Waterproof wall split bolt hole plugging structure and construction method thereof Download PDFInfo
- Publication number
- CN103711205A CN103711205A CN201410011948.7A CN201410011948A CN103711205A CN 103711205 A CN103711205 A CN 103711205A CN 201410011948 A CN201410011948 A CN 201410011948A CN 103711205 A CN103711205 A CN 103711205A
- Authority
- CN
- China
- Prior art keywords
- bolt
- hole
- construction method
- bolt hole
- plugging structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention provides a waterproof wall split bolt hole plugging structure and a construction method of the waterproof wall split bolt hole plugging structure. The construction method is characterized by comprising the steps that firstly, an outer wall bolt and bolt plastic horn plugs are taken out, the whole hole of the bolt is cleaned, a bolt hole in a plastic tube 1 is filled with an expansion foaming agent 3, and bolt horn holes 2 are filled with water-expanding water stopping glue 4; secondly, micro-expansion cement grout 5 is used for filling up the bolt horn holes 2; finally, repair surfaces larger than the bolt horn holes are coated with JS waterproof coatings twice. The waterproof wall split bolt hole plugging structure and the construction method of the waterproof wall split bolt hole plugging structure have the advantages that the situation that hole expansion is conducted to take out a plastic sleeve tube is not needed, a hole structure is not damaged, the inner wall of the hole is smooth, the foaming agent, the water stopping glue and the micro-expansion cement grout can easily make full contact with the inner wall to seal the hole, so that it is guaranteed that the functions of various water-contact materials in the hole can be brought into full play, and therefore tight plugging is achieved.
Description
Technical field
The present invention relates to a kind of body of wall split bolt hole waterproof plugging structure and construction method, relate in particular to the waterproof blocking technology that cast-in-place structural wall form is removed rear through-wall bolt hole.
Background technology
Exterior wall through-wall bolt hole repair, as dealt with improperly, will cause the seepage at this position, and this will affect habitat condition, destroy indoor environment.After exterior-wall heat insulation, indoor and outdoor decoration construction, it is very inconvenient that breakthrough is repaired leak stopping again, and outdoor while studying for a second time courses one has flunked operation danger larger.Be necessary disposablely by exterior wall split bolt holes blocking success for this reason, stop hidden leakage defect.
Summary of the invention
The problem that the present invention exists existing blocking construction technology, provides a kind of body of wall split bolt hole waterproof plugging structure and construction method, and described the present invention has the convenience of drawing materials, quick construction, step is simple, effect is high and economic dispatch feature.
The technical solution adopted for the present invention to solve the technical problems:
Described a kind of body of wall split bolt hole waterproof plugging structure and construction method, take out exterior wall split bolt and bolt plastics loudspeaker plug, the whole hole of cleaning bolt, only in the bolt hole of plastic bushing, fill with expanded foamed dose, to bolt loudspeaker hole, inject water-swellable sealing glue, with micro-expansion cement mortar, fill up flat bolt loudspeaker hole again, finally brush JS water-repellent paint two times.
The invention has the beneficial effects as follows, do not need reaming to take out plastic bushing, do not destroy pore space structure, its hole inner wall smooth, be easy to blowing agent, sealing glue, the abundant contact hole inwall of micro-expansion cement mortar, thereby ensure the Function of various chance water materials in hole and to realize shutoff closely knit.
Accompanying drawing explanation
Fig. 1 is a kind of body of wall split bolt hole waterproof plugging structure of the present invention and construction method schematic diagram.
The specific embodiment
Below in conjunction with drawings and Examples, the present invention is further described, is to clear, the complete description that technical scheme is carried out in the embodiment of the present invention, and obviously, described embodiment is only a part of embodiment of the present invention, rather than whole embodiment.Embodiment based in the present invention, those of ordinary skills, not making the every other embodiment obtaining under creative work prerequisite, belong to protection scope of the present invention.
Refer to Fig. 1, Fig. 1 is a kind of body of wall split bolt hole waterproof plugging structure of the present invention and construction method schematic diagram.
Described a kind of body of wall split bolt hole waterproof plugging structure, comprise: in the bolt hole of plastic pipe 1, fill with expanded foamed dose 3, to bolt loudspeaker hole 2, inject water-swellable sealing glue 4, with micro-expansion cement sand 5 slurries, fill up flat bolt loudspeaker hole 2 again, be finally greater than bolt hole repair face 6 brushing JS water-repellent paint two times.
Described a kind of body of wall split bolt hole waterproof plugging structure and construction method, according to following steps, implement:
Take out outer wall screw and bolt plastics loudspeaker plug, the whole hole of cleaning bolt, only in the bolt hole of plastic pipe 1, fill with expanded foamed dose 3, to bolt loudspeaker hole 2, inject water-swellable sealing glue 4, with micro-expansion cement sand 5 slurries, fill up flat bolt loudspeaker hole 2 again, be finally greater than bolt hole repair face 6 brushing JS water-repellent paint two times.
The above-mentioned explanation of the present invention to the disclosed embodiments, makes professional and technical personnel in the field can realize or use the present invention.To the multiple modification of these embodiment, will be apparent for those skilled in the art, General Principle as defined herein can, in the situation that not departing from the spirit or scope of the present invention, realize in other embodiments.Therefore, the present invention will can not be restricted to these embodiment shown in this article, but will meet the widest scope consistent with principle disclosed herein and features of novelty.
Claims (6)
1. body of wall split bolt hole waterproof plugging structure and a construction method, is characterized in that: bolt hole waterproof plugging structure and construction method.
2. as claimed in claim 1, it is characterized in that: take out outer wall screw and bolt plastics loudspeaker plug, the whole hole of cleaning bolt.
3. it is characterized in that as claimed in claim 1: only in the bolt hole of plastic pipe 1, fill with expanded foamed dose 3.
4. it is characterized in that as claimed in claim 1: to bolt loudspeaker hole 2, inject water-swellable sealing glue 4.
5. it is characterized in that as claimed in claim 1: with micro-expansion cement sand 5 slurries, fill up flat bolt loudspeaker hole 2 again.
6. it is characterized in that as claimed in claim 1: be finally greater than bolt hole repair face 6 brushing JS water-repellent paint two times.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410011948.7A CN103711205A (en) | 2014-01-13 | 2014-01-13 | Waterproof wall split bolt hole plugging structure and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410011948.7A CN103711205A (en) | 2014-01-13 | 2014-01-13 | Waterproof wall split bolt hole plugging structure and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103711205A true CN103711205A (en) | 2014-04-09 |
Family
ID=50404522
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410011948.7A Pending CN103711205A (en) | 2014-01-13 | 2014-01-13 | Waterproof wall split bolt hole plugging structure and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103711205A (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104831925A (en) * | 2015-04-09 | 2015-08-12 | 江苏建筑职业技术学院 | Passive house wall bushing waterproof air tightness structure construction method |
CN104895202A (en) * | 2015-06-17 | 2015-09-09 | 青岛海川建设集团有限公司 | Building external wall insulation construction method based on vitrified microsphere compound polyurethane |
CN105442842A (en) * | 2015-11-17 | 2016-03-30 | 甘肃第七建设集团股份有限公司 | Construction method for plugging fair-faced concrete split bolt hole |
CN106245791A (en) * | 2016-10-10 | 2016-12-21 | 天津盛泰佳业科技有限公司 | A kind of architectural shape |
CN107246148A (en) * | 2017-06-13 | 2017-10-13 | 河南省水利第工程局 | Thin wall concrete is to drawing screw water sealing structure and sealing technique |
CN108442698A (en) * | 2018-04-17 | 2018-08-24 | 中冶天工集团天津有限公司 | A kind of deformation joint split bolt pvc casings cram method and block fixed sleeve part |
CN111058629A (en) * | 2020-02-27 | 2020-04-24 | 中国二十二冶集团有限公司 | Construction method for plugging through-wall bolt hole of concrete outer wall |
CN112502298A (en) * | 2020-11-29 | 2021-03-16 | 国家电网有限公司 | Construction device and method for plugging bare concrete wall hole |
CN113622708A (en) * | 2021-09-16 | 2021-11-09 | 北京路鹏达建设发展有限责任公司 | Construction method for plugging split bolt hole of building outer wall |
CN113737969A (en) * | 2021-09-02 | 2021-12-03 | 三维建设工程咨询有限公司 | Wall split bolt hole plugging method |
CN113802698A (en) * | 2021-08-20 | 2021-12-17 | 上海宝冶集团有限公司 | Construction method for plugging split bolt holes of shear wall |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010242470A (en) * | 2009-04-02 | 2010-10-28 | Woody Kobo:Kk | Waterproof structure of bearing wall intersection according to log-frame construction method |
CN202559540U (en) * | 2012-05-08 | 2012-11-28 | 中建六局建设发展有限公司 | Waterproof plugging structure for outer wall split bolt hole |
CN103334501A (en) * | 2013-06-26 | 2013-10-02 | 青岛建安建设集团有限公司 | Seepage prevention construction method for bolt holes in exterior walls of buildings |
-
2014
- 2014-01-13 CN CN201410011948.7A patent/CN103711205A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010242470A (en) * | 2009-04-02 | 2010-10-28 | Woody Kobo:Kk | Waterproof structure of bearing wall intersection according to log-frame construction method |
CN202559540U (en) * | 2012-05-08 | 2012-11-28 | 中建六局建设发展有限公司 | Waterproof plugging structure for outer wall split bolt hole |
CN103334501A (en) * | 2013-06-26 | 2013-10-02 | 青岛建安建设集团有限公司 | Seepage prevention construction method for bolt holes in exterior walls of buildings |
Non-Patent Citations (2)
Title |
---|
CTRL_327: ""混凝土施工对拉螺栓锥形孔封堵专项方案"", 《HTTP://WENKU.BAIDU.COM/LINK?URL=SPJ73_GQJF5XHQFHKPKQWEBUN0WGJ1MLP0_DDX1R_UG4R3DNHRUYAX5Z4A-S7XAO1IW_FUX7JSPNFAKXNXJY07ZCIMDCEQL3U4TAET-FYLW》 * |
南通四建集团有限公司山东总部: ""外墙螺栓孔封堵方案"", 《HTTP://WENKU.BAIDU.COM/LINK?URL=14DRHRGJWTV7YTD_A2H_KDD-BJINIKLKDOITVMSR1OMMABUKGDNUEILE9LRRFILBLQOHLQE0R279YF_M6_0J0LKPBD_L5A0SVLC9-RWQL4S》 * |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104831925A (en) * | 2015-04-09 | 2015-08-12 | 江苏建筑职业技术学院 | Passive house wall bushing waterproof air tightness structure construction method |
CN104895202A (en) * | 2015-06-17 | 2015-09-09 | 青岛海川建设集团有限公司 | Building external wall insulation construction method based on vitrified microsphere compound polyurethane |
CN105442842A (en) * | 2015-11-17 | 2016-03-30 | 甘肃第七建设集团股份有限公司 | Construction method for plugging fair-faced concrete split bolt hole |
CN106245791B (en) * | 2016-10-10 | 2018-12-04 | 绍兴上虞霓虹科技有限公司 | A kind of architectural shape |
CN106245791A (en) * | 2016-10-10 | 2016-12-21 | 天津盛泰佳业科技有限公司 | A kind of architectural shape |
CN107246148A (en) * | 2017-06-13 | 2017-10-13 | 河南省水利第工程局 | Thin wall concrete is to drawing screw water sealing structure and sealing technique |
CN108442698A (en) * | 2018-04-17 | 2018-08-24 | 中冶天工集团天津有限公司 | A kind of deformation joint split bolt pvc casings cram method and block fixed sleeve part |
CN108442698B (en) * | 2018-04-17 | 2024-03-26 | 中冶天工集团天津有限公司 | Deformation joint split bolt pvc sleeve plugging method and plugging fixing sleeve |
CN111058629A (en) * | 2020-02-27 | 2020-04-24 | 中国二十二冶集团有限公司 | Construction method for plugging through-wall bolt hole of concrete outer wall |
CN112502298A (en) * | 2020-11-29 | 2021-03-16 | 国家电网有限公司 | Construction device and method for plugging bare concrete wall hole |
CN113802698A (en) * | 2021-08-20 | 2021-12-17 | 上海宝冶集团有限公司 | Construction method for plugging split bolt holes of shear wall |
CN113737969A (en) * | 2021-09-02 | 2021-12-03 | 三维建设工程咨询有限公司 | Wall split bolt hole plugging method |
CN113622708A (en) * | 2021-09-16 | 2021-11-09 | 北京路鹏达建设发展有限责任公司 | Construction method for plugging split bolt hole of building outer wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103711205A (en) | Waterproof wall split bolt hole plugging structure and construction method thereof | |
CN202730973U (en) | Concrete outer wall bolt hole leakproof structure | |
CN103790382A (en) | Rapid blocking method and structure of external wall screw hole of concrete structure | |
CN202559540U (en) | Waterproof plugging structure for outer wall split bolt hole | |
WO2011143588A3 (en) | System and method for leaking crack repair | |
CN206279789U (en) | A kind of plugging structure of exterior wall Screw arbor with nut at both-ends hole | |
WO2009149458A8 (en) | Compression sealing apparatus and method for use of the same | |
CN203684414U (en) | Rapid blocking structure of screw hole of concrete structure outer wall | |
CN203743640U (en) | Seawater pool PE pipeline waterproof sealing structure | |
CN203947598U (en) | A kind of body of wall split bolt hole waterproof plugging structure | |
CN104235551B (en) | A kind of toilet or kitchen water pipe leak and keep in repair the method for not tearing floor tile open | |
CN205153571U (en) | Outer wall bolt hole novel to drawing block structure | |
CN203334440U (en) | Structure for plugging threaded rod hole with corks | |
CN206308895U (en) | A kind of light-weight environment-friendly pure water silt wallboard | |
CN203961067U (en) | The external wall structure in a kind of shutoff screw rod hole | |
CN202530581U (en) | Plugging structure of screw hole of outer wall | |
CN105442842A (en) | Construction method for plugging fair-faced concrete split bolt hole | |
CN202544145U (en) | External wall thermal insulation system | |
CN114109064A (en) | Construction method for plugging screw hole of outer wall by polyurethane foaming agent | |
CN109680941A (en) | Exterior walls of buildings screw hole rubber pipe close plugging construction method | |
CN210857547U (en) | Be used for outer wall screw rod entrance to a cave plugging device | |
CN203296383U (en) | Plugging rod for split bolt holes | |
CN202324617U (en) | Sleeve for sealing scaffold wall-passing hole | |
CN203821523U (en) | Downstream three-way pipe | |
TWM334169U (en) | High pressure and leakage ceasing injector |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20140409 |