CN115238359A - Construction progress simulation method and device, electronic equipment and storage medium - Google Patents

Construction progress simulation method and device, electronic equipment and storage medium Download PDF

Info

Publication number
CN115238359A
CN115238359A CN202210928318.0A CN202210928318A CN115238359A CN 115238359 A CN115238359 A CN 115238359A CN 202210928318 A CN202210928318 A CN 202210928318A CN 115238359 A CN115238359 A CN 115238359A
Authority
CN
China
Prior art keywords
progress
model
bim
simulation
expected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210928318.0A
Other languages
Chinese (zh)
Inventor
金和平
朱强
王建东
辜斌
张晨
刘晓青
赵鲲
陈娣
田武
周灿
潘建初
张晓萌
姜鹏
习兰云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Three Gorges High Technology Information Technology Co ltd
China Three Gorges Corp
Original Assignee
Three Gorges High Technology Information Technology Co ltd
China Three Gorges Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Three Gorges High Technology Information Technology Co ltd, China Three Gorges Corp filed Critical Three Gorges High Technology Information Technology Co ltd
Priority to CN202210928318.0A priority Critical patent/CN115238359A/en
Publication of CN115238359A publication Critical patent/CN115238359A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Civil Engineering (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Architecture (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application discloses a construction progress simulation method and device, electronic equipment and a storage medium. The method comprises the following steps: acquiring an initial BIM model to be subjected to progress simulation; establishing an incidence relation between an expected progress and a model member in the initial BIM by using the coding information to obtain a target BIM; acquiring the current corresponding overall actual progress of the target BIM model, and comparing the actual progress of the overall actual progress, which comprises the actual progress corresponding to each model member, with the expected progress to obtain a target comparison result; and generating progress simulation information for display based on the expected progress, the actual progress and the target comparison result. According to the method and the device, the incidence relation between the expected progress and the model component is established in the BIM model, dynamic linkage from the construction task to the model and from the model to the construction task is realized, progress simulation is carried out, the construction plan can be adjusted in time, and the effectiveness of the adjusted construction plan is guaranteed.

Description

Construction progress simulation method and device, electronic equipment and storage medium
Technical Field
The present application relates to the field of computer technologies, and in particular, to a method and an apparatus for simulating a construction progress, an electronic device, and a storage medium.
Background
Traditional progress management is to break down project work into smaller, more manageable tasks or activities through WBS work breakdown and to show progress plan completion through gantt charts. In the actual project implementation process, factors influencing progress control are complex, such as unreasonable schedule planning, uncoordinated resource distribution, untimely progress adjustment, policies, environments, technologies and the like all influence construction progress; meanwhile, the number of project participation units is large, the communication efficiency of the traditional two-dimensional drawing is low, the cooperation efficiency is influenced, and the progress is delayed; finally, the project schedule is compiled by human experience, but the actual construction is a constantly changing process, the actual schedule is often inconsistent with the schedule, and the construction schedule cannot be adjusted in time. And the progress plan after manual adjustment can not be guaranteed to effectively guide the construction.
Disclosure of Invention
In order to solve the technical problems or at least partially solve the technical problems, the application provides a simulation method and device of construction progress, an electronic device and a storage medium.
According to an aspect of an embodiment of the present application, there is provided a method for simulating a construction progress, including:
acquiring an initial BIM model to be subjected to progress simulation, wherein the initial BIM model carries coding information for representing the corresponding expected progress of each model component in the initial BIM model;
establishing an incidence relation between the expected progress and the model component in the initial BIM by using the coding information to obtain a target BIM;
acquiring the current corresponding overall actual progress of the target BIM model, and comparing the actual progress of each model member included in the overall actual progress with the expected progress to obtain a target comparison result;
and generating progress simulation information for display based on the expected progress, the actual progress and the target comparison result.
Further, the obtaining of the initial BIM model to be subjected to progress simulation includes:
acquiring an overall construction task corresponding to a BIM (building information modeling) model, wherein the overall construction task comprises expected progress corresponding to each model component in the initial BIM model, and the BIM model is an original BIM model corresponding to the initial BIM model;
detecting editing operation acting on the BIM model, and assigning the expected progress to the attribute corresponding to the model component based on the editing operation to obtain coding information of the model component;
and taking the BIM carrying the coding information as an initial BIM to be subjected to progress simulation.
Further, the comparing the actual progress, which is included in the overall actual progress and corresponds to each model component, with the expected progress to obtain a target comparison result includes:
comparing the actual progress and the expected progress corresponding to the model component to obtain a component progress comparison result;
determining the overall actual progress corresponding to the target BIM based on the actual progress corresponding to each model component, and comparing the overall actual progress with the overall expected progress to obtain an overall progress comparison result, wherein the overall expected progress is carried in the overall construction task;
and determining the member progress comparison result and the overall progress comparison result as the target comparison result.
Further, the generating of the progress simulation information for displaying based on the expected progress, the actual progress and the target comparison result includes:
acquiring a progress difference factor and risk information corresponding to the progress difference factor by using the target comparison result;
and generating a three-dimensional sectional view corresponding to the target BIM model based on the expected progress, the actual progress, the progress difference factor and the risk information, and taking the three-dimensional sectional view as progress simulation information for display.
Further, the generating of the progress simulation information for displaying based on the expected progress, the actual progress and the target comparison result includes:
generating a milestone timeline based on the actual progress corresponding to the model component, the milestone timeline comprising a plurality of simulated time tick marks;
acquiring a Gantt chart view and a BIM model view after initialization;
and respectively associating the Gantt chart view and the BIM model view with the simulation time scale marks one by one to generate a progress simulation animation, and using the progress simulation animation as progress simulation information for display.
Further, the method further comprises:
acquiring construction quality data corresponding to the target BIM model;
and integrally displaying the construction quality data on the target BIM, determining the construction unit of which the construction quality data does not meet the preset quality standard as an abnormal construction unit, and highlighting the correction state of the abnormal construction unit.
Further, the method further comprises:
acquiring a rectification condition corresponding to the abnormal construction unit, wherein the rectification condition comprises a rectification progress and rectified construction quality data;
and under the condition that the rectification progress reaches a preset rectification progress and the rectified construction quality data reaches a preset quality standard, updating the rectification state corresponding to the abnormal construction unit and canceling the highlight display.
According to another aspect of the embodiments of the present application, there is also provided a simulation apparatus for a construction progress, including:
the device comprises an acquisition module, a processing module and a processing module, wherein the acquisition module is used for acquiring an initial BIM model to be subjected to progress simulation, and the initial BIM model carries coding information for representing the corresponding expected progress of each model component in the initial BIM model;
the processing module is used for establishing the incidence relation between the expected progress and the model component in the initial BIM model by utilizing the coding information to obtain a target BIM model;
the comparison module is used for acquiring the current corresponding overall actual progress of the target BIM model and comparing the actual progress, which is included in the overall actual progress and corresponds to each model component, with the expected progress to obtain a target comparison result;
and the generation module is used for generating progress simulation information for display based on the expected progress, the actual progress and the target comparison result.
According to another aspect of the embodiments of the present application, there is also provided a storage medium including a stored program which performs the above steps when the program is executed.
According to another aspect of the embodiments of the present application, there is also provided an electronic apparatus, including a processor, a communication interface, a memory, and a communication bus, where the processor, the communication interface, and the memory complete communication with each other through the communication bus; wherein: a memory for storing a computer program; a processor for executing the steps of the method by running the program stored in the memory.
Embodiments of the present application further provide a computer program product containing instructions, which when executed on a computer, cause the computer to perform the steps of the above method.
Compared with the prior art, the technical scheme provided by the embodiment of the application has the following advantages: according to the method provided by the embodiment of the application, the incidence relation between the expected progress and the model member is established in the BIM model, the dynamic linkage from the construction task to the model and from the model to the construction task is realized, meanwhile, the actual progress and the expected progress are compared, and the progress simulation is carried out, so that the construction plan can be timely adjusted, and the adjusted construction plan can effectively guide the construction.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and together with the description, serve to explain the principles of the application.
In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly described below, and it is obvious for those skilled in the art to obtain other drawings without inventive exercise.
Fig. 1 is a flowchart of a simulation method for a construction progress according to an embodiment of the present application;
FIG. 2 is a diagram illustrating encoded information of a model component according to an embodiment of the present disclosure;
FIG. 3 is a schematic diagram of a target BIM model provided in an embodiment of the present application;
fig. 4 is a flowchart of a simulation method of a construction progress according to another embodiment of the present application;
fig. 5 is a block diagram of a simulation apparatus for a construction progress according to an embodiment of the present application;
fig. 6 is a schematic structural diagram of an electronic device according to an embodiment of the present application.
Detailed Description
In order to make the purpose, technical solutions and advantages of the embodiments of the present application clearer and more fully described below with reference to the accompanying drawings in the embodiments of the present application, it is obvious that the described embodiments are some, but not all, embodiments of the present application, and the exemplary embodiments and descriptions thereof in the present application are used for explaining the present application and do not constitute an undue limitation on the present application. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
It is noted that, in this document, relational terms such as "first" and "second," and the like, may be used solely to distinguish one entity or action from another similar entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising a … …" does not exclude the presence of another identical element in a process, method, article, or apparatus that comprises the element.
The embodiment of the application provides a construction progress simulation method and device, electronic equipment and a storage medium. The method provided by the embodiment of the invention can be applied to any required electronic equipment, for example, the electronic equipment can be electronic equipment such as a server and a terminal, and the method is not particularly limited herein, and is hereinafter simply referred to as electronic equipment for convenience in description.
According to an aspect of the embodiment of the present application, an embodiment of a method for simulating a construction progress is provided, and fig. 1 is a flowchart of the method for simulating a construction progress provided by the embodiment of the present application, as shown in fig. 1, the method includes:
and S11, acquiring an initial BIM model to be subjected to progress simulation, wherein the initial BIM model carries coding information for representing the corresponding expected progress of each model member in the initial BIM model.
The method provided by the embodiment of the application is applied to the intelligent terminal with the simulation platform, and the intelligent terminal can be a notebook computer, a tablet computer and the like. Before performing the progress simulation, since the BIM model in the construction stage is different from the project deliverable object or range in the design stage, the present application needs to process the BIM model in the construction stage. Specifically, developers need to deepen the BIM design model according to the construction feasibility requirements to achieve the purpose of meeting the requirements of the decomposition of the construction plan, planning, association of operation and components and the feedback of actual construction operation information through inspection batches.
In the embodiment of the application, the obtaining of the initial BIM model to be subjected to progress simulation comprises the following steps A1-A3:
step A1, obtaining an overall construction task corresponding to the BIM, wherein the overall construction task comprises expected progress corresponding to each model component in the initial BIM, and the BIM is an original BIM corresponding to the initial BIM.
And A2, detecting the editing operation acting on the BIM model, and assigning the expected progress to the attribute corresponding to the model component based on the editing operation to obtain the coding information of the model component.
And step A3, taking the BIM carrying the coding information as an initial BIM to be subjected to progress simulation.
In the embodiment of the application, the intelligent terminal can receive the uploaded construction files and obtain the whole construction task corresponding to the BIM from the construction files, and the whole construction task comprises the expected progress corresponding to each model component in the initial BIM. For example: the overall construction task comprises: roofing project, expected progress (planned start time 2016.11.20, planned end time 2017.2.4), masonry and secondary structural project, expected progress (planned start time 2016.9.24, planned end time 2017.4.6).
In this embodiment of the present application, after determining that each model component corresponds to an expected progress, an editing operation performed by a user on a BIM model is detected, and the expected progress is assigned to an attribute corresponding to the model component based on the editing operation, so as to obtain encoded information of the model component, as shown in fig. 2, where the encoded information includes: WBS encoding: 1.2.3, task name: roofing engineering, planning time limit for a project: and after each model component in the BIM carries coding information, obtaining an initial BIM model to be subjected to progress simulation, wherein the time comprises a planned starting time 2016.11.20, a planned ending time 2017.2.4 and the like in 76 days.
And S12, establishing an incidence relation between the expected progress and the model component in the initial BIM by using the coding information to obtain a target BIM.
In the embodiment of the application, after an initial BIM model to be subjected to progress simulation is determined, the initial BIM model is imported into a simulation platform, the initial BIM model is analyzed through the simulation platform to obtain coding information, and an association relationship between an expected progress and a model component, namely an association relationship between a WBS code and the expected progress (a planned starting time and a planned ending time), is established in the initial BIM model by using the coding information to obtain a target BIM model (refer to fig. 3).
According to the method and the device, the WBS codes of the members in the BIM model are linked with the progress information, the 4D construction model is generated in an integrated mode, the integrity and systematicness of the WBS and the three-dimensional entity model are guaranteed, dynamic linkage from the construction task to the model and from the model to the construction task is achieved, and the mutually independent relation between the progress task and the model is broken.
And S13, acquiring the current corresponding overall actual progress of the target BIM, and comparing the actual progress corresponding to each model component included in the overall actual progress with the expected progress to obtain a target comparison result.
In the embodiment of the application, the actual progress corresponding to each model component included in the overall actual progress is compared with the expected progress to obtain a target comparison result, and the method comprises the following steps B1-B3:
and B1, comparing the actual progress and the expected progress corresponding to the model component to obtain a component progress comparison result.
And B2, determining the overall actual progress corresponding to the target BIM based on the actual progress corresponding to each model component, and comparing the overall actual progress with the overall expected progress to obtain an overall progress comparison result, wherein the overall expected progress is carried in the overall construction task.
And step B3, determining the member progress comparison result and the overall progress comparison result as a target comparison result.
In the embodiment of the application, the progress comparison mainly comprises two dimensions, namely a component progress comparison result and an overall progress comparison result of the model component. And generating an overall progress curve through comparison and simulation of the actual progress and the expected progress, and displaying in real time. Therefore, the reason and the risk caused by the progress difference in the construction process can be conveniently inquired.
And S14, generating progress simulation information for display based on the expected progress, the actual progress and the target comparison result.
In the embodiment of the application, the process simulation information for display is generated based on the expected process, the actual process and the target comparison result, and the method comprises the following steps C1-C2:
and C1, acquiring progress difference factors and risk information corresponding to the progress difference factors by using the target comparison result.
And C2, generating a three-dimensional sectional view corresponding to the target BIM model based on the expected progress, the actual progress, the progress difference factors and the risk information, and taking the three-dimensional sectional view as progress simulation information for display.
In the embodiment of the application, the comprehensive statistics and summarization of the progress percentage of each civil engineering construction standard of the project, the planned starting time, the actual starting time, the planned ending date, the actual ending date, the planned construction period days, the implemented construction period days, the milestone time node information and the like are realized by combining the forms of the three-dimensional view and the statistical chart. The progress simulation based on the BIM model can dynamically preview the progress of the project according to the time of the progress plan, and combines various data sources to more intuitively grasp the progress situation of the project and provide decision support for modification and correction of the progress plan.
In the embodiment of the application, the process simulation information for display is generated based on the expected process, the actual process and the target comparison result, and the method comprises the following steps D1-D3:
and D1, generating a milestone time axis based on the actual progress corresponding to the model component, wherein the milestone time axis comprises a plurality of simulation time scale lines.
And D2, acquiring the initialized Gantt chart view and the BIM model view.
And D3, respectively associating the Gantt chart view and the BIM model view with the simulation time scale marks one by one to generate a progress simulation animation, and using the progress simulation animation as progress simulation information for display.
As an example, a user can perform initial simulation setting on a construction task milestone time axis, a Gantt chart view, a BIM model view and the like in a simulation platform, wherein the initial simulation setting comprises simulation objects, simulation modes, animation speed, dragging of the task milestone time axis, and selection of a start simulation date and an end simulation date. And the progress simulation animation enters a playing state based on the trigger operation by detecting the trigger operation acting on the playing control. And in the process of playing the progress simulation animation, when the trigger operation acting on the playing control is detected again, the progress simulation animation is changed from a playing state to a pause state. And simultaneously, displaying a scale mark of the simulation time in a time axis, and automatically demonstrating the planned task/actual construction progress (simulation object) of each day/week/month (simulation unit) in a simulation date range according to a set animation speed by the system in a BIM model view and a Gantt chart view. And after the simulation ending time is played, automatically ending the simulation animation, updating the column diagram of the predicted input resource quantity and the predicted input engineering quantity in the simulation time interval (the simulation starting time-simulation ending time of the current time axis) and the column diagram of the predicted input resource quantity and the predicted input engineering quantity of all tasks in the process of the scale mark of the current simulation time. By detecting the trigger operation acting on the contrast control, different colors are displayed in the BIM model view and the Gantt chart view aiming at tasks with different progresses, and the contrast result is visually displayed by checking the colors of the BIM view component and the Gantt chart.
According to the method provided by the embodiment of the application, the incidence relation between the expected progress and the model member is established in the BIM model, the dynamic linkage from the construction task to the model and from the model to the construction task is realized, meanwhile, the actual progress and the expected progress are compared, and the progress simulation is carried out, so that the construction plan can be timely adjusted, and the adjusted construction plan can effectively guide the construction.
Fig. 4 is a flowchart of a simulation method of a construction progress according to an embodiment of the present application, and as shown in fig. 4, the method may include the following steps:
and S21, acquiring construction quality data corresponding to the target BIM model.
And S22, integrally displaying the construction quality data on the target BIM, determining the construction unit of which the construction quality data does not meet the preset quality standard as an abnormal construction unit, and highlighting the correction state of the abnormal construction unit.
In the embodiment of the application, the collected engineering quality management related data is integrated and displayed on the target BIM. The method mainly comprises quality inspection and quality unqualified item analysis, specifically, at least one preset quality standard for evaluating construction quality data is obtained, construction quality is compared with the preset quality standard, a construction unit of which the construction quality data does not accord with the preset quality standard is determined as an abnormal construction unit, and the rectification state of the abnormal construction unit is highlighted.
According to the embodiment of the application, construction quality data and quality inspection results are displayed in real time, data statistics, analysis and management application are carried out according to field quality management requirements, and finally an auxiliary decision-making effect on field quality management is achieved.
In an embodiment of the application, the method further comprises the following steps E1-E2:
step E1, obtaining a rectification condition corresponding to the abnormal construction unit, wherein the rectification condition comprises a rectification progress and rectified construction quality data;
and E2, under the condition that the rectification progress reaches the preset rectification progress and the rectified construction quality data reaches the preset quality standard, updating the rectification state corresponding to the abnormal construction unit and canceling the highlight display.
In the examples of the present application, the quality assessment feedback: summarizing and counting the quality evaluation results of each unit project, subsection project, unit project and process and the construction quality defect correction condition, displaying the quality evaluation information of each section, highlighting the conditions of low evaluation qualification rate, overdue evaluation progress and the like according to the set threshold information, and timely giving out early warning.
Fig. 5 is a block diagram of a construction progress simulation apparatus according to an embodiment of the present disclosure, which may be implemented as part or all of an electronic device through software, hardware, or a combination of the two. As shown in fig. 5, the apparatus includes:
the obtaining module 51 is configured to obtain an initial BIM model to be subjected to progress simulation, where the initial BIM model carries coding information used for representing an expected progress corresponding to each model component in the initial BIM model;
the processing module 52 is configured to establish an association relationship between the expected progress and the model component in the initial BIM model by using the coding information, so as to obtain a target BIM model;
the comparison module 53 is configured to obtain an overall actual progress currently corresponding to the target BIM model, and compare actual progress corresponding to each model member included in the overall actual progress with an expected progress to obtain a target comparison result;
and a generating module 54 for generating progress simulation information for display based on the expected progress, the actual progress and the target comparison result.
In the embodiment of the present application, the obtaining module 51 is configured to obtain an overall construction task corresponding to a BIM model, where the overall construction task includes an expected progress corresponding to each model component in an initial BIM model, and the BIM model is an original BIM model corresponding to the initial BIM model; detecting editing operation acting on the BIM, and assigning the expected progress to the corresponding attribute of the model component based on the editing operation to obtain the coding information of the model component; and taking the BIM carrying the coding information as an initial BIM to be subjected to progress simulation.
In the embodiment of the present application, the comparing module 53 is configured to compare an actual progress and an expected progress corresponding to a model component, so as to obtain a component progress comparison result; determining the overall actual progress corresponding to the target BIM model based on the actual progress corresponding to each model component, and comparing the overall actual progress with the overall expected progress to obtain an overall progress comparison result, wherein the overall expected progress is carried in the overall construction task; and determining the member progress comparison result and the overall progress comparison result as a target comparison result.
In the embodiment of the present application, the generating module 54 is configured to obtain a progress difference factor and risk information corresponding to the progress difference factor by using the target comparison result; and generating a three-dimensional sectional view corresponding to the target BIM model based on the expected progress, the actual progress, the progress difference factors and the risk information, and taking the three-dimensional sectional view as progress simulation information for display.
In the embodiment of the present application, the generating module 54 is configured to generate a milestone timeline based on the actual progress corresponding to the model component, where the milestone timeline includes a plurality of simulated time scale lines; acquiring a Gantt chart view and a BIM model view after initialization; and respectively associating the Gantt chart view and the BIM model view with the simulation time scale marks one by one to generate a progress simulation animation, and using the progress simulation animation as progress simulation information for display.
In this embodiment of the present application, the simulation apparatus for a construction progress further includes: the quality detection module is used for acquiring construction quality data corresponding to the target BIM model; and integrating and displaying the construction quality data on the target BIM, determining the construction unit of which the construction quality data does not accord with the preset quality standard as an abnormal construction unit, and highlighting the correction state of the abnormal construction unit.
In the embodiment of the application, the quality detection model is further used for acquiring a rectification condition corresponding to the abnormal construction unit, wherein the rectification condition comprises a rectification progress and rectified construction quality data; and under the condition that the rectification progress reaches the preset rectification progress and the rectified construction quality data reaches the preset quality standard, updating the rectification state corresponding to the abnormal construction unit and canceling the highlight display.
An embodiment of the present application further provides an electronic device, as shown in fig. 6, the electronic device may include: the system comprises a processor 1501, a communication interface 1502, a memory 1503 and a communication bus 1504, wherein the processor 1501, the communication interface 1502 and the memory 1503 complete communication with each other through the communication bus 1504.
A memory 1503 for storing a computer program;
the processor 1501 is configured to implement the steps of the above embodiments when executing the computer program stored in the memory 1503.
The communication bus mentioned in the above terminal may be a Peripheral Component Interconnect (PCI) bus, an Extended Industry Standard Architecture (EISA) bus, or the like. The communication bus may be divided into an address bus, a data bus, a control bus, etc. For ease of illustration, only one thick line is shown, but this does not mean that there is only one bus or one type of bus.
The communication interface is used for communication between the terminal and other equipment.
The Memory may include a Random Access Memory (RAM) or a non-volatile Memory (non-volatile Memory), such as at least one disk Memory. Optionally, the memory may also be at least one memory device located remotely from the processor.
The Processor may be a general-purpose Processor, including a Central Processing Unit (CPU), a Network Processor (NP), and the like; the Integrated Circuit may also be a Digital Signal Processor (DSP), an Application Specific Integrated Circuit (ASIC), a Field Programmable Gate Array (FPGA) or other Programmable logic device, a discrete Gate or transistor logic device, or a discrete hardware component.
In another embodiment provided by the present application, there is further provided a computer-readable storage medium, having stored therein instructions, which when run on a computer, cause the computer to execute the method for simulating a construction progress as described in any of the above embodiments.
In yet another embodiment provided by the present application, there is also provided a computer program product containing instructions which, when run on a computer, cause the computer to perform the method for simulating a construction progress as described in any of the above embodiments.
In the above embodiments, the implementation may be wholly or partially realized by software, hardware, firmware, or any combination thereof. When implemented in software, may be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions. When loaded and executed on a computer, cause the processes or functions described in accordance with the embodiments of the application to occur, in whole or in part. The computer may be a general purpose computer, a special purpose computer, a network of computers, or other programmable device. The computer instructions may be stored in a computer readable storage medium or transmitted from one computer readable storage medium to another, for example, the computer instructions may be transmitted from one website, computer, server, or data center to another website, computer, server, or data center by wire (e.g., coaxial cable, fiber optic, digital subscriber line) or wirelessly (e.g., infrared, wireless, microwave, etc.). The computer-readable storage medium can be any available medium that can be accessed by a computer or a data storage device, such as a server, a data center, etc., that incorporates one or more of the available media. The usable medium may be a magnetic medium (e.g., floppy Disk, hard Disk, magnetic tape), an optical medium (e.g., DVD), or a semiconductor medium (e.g., solid State Disk), among others.
The above description is only for the preferred embodiment of the present application, and is not intended to limit the scope of the present application. Any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present application are included in the protection scope of the present application.
The above description is merely exemplary of the present application and is presented to enable those skilled in the art to understand and practice the present application. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the application. Thus, the present application is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (10)

1. A simulation method of construction progress is characterized by comprising the following steps:
acquiring an initial BIM model to be subjected to progress simulation, wherein the initial BIM model carries coding information for representing the corresponding expected progress of each model component in the initial BIM model;
establishing an incidence relation between the expected progress and the model component in the initial BIM by using the coding information to obtain a target BIM;
acquiring the current corresponding overall actual progress of the target BIM model, and comparing the actual progress corresponding to each model component included in the overall actual progress with the expected progress to obtain a target comparison result;
and generating progress simulation information for display based on the expected progress, the actual progress and the target comparison result.
2. The method of claim 1, wherein the obtaining an initial BIM model to be progress-simulated comprises:
acquiring an overall construction task corresponding to a BIM (building information modeling) model, wherein the overall construction task comprises expected progress corresponding to each model component in the initial BIM model, and the BIM model is an original BIM model corresponding to the initial BIM model;
detecting editing operation acting on the BIM model, and assigning the expected progress to the attribute corresponding to the model component based on the editing operation to obtain coding information of the model component;
and taking the BIM carrying the coding information as an initial BIM to be subjected to progress simulation.
3. The method according to claim 2, wherein the comparing the actual progress of the overall actual progress, which includes the actual progress corresponding to each model component, with the expected progress to obtain a target comparison result comprises:
comparing the actual progress and the expected progress corresponding to the model component to obtain a component progress comparison result;
determining the overall actual progress corresponding to the target BIM based on the actual progress corresponding to each model component, and comparing the overall actual progress with the overall expected progress to obtain an overall progress comparison result, wherein the overall expected progress is carried in the overall construction task;
and determining the member progress comparison result and the overall progress comparison result as the target comparison result.
4. The method of claim 1, wherein generating progress simulation information for display based on the expected progress, the actual progress, and the goal comparison result comprises:
acquiring a progress difference factor and risk information corresponding to the progress difference factor by using the target comparison result;
and generating a three-dimensional sectional view corresponding to the target BIM model based on the expected progress, the actual progress, the progress difference factor and the risk information, and taking the three-dimensional sectional view as progress simulation information for display.
5. The method of claim 1, wherein generating progress simulation information for display based on the expected progress, the actual progress, and the goal comparison result comprises:
generating a milestone timeline based on the actual progress corresponding to the model component, the milestone timeline comprising a plurality of simulated time tick marks;
acquiring a Gantt chart view and a BIM model view after initialization;
and respectively associating the Gantt chart view and the BIM model view with the simulation time scale mark one by one to generate a progress simulation animation, and using the progress simulation animation as progress simulation information for display.
6. The method of claim 1, further comprising:
acquiring construction quality data corresponding to the target BIM model;
and integrally displaying the construction quality data on the target BIM, determining the construction unit of which the construction quality data does not meet the preset quality standard as an abnormal construction unit, and highlighting the correction state of the abnormal construction unit.
7. The method of claim 6, further comprising:
acquiring a rectification condition corresponding to the abnormal construction unit, wherein the rectification condition comprises a rectification progress and rectified construction quality data;
and under the condition that the rectification progress reaches a preset rectification progress and the rectified construction quality data reaches a preset quality standard, updating the rectification state corresponding to the abnormal construction unit and canceling the highlight display.
8. A simulation apparatus of a construction progress, characterized by comprising:
the device comprises an acquisition module, a processing module and a processing module, wherein the acquisition module is used for acquiring an initial BIM model to be subjected to progress simulation, and the initial BIM model carries coding information for representing the corresponding expected progress of each model component in the initial BIM model;
the processing module is used for establishing the incidence relation between the expected progress and the model component in the initial BIM by utilizing the coding information to obtain a target BIM;
the comparison module is used for acquiring the current corresponding overall actual progress of the target BIM model and comparing the actual progress corresponding to each model component included in the overall actual progress with the expected progress to obtain a target comparison result;
and the generation module is used for generating progress simulation information for display based on the expected progress, the actual progress and the target comparison result.
9. A storage medium, characterized in that the storage medium comprises a stored program, wherein the program is operative to perform the method steps of any of the preceding claims 1 to 7.
10. An electronic device is characterized by comprising a processor, a communication interface, a memory and a communication bus, wherein the processor and the communication interface are used for realizing mutual communication by the memory through the communication bus; wherein:
a memory for storing a computer program;
a processor for performing the method steps of any of claims 1 to 7 by executing a program stored on a memory.
CN202210928318.0A 2022-08-03 2022-08-03 Construction progress simulation method and device, electronic equipment and storage medium Pending CN115238359A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210928318.0A CN115238359A (en) 2022-08-03 2022-08-03 Construction progress simulation method and device, electronic equipment and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210928318.0A CN115238359A (en) 2022-08-03 2022-08-03 Construction progress simulation method and device, electronic equipment and storage medium

Publications (1)

Publication Number Publication Date
CN115238359A true CN115238359A (en) 2022-10-25

Family

ID=83677360

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210928318.0A Pending CN115238359A (en) 2022-08-03 2022-08-03 Construction progress simulation method and device, electronic equipment and storage medium

Country Status (1)

Country Link
CN (1) CN115238359A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115878872A (en) * 2023-02-08 2023-03-31 一智科技(成都)有限公司 Construction progress visualization method and system
CN116029682A (en) * 2023-03-29 2023-04-28 北京中昌工程咨询有限公司 Construction progress management method and system based on BIM technology
CN117151643A (en) * 2023-09-11 2023-12-01 三峡高科信息技术有限责任公司 Visual construction progress, quality and cost integrated control method
CN117236525A (en) * 2023-11-13 2023-12-15 无锡恒大电子科技有限公司 Engineering construction safety management detection system and method based on BIM
CN117252328A (en) * 2023-07-04 2023-12-19 南通理工学院 Project integrated management method and system based on BIM
CN117349917A (en) * 2023-12-05 2024-01-05 深圳图为技术有限公司 Construction scheme simulation system, method and storage medium

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115878872A (en) * 2023-02-08 2023-03-31 一智科技(成都)有限公司 Construction progress visualization method and system
CN116029682A (en) * 2023-03-29 2023-04-28 北京中昌工程咨询有限公司 Construction progress management method and system based on BIM technology
CN117252328A (en) * 2023-07-04 2023-12-19 南通理工学院 Project integrated management method and system based on BIM
CN117151643A (en) * 2023-09-11 2023-12-01 三峡高科信息技术有限责任公司 Visual construction progress, quality and cost integrated control method
CN117236525A (en) * 2023-11-13 2023-12-15 无锡恒大电子科技有限公司 Engineering construction safety management detection system and method based on BIM
CN117236525B (en) * 2023-11-13 2024-02-13 无锡恒大电子科技有限公司 Engineering construction safety management detection system and method based on BIM
CN117349917A (en) * 2023-12-05 2024-01-05 深圳图为技术有限公司 Construction scheme simulation system, method and storage medium
CN117349917B (en) * 2023-12-05 2024-04-02 深圳图为技术有限公司 Construction scheme simulation system, method and storage medium

Similar Documents

Publication Publication Date Title
CN115238359A (en) Construction progress simulation method and device, electronic equipment and storage medium
CN108984418B (en) Software test management method and device, electronic equipment and storage medium
CN109559069B (en) Production management method and device based on assembly type building platform and terminal equipment
US20160162819A1 (en) Workflow definition, orchestration and enforcement via a collaborative interface according to a hierarchical procedure list
US20220058552A1 (en) Project management system, method of operating project management system, and non-transitory computer-readable medium
Haight et al. Safety management systems: comparing content & impact
EP4381439A1 (en) Method and system for managing construction projects with automatic generation of smart contract
US20220327452A1 (en) Method for automatically updating unit cost of inspection by using comparison between inspection time and work time of crowdsourcing-based project for generating artificial intelligence training data
Likhitruangsilp et al. A BIM-enabled system for evaluating impacts of construction change orders
Ghannadpour et al. Reducing rework and increasing the civil projects quality, through total quality management (TQM), by using the concept of building information modeling (BIM)
Ratajczak et al. Augmented reality combined with location-based management system to improve the construction process, quality control and information flow
CN115657890A (en) PRA robot customizable method
CN113344513A (en) Project information management method and device, electronic equipment and storage medium
CN113986730A (en) Method, device, equipment and storage medium for testing offer file
CN113807773A (en) Method, device and equipment for generating steel structure industry manufacturing list and storage medium
CN111191999B (en) Product research and development management method, device, computer equipment and storage medium
US20120089435A1 (en) Method and system for optimizing process models
CN110309047B (en) Test point generation method, device and system
KR100341393B1 (en) System and method for object oriented ERP project implementation
Harty et al. Facilitating meaningful collaboration in architectural design through the adoption of BIM (Building Information Modelling)
CN114548631A (en) Dynamic evaluation method and device
US20210279655A1 (en) Optimization of human-centric processes
US20200342302A1 (en) Cognitive forecasting
O'Brien Software quality starts with the customer
Patacas et al. Supporting building owners and facility managers in the visualisation of an Integrated Asset Information model (AIM) based on open standards

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination