CN103758133A - Deep soft soil foundation pit reinforcement method - Google Patents

Deep soft soil foundation pit reinforcement method Download PDF

Info

Publication number
CN103758133A
CN103758133A CN201410013704.2A CN201410013704A CN103758133A CN 103758133 A CN103758133 A CN 103758133A CN 201410013704 A CN201410013704 A CN 201410013704A CN 103758133 A CN103758133 A CN 103758133A
Authority
CN
China
Prior art keywords
excavation
area
foundation ditch
reinforcing
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410013704.2A
Other languages
Chinese (zh)
Other versions
CN103758133B (en
Inventor
殷德顺
孟瑞繁
周超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hohai University HHU
Original Assignee
Hohai University HHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hohai University HHU filed Critical Hohai University HHU
Priority to CN201410013704.2A priority Critical patent/CN103758133B/en
Publication of CN103758133A publication Critical patent/CN103758133A/en
Application granted granted Critical
Publication of CN103758133B publication Critical patent/CN103758133B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a deep soft soil foundation pit reinforcement method and belongs to the technical field of foundation reinforcement. Firstly, an area requiring excavation is supported according to standards and divided into two zones which are sequentially marked as a first excavation zone and a second excavation zone from top to bottom, and the first excavation zone is excavated; secondly, the bottom of a foundation pit is reinforced to form a reinforced area, and the second excavation zone is excavated. The reinforcement method includes: piling the reinforced area according to a layout, by means of a high pressure jet grouting pile technology, when a power drill reaches a design depth, jetting curing agent and slowly lifting a drill bit upwards by a grouting pipe, stopping jetting the curing agent when the drill bit reaches an appointed position according to the designed pile length, and then quickly lifting the drill bit upwards. Owing to the deep soft soil foundation pit reinforcement method, influences of deformation of a supporting structure on the foundation pit can be effectively controlled while early deformation during excavation can be reduced, and accordingly stability of the foundation pit can be maintained more economically and effectively.

Description

A kind of method of deep weak soil foundation ditch strengthening
Technical field
The present invention relates to the technical field of foundation ditch strengthening, in particular to a kind of method of deep weak soil foundation ditch strengthening.
Background technology
Traditional foundation ditch strengthening method is after excavation of foundation pit completes, flowing of its driven pile restriction bottom, bottom soil body, to reach the object that prevents bottom heave.The key of this technical method is that stake will reach comparatively hard bearing stratum competence exertion effect, and often only the protuberance of the foundation ditch bottom soil body is had to control action.In fact, in Excavation Process, due to the off-load of excavation face, enclosure wall can produce horizontal movement under the poor effect of pressure at both sides, this displacement meeting makes to produce plastic strain upwards at the bottom of Foundation Pit, produces larger plastic zone simultaneously, and cause surface settlement around foundation ditch; And after excavation of foundation pit, the body of wall below foundation ditch bottom surface still can move to foundation ditch direction, push the soil body before wall, thereby continue to cause foundation pit deformation.In addition, because excavation is front, reinforce rear, conventional method is carried out bottom consolidation process after excavation completes again, and cannot avoid the distortion in advance producing in digging process.
?
Summary of the invention
For solving the foundation pit deformation that causes due to Supporting Structure deformation in deep weak soil foundation ditch and problem on deformation in advance, the present invention proposes a kind of method of deep weak soil foundation ditch strengthening.
The present invention is that the technical scheme that solves the problems of the technologies described above proposition is: the method for deep weak soil foundation ditch strengthening, and the method comprises the following steps: 1 pair needs the region of excavation to carry out supporting; 2) region of needs excavation is divided into two regions, is labeled as successively from top to bottom the first excavation area and the second excavation area; 3) cut out the first excavation area; 4) foundation ditch bottom is reinforced and forms reinforcing area; 5) cut out the second excavation area.
Preferably, the method is further comprising the steps of: before step 3) cuts out the first excavation area, determine the regional extent at the first excavation area and the second place, excavation area according to the design of foundation ditch; According to soil layer property and deep foundation ditch size, determine the scope of reinforcing area and the length of the needed stake of reinforcing area.
Preferably, the method is further comprising the steps of: step 4) to the reinforcing of foundation ditch bottom before, in the position of the second corresponding reinforcing area in surface, excavation area, reinforcing area is carried out to setting-out according to the area displacement of calculating design with the reinforcing mode of quincuncial pile, the position of determining every pile, finally reinforces reinforcing area.
Preferably, described reinforcing mode is: according to setting-out, reinforcing area is driven piles, adopt high-pressure rotary jet grouting pile technique, when machinery gets into projected depth, Grouting Pipe is sprayed curing compound and is upwards carried lentamente drill bit, according to the length of the stake of design, when drill bit arrives the position of specifying, stop spraying curing compound, then upwards carry fast drill bit.
The method of deep weak soil foundation ditch strengthening of the present invention, compared to existing technology, has following beneficial effect:
1. the impact of the horizontal movement that the present invention has taken into full account supporting and protection structure in digging process on foundation ditch, in the method that foundation ditch underrun is artificial, manufactured hard formation, enclosure wall under supporting and protection structure especially foundation ditch bottom surface is played a supporting role, thereby effectively controlled the distortion of supporting and protection structure, safeguarded the stable of foundation ditch.
2. this reinforcement means has been avoided the phenomenon of traditional reinforcement means " excavation, front, is reinforced rear ", can effectively reduce the distortion in advance in Excavation Process.
3. this method, after reinforcing completes, possesses the effect of conventional method consolidated subsoil equally, thereby economical and effective more.
 
Accompanying drawing explanation
Fig. 1 is the structural representation of the embodiment of the present invention;
Wherein: 1 is the first excavation region, 2 is the second excavation region, and 3 is reinforcing area, and 4 is braced structures, and 5 is supporting and protection structure, and 6 is ground.
 
The specific embodiment
For making object and the technical scheme of the embodiment of the present invention clearer, below in conjunction with the accompanying drawing of the embodiment of the present invention, the technical scheme of the embodiment of the present invention is clearly and completely described.Obviously, described embodiment is a part of embodiment of the present invention, rather than whole embodiment.Based on described embodiments of the invention, the every other embodiment that those of ordinary skills obtain under the prerequisite without creative work, belongs to the scope of protection of the invention.
Those skilled in the art of the present technique are appreciated that unless otherwise defined, all terms used herein (comprising technical term and scientific terminology) have with the present invention under the identical meaning of the general understanding of those of ordinary skill in field.Should also be understood that such as those terms that define in general dictionary and should be understood to have the meaning consistent with meaning in the context of prior art, unless and definition as here, can not explain by idealized or too formal implication.
The method of a kind of deep weak soil foundation ditch strengthening of the present embodiment, as shown in Figure 1, needs the region of excavation to be divided into two regions, is labeled as successively from top to bottom the first excavation area and the second excavation area; First according to the design of foundation ditch, determine the degree of depth that needs excavation, and the regional extent at the first excavation area, the second place, excavation area, and according to the standard of deep foundation pit support, supporting is carried out in the region of needs excavation, then cut out the first excavation area; According to soil layer property and deep foundation ditch size, determine the regional extent of reinforcing area, and calculate the length of needed stake, and in the position of the second corresponding reinforcing area in excavation area, reinforcing area is carried out to setting-out according to the area displacement of calculating design with the reinforcing mode of quincuncial pile, determine the position of every pile; Finally reinforcing area is reinforced, and cut out the second excavation area.
Described region reinforcement means is: according to setting-out, reinforcing area is driven piles, adopt high-pressure rotary jet grouting pile technique, when machinery gets into the particular design degree of depth, Grouting Pipe is sprayed curing compound and is upwards carried lentamente drill bit, according to the length of the stake of design, to the position of specifying, stop spraying curing compound, then upwards carry fast drill bit.
The method of deep weak soil foundation ditch strengthening of the present invention, according to the following step, carry out:
1. according to the design of foundation ditch, determine the degree of depth of excavation, and the scope at the place, region of the first excavation area, the second excavation area.
2. according to the standard of deep foundation pit support, supporting is carried out in excavation region.
3. carry out first step excavation, cut out the first excavation area, reduce the degree of depth of piling.
4. according to soil layer property and deep foundation ditch size, determine the length of the stake that reinforcing area and reinforcing used.The position corresponding on the second surface, excavation area carried out setting-out according to the area displacement of calculating design with the reinforcing mode of quincuncial pile, determines the position of every pile.
5. in the second excavation area, according to setting-out, drive piles, adopt high-pressure rotary jet grouting pile technique, when machinery gets into reinforcing area projected depth, Grouting Pipe is sprayed curing compound and is slowly upwards promoted drill bit, according to the length of the stake of design, to the position of specifying, stop spraying curing compound, then upwards carry fast drill bit.
6. through the regular hour, after the intensity of stake meets the demands, carry out second step excavation, cut out the second excavation area.
These are only the specific embodiment of the present invention, it describes comparatively concrete and detailed, but can not therefore be interpreted as the restriction to the scope of the claims of the present invention.It should be pointed out that for the person of ordinary skill of the art, without departing from the inventive concept of the premise, can also make some distortion and improvement, these all belong to protection scope of the present invention.

Claims (4)

1. a method for deep weak soil foundation ditch strengthening, is characterized in that: the method comprises the following steps:
1) supporting is carried out in the region of needs excavation;
2) region of needs excavation is divided into two regions, is labeled as successively from top to bottom the first excavation area and the second excavation area;
3) cut out the first excavation area;
4) foundation ditch bottom is reinforced and forms reinforcing area;
5) cut out the second excavation area.
2. the method for deep weak soil foundation ditch strengthening according to claim 1, it is characterized in that: the method is further comprising the steps of: before step 3) cuts out the first excavation area, according to the design of foundation ditch, determine the regional extent at the first excavation area and the second place, excavation area; According to soil layer property and deep foundation ditch size, determine the scope of reinforcing area and the length of the needed stake of reinforcing area.
3. the method for deep weak soil foundation ditch strengthening according to claim 1, it is characterized in that: the method is further comprising the steps of: before step 4) is reinforced foundation ditch bottom, in the position of the second corresponding reinforcing area in surface, excavation area, reinforcing area is carried out to setting-out according to the area displacement of calculating design with the reinforcing mode of quincuncial pile, the position of determining every pile, finally reinforces reinforcing area.
4. according to the method for the deep weak soil foundation ditch strengthening described in any one in claim 1-3, it is characterized in that: described reinforcing mode is: according to setting-out, reinforcing area is driven piles, adopt high-pressure rotary jet grouting pile technique, when machinery gets into projected depth, Grouting Pipe is sprayed curing compound and is upwards carried lentamente drill bit, according to the length of the stake of design, when drill bit arrives the position of specifying, stop spraying curing compound, then upwards carry fast drill bit.
CN201410013704.2A 2014-01-13 2014-01-13 A kind of method of deep soft soil foundation pit reinforcement Expired - Fee Related CN103758133B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410013704.2A CN103758133B (en) 2014-01-13 2014-01-13 A kind of method of deep soft soil foundation pit reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410013704.2A CN103758133B (en) 2014-01-13 2014-01-13 A kind of method of deep soft soil foundation pit reinforcement

Publications (2)

Publication Number Publication Date
CN103758133A true CN103758133A (en) 2014-04-30
CN103758133B CN103758133B (en) 2016-01-20

Family

ID=50525442

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410013704.2A Expired - Fee Related CN103758133B (en) 2014-01-13 2014-01-13 A kind of method of deep soft soil foundation pit reinforcement

Country Status (1)

Country Link
CN (1) CN103758133B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109537598A (en) * 2018-12-05 2019-03-29 上海公路桥梁(集团)有限公司 Control excavation of foundation pit deformation method
CN109594442A (en) * 2018-12-14 2019-04-09 北京绿视点园林景观工程有限公司 Garden path construction technology

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1563605A (en) * 2004-03-23 2005-01-12 孙学毅 Constructing method for controlling deformation on ground excavated
CN101148882A (en) * 2007-10-29 2008-03-26 中铁二院工程集团有限责任公司 Stable excavating method for cracked weak rock road cutting high slope
KR20090091463A (en) * 2008-02-25 2009-08-28 코오롱건설주식회사 Soil retaining method for two rows pile using soil nailing
CN102031781A (en) * 2009-09-24 2011-04-27 上海市第一建筑有限公司 Foundation pit reinforcing technology from shallow position to deep position for group pit construction

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1563605A (en) * 2004-03-23 2005-01-12 孙学毅 Constructing method for controlling deformation on ground excavated
CN101148882A (en) * 2007-10-29 2008-03-26 中铁二院工程集团有限责任公司 Stable excavating method for cracked weak rock road cutting high slope
KR20090091463A (en) * 2008-02-25 2009-08-28 코오롱건설주식회사 Soil retaining method for two rows pile using soil nailing
CN102031781A (en) * 2009-09-24 2011-04-27 上海市第一建筑有限公司 Foundation pit reinforcing technology from shallow position to deep position for group pit construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109537598A (en) * 2018-12-05 2019-03-29 上海公路桥梁(集团)有限公司 Control excavation of foundation pit deformation method
CN109594442A (en) * 2018-12-14 2019-04-09 北京绿视点园林景观工程有限公司 Garden path construction technology
CN109594442B (en) * 2018-12-14 2020-12-11 北京绿视点园林景观工程有限公司 Garden road construction process

Also Published As

Publication number Publication date
CN103758133B (en) 2016-01-20

Similar Documents

Publication Publication Date Title
CN103290849B (en) Pit-in-pit supporting structure of half topdown construction method and construction method thereof
CN104912098A (en) Combined construction method for supporting beam plate and structural plate of deep foundation pit
CN105178327A (en) Composite retaining structure of foundation pit project and construction method thereof
CN108086296B (en) Dynamic and static combined grouting foundation reinforcing construction method
CN107401161A (en) High ferro shield tunnel construction method is worn under pipe-roof method and MJS method joint reinforcements
CN205260041U (en) Method of freezing supporting construction is spouted soon to level
CN104563129B (en) A kind of pile body is provided with the Double-row-piles Structure that adds the stake of core horizontal jet grouting
CN102071675A (en) Soft soil foundation consolidation method combining drainage pile loading prepressing and deep mixing piles
CN107401411A (en) Step excavation construction method is strengthened in a kind of interim perpendicular support for being applied to IV grade of country rock Shallow depth bored tunnel
CN104074183A (en) Drilling and concrete injected root composite pile implanting pile structure and construction method
CN104895121A (en) Transverse partition method for reducing ground surface settlement and building structure deformation of underground structure construction
CN110761300A (en) Construction method for supporting impervious soft soil body on side slope of deep foundation pit of high-rise building through micro-expansion
CN103758133B (en) A kind of method of deep soft soil foundation pit reinforcement
CN101575855A (en) Non soil taking hole guiding process for sinking prestressed pipe pile or prefabricated square pile
CN102220764A (en) Deep foundation pit bracing system and construction method thereof
CN218934444U (en) High-pressure horizontal jet grouting pile tunnel reinforcing structure in frozen soil area
CN104153355B (en) The constructing device of concrete-pile and construction method thereof
CN104594367B (en) A kind of combined type cofferdam structure and construction method
CN207846429U (en) A kind of phreatic high, high basement rock go out the foundation pit supporting system shown up
CN105421488A (en) Constriction method for changing support of foundation slab in underground composite enclosure system
CN105239579A (en) Blocking wall type control method for deformation of soft soil deep foundation pit
CN108396728A (en) Constructing device and construction method for the multi-functional pile pile that the islands Tian Haizhu can drain
CN204645057U (en) A kind of pile body is provided with the Double-row-piles Structure adding the stake of core horizontal jet grouting
CN103866779A (en) Construction method of water stopping surrounding and protecting structure of soft soil foundation building foundation pit
CN104404944B (en) The anti-liquifying method of liquefiable sandy soil layer

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160120

Termination date: 20200113

CF01 Termination of patent right due to non-payment of annual fee