CN103745287A - Software project progress management method and system - Google Patents

Software project progress management method and system Download PDF

Info

Publication number
CN103745287A
CN103745287A CN201310064688.5A CN201310064688A CN103745287A CN 103745287 A CN103745287 A CN 103745287A CN 201310064688 A CN201310064688 A CN 201310064688A CN 103745287 A CN103745287 A CN 103745287A
Authority
CN
China
Prior art keywords
key point
test
module
project
software project
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310064688.5A
Other languages
Chinese (zh)
Inventor
王新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING YIQILIAN TECHNOLOGY CO., LTD.
Original Assignee
王新
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 王新 filed Critical 王新
Priority to CN201310064688.5A priority Critical patent/CN103745287A/en
Publication of CN103745287A publication Critical patent/CN103745287A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Stored Programmes (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention discloses a software project progress management method and a system. The method comprises the following steps of identifying the test stages of a Microsoft Project test plan; reading the start key points and the end key points of the test stages respectively; reading the current date and time of a computer, automatically judging the current test stage of a software project and popping up a prompt dialog box; calculating the number of days from the current test stage of the software project to the end key point via a time function, and popping up the prompt dialog box once a day from the preset number of days before the end key point. The system comprises a correlation test module, a date reading module, a project identification module, a comparison module and a prompt module. According to the method, the progress of the software project is real-timely monitored, and the progress condition of the software project is outputted reasonably, so that users can grasp the progress of the software project more accurately, the system is simple and convenient to use, and the progress of the project can be prompted automatically.

Description

Software project schedule management method and system
Technical field
The present invention relates to a kind of computer software project management method and system, relate in particular to a kind of Software project schedule management method and system, belong to software testing technology field.
Background technology
Present software test procedure, is all to start from test plan, according to plan, carries out enforcement.But often a plan may not be able to keep up with changes.Along with the carrying out of project, the interference of middle variety of issue and factor, makes the process of test duration, and namely project process departs from original designed path, towards uncontrollable future development.And industry does not have the method and system instrument of concrete management project process.The most widely used two large class instruments now, business type is as QC (Quality Center), TC (test center), and Open-Source Tools, as BugFree, does not all have the function of design schedule management.Also there is at present following phenomenon: first, present most project leader all can be after pinpointing the problems the reason that produces of problem analysis in time, the corresponding solution of taking out is adjusted deployment, so, project testing plan is also updated accordingly, and a lot of project leaders, at the beginning of approving and initiate a project, often elaborate plan is often delayed and is carried out in implementation process; The second, although test plan can be updated, the problem of project delay still can inevitably occur, this problem is not effectively solved so far.A main cause that produces above problem is exactly, and tests each phases-time control ability poor, causes task to be delayed, and just makes project delay.
Summary of the invention
Goal of the invention: the object of the invention is to for above-mentioned problems of the prior art and deficiency, a kind of Software project schedule management method and system of software project being carried out to time management and prompting is provided.
Technical scheme: Software project schedule management method of the present invention, comprises the steps:
1) each test phase in identification Microsoft Project test plan;
2) read each test phase and start key point and finish key point, the beginning key point of each test phase and end key point are one group of key point;
3) read computer current date and time, the current test phase of living in of automatic decision software project ejects prompting frame;
4) number of days apart from end key point by the current test phase of living in of function of time software for calculation project, from end key point, default number of days starts to eject prompting frame one time every day;
5) if the current test phase of living in of software project finishes in advance, before starting key point, next group just comes into effect next group stage corresponding to key point, according to the arrangement of software project, the beginning of next group key point and end key point in manual modification Microsoft Project test plan, and next group key point beginning and end key point in all stages afterwards;
6) if the current test phase of living in of software project postpones to finish, the end key point mistake of current key point group, according to software project arrangement, end key point in manual modification Microsoft Project test plan in current key point group, and in all stages afterwards the beginning in key point group and finish key point.
Above-mentioned Software project schedule management method, carrys out reminding user according to Preset Time, thereby causes that user removes to pay close attention to Software project schedule, increases work efficiency.
Described test phase comprises test preparatory stage, demand analysis design phase, use-case design phase, test execution stage, system maintenance and BUG stage and test summary stage.
In one group of key point of each described test phase, described beginning key point is " newly-built " key point, and described end key point is " examination finishes " key point.
Realize the system of above-mentioned Software project schedule management method, comprise associated test module for testing Microsoft Project file, for reading the date read module of computer dates, for the item recognition module of identification project test phase of living in, for comparison module and the reminding module of computing time; The output terminal of described associated test module connects respectively the input end of date read module input end and item recognition module, described date read module is connected the input end of comparison module with the output terminal of item recognition module, described comparison module output terminal connects the input end of reminding module;
Wherein, described associated test module by test to the successful information of Microsoft Project file association send to respectively date read module and item recognition module; Described date read module reads computer dates, and the computer dates reading is issued to item recognition module; Each test phase in item recognition Module recognition Microsoft Project test plan, issues item recognition module by the time of the key point of each test phase; Item recognition module is time and the computer dates of key point relatively, and when the date that time and the computer dates of key point differ is less than or equal to default number of days, reminding module is pointed out output.
When time of each test phase key point of software project is in default time phase, reminding module ejects prompting frame to be carried out reminding user test phase of living in and how long also has apart from key point, thereby causes that user goes to pay close attention to the progress of software project.
Beneficial effect: 1, Software project schedule management method provided by the present invention has realized the progress of real-time monitoring software project process, reasonably output software project process situation, make user can grasp more accurately Software project schedule, know effective test plan, and by completing of planning; 2, Software project schedule management system provided by the present invention has the following advantages: the one, and easy to use, as long as Software project schedule management system has been installed, and guarantee this system random start, just can realize project process automatic-prompting; The 2nd, test process is controlled, understands at any time PROJECT TIME arrangement and progress situation; The 3rd, improved work efficiency.
Accompanying drawing explanation
Fig. 1 is the process flow diagram of software project management embodiment of the method for the present invention.
Fig. 2 is the structured flowchart of software project management system embodiment of the present invention.
Embodiment
Below in conjunction with the drawings and specific embodiments, further illustrate the present invention, should understand these embodiment is only not used in and limits the scope of the invention for the present invention is described, after having read the present invention, those skilled in the art all fall within the application's claims limited range to the modification of the various equivalent form of values of the present invention.
The embodiment of Software project schedule management method as shown in Figure 1, comprises the steps:
1) associated Microsoft Project file, each test phase in identification Microsoft Project test plan, test phase comprises test preparatory stage, demand analysis design phase, use-case design phase, test execution stage, system maintenance and BUG stage and test summary stage;
2) read each test phase " newly-built " key point and " examination finishes " key point, " newly-built " key point of each test phase and " examination finishes " key point are one group of key point;
3) read computer current date and time, the current test phase of living in of automatic decision software project, ejects prompting frame;
4), by the number of days of the current test phase distance of living in of function of time software for calculation project " examination finishes " key point, from " examination finishes " key point, within 5 days, start to eject one time every day prompting frame;
5) if the current test phase of living in of software project finishes in advance, before next group " newly-built " key point, just " newly-built " implements next group stage corresponding to key point, according to the arrangement of software project, " newly-built " of next group key point and " examination finishes " key point in manual modification Microsoft Project test plan, and next group key point " newly-built " and " examination finishes " key point in all stages afterwards;
6) if the current test phase of living in of software project postpones to finish, " examination finishes " key point mistake of current key point group, according to software project arrangement, " examination finish " key point in manual modification Microsoft Project test plan in current key point group, and " newly-built " in key point group and " examination end " key point in all stages afterwards.
The embodiment of Software project schedule management method system as shown in Figure 2, the output terminal of associated test module connects respectively the input end of date read module input end and item recognition module, date read module is connected the input end of comparison module with the output terminal of item recognition module, comparison module output terminal connects the input end of reminding module.
Wherein, associated test module by test to the successful information of Microsoft Project file association send to respectively date read module and item recognition module; Date read module reads computer dates, and the computer dates reading is issued to item recognition module; Each test phase in item recognition Module recognition Microsoft Project test plan, issues item recognition module by the time of the key point of each test phase; Item recognition module is time and the computer dates of key point relatively, and when the date that time and the computer dates of key point differ is less than or equal to 5 days, reminding module is pointed out output.

Claims (4)

1. a Software project schedule management method, is characterized in that: comprise the steps:
1) each test phase in identification Microsoft Project test plan;
2) read each test phase and start key point and finish key point, the beginning key point of each test phase and end key point are one group of key point;
3) read computer current date and time, the current test phase of living in of automatic decision software project, ejects prompting frame;
4) number of days apart from end key point by the current test phase of living in of function of time software for calculation project, from end key point, default number of days starts to eject prompting frame one time every day;
5) if the current test phase of living in of software project finishes in advance, before starting key point, next group just comes into effect next group stage corresponding to key point, according to the arrangement of software project, manually repair the beginning of next group key point in MicrosoftProject test plan and finish key point, and next group key point beginning and end key point in all stages afterwards;
6) if the current test phase of living in of software project postpones to finish, the end key point mistake of current key point group, according to software project arrangement, end key point in manual modification Microsoft Project test plan in current key point group, and in all stages afterwards the beginning in key point group and finish key point.
2. Software project schedule management method as claimed in claim 1, is characterized in that: described test phase comprises test preparatory stage, demand analysis design phase, use-case design phase, test execution stage, system maintenance and BUG stage and test summary stage.
3. Software project schedule management method as claimed in claim 1 or 2, is characterized in that: in one group of key point of each described test phase, described beginning key point is " newly-built " key point, and described end key point is " examination finishes " key point.
4. a system that realizes Software project schedule management method described in claim 1, is characterized in that: comprise associated test module for testing Microsoft Project file, for reading the date read module of computer dates, for the item recognition module of identification project test phase of living in, for comparison module and the reminding module of computing time; The output terminal of described associated test module connects respectively the input end of date read module input end and item recognition module, described date read module is connected the input end of comparison module with the output terminal of item recognition module, described comparison module output terminal connects the input end of reminding module; Wherein, described associated test module by test to the successful information of Microsoft Project file association send to respectively date read module and item recognition module; Described date read module reads computer dates, and the computer dates reading is issued to item recognition module; Each survey in described item recognition Module recognition Microsoft Project test plan
In the examination stage, the time of the key point of each test phase is issued to item recognition module; Described item recognition module is time and the computer dates of key point relatively, and when the date that time and the computer dates of key point differ is less than or equal to default number of days, reminding module is pointed out output.
CN201310064688.5A 2013-03-01 2013-03-01 Software project progress management method and system Pending CN103745287A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310064688.5A CN103745287A (en) 2013-03-01 2013-03-01 Software project progress management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310064688.5A CN103745287A (en) 2013-03-01 2013-03-01 Software project progress management method and system

Publications (1)

Publication Number Publication Date
CN103745287A true CN103745287A (en) 2014-04-23

Family

ID=50502304

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310064688.5A Pending CN103745287A (en) 2013-03-01 2013-03-01 Software project progress management method and system

Country Status (1)

Country Link
CN (1) CN103745287A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104994410A (en) * 2015-07-06 2015-10-21 无锡天脉聚源传媒科技有限公司 Program list creation method and device
CN107680149A (en) * 2017-10-09 2018-02-09 广州四三九九信息科技有限公司 Project tendency drawing drawing method, device and server
CN107705027A (en) * 2017-10-17 2018-02-16 通辽霍林河坑口发电有限责任公司 Information cuing method and device
CN111340976A (en) * 2020-02-24 2020-06-26 北京百度网讯科技有限公司 Method and device for debugging vehicle module, electronic equipment and computer-readable storage medium
CN112035362A (en) * 2020-08-29 2020-12-04 中国平安人寿保险股份有限公司 Test project progress management method, device, equipment and storage medium

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102360465A (en) * 2011-09-30 2012-02-22 镇江睿泰信息科技有限公司 Software project schedule management method and system thereof
CN102456177A (en) * 2010-10-27 2012-05-16 镇江华扬信息科技有限公司 Software project management system
CN102456168A (en) * 2010-10-18 2012-05-16 捷达世软件(深圳)有限公司 Software project management system and method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102456168A (en) * 2010-10-18 2012-05-16 捷达世软件(深圳)有限公司 Software project management system and method
CN102456177A (en) * 2010-10-27 2012-05-16 镇江华扬信息科技有限公司 Software project management system
CN102360465A (en) * 2011-09-30 2012-02-22 镇江睿泰信息科技有限公司 Software project schedule management method and system thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104994410A (en) * 2015-07-06 2015-10-21 无锡天脉聚源传媒科技有限公司 Program list creation method and device
CN104994410B (en) * 2015-07-06 2018-03-09 无锡天脉聚源传媒科技有限公司 It is a kind of to compile single creation method and device
CN107680149A (en) * 2017-10-09 2018-02-09 广州四三九九信息科技有限公司 Project tendency drawing drawing method, device and server
CN107705027A (en) * 2017-10-17 2018-02-16 通辽霍林河坑口发电有限责任公司 Information cuing method and device
CN111340976A (en) * 2020-02-24 2020-06-26 北京百度网讯科技有限公司 Method and device for debugging vehicle module, electronic equipment and computer-readable storage medium
CN111340976B (en) * 2020-02-24 2022-11-15 北京百度网讯科技有限公司 Method and device for debugging automatic driving vehicle module and electronic equipment
CN112035362A (en) * 2020-08-29 2020-12-04 中国平安人寿保险股份有限公司 Test project progress management method, device, equipment and storage medium

Similar Documents

Publication Publication Date Title
CN107861871B (en) Gray scale publishing method, device, server and storage medium
CN103745287A (en) Software project progress management method and system
US10832179B2 (en) Method for constructing a future-state power grid model, device and equipment and storage medium
CN102360465A (en) Software project schedule management method and system thereof
US8930882B2 (en) Method, system, and computer program product for efficient resource allocation
CN104360922A (en) Method for automatically monitoring BMC working state based on ipmitool
CN102662833A (en) Method for managing test cases
CN109934433A (en) A kind of personnel ability's appraisal procedure, device and cloud service platform
CN103257917A (en) Management method for software evaluation system
CN103257918A (en) Project test procedure management method based on software testing and evaluation platform
CN104778118A (en) Improvement method for automatic testing technology
SA119400366B1 (en) System and Method of Automating a Slide Drilling Operation
CN104270389A (en) Method and system for automatically restoring security configuration vulnerability of router/ interchanger
CN102693460A (en) Tester management system and method thereof
CN103679972B (en) The monitoring method of tax-control terminal, Apparatus and system
CN117252420A (en) Job risk assessment method, device, equipment and storage medium
CN106484503B (en) A kind of calculation method and network processing unit verifying sum
US20160048794A1 (en) Project and task status indicator generator using baseline metrics
CN109740766B (en) Industrial equipment maintenance service planning method
CN102306333A (en) Work order time limit prompting device and work order time limit prompting method
CN104299038A (en) Method for periodic inspection and management of relay protection device
RU2011116440A (en) METHOD FOR AUTOMATED DATA PROCESSING FOR MAKING MANAGEMENT DECISIONS ON THE PROJECT AND PROJECT PORTFOLIO
CN102567351A (en) Testing method and testing device for database modification effects
CN108122060A (en) Software project schedule management method and system
CN103546341A (en) Automatic setup method of test environment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: BEIJING YIQILIAN TECHNOLOGY CO., LTD.

Free format text: FORMER OWNER: WANG XIN

Effective date: 20140815

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 242310 XUANCHENG, ANHUI PROVINCE TO: 101121 TONGZHOU, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20140815

Address after: 101121, No. 141, No. 2-1, 2536 North brick factory, Beijing, Tongzhou District

Applicant after: Beijing billion union Technology Co., Ltd.

Address before: 242310, No. 214, Ningguo cement factory, Ningguo Town, port town, Anhui, China

Applicant before: Wang Xin

WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140423