CN103696581A - 一种保护杆件的施工方法 - Google Patents

一种保护杆件的施工方法 Download PDF

Info

Publication number
CN103696581A
CN103696581A CN201310719678.0A CN201310719678A CN103696581A CN 103696581 A CN103696581 A CN 103696581A CN 201310719678 A CN201310719678 A CN 201310719678A CN 103696581 A CN103696581 A CN 103696581A
Authority
CN
China
Prior art keywords
rod member
wire rope
construction method
steel plate
fixed point
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310719678.0A
Other languages
English (en)
Other versions
CN103696581B (zh
Inventor
苏培奇
郭军强
黄国荣
吴健
杜彦东
黎萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG PROV FOUNDATION ENGINEERING Co
Original Assignee
GUANGDONG PROV FOUNDATION ENGINEERING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG PROV FOUNDATION ENGINEERING Co filed Critical GUANGDONG PROV FOUNDATION ENGINEERING Co
Priority to CN201310719678.0A priority Critical patent/CN103696581B/zh
Publication of CN103696581A publication Critical patent/CN103696581A/zh
Application granted granted Critical
Publication of CN103696581B publication Critical patent/CN103696581B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明公开了本发明通过将杆件周围底部土方挖除后,安放上钢板,利用钢丝绳将杆件顶部和底部的带拉力环的铁箍拉紧,锚固定在钢丝绳固定点处,使钢丝绳承担杆件身重力,也使杆件底部不与土方接触,从而使杆件不与土方一起滑动位移,利用钢丝绳的拉力来平衡杆件与钢板之间的摩擦力,起到固定杆件,从而替代用支护支撑加固等方法,降低了保护措施处理成本,并且可以操作简单、安全性能可靠。

Description

一种保护杆件的施工方法
技术领域
本发明涉及建筑工程技术领域,特别是涉及基坑、沟槽和边坡开挖时周边保护杆件的方法。
背景技术
杆件保护常规方法是采用基础加固、支撑加固等方法。这些方法要求必须在地质条件好的情况下才能做到,而对于地质条件差的情况下成功的几率比较低。
现需要一种适应范围更广、在任何地质下都可以安全保护杆件、操作简单、安全性和成功率高的保护方法。
发明内容
本发明的目的,在于提供一种适应范围更广、在任何地质下都可以安全保护杆件、操作简单、安全性和成功率高的保护方法。
本发明解决其技术问题的解决方案是:一种保护杆件的施工方法,其包括以下步骤,
1)、土方开挖前,将杆件稍微吊起或固定;
2)、将杆件底部周围表层土挖除,装上钢板;
3)、松开杆件,让其垂直置于钢板上,杆件的底端直接与钢板接触;
4)、在杆件周围一定范围内对称设置钢丝绳固定点;
5)、在杆件顶部和底部分别安装带拉力环的铁箍;
6)、用钢丝绳将杆件顶部和底部的带拉力环的铁箍拉紧,锚固在钢丝绳固定点处。
7)、进行管沟土方开挖。
作为上述技术方案的进一步改进,在步骤4)中,所述钢丝绳设置在工字钢中上部,所述工字钢的中下部插入土层后锚固。
作为上述技术方案的进一步改进,所述钢丝绳固定点位于同一水平面。
作为上述技术方案的进一步改进,在步骤5)中,所述底部铁箍的拉力环与其所对应的钢丝绳固定点位于同一水平位置。
作为上述技术方案的进一步改进,在步骤6)中,所述钢丝绳依次穿过顶部和底部的铁箍中的拉力环后,钢丝绳与杆件之间构成一个稳定的三角形受力结构。
本发明的有益效果是:本发明通过将杆件周围底部土方挖除后,安放上钢板,利用钢丝绳将杆件顶部和底部的带拉力环的铁箍拉紧,锚固定在钢丝绳固定点处,使钢丝绳承担杆件身重力,也使杆件底部不与土方接触,从而使杆件不与土方一起滑动位移,利用钢丝绳的拉力来平衡杆件与钢板之间的摩擦力,起到固定杆件,从而替代用支护支撑加固等方法,降低了保护措施处理成本,并且可以操作简单、安全性能可靠。
附图说明
为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单说明。显然,所描述的附图只是本发明的一部分实施例,而不是全部实施例,本领域的技术人员在不付出创造性劳动的前提下,还可以根据这些附图获得其他设计方案和附图。
图1是本发明的杆件保护剖面图。
具体实施方式
以下将结合实施例和附图对本发明的构思、具体结构及产生的技术效果进行清楚、完整地描述,以充分地理解本发明的目的、特征和效果。显然,所描述的实施例只是本发明的一部分实施例,而不是全部实施例,基于本发明的实施例,本领域的技术人员在不付出创造性劳动的前提下所获得的其他实施例,均属于本发明保护的范围。另外,文中所提到的所有联接/连接关系,并非单指构件直接相接,而是指可根据具体实施情况,通过添加或减少联接辅件,来组成更优的联接结构。
参照图1,一种保护杆件的施工方法,其包括以下步骤,
1)、土方开挖前,用设备(如吊车等)将杆件6稍微吊起或固定;
2)、将杆件6底部周围表层土挖除,装上钢板4;
3)、松开杆件6,让其垂直置于钢板4上,杆件6的底端直接与钢板4接触;
4)、在杆件6周围一定范围内对称设置钢丝绳固定点5;
5)、在杆件6顶部和底部分别安装带拉力环的铁箍2;
6)、用钢丝绳1将杆件6顶部和底部的带拉力环的铁箍2拉紧,锚固在钢丝绳固定点5处。
7)、进行管沟土方开挖。
通过将杆件6周围底部土方挖除后,安放上钢板4,利用钢丝绳1将杆件6顶部和底部的带拉力环的铁箍2拉紧,锚固定在钢丝绳固定点5处,使钢丝绳1承担杆件6身重力,也使杆件6底部不与土方接触,从而使杆件6不与土方一起滑动位移,利用钢丝绳1的拉力来平衡杆件6与钢板4之间的摩擦力,起到固定杆件6,从而替代用支护支撑加固等方法,降低了保护措施处理成本,并且可以操作简单、安全性能可靠。这里的杆件6,一般指的是市政工程里面的电线杆或者路灯杆。
进一步作为优选的实施方式,在步骤4)中,所述钢丝绳1设置在工字钢3中上部,所述工字钢3的中下部插入土层后锚固,其施工方便,节省施工时间。
进一步作为优选的实施方式,所述钢丝绳固定点5位于同一水平面,这样使得杆件6受力均匀,不管土方往哪一个方向滑动位移时,保证钢丝绳1的拉力能平衡杆件与钢板4的摩擦力。
进一步作为优选的实施方式,在步骤5)中,所述底部铁箍的拉力环与其所对应的钢丝绳固定点5位于同一水平位置,这样设置,使得钢丝绳1用来抵消杆件与钢板4的摩擦力的拉力最大。
进一步作为优选的实施方式,在步骤6)中,所述钢丝绳1依次穿过顶部和底部的铁箍2中的拉力环后,钢丝绳1与杆件之间构成一个稳定的三角形受力结构。三角形的受力结构最稳定,优选地,该三角形为直角三角形,杆件的部分或全部为直角三角形的一条直角边。
当然,根据不同的施工环境和施工的土质,利用力学原理,根据杆件的直径和高度参数,计算出钢丝绳1的直径大小、拉力环的铁箍及工字钢型号,使得本发明创造的效果最优化。
以上是对本发明的较佳实施方式进行了具体说明,但本发明创造并不限于所述实施例,熟悉本领域的技术人员在不违背本发明精神的前提下还可作出种种的等同变型或替换,这些等同的变型或替换均包含在本申请权利要求所限定的范围内。

Claims (5)

1.一种保护杆件的施工方法,其特征在于:其包括以下步骤,
1)、土方开挖前,将杆件稍微吊起或固定;
2)、将杆件底部周围表层土挖除,装上钢板;
3)、松开杆件,让其垂直置于钢板上,杆件的底端直接与钢板接触;
4)、在杆件周围一定范围内对称设置钢丝绳固定点;
5)、在杆件顶部和底部分别安装带拉力环的铁箍;
6)、用钢丝绳将杆件顶部和底部的带拉力环的铁箍拉紧,锚固在钢丝绳固定点处;
7)、进行管沟土方开挖。
2.根据权利要求1所述的保护杆件的施工方法,其特征在于:在步骤4)中,所述钢丝绳设置在工字钢中上部,所述工字钢的中下部插入土层后锚固。
3.根据权利要求1或2所述的保护杆件的施工方法,其特征在于:所述钢丝绳固定点位于同一水平面。
4.根据权利要求1所述的保护杆件的施工方法,其特征在于:在步骤5)中,所述底部铁箍的拉力环与其所对应的钢丝绳固定点位于同一水平位置。
5.根据权利要求1所述的保护杆件的施工方法,其特征在于:在步骤6)中,所述钢丝绳依次穿过顶部和底部的铁箍中的拉力环后,钢丝绳与杆件之间构成一个稳定的三角形受力结构。
CN201310719678.0A 2013-12-23 2013-12-23 一种保护杆件的施工方法 Expired - Fee Related CN103696581B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310719678.0A CN103696581B (zh) 2013-12-23 2013-12-23 一种保护杆件的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310719678.0A CN103696581B (zh) 2013-12-23 2013-12-23 一种保护杆件的施工方法

Publications (2)

Publication Number Publication Date
CN103696581A true CN103696581A (zh) 2014-04-02
CN103696581B CN103696581B (zh) 2016-01-20

Family

ID=50358231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310719678.0A Expired - Fee Related CN103696581B (zh) 2013-12-23 2013-12-23 一种保护杆件的施工方法

Country Status (1)

Country Link
CN (1) CN103696581B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107130610A (zh) * 2017-05-24 2017-09-05 广州市第建筑工程有限公司 一种深基坑支护的施工方法
CN107191048A (zh) * 2017-04-30 2017-09-22 陶霞霞 一种防止特高压输电电线杆下沉的方法
CN110630081A (zh) * 2019-08-26 2019-12-31 中冶天工集团有限公司 一种重型钢柱的安装装置及其安装找正方法
CN112190111A (zh) * 2020-10-09 2021-01-08 抚州市王冠实业有限公司 一种双轨道窗帘杆

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1066313A (zh) * 1991-04-25 1992-11-18 高波 高层建筑法
JP2009287229A (ja) * 2008-05-28 2009-12-10 Chugoku Electric Power Co Inc:The 支柱の支持構造
JP2012255299A (ja) * 2011-06-09 2012-12-27 Mitsubishi Electric Corp 支線支持柱状構造物
CN203175138U (zh) * 2013-04-27 2013-09-04 国家电网公司 高压电线杆

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1066313A (zh) * 1991-04-25 1992-11-18 高波 高层建筑法
JP2009287229A (ja) * 2008-05-28 2009-12-10 Chugoku Electric Power Co Inc:The 支柱の支持構造
JP2012255299A (ja) * 2011-06-09 2012-12-27 Mitsubishi Electric Corp 支線支持柱状構造物
CN203175138U (zh) * 2013-04-27 2013-09-04 国家电网公司 高压电线杆

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107191048A (zh) * 2017-04-30 2017-09-22 陶霞霞 一种防止特高压输电电线杆下沉的方法
CN107130610A (zh) * 2017-05-24 2017-09-05 广州市第建筑工程有限公司 一种深基坑支护的施工方法
CN110630081A (zh) * 2019-08-26 2019-12-31 中冶天工集团有限公司 一种重型钢柱的安装装置及其安装找正方法
CN112190111A (zh) * 2020-10-09 2021-01-08 抚州市王冠实业有限公司 一种双轨道窗帘杆

Also Published As

Publication number Publication date
CN103696581B (zh) 2016-01-20

Similar Documents

Publication Publication Date Title
CN103696581B (zh) 一种保护杆件的施工方法
CN201902703U (zh) 一种地下管线悬吊保护装置
CN203654295U (zh) 单肢斜撑加固基坑支护结构
CN110023570B (zh) 一种便携式机械组合地上固定桩装置
JPWO2019176057A1 (ja) 係留アンカー装置
CN207500624U (zh) 一种埋地管道抗沉降装置
CN202492845U (zh) 一种可连环锚固的地锚
CN204570684U (zh) 一种可回收锚索的锚头固定及导向装置
CN206376274U (zh) 一种单桩高位承台与锚索塔吊基础结构
CN103742717A (zh) 平行式海底管道及海缆的保护支架
CN114541438A (zh) 一种具有定位功能的钢围堰及其定位方法
CN114396063A (zh) 一种钢围堰定位调整系统及定位方法
CN203322634U (zh) 一种石油平台管道护套
CN208472750U (zh) 导管架基础施工装置
CN202658874U (zh) 一种柔性连墙件装置
CN204059173U (zh) 一种人行天桥
CN104109995B (zh) 一种人行天桥及其施工方法
CN204632295U (zh) 一种广告牌
CN209368906U (zh) 一种用于深层岩基载荷板试验平台系统传力的装置
CN103322312B (zh) 一种石油平台管道护套
CN102644294A (zh) 一种基坑周边基础托换的方法
CN202220342U (zh) 安全边坡结构
JP6966133B1 (ja) 建柱方法
CN213629474U (zh) 一种地下原有管道原位保护装置
CN214614126U (zh) 一种带有锚索穿越深厚回填土层保护装置的边坡支护结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 19-20, No. 510620, Tianhe Road, 99 Tianhe Road, Guangdong, Guangzhou

Applicant after: Foundation Design Group Co., Ltd of Guangdong Province

Address before: 19-20, No. 510620, Tianhe Road, 99 Tianhe Road, Guangdong, Guangzhou

Applicant before: Guangdong Prov. Foundation Engineering Co.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: GUANGDONG PROV. FOUNDATION ENGINEERING CO. TO: GUANGDONG FOUNDATION ENGINEERING GROUP CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160120

Termination date: 20201223