筑堤的方法,解决粉土排水固结慢、地基承载力偏低的问题。
本发明的技术方案是用粉土、土工织物袋、塑料排水板和降水井构筑的堤坝,其特征是粉土中粒径大于0.075mm的颗粒含量不超过总质量的50%,且粉土塑性指数不大于10;土工织物袋侧面采用复合土工布,上下面采用编织布制成,复合土工布由150~250g/m2的机织布与100~250g/m2无纺土工布复合而成,编织布规格为150~300g/m2;构筑的堤坝二侧为土工织物袋充填粉土筑成的棱体,堤坝中间吹填粉土堤心,在充填粉土的土工织物袋之间埋设水平向塑料排水板,连接吹填粉土堤心和棱体外侧,形成横向排水通道,塑料排水板水平间距1~5m;施工时,采用水力吹填工艺从取土区取粉土吹填至堤心,然后采用泥浆泵从堤心取粉土充灌土工织物袋形成袋装粉土棱体;吹填粉土堤心后,采用降水井和能量为800~1200kJ的低能级强夯法,加快吹填粉土堤心的排水固结速度,提高堤吹填粉土堤心的密实度和承载力。
本发明的突出特点是利用了粒径小于0.075mm的粉土,突破了现行规范中土工织物充填袋对充填料需采用砂性土的限制,通过采取有效措施解决了粉土筑堤存在的排水性、保土性、固结密实慢等技术难题,实现了直接采用粉土充填土工织物袋筑堤形成堤坝;组成粉土的主要粒组为粉粒,粒径范围在0.075~0.005mm之间,粉土的物理力学性质受粉粒控制,颗粒细、孔隙小、粘性低、弱~中等透水性,自然排水固结时间长,难以满足堤坝工程应用需求;但粉土一旦排水固结密实,则具有强度高、密实度高、承载力高的特点,是较好的筑堤材料;本发明通过采用包括缩短排水路径、降水结合动力密实法等技术措施,将粉土排水固结时间由20天以上缩短至5天左右,地基承载力满足堤坝工程应用需求。利用水力吹填的分选过滤作用,去除粉土中的部分细颗粒,使充灌入土工织物充填袋内的粉土排水固结性能优于原状粉土;土工织物袋侧面采用复合土工布,机织布强度高、孔隙率高,无纺土工布具有保土性好的特点,二者复合,有效解决了粉土充灌土工织物袋存在的排水、保土技术难题,而上下侧采用编织布利于排水,同时降低造价;设置塑料排水板,利用塑料排水板形成排水通道,缩短排水路径;设置降水井,去除粉土中的部分自由水,降低地下水位,然后采用低能量强夯使土体密实,实现较好的密实效果。
附图说明
图1 表示的是粉土充填土工织物袋筑堤形成的堤坝断面示意图。
图2 表示的是粉土充填土工织物袋筑堤第一阶段施工示意图。
图3 表示的是粉土充填土工织物袋筑堤第二阶段施工示意图。
图4 表示的是土工织物充填袋结构示意图。
图5 表示的是水力吹填粉土充灌土工织物袋工艺示意图。
具体实施方式
本发明釆用粉土、土工织物袋、塑料排水板和降水井构筑的堤坝(见图1),粉土中粒径大于0.075mm的颗粒含量不超过总质量的50%,且粉土塑性指数不大于10;土工织物袋(见图4)侧面采用复合土工布8,上下面采用编织布9,复合土工布由150~250g/m2的机织布与100~250g/m2无纺土工布复合而成,编织布规格为150~300g/m2;构筑的堤坝二侧为土工织物袋充填粉土筑成的棱体1,堤坝中间是吹填粉土堤心2,在充填粉土的土工织物袋之间埋设有水平向塑料排水板3,连接吹填粉土堤心和棱体外侧,形成横向排水通道,塑料排水板水平间距1~5m;施工时,第一阶段(见图2)采用绞吸船10(见图5)或泥浆泵等水力吹填工艺从取土区取粉土吹填至堤心,然后采用泥浆泵11从堤心取粉土充灌土工织物袋形成二侧袋装粉土棱体及吹填粉土堤心,在充填袋分层之间铺设水平向塑料排水板;第二阶段施工(见图3)吹填粉土堤心后,采用降水井4和能量为800~1200kJ的低能级强夯机5,加快吹填粉土堤心的排水固结速度,提高堤吹填粉土堤心的密实度和承载力。粉土充填土工织物袋筑堤完成后,构筑堤顶结构6和外坡防护结构7。

Claims (1)

1. 一种粉土充填土工织物袋筑堤的方法,釆用粉土、土工织物袋、塑料排水板和降水井构筑堤坝,其特征是粉土中粒径大于0.075mm的颗粒含量不超过总质量的50%,且粉土塑性指数不大于10;土工织物袋侧面采用复合土工布,上下面采用编织布制成,复合土工布由150~250g/m2的机织布与100~250g/m2无纺土工布复合而成,编织布规格为150~300g/m2;构筑的堤坝二侧为土工织物袋充填粉土筑成的棱体,堤坝中间吹填粉土堤心,在充填粉土的土工织物袋之间埋设水平向塑料排水板,连接吹填粉土堤心和棱体外侧,形成横向排水通道,塑料排水板水平间距1~5m;施工时,采用水力吹填工艺从取土区取粉土吹填至堤心,然后采用泥浆泵从堤心取粉土充灌土工织物袋形成袋装粉土棱体;吹填粉土堤心后,采用降水井和能量为800~1200kJ的低能级强夯法,加快吹填粉土堤心的排水固结速度,提高堤吹填粉土堤心的密实度和承载力。
CN201410074144.1A 2014-03-03 2014-03-03 一种粉土充填土工织物袋筑堤的方法 Active CN103821105B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410074144.1A CN103821105B (zh) 2014-03-03 2014-03-03 一种粉土充填土工织物袋筑堤的方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410074144.1A CN103821105B (zh) 2014-03-03 2014-03-03 一种粉土充填土工织物袋筑堤的方法

Publications (2)

Publication Number Publication Date
CN103821105A true CN103821105A (zh) 2014-05-28
CN103821105B CN103821105B (zh) 2016-09-14

Family

ID=50756373

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410074144.1A Active CN103821105B (zh) 2014-03-03 2014-03-03 一种粉土充填土工织物袋筑堤的方法

Country Status (1)

Country Link
CN (1) CN103821105B (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120825A (zh) * 2016-08-22 2016-11-16 中交天航港湾建设工程有限公司 利用小型绞吸挖泥船打设充填袋围堰的施工系统及方法
CN106836181A (zh) * 2017-01-12 2017-06-13 中交天航南方交通建设有限公司 一种用于吹填施工的填围护同步进行施工方法
CN109083172A (zh) * 2018-09-21 2018-12-25 大连兴利路桥工程有限公司 沿海滩涂地区适应北方冰凌影响的土石围堰及其施工方法
CN109355990A (zh) * 2018-11-29 2019-02-19 中国电建集团成都勘测设计研究院有限公司 低洼沼泽地区吹填特细砂路基结构
CN112709190A (zh) * 2020-12-25 2021-04-27 浙江省围海建设集团股份有限公司 一种堤坝加固控制方法
CN112962525A (zh) * 2021-02-23 2021-06-15 江苏筑港建设集团有限公司 一种疏浚土充灌筑堤结构及其充灌袋筑堤方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09158160A (ja) * 1995-12-13 1997-06-17 Tsutomu Nozaki 砂泥取込み口に吹出しを備えた貯水ダムのサイフォン式排砂装 置
CN2782765Y (zh) * 2005-04-28 2006-05-24 上海航道勘察设计研究院 加筋砂被
CN101016734A (zh) * 2006-02-06 2007-08-15 中交上海航道勘察设计研究院有限公司 软土充填袋筑堤反压固化方法
CN102839630A (zh) * 2012-09-21 2012-12-26 中交上航局航道建设有限公司 淤泥质土充填袋筑堤施工方法
CN103205952A (zh) * 2012-01-12 2013-07-17 中交上海航道勘察设计研究院有限公司 充填泥袋结合真空预压填筑堤坝的方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09158160A (ja) * 1995-12-13 1997-06-17 Tsutomu Nozaki 砂泥取込み口に吹出しを備えた貯水ダムのサイフォン式排砂装 置
CN2782765Y (zh) * 2005-04-28 2006-05-24 上海航道勘察设计研究院 加筋砂被
CN101016734A (zh) * 2006-02-06 2007-08-15 中交上海航道勘察设计研究院有限公司 软土充填袋筑堤反压固化方法
CN103205952A (zh) * 2012-01-12 2013-07-17 中交上海航道勘察设计研究院有限公司 充填泥袋结合真空预压填筑堤坝的方法
CN102839630A (zh) * 2012-09-21 2012-12-26 中交上航局航道建设有限公司 淤泥质土充填袋筑堤施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李凯双等: "袋装砂筑堤技术在滩海、浅海工程中的应用", 《石油工程建设》 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106120825A (zh) * 2016-08-22 2016-11-16 中交天航港湾建设工程有限公司 利用小型绞吸挖泥船打设充填袋围堰的施工系统及方法
CN106836181A (zh) * 2017-01-12 2017-06-13 中交天航南方交通建设有限公司 一种用于吹填施工的填围护同步进行施工方法
CN109083172A (zh) * 2018-09-21 2018-12-25 大连兴利路桥工程有限公司 沿海滩涂地区适应北方冰凌影响的土石围堰及其施工方法
CN109355990A (zh) * 2018-11-29 2019-02-19 中国电建集团成都勘测设计研究院有限公司 低洼沼泽地区吹填特细砂路基结构
CN109355990B (zh) * 2018-11-29 2023-09-19 中国电建集团成都勘测设计研究院有限公司 低洼沼泽地区吹填特细砂路基结构
CN112709190A (zh) * 2020-12-25 2021-04-27 浙江省围海建设集团股份有限公司 一种堤坝加固控制方法
CN112962525A (zh) * 2021-02-23 2021-06-15 江苏筑港建设集团有限公司 一种疏浚土充灌筑堤结构及其充灌袋筑堤方法
CN112962525B (zh) * 2021-02-23 2022-04-22 江苏筑港建设集团有限公司 一种疏浚土充灌筑堤结构及其充灌袋筑堤方法

Also Published As

Publication number Publication date
CN103821105B (zh) 2016-09-14

Similar Documents

Publication Publication Date Title
CN103821105B (zh) 一种粉土充填土工织物袋筑堤的方法
CN101302757B (zh) 一种快速处理厚层软土地基的方法
CN102767157B (zh) 模袋充淤泥真空预压筑堤方法
CN103614955B (zh) 一种软土地基施工道路的处理方法
CN105178245A (zh) 河湖航道大型充填袋生态堤防和护岸的建造方法
CN201485847U (zh) 一种新型尾矿坝同步排渗加固装置
CN106284205B (zh) 一种模袋边梗的尾砂水力冲填筑坝的方法
CN101220589B (zh) 土工袋与动力挤密综合加固软土地基的方法
CN109972469A (zh) 单元式碎石桩复合地基结合超载预压的软弱路基处理装置和方法
CN111851505A (zh) 一种灌注式防渗心墙土石坝的构筑方法及其结构
CN108532581A (zh) 一种具有综合处理功能的模块式土体施压成型装置
CN106381880A (zh) 泥炭土坝基的处理方法
CN104711968B (zh) 一种负压立体导流扰动冲击固结吹填土方法
CN209816885U (zh) 软弱覆盖层下新型围堰结构
CN215669631U (zh) 一种深厚覆盖层地基结构
CN110552324A (zh) 一种可水下施工的边坡防护结构及其施工方法
CN104846774A (zh) 城市小流域河道快储缓释海绵堤岸结构
CN2706510Y (zh) 模袋固化土围堰、堤坝、护岸的堤心结构
CN106498923A (zh) 自排水后固结充填砂袋复合桩体系及其施工方法
CN108018854A (zh) 一种生态型混凝土支护桩
CN112854144A (zh) 一种深厚淤泥层上土石坝的构筑结构及其施工方法
CN203855934U (zh) 一种粉土充填土工织物袋堤坝
CN205617341U (zh) 一种矿山尾矿库排渗盲沟
CN203049533U (zh) 山区沟谷弃碴回填造地构造
CN101967785A (zh) 滨海地区浸水吹填砂路基的高等级公路结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180122

Address after: No. 850 Pudong Avenue, Pudong New Area, Shanghai

Co-patentee after: NATIONAL ENGINEERING RESEARCH CENTER OF DREDGING TECHNOLOGY AND EQUIPMENT

Patentee after: Shanghai Waterway Engineering Design and Consulting Co., Ltd.

Address before: No. 850 Pudong Avenue, Pudong New Area, Shanghai

Patentee before: Shanghai Waterway Engineering Design and Consulting Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20220426

Address after: 200120 No. 850, Pudong Avenue, Pudong New Area, Shanghai

Patentee after: SHANGHAI WATERWAY ENGINEERING DESIGN AND CONSULTING Co.,Ltd.

Address before: 200120 No. 850, Pudong Avenue, Pudong New Area, Shanghai

Patentee before: SHANGHAI WATERWAY ENGINEERING DESIGN AND CONSULTING Co.,Ltd.

Patentee before: CCCC dredging technology and equipment National Engineering Research Center Co., Ltd

TR01 Transfer of patent right