CN108122060A - Software project schedule management method and system - Google Patents

Software project schedule management method and system Download PDF

Info

Publication number
CN108122060A
CN108122060A CN201611086064.3A CN201611086064A CN108122060A CN 108122060 A CN108122060 A CN 108122060A CN 201611086064 A CN201611086064 A CN 201611086064A CN 108122060 A CN108122060 A CN 108122060A
Authority
CN
China
Prior art keywords
key point
test
module
project
test phase
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611086064.3A
Other languages
Chinese (zh)
Inventor
谢楚楚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Zhenhai Yongxin Mdt Infotech Ltd
Original Assignee
Ningbo Zhenhai Yongxin Mdt Infotech Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Zhenhai Yongxin Mdt Infotech Ltd filed Critical Ningbo Zhenhai Yongxin Mdt Infotech Ltd
Priority to CN201611086064.3A priority Critical patent/CN108122060A/en
Publication of CN108122060A publication Critical patent/CN108122060A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Marketing (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Stored Programmes (AREA)

Abstract

The invention discloses a kind of Software project schedule management methods and system, method to include the following steps:Identify each test phase in Microsoft Project test plans;Each test phase is read to start key point and terminate key point;It reads computer current date and time, automatic decision software project is presently in test phase, pops up prompting frame;The number of days that test phase distance terminates key point is presently in by function of time software for calculation project, pops up a prompting frame before terminates key point default number of days daily.System includes association test module, date read module, item recognition module, comparison module and reminding module.Method realizes the progress of watch on-line project process, and reasonably output software project process situation, allows user more accurately to grasp Software project schedule.System uses easy, realization project process automatic prompt.

Description

Software project schedule management method and system
Technical field
The present invention relates to a kind of computer software project management method and system more particularly to a kind of Software project schedule pipes Method and system are managed, belong to software testing technology field.
Background technology
Present software test procedure is all to start from test plan, is implemented according to plan to carry out.But it often counts It draws and is unable to catch up with changing.With the progress of project, the interference of intermediate various problems and factor so that the process of testing time, also It is that project process deviates original designed path, develops towards uncontrollable direction.Also, industry do not have concrete management project into The method and system instrument of degree.Present the most widely used two major classes instrument, business type such as QC (Quality Center), TC (test center), all Open-Source Tools such as Bug Free, the function without design schedule management.Also there are following phenomenons at present: First, now most project leader all can after pinpointing the problems timely problem analysis Producing reason, it is corresponding to take out Solution is disposed to adjust, so, project testing plan is also updated accordingly, and many project leaders are approving and initiate a project At the beginning of, often elaborate plan often is held off performing in implementation process;Second, although test plan can be by more Newly, but the problem of project delay, still can inevitably occur, this problem is not solved effectively so far.It generates One main cause of problem above is exactly that test each phases-time control ability poor, task is caused to be delayed, just so that project is prolonged Phase.
The content of the invention
Goal of the invention:It is an object of the invention to problem and shortage present in for the above-mentioned prior art, provide one kind The Software project schedule management method and system of time management and prompting are carried out to software project.
Technical solution:Software project schedule management method of the present invention, includes the following steps:
1) each test phase in Microsoft Project test plans is identified;
2) each test phase is read to start key point and terminate key point, the beginning key point of each test phase and end Key point is one group of key point;
3) read computer current date and time, automatic decision software project is presently in test phase, pops up prompting frame;
4) number of days of test phase distance end key point is presently in by function of time software for calculation project, from end The preceding default number of days of key point starts to pop up a prompting frame daily;
5) if software project is presently in test phase and terminates in advance, reality is begun to before next group starts key point The next group of key point corresponding stage is applied, then according to the arrangement of software project, manual modification Microsoft Project testers The beginning and end in all stages is crucial after the beginning and end key point of next group of key point and next group of key point in drawing Point;
If 6) software project is presently in test phase delay and terminates, the end key point of current key point group mistake, Then according to software project arrangement, the end in manual modification Microsoft Project test plans in current key point group is closed Key point and the beginning and end key point in all stages afterwards in key point group.
Above-mentioned Software project schedule management method, user is reminded according to preset time, goes to pay close attention to so as to cause user soft Part project process improves work efficiency.
The test phase includes test preparation stage, demand analysis design phase, case designing stage, test execution rank Section, system maintenance and BUG stages and test feedback and evaluation.
In one group of key point of each test phase, the key point that starts is " newly-built " key point, the knot Beam key point is " examination terminates " key point.
The system for realizing above-mentioned Software project schedule management method, including being used to test Microsoft Project files Association test module, for reading the date read module of computer dates, the project for identifying test phase residing for project Identification module, for calculating the comparison module and reminding module of time;The output terminal of the association test module connects the date respectively The output terminal of the input terminal of read module input terminal and item recognition module, the date read module and item recognition module connects Connect the input terminal of comparison module, the input terminal of the comparison module output terminal connection reminding module;
Wherein, the Microsoft Project file associations successful information point that the association test module will be tested Date read module and item recognition module are not sent to;The date read module reads computer dates, and will read Computer dates issue item recognition module;Each survey in item recognition module identification Microsoft Project test plans The time of the key point of each test phase is issued item recognition module by the examination stage;Item recognition module compares key point Time and computer dates when being less than or equal to preset number of days on the date that the time of key point differs with computer dates, prompt mould Block carries out prompting output.
When software project each test phase key point time in default time phase when, reminding module pop-up Prompting frame come remind test phase residing for user apart from key point also have how long, so as to cause user go concern software project Progress.
Advantageous effect:1st, Software project schedule management method provided by the present invention realize watch on-line project into The progress of degree, reasonably output software project process situation, allows user more accurately to grasp Software project schedule, it is known that has The test plan of effect, and the completion by planning;2nd, Software project schedule management system provided by the present invention has the following advantages: First, using simplicity, as long as being mounted with that Software project schedule manages system, and ensure the system random start, so that it may realize project Progress automatic prompt;Second is that test process is controllable, PROJECT TIME arrangement and progress status are understood at any time;Third, improve work effect Rate.
Description of the drawings
Fig. 1 is the flow chart of invention software project management method embodiment.
Fig. 2 is the structure diagram of invention software project management system embodiment.
Specific embodiment
In the following with reference to the drawings and specific embodiments, the present invention is furture elucidated, it should be understood that these embodiments are merely to illustrate It the present invention rather than limits the scope of the invention, after the present invention has been read, those skilled in the art are to of the invention each The modification of kind equivalent form falls within the application scope as defined in the appended claims.
The embodiment of Software project schedule management method is as shown in Figure 1, include the following steps:
1) Microsoft Project files are associated, identify each test in Microsoft Project test plans Stage, test phase include test preparation stage, demand analysis design phase, case designing stage, test execution stage, system It safeguards and BUG stages and test feedback and evaluation;
2) each test phase " newly-built " key point and " examination terminates " key point, " newly-built " pass of each test phase are read Key point and " examination terminates " key point are one group of key point;
3) read computer current date and time, automatic decision software project is presently in test phase, pops up prompting frame;
4) number of days of test phase distance " examination terminates " key point is presently in by function of time software for calculation project, Pop up a prompting frame daily since first 5 days of " examination terminates " key point;
It is just " new before next group of " newly-built " key point if 5) software project is presently in test phase and terminates in advance Build " implement the next group of key point corresponding stage, then according to the arrangement of software project, manual modification Microsoft Project All stages after " newly-built " of next group of key point and " examination terminates " key point and next group of key point in test plan " newly-built " and " examination terminates " key point;
If 6) software project be presently in test phase delay terminate, " examination terminates " key point of current key point group It has been crossed that, then according to software project arrangement, in manual modification Microsoft Project test plans in current key point group " examination terminates " key point and " newly-built " and " examination terminates " key point in all stages afterwards in key point group.
The embodiment of Software project schedule management method system is as shown in Fig. 2, the output terminal of association test module connects respectively The output terminal of the input terminal of date read module input terminal and item recognition module, date read module and item recognition module connects The input terminal of comparison module is connect, comparison module output terminal connects the input terminal of reminding module.
Wherein, association test module sends out the successful information of Microsoft Project file associations tested respectively Give date read module and item recognition module;Date read module reads computer dates, and the computer dates that will be read Issue item recognition module;Each test phase in item recognition module identification Microsoft Project test plans, will The time of the key point of each test phase issues item recognition module;Item recognition module compares time and the computer of key point On the date, when being less than or equal to 5 days on the date that the time of key point differs with computer dates, reminding module carries out prompting output.

Claims (4)

1. a kind of Software project schedule management method, it is characterised in that:Include the following steps:
1) each test phase in Microsoft Project test plans is identified;
2) read each test phase to start key point and terminate key point, the beginning key point of each test phase and end are crucial Point is one group of key point;
3) read computer current date and time, automatic decision software project is presently in test phase, pops up prompting frame;
4) number of days of test phase distance end key point is presently in by function of time software for calculation project, it is crucial from terminating The preceding default number of days of point starts to pop up a prompting frame daily;
5) if software project is presently in test phase and terminates in advance, begun to before next group starts key point under implementation One group of key point corresponding stage, then according to the arrangement of software project, in manual modification Microsoft Project test plans The beginning and end key point in all stages after the beginning and end key point and next group of key point of next group of key point;
If 6) software project is presently in test phase delay and terminates, the end key point of current key point group mistake, then root According to software project arrangement, the end key point in manual modification Microsoft Project test plans in current key point group, And the beginning and end key point in all stages afterwards in key point group.
2. Software project schedule management method as described in claim 1, it is characterised in that:It is accurate that the test phase includes test Standby stage, demand analysis design phase, case designing stage, test execution stage, system maintenance and BUG stages and test are summarized Stage.
3. Software project schedule management method as claimed in claim 1 or 2, it is characterised in that:In each test phase One group of key point in, the beginning key point is " newly-built " key point, and the end key point is " examination terminates " key point.
4. a kind of system for realizing Software project schedule management method described in claim 1, it is characterised in that:Including being used to test The association test module of Microsoft Project files, for read computer dates date read module, for identifying item The item recognition module of test phase residing for mesh, for calculating the comparison module and reminding module of time;The association test mould The output terminal of block connects date read module input terminal and the input terminal of item recognition module, the date read module and item respectively The input terminal of the output terminal connection comparison module of mesh identification module, the input of the comparison module output terminal connection reminding module End;
Wherein, the association test module sends out the successful information of Microsoft Project file associations tested respectively Give date read module and item recognition module;The date read module reads computer dates, and the computer that will be read Date issues item recognition module;Each survey in the item recognition module identification Microsoft Project test plans The time of the key point of each test phase is issued item recognition module by the examination stage;The item recognition module is more crucial The time of point and computer dates when being less than or equal to preset number of days on the date that the time of key point differs with computer dates, carry Show that module carries out prompting output.
CN201611086064.3A 2016-11-28 2016-11-28 Software project schedule management method and system Pending CN108122060A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611086064.3A CN108122060A (en) 2016-11-28 2016-11-28 Software project schedule management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611086064.3A CN108122060A (en) 2016-11-28 2016-11-28 Software project schedule management method and system

Publications (1)

Publication Number Publication Date
CN108122060A true CN108122060A (en) 2018-06-05

Family

ID=62226377

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611086064.3A Pending CN108122060A (en) 2016-11-28 2016-11-28 Software project schedule management method and system

Country Status (1)

Country Link
CN (1) CN108122060A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108845943A (en) * 2018-06-25 2018-11-20 郑州云海信息技术有限公司 A kind of method and system that judgement software test stage is completed

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108845943A (en) * 2018-06-25 2018-11-20 郑州云海信息技术有限公司 A kind of method and system that judgement software test stage is completed

Similar Documents

Publication Publication Date Title
US9710260B2 (en) Increasing proficiency status of developers
CN104679488B (en) A kind of flow custom development platform and flow custom development approach
Wynn et al. Business process simulation for operational decision support
CN105069524B (en) Planned dispatching optimization method based on big data analysis
US9606901B1 (en) System, method, and computer program for generating a detailed design of at least one telecommunications based integration testing project
CN115238359A (en) Construction progress simulation method and device, electronic equipment and storage medium
CN108229912A (en) Completion of works acceptance method and storage medium
Freitas et al. Process simulation support in BPM tools: The case of BPMN
CN111190814B (en) Method and device for generating software test case, storage medium and terminal
Likhitruangsilp et al. A BIM-enabled system for evaluating impacts of construction change orders
CN103745287A (en) Software project progress management method and system
Omar et al. Implementation of six sigma in service industry
CN102360465A (en) Software project schedule management method and system thereof
CN108122060A (en) Software project schedule management method and system
Clauberg et al. BPM and Simulation
CN109658014A (en) A kind of construction overall management method
KR20160081246A (en) Progress measurement and management system for EPC projects
US20110172801A1 (en) Method and system for determining manufacturing throughput target
Salih et al. The application of six sigma-supported expert system in construction projects
CN108537509A (en) Daily behavior manages system
CN111208993B (en) Flow data analysis processing system
Mehta et al. An Approach to Reduce Non-Value Added Time and Improve Process Cycle Efficiency by Implementing Project Information System
Yifan et al. University discipline construction progress monitoring system
Urbina et al. Process Improvement at Howmet Aerospace
Bode Maintenance Content Reduction and Digitalization for Performance Optimization

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20180605

WD01 Invention patent application deemed withdrawn after publication