Software project schedule management method and system
Technical field
The present invention relates to a kind of computer software project management method and system, relate in particular to a kind of Software project schedule management method and system, belong to software testing technology field.
Background technology
Present software test procedure, is all to start from test plan, according to plan, carries out enforcement.But often a plan may not be able to keep up with changes.Along with the carrying out of project, the interference of middle variety of issue and factor, makes the process of test duration, and namely project process departs from original designed path, towards uncontrollable future development.And industry does not have the method and system instrument of concrete management project process.The most widely used two large class instruments now, business type is as QC (Quality Center), TC (test center), and Open-Source Tools, as BugFree, does not all have the function of design schedule management.Also there is at present following phenomenon: first, present most project leader all can be after pinpointing the problems the reason that produces of problem analysis in time, the corresponding solution of taking out is adjusted deployment, so, project testing plan is also updated accordingly, and a lot of project leaders, at the beginning of approving and initiate a project, often elaborate plan is often delayed and is carried out in implementation process; The second, although test plan can be updated, the problem of project delay still can inevitably occur, this problem is not effectively solved so far.A main cause that produces above problem is exactly, and tests each phases-time control ability poor, causes task to be delayed, and just makes project delay.
Summary of the invention
Goal of the invention: the object of the invention is to for above-mentioned problems of the prior art and deficiency, a kind of Software project schedule management method and system of software project being carried out to time management and prompting is provided.
Technical scheme: Software project schedule management method of the present invention, comprises the steps:
1) each test phase in identification Microsoft Project test plan;
2) read each test phase and start key point and finish key point, the beginning key point of each test phase and end key point are one group of key point;
3) read computer current date and time, the current test phase of living in of automatic decision software project ejects prompting frame;
4) number of days apart from end key point by the current test phase of living in of function of time software for calculation project, from end key point, default number of days starts to eject prompting frame one time every day;
5) if the current test phase of living in of software project finishes in advance, before starting key point, next group just comes into effect next group stage corresponding to key point, according to the arrangement of software project, the beginning of next group key point and end key point in manual modification Microsoft Project test plan, and next group key point beginning and end key point in all stages afterwards;
6) if the current test phase of living in of software project postpones to finish, the end key point mistake of current key point group, according to software project arrangement, end key point in manual modification Microsoft Project test plan in current key point group, and in all stages afterwards the beginning in key point group and finish key point.
Above-mentioned Software project schedule management method, carrys out reminding user according to Preset Time, thereby causes that user removes to pay close attention to Software project schedule, increases work efficiency.
Described test phase comprises test preparatory stage, demand analysis design phase, use-case design phase, test execution stage, system maintenance and BUG stage and test summary stage.
In one group of key point of each described test phase, described beginning key point is " newly-built " key point, and described end key point is " examination finishes " key point.
Realize the system of above-mentioned Software project schedule management method, comprise associated test module for testing Microsoft Project file, for reading the date read module of computer dates, for the item recognition module of identification project test phase of living in, for comparison module and the reminding module of computing time; The output terminal of described associated test module connects respectively the input end of date read module input end and item recognition module, described date read module is connected the input end of comparison module with the output terminal of item recognition module, described comparison module output terminal connects the input end of reminding module;
Wherein, described associated test module by test to the successful information of Microsoft Project file association send to respectively date read module and item recognition module; Described date read module reads computer dates, and the computer dates reading is issued to item recognition module; Each test phase in item recognition Module recognition Microsoft Project test plan, issues item recognition module by the time of the key point of each test phase; Item recognition module is time and the computer dates of key point relatively, and when the date that time and the computer dates of key point differ is less than or equal to default number of days, reminding module is pointed out output.
When time of each test phase key point of software project is in default time phase, reminding module ejects prompting frame to be carried out reminding user test phase of living in and how long also has apart from key point, thereby causes that user goes to pay close attention to the progress of software project.
Beneficial effect: 1, Software project schedule management method provided by the present invention has realized the progress of real-time monitoring software project process, reasonably output software project process situation, make user can grasp more accurately Software project schedule, know effective test plan, and by completing of planning; 2, Software project schedule management system provided by the present invention has the following advantages: the one, and easy to use, as long as Software project schedule management system has been installed, and guarantee this system random start, just can realize project process automatic-prompting; The 2nd, test process is controlled, understands at any time PROJECT TIME arrangement and progress situation; The 3rd, improved work efficiency.
Accompanying drawing explanation
Fig. 1 is the process flow diagram of software project management embodiment of the method for the present invention.
Fig. 2 is the structured flowchart of software project management system embodiment of the present invention.
Embodiment
Below in conjunction with the drawings and specific embodiments, further illustrate the present invention, should understand these embodiment is only not used in and limits the scope of the invention for the present invention is described, after having read the present invention, those skilled in the art all fall within the application's claims limited range to the modification of the various equivalent form of values of the present invention.
The embodiment of Software project schedule management method as shown in Figure 1, comprises the steps:
1) associated Microsoft Project file, each test phase in identification Microsoft Project test plan, test phase comprises test preparatory stage, demand analysis design phase, use-case design phase, test execution stage, system maintenance and BUG stage and test summary stage;
2) read each test phase " newly-built " key point and " examination finishes " key point, " newly-built " key point of each test phase and " examination finishes " key point are one group of key point;
3) read computer current date and time, the current test phase of living in of automatic decision software project, ejects prompting frame;
4), by the number of days of the current test phase distance of living in of function of time software for calculation project " examination finishes " key point, from " examination finishes " key point, within 5 days, start to eject one time every day prompting frame;
5) if the current test phase of living in of software project finishes in advance, before next group " newly-built " key point, just " newly-built " implements next group stage corresponding to key point, according to the arrangement of software project, " newly-built " of next group key point and " examination finishes " key point in manual modification Microsoft Project test plan, and next group key point " newly-built " and " examination finishes " key point in all stages afterwards;
6) if the current test phase of living in of software project postpones to finish, " examination finishes " key point mistake of current key point group, according to software project arrangement, " examination finish " key point in manual modification Microsoft Project test plan in current key point group, and " newly-built " in key point group and " examination end " key point in all stages afterwards.
The embodiment of Software project schedule management method system as shown in Figure 2, the output terminal of associated test module connects respectively the input end of date read module input end and item recognition module, date read module is connected the input end of comparison module with the output terminal of item recognition module, comparison module output terminal connects the input end of reminding module.
Wherein, associated test module by test to the successful information of Microsoft Project file association send to respectively date read module and item recognition module; Date read module reads computer dates, and the computer dates reading is issued to item recognition module; Each test phase in item recognition Module recognition Microsoft Project test plan, issues item recognition module by the time of the key point of each test phase; Item recognition module is time and the computer dates of key point relatively, and when the date that time and the computer dates of key point differ is less than or equal to 5 days, reminding module is pointed out output.