CN103806457A - Novel construction technology of waterproof curtain - Google Patents

Novel construction technology of waterproof curtain Download PDF

Info

Publication number
CN103806457A
CN103806457A CN201210439973.6A CN201210439973A CN103806457A CN 103806457 A CN103806457 A CN 103806457A CN 201210439973 A CN201210439973 A CN 201210439973A CN 103806457 A CN103806457 A CN 103806457A
Authority
CN
China
Prior art keywords
hole
construction technology
water
pressure
stop curtain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201210439973.6A
Other languages
Chinese (zh)
Inventor
刘其铎
陈希林
姜雪强
卢常亘
郭彩霞
史亚军
史磊磊
胡建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing No 4 Municipal Construction Engineering Co Ltd
Original Assignee
Beijing No 4 Municipal Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing No 4 Municipal Construction Engineering Co Ltd filed Critical Beijing No 4 Municipal Construction Engineering Co Ltd
Priority to CN201210439973.6A priority Critical patent/CN103806457A/en
Publication of CN103806457A publication Critical patent/CN103806457A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a novel construction technology of a waterproof curtain. The novel construction technology includes the following processing steps: (1) carrying out measurement positioning, (2) enabling a hole leading drilling machine to be in place according to the marked position to carry out hole drilling, (3) cleaning a hole after hole drilling is completed, moving the hole leading drilling machine to a next hole position, and repeating the step (2) and the step (3), (4) preparing cement paste, (5) inserting a high-pressure spraying pipe into the hole, meanwhile, starting an air compressor to supply air, and starting a high-pressure water pump to supply water, (6) carrying out high-pressure jet grouting operation: forming the waterproof curtain by pumping the cement paste, and enabling the high-pressure spraying pipe to be lifted in a rotary mode, (7) carrying out recharging to enable the hole to be filled with the paste, and (8) carrying out movement: moving the high-pressure spraying pipe to the next hole position, repeating the step (5), the step (6) and the step (7), and finally completing construction of the whole waterproof curtain. The novel construction technology of the waterproof curtain has the advantages of being rapid in construction, good in waterproof effect, capable of keeping a soil layer structure stable and the like.

Description

A kind of construction technology of Novel water-stop curtain
[technical field]
The present invention relates to a kind of construction techniques, be specifically related to a kind of construction technology of Novel water-stop curtain.
[background technology]
In the prior art, water-stop curtain conventionally need to excavate a complete foundation ditch between moulding, easily cause foundation ditch surrounding soil unstable, and concreting is also insecure in digging process.
When excavation of foundation pit is to phreatic line lower time, conventionally there will be mud particles constantly to drop from margin of foundation pit, construction is caused to puzzlement, and finally affect the quality that water-stop curtain is built.
Therefore,, for solving the problems of the technologies described above, the necessary construction technology that a kind of Novel water-stop curtain with improved process is provided, to overcome described defect of the prior art.
[summary of the invention]
For addressing the above problem, the object of the present invention is to provide a kind ofly construct fast, stagnant water effect is good and can keep the construction technology of the stable Novel water-stop curtain of soil layer construction.
For achieving the above object, the technical scheme that the present invention takes is: a kind of construction technology of Novel water-stop curtain, it comprises following processing step: 1), measurement and positioning: with transit and level gauge measurement and positioning, and determine the position in churning hole after secondary detection confirmation, and make marks on position, hole; 2), hole after in place by the position of mark drawing drilling machine; 3), carry out hole clearly after having holed, and will draw drilling machine and be displaced to next position, hole, and repeating step 2) and step 3); 4), configuration cement paste; 5), insert high-pressure nozzle to hole, start air compressor machine air-supply, water under high pressure pumping water simultaneously; 6), high-pressure rotary-spray operation: form water-stop curtain by pumps water mud, high pressure spray tube edge rotation limit promotes; 7), recharge, make to keep full in hole and starch; 8), resettlement: high-pressure nozzle is moved to next position, hole, repeating step 5) to step 7), and finally complete the water curtain construction of whole road.
The construction technology of Novel water-stop curtain of the present invention is further: the gradient of described boring must not be greater than 1.5%.
The construction technology of Novel water-stop curtain of the present invention is further: the material of described cement paste is neat slurry, and cement adopts P.C.32.5 Composite portland cement; The water/binder ratio of cement paste is 1.0, and serum density is 1.49kg/L.
The construction technology of Novel water-stop curtain of the present invention is further: the air pressure of described air compressor machine air-supply is 0.7Mpa, and air mass flow is 3m 3/ min.
The construction technology of Novel water-stop curtain of the present invention is further: the pressure of described water under high pressure pumping water is greater than 30Mpa, and discharge is 100L/min.
The construction technology of Novel water-stop curtain of the present invention is further: the pressure of described pumps water mud is 2Mpa, and slurry flow is 80L/min.
The construction technology of Novel water-stop curtain of the present invention is further: the rotary speed of described high-pressure nozzle is 15Rpm, and hoisting velocity is 15~20cm/min.
The construction technology of Novel water-stop curtain of the present invention is further: before high-pressure nozzle promotes, and the quiet spray of original position 1~3 minute at the bottom of Ying Kong.
The construction technology of Novel water-stop curtain of the present invention is further: described cement paste consumption is 180~250kg/m.
The construction technology of Novel water-stop curtain of the present invention is further: before high-pressure nozzle inserts in the hole, need to try spray inspection.
Compared with prior art, the present invention has following beneficial effect: the construction technology of Novel water-stop curtain of the present invention have construction fast, stagnant water effect is good and can keep soil layer construction the plurality of advantages such as to stablize.
[accompanying drawing explanation].
Fig. 1 is the process chart of the construction technology of Novel water-stop curtain of the present invention.
[specific embodiment]
Refer to shown in Figure of description 1, the present invention is a kind of construction technology of Novel water-stop curtain, and it comprises following processing step:
1), measurement and positioning: with transit and level gauge measurement and positioning, and determine the position in churning hole after secondary detection confirmation, and make marks on position, hole;
2), hole after in place by the position of mark drawing drilling machine, wherein, the gradient of described boring must not be greater than 1.5%;
3), carry out hole clearly after having holed, and will draw drilling machine and be displaced to next position, hole, and repeating step 2) and step 3);
4), configuration cement paste, wherein, the material of described cement paste is neat slurry, cement adopts P.C.32.5 Composite portland cement; The water/binder ratio of cement paste is 1.0, and serum density is 1.49kg/L; Its consumption is 180~250kg/m;
5), insert high-pressure nozzle to hole, start air compressor machine air-supply, water under high pressure pumping water simultaneously; Wherein, the air pressure of described air compressor machine air-supply is 0.7Mpa, and air mass flow is 3m 3/ min; The pressure of described water under high pressure pumping water is greater than 30Mpa, and discharge is 100L/min; Before inserting in the hole, high-pressure nozzle needs to try spray inspection;
6), high-pressure rotary-spray operation: form water-stop curtain by pumps water mud, high pressure spray tube edge rotation limit promotes; Wherein, the pressure of described pumps water mud is 2Mpa, and slurry flow is 80L/min; The rotary speed of described high-pressure nozzle is 15Rpm, and hoisting velocity is 15~20cm/min; Meanwhile, before high-pressure nozzle promotes, the quiet spray of original position 1~3 minute at the bottom of Ying Kong;
7), recharge, make to keep full in hole and starch;
8), resettlement: high-pressure nozzle is moved to next position, hole, repeating step 5) to step 7), and finally complete the water curtain construction of whole road.
The above specific embodiment is only the preferred embodiment of this creation, not in order to limit this creation, any modification of making, is equal to replacement, improvement etc., within all should being included in the protection domain of this creation within all spirit in this creation and principle.

Claims (10)

1. a construction technology for Novel water-stop curtain, is characterized in that: comprise following processing step:
1), measurement and positioning: with transit and level gauge measurement and positioning, and determine the position in churning hole after secondary detection confirmation, and make marks on position, hole;
2), hole after in place by the position of mark drawing drilling machine;
3), carry out hole clearly after having holed, and will draw drilling machine and be displaced to next position, hole, and repeating step 2) and step 3);
4), configuration cement paste;
5), insert high-pressure nozzle to hole, start air compressor machine air-supply, water under high pressure pumping water simultaneously;
6), high-pressure rotary-spray operation: form water-stop curtain by pumps water mud, high pressure spray tube edge rotation limit promotes;
7), recharge, make to keep full in hole and starch;
8), resettlement: high-pressure nozzle is moved to next position, hole, repeating step 5) to step 7), and finally complete the water curtain construction of whole road.
2. the construction technology of Novel water-stop curtain as claimed in claim 1, is characterized in that: the gradient of described boring must not be greater than 1.5%.
3. the construction technology of Novel water-stop curtain as claimed in claim 1, is characterized in that: the material of described cement paste is neat slurry, and cement adopts P.C.32.5 Composite portland cement; The water/binder ratio of cement paste is 1.0, and serum density is 1.49kg/L.
4. the construction technology of Novel water-stop curtain as claimed in claim 1, is characterized in that: the air pressure of described air compressor machine air-supply is 0.7Mpa, and air mass flow is 3m 3/ min.
5. the construction technology of Novel water-stop curtain as claimed in claim 1, is characterized in that: the pressure of described water under high pressure pumping water is greater than 30Mpa, and discharge is 100L/min.
6. the construction technology of Novel water-stop curtain as claimed in claim 1, is characterized in that: the pressure of described pumps water mud is 2Mpa, and slurry flow is 80L/min.
7. the construction technology of Novel water-stop curtain as claimed in claim 1, is characterized in that: the rotary speed of described high-pressure nozzle is 15Rpm, and hoisting velocity is 15~20cm/min.
8. the construction technology of Novel water-stop curtain as claimed in claim 1, is characterized in that: before high-pressure nozzle promotes, and the quiet spray of original position 1~3 minute at the bottom of Ying Kong.
9. the construction technology of Novel water-stop curtain as claimed in claim 1, is characterized in that: described cement paste consumption is 180~250kg/m.
10. the construction technology of Novel water-stop curtain as claimed in claim 1, is characterized in that: before high-pressure nozzle inserts in the hole, need to try spray inspection.
CN201210439973.6A 2012-11-07 2012-11-07 Novel construction technology of waterproof curtain Pending CN103806457A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210439973.6A CN103806457A (en) 2012-11-07 2012-11-07 Novel construction technology of waterproof curtain

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210439973.6A CN103806457A (en) 2012-11-07 2012-11-07 Novel construction technology of waterproof curtain

Publications (1)

Publication Number Publication Date
CN103806457A true CN103806457A (en) 2014-05-21

Family

ID=50703809

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210439973.6A Pending CN103806457A (en) 2012-11-07 2012-11-07 Novel construction technology of waterproof curtain

Country Status (1)

Country Link
CN (1) CN103806457A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196041A (en) * 2014-08-09 2014-12-10 葛洲坝集团基础工程有限公司 Construction method for concrete diaphragm wall cofferdam heightening
CN105220695A (en) * 2015-08-21 2016-01-06 中铁建大桥工程局集团第五工程有限公司 Close sand ovum layer moves water slip casting solidification construction
CN105649053A (en) * 2016-02-05 2016-06-08 沙焕焕 Construction method of multielement stiffness composite pile
CN105862872A (en) * 2016-04-05 2016-08-17 中铁十局集团第四工程有限公司 Deep foundation pit support structure joint water stop construction method
CN105862725A (en) * 2016-03-31 2016-08-17 大连久鼎祥瑞特种工程技术研究院有限公司 Underground construction preliminary grouting waterproof and anti-seepage supporting technology
CN107119692A (en) * 2017-05-03 2017-09-01 中交航局第工程有限公司 A kind of Soft Deep Foundation Pit support construction process
CN107842030A (en) * 2017-12-07 2018-03-27 中铁二十局集团第六工程有限公司 High-pressure rotary jet grouting pile equipment and construction method are used in a kind of material for diaphragm wall of Cofferdam construction

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09111750A (en) * 1995-10-16 1997-04-28 Kazuo Iki High pressure jet agitation pile method
CN101250873A (en) * 2008-04-10 2008-08-27 徐玉杰 High-pressure injection slip-casting construction method for flabbiness foundation

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09111750A (en) * 1995-10-16 1997-04-28 Kazuo Iki High pressure jet agitation pile method
CN101250873A (en) * 2008-04-10 2008-08-27 徐玉杰 High-pressure injection slip-casting construction method for flabbiness foundation

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
刘兆慧: "建筑基坑止水帷幕方案设计与施工技术", 《山西建筑》 *
刘震国: "高压旋喷桩止水帷幕在深基坑支护中的应用", 《建筑机械化》 *
刘震国: "高压旋喷桩止水帷幕在深基坑支护中的应用", 《建筑机械化》, 30 August 2012 (2012-08-30) *
张海全: "旋喷桩止水帷幕在深基坑中的应用", 《中国高新技术企业》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196041A (en) * 2014-08-09 2014-12-10 葛洲坝集团基础工程有限公司 Construction method for concrete diaphragm wall cofferdam heightening
CN104196041B (en) * 2014-08-09 2016-08-17 中国葛洲坝集团基础工程有限公司 A kind of concrete cut cofferdam body heightening construction method
CN105220695A (en) * 2015-08-21 2016-01-06 中铁建大桥工程局集团第五工程有限公司 Close sand ovum layer moves water slip casting solidification construction
CN105220695B (en) * 2015-08-21 2017-05-10 中铁建大桥工程局集团第五工程有限公司 Compact sandy-pebble layer dynamic grouting curing construction method
CN105649053A (en) * 2016-02-05 2016-06-08 沙焕焕 Construction method of multielement stiffness composite pile
CN105862725A (en) * 2016-03-31 2016-08-17 大连久鼎祥瑞特种工程技术研究院有限公司 Underground construction preliminary grouting waterproof and anti-seepage supporting technology
CN105862872A (en) * 2016-04-05 2016-08-17 中铁十局集团第四工程有限公司 Deep foundation pit support structure joint water stop construction method
CN107119692A (en) * 2017-05-03 2017-09-01 中交航局第工程有限公司 A kind of Soft Deep Foundation Pit support construction process
CN107842030A (en) * 2017-12-07 2018-03-27 中铁二十局集团第六工程有限公司 High-pressure rotary jet grouting pile equipment and construction method are used in a kind of material for diaphragm wall of Cofferdam construction

Similar Documents

Publication Publication Date Title
CN103806457A (en) Novel construction technology of waterproof curtain
CN104532821A (en) Extra-large karst cave bottom treatment construction method
CN103485345A (en) Construction method for covering layer closed porthole high-pressure curtain grouting
CN102704871B (en) The method of further well-flushing and well washing apparatus in water source heat pump system
CN204753574U (en) High pressure jet grouting pile stagnant water curtain construction equipment
CN108104865B (en) A kind of concordant drilling Anti-air-leakage gas pumping method
CN203361143U (en) Combination structure of high-pressure jet grouting pile and prestressed pipe pile
CN104631463B (en) Earth source heat pump deep-well backfilling grouting method
CN107503770A (en) A kind of duct pieces of shield tunnel secondary grouting method
CN105544573B (en) Water pressure jetting type well completion construction method of dewatering tube well
CN108265720A (en) A kind of single-point bellows grouting device and its method for controlling soil deformation
CN107218078A (en) Filled for underground coal goaf and abandoned workings, the new technology of grouting filling
CN203684210U (en) Secondary hole cleaning device for bottom of bored pile
CN203569561U (en) Novel pile forming device of steel pipe protection wall cast-in-place piles following up drill
CN104831701A (en) Multifunctional detection rod-free in-situ static force test system and using method
CN202215169U (en) Pump circulating construction device and in-water pile construction system
CN204456124U (en) One is slip casing by pressure pipe repeatedly
CN204357447U (en) A kind of prefabricated pipe section for shield tunnel lining cutting stratum grouting device behind
CN207377561U (en) The bad water-bearing layer positioning targeting slip casting Mine Shaft Lining of rock section and constructing device
CN205934916U (en) Steel casing pipe pore -forming anti -floating anchor rod
CN104712288A (en) Argillaceous cementing soft rock-soil body high-energy gas fracturing grouting method
CN202249851U (en) Reverse circulation hole forming equipment for cast-in-place pile
CN204715334U (en) Multi-functional without feeler lever original position static(al) testing arrangement
CN203891785U (en) Special joint pipe assembly for throwing of gravels in pipe of hydrogeological water well
CN103590394B (en) The construction method of original state soil taking and filling pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Jiang Xueqiang

Inventor after: Lu Changgen

Inventor after: Guo Caixia

Inventor after: Shi Leilei

Inventor after: Chen Xilin

Inventor after: Di Yongshan

Inventor after: Wang Wenzhi

Inventor before: Liu Qiduo

Inventor before: Chen Xilin

Inventor before: Jiang Xueqiang

Inventor before: Lu Changgen

Inventor before: Guo Caixia

Inventor before: Shi Yajun

Inventor before: Shi Leilei

Inventor before: Hu Jianjun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LIU QIDUO CHEN XILIN JIANG XUEQIANG LU CHANGGEN GUO CAIXIA SHI YAJUN SHI LEILEI HU JIANJUN TO: JIANG XUEQIANG LU CHANGGEN GUO CAIXIA SHI LEILEI CHEN XILIN ZHAI YONGSHAN WANG WENZHI

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140521