Prior art keywords
slip casting
valve
slurry feeding
grouting
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310723505.6A
Other languages
English (en)
Other versions
CN103644369B (zh
Inventor
孙焕斌
刘广超
张立新
孙东晓
王靖
张海涛
吴杭州
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Civil Engineering Co Ltd of CREC
Municipal Environmental Construction Co Ltd of CREC
Original Assignee
Shanghai Civil Engineering Co Ltd of CREC
Municipal Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Civil Engineering Co Ltd of CREC, Municipal Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC filed Critical Shanghai Civil Engineering Co Ltd of CREC
Priority to CN201310723505.6A priority Critical patent/CN103644369B/zh
Publication of CN103644369A publication Critical patent/CN103644369A/zh
Application granted granted Critical
Publication of CN103644369B publication Critical patent/CN103644369B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground

Abstract

本发明涉及工程施工技术领域,具体是一种顶管用润滑减阻泥浆自动压注装置及方法,包括顶管机、管节、控制电缆、注浆总管、注浆分管、阀站、集中控制箱和泵站,顶管机后部设有管节,管节内设有注浆管,注浆管由一根注浆总管和若干注浆分管组成,注浆总管上设有若干阀站,单个阀站由注浆总管、注浆分管、注浆分阀、注浆总阀和远程控制箱组成,注浆总阀和若干注浆分阀通过信号线连接远程控制箱。本发明同现有技术相比,其优点在于:远程集中控制,集中控制箱控制电缆直接控制注浆的过程,避免了人工操作带来的各种弊端,提高施工效率、加快操作响应、降低劳动强度、提高了注浆润滑效果,注浆量稳定,注浆过程高效。

Description

一种顶管用润滑减阻泥浆自动压注装置及方法
[技术领域]
本发明涉及工程施工技术领域,具体是一种顶管用润滑减阻泥浆自动压注装置及方法。
[背景技术]
工程施工过程中注浆是施工的关键步骤,注浆是以改善顶管中管壁周围被扰动土层松散的性状为目的,使管道顶部及侧面增加抗压强度和粘结性,实现加固目的,防止路面沉陷,保证管道的使用安全。在顶管施工过程中润滑减阻泥浆的主要作用是:在顶进过程中形成泥浆套,减小与周围土体之间的摩擦力,进而减小顶进阻力。注浆的工程质量需要严格按照国家有关技术规范、规划、标准来控制施工,根据施工程序,严格控制配料、注浆压力、注浆量等。目前,现有的大多顶管注浆是人工注浆,配料、注浆压力、注浆量每一道工序都需要专人负责,以准确控制注浆压力、注浆时间、注浆量等,用人工操作手动阀门,其数量多、分散布置,需要在管道中来回频繁走动,造成注浆量无法精确控制,劳动强度大,且注浆效果差、操作效率低等缺点。
[发明内容]
本发明是对人工注浆的注浆效果差、效率低等不足进行改进,提供一种无需人工操作,自动完成注浆全过程的设定好阀站内各注浆分管的顶管用润滑减阻泥浆自动压注装置及方法。
为了实现上述目的,提供一种顶管用润滑减阻泥浆自动压注装置,包括顶管机、管节、控制电缆、注浆总管、注浆分管、阀站、集中控制箱和泵站,所述的顶管机后部设有管节,管节内设有注浆管,所述的注浆管由一根注浆总管和若干注浆分管组成,所述的注浆总管注浆进口端连接泵站,注浆总管上设有若干阀站,单个阀站由注浆总管、注浆分管、注浆分阀、注浆总阀和远程控制箱组成,注浆总管连接若干注浆分管,注浆总管上设有注浆总阀,若干注浆分管上分别设有注浆分阀,注浆总阀和若干注浆分阀通过信号线连接远程控制箱,每个阀站的远程控制箱通过信号线连接集中控制箱,集中控制箱通过信号线连接泵站。
所述的泵站内设有注浆泵、调速电机、电磁流量计和压力传感器,所述的注浆泵通过线路连接调速电机,注浆泵通过管道连接压力传感器,注浆泵与压力传感器之间的管道上设有电磁流量计,压力传感器通过管道连接注浆总管。
所述的注浆分管的管节上设有若干注浆孔,用软管将所有注浆孔接通。
所述的一个阀站包括5个自动球阀,即1个注浆总阀,4个注浆分阀,注浆总阀控制浆液的进入,4个注浆分阀分别与对应的4个注浆孔连接,可以针对单个孔进行均匀注浆。
一种采用顶管用润滑减阻泥浆自动压注装置的自动压注方法,具体方法如下:
a.在顶管的顶进过程中,从机尾注浆阀站起,每隔30m在管内安装一个阀站,在全线顶进过程中,机尾注浆处于常开状态,沿线注浆安装了n只阀站,首先开启第n号阀站,隔4个单位时间提前5秒开启第n-1号阀站,继续顶进35m后,开到第m个阀站,m<n,根据安装了第n+1个阀站后,开启n+1个,然后开启第m个号阀站,依次类推,直到全线贯通;
b.对于单点阀站,总阀处于常开状态,然后依次开启第1-第4电动球阀,第2电动球阀在第1电动球阀关闭的前5s时开启,依次类推。
上述的方法还包括注浆过程中,通过压力传感器来检测注浆压力的大小,当注浆压力超过设定值时报警,减小螺杆泵的转速,或者使泵停止旋转;当压力过低则加速螺杆泵的旋转,以此,通过调节泵的转速来调节注浆压力及注浆量的大小。
本发明同现有技术相比,其优点在于:
1.远程集中控制,集中控制箱控制电缆直接控制注浆的过程,可直接设定好阀站内各注浆分管的注浆时间或注浆量、注浆压力,无需工作人员操作,避免了人工操作带来的各种弊端,提高施工效率、加快操作响应、降低劳动强度、提高了注浆润滑效果,注浆量稳定,注浆过程高效;
2.单点工作,每点都能精确控制,注浆过程注浆量是设定值,注浆量能精确控制,节约成本;
3.控制泵站的压力,根据压力传感器来适时调节螺杆泵的转速,以实现注浆压力的控制,防止崩管现象的发生;
4.三种注浆模式可选,根据管道内个点压力的不同,设定顶注浆、管底注浆、全线注浆三种模式,以满足穿越不同地方不同点对注浆量的要求。
[附图说明]
图1为本发明顶管用润滑减阻泥浆自动压注装置的结构图;
图2为本发明中自动注浆系统洞口的截面图;
图3为本发明中泵站的系统图;
图4为本发明中阀站的系统图;
图中:1.顶管机  2.管节  3.控制电缆  4.注浆总管  5.注浆分管6.阀站  7.集中控制箱  8.泵站  9.注浆泵  10.调速电机  11.电磁流量计  12.压力传感器  13.控制箱  14.触摸屏  15.PLC程序  16.注浆分阀  17.注浆总阀  18.远程控制箱;
指定图1作为本发明的摘要附图。
[具体实施方式]
下面结合附图对本发明作进一步说明,这种装置的结构和原理对本专业的人来说是非常清楚的。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
实施例1
如图1、图2所示,本发明顶管用润滑减阻泥浆自动压注装置,包括有控制电缆3、注浆总管4、注浆分管5、阀站6、集中控制箱7及泵站8等主要部分,集中控制箱7通过控制电缆3控制泵站8和阀站6,注浆泵9吸入减阻泥浆并从泵的出口排出,再依次通过调速电机10、电磁流量计11、压力传感器12、控制器13,通过注浆总管4、注浆分管5输送至管内,阀站6依次分布在顶进管道内。注浆总管4和注浆分管5上相应的注浆参数是通过控制电缆3来传递数据,方便人员观测、记录。注浆总管4根据施工需要连接至相应的长度,注浆分管5的管节上设一定数量的注浆孔,用软管将所有注浆孔接通。
如图3所示,对于泵站8,主要包括注浆泵9、调速电机10、电磁流量计11、压力传感器12及控制箱13。在整个注浆过程中,注浆泵9的转速可以实现对注浆量的控制,而压力传感器12用以检测注浆压力的大小,当注浆压力超过设定值时报警,防止崩管现象的发生,若压力过高,可减小注浆泵9的转速,或者使注浆泵9停止旋转;若压力过低则加速注浆泵9的旋转,通过电磁流量11计来测定浆液的流速和注浆总量,为注浆系统的注浆模式提供参考依据,控制箱13总体控制注浆阀依次开关的顺序。
集中控制箱7主要包括触摸屏14和PLC程序15,触摸屏14是操作人员用以设置注浆过程中的参数、注浆阀门依次开关的顺序及注浆模式,并监控整个注浆过程及电机频率的变化,PLC程序15控制整个注浆过程,根据实际需要,注浆分管顶注浆、管底注浆、全线注浆三种模式,以满足穿越不同地方不同点对注浆量的要求;同时,注浆分为自动和手动两种功能,一般情况选用自动注浆,而在穿越房屋、河道等时根据需要选用手动注浆,进行单点选择性注浆。
如图4所示,为阀站的系统图,阀站6主要包括注浆分阀16、注浆总阀17和远程控制模块18,一个阀站包括5个自动球阀,即1个注浆总阀17,编号0#,4个注浆分阀16,编号1#至4#,0#注浆总阀17控制浆液的进入,4个注浆分阀16分别与对应的4个注浆孔连接,可以针对单个孔进行均匀注浆。远程控制模块18提供电动球阀所需的电量,并实现对电动球阀的控制,与集中控制箱7相连实现对整个系统的控制。
实施例2
采用顶管用润滑减阻泥浆自动压注装置的自动压注方法,阀站的工作是注浆的关键,在顶管的顶进过程中,依据顶进里程不同,从机尾注浆阀站起,每隔约30m在管内安装一个阀站,在全线顶进过程中,机尾注浆处于常开状态,假设沿线注浆安装了n只阀站,首先开启第n#阀站,隔4个单位时间提前5s第n-1#阀站,继续顶进35m后,假设开到第m#(m<n),根据安装了第n+1#阀站后,开启n+1#,然后开启第m#号阀站,依次类推,直到全线贯通。
对于单点阀站,0#总阀处于常开状态,然后依次开启1#至4#电动球阀,2#电动球阀在1#电动球阀关闭的前5s时开启,依次类推。
注浆过程中,通过压力传感器来检测注浆压力的大小,当注浆压力超过设定值时报警,可减小螺杆泵的转速,或者使泵停止旋转;当压力过低则加速螺杆泵的旋转,以此,通过调节泵的转速来调节注浆压力及注浆量的大小。
根据电磁流量计记录的浆液的流速及流经总量来设定设定单点排量的时间,并根据流量来适时调节螺杆泵的转速。

Claims (6)

1.一种顶管用润滑减阻泥浆自动压注装置,包括顶管机、管节、控制电缆、注浆总管、注浆分管、阀站、集中控制箱和泵站,所述的顶管机后部设有管节,管节内设有注浆管,其特征在于所述的注浆管由一根注浆总管和若干注浆分管组成,所述的注浆总管注浆进口端连接泵站,注浆总管上设有若干阀站,单个阀站由注浆总管、注浆分管、注浆分阀、注浆总阀和远程控制箱组成,注浆总管连接若干注浆分管,注浆总管上设有注浆总阀,若干注浆分管上分别设有注浆分阀,注浆总阀和若干注浆分阀通过信号线连接远程控制箱,每个阀站的远程控制箱通过信号线连接集中控制箱,集中控制箱通过信号线连接泵站。
2.如权利要求1所述的一种顶管用润滑减阻泥浆自动压注装置,其特征在于所述的泵站内设有注浆泵、调速电机、电磁流量计和压力传感器,所述的注浆泵通过线路连接调速电机,注浆泵通过管道连接压力传感器,注浆泵与压力传感器之间的管道上设有电磁流量计,压力传感器通过管道连接注浆总管。
3.如权利要求1所述的一种顶管用润滑减阻泥浆自动压注装置,其特征在于所述的注浆分管的管节上设有若干注浆孔,用软管将所有注浆孔接通。
4.如权利要求1所述的一种顶管用润滑减阻泥浆自动压注装置,其特征在于所述的一个阀站包括5个自动球阀,即1个注浆总阀,4个注浆分阀,注浆总阀控制浆液的进入,4个注浆分阀分别与对应的4个注浆孔连接,可以针对单个孔进行均匀注浆。
5.一种采用如权利要求1所述的顶管用润滑减阻泥浆自动压注装置的自动压注方法,其特征在于具体方法如下:
a.在顶管的顶进过程中,从机尾注浆阀站起,每隔30m在管内安装一个阀站,在全线顶进过程中,机尾注浆处于常开状态,沿线注浆安装了n只阀站,首先开启第n号阀站,隔4个单位时间提前5秒开启第n-1号阀站,继续顶进35m后,开到第m个阀站,m<n,根据安装了第n+1个阀站后,开启n+1个,然后开启第m个号阀站,依次类推,直到全线贯通;
b.对于单点阀站,总阀处于常开状态,然后依次开启第1-第4电动球阀,第2电动球阀在第1电动球阀关闭的前5s时开启,依次类推。
6.如权利要求5所述的自动压注方法,其特征在于所述的方法还包括注浆过程中,通过压力传感器来检测注浆压力的大小,当注浆压力超过设定值时报警,减小螺杆泵的转速,或者使泵停止旋转;当压力过低则加速螺杆泵的旋转,以此,通过调节泵的转速来调节注浆压力及注浆量的大小。
CN201310723505.6A 2013-12-24 2013-12-24 一种顶管用润滑减阻泥浆自动压注装置及方法 Active CN103644369B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310723505.6A CN103644369B (zh) 2013-12-24 2013-12-24 一种顶管用润滑减阻泥浆自动压注装置及方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310723505.6A CN103644369B (zh) 2013-12-24 2013-12-24 一种顶管用润滑减阻泥浆自动压注装置及方法

Publications (2)

Publication Number Publication Date
CN103644369A true CN103644369A (zh) 2014-03-19
CN103644369B CN103644369B (zh) 2015-11-18

Family

ID=50249628

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310723505.6A Active CN103644369B (zh) 2013-12-24 2013-12-24 一种顶管用润滑减阻泥浆自动压注装置及方法

Country Status (1)

Country Link
CN (1) CN103644369B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104265326A (zh) * 2014-08-06 2015-01-07 上海隧道工程有限公司 一种控制大型矩形顶管掘进土体变形的方法
CN104632252A (zh) * 2015-01-09 2015-05-20 广州鑫桥建筑劳务有限公司 自动注浆系统
CN106015733A (zh) * 2016-08-03 2016-10-12 北京政平建设投资集团有限公司 一种直顶钢管管道顶进施工方法
CN108331967A (zh) * 2018-03-14 2018-07-27 安徽路鼎科技股份有限公司 自动定压注浆系统
CN110700859A (zh) * 2019-10-28 2020-01-17 煤科集团沈阳研究院有限公司 一种井下救援用顶管注浆装置及方法
CN112305988A (zh) * 2020-11-02 2021-02-02 上海市基础工程集团有限公司 顶管减阻注浆无线远程控制系统
CN112308838A (zh) * 2020-10-30 2021-02-02 广东博智林机器人有限公司 螺杆洞的封堵方法、封堵装置、螺杆洞封堵设备和处理器
CN112901178A (zh) * 2021-01-18 2021-06-04 中铁上海工程局集团第五工程有限公司 中长距离超大直径顶管触变泥浆减阻注浆系统及注浆方法
CN110700859B (zh) * 2019-10-28 2024-04-30 中煤科工集团沈阳研究院有限公司 一种井下救援用顶管注浆装置及方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08284140A (ja) * 1995-04-11 1996-10-29 Iseki Tory Tech Inc 掘進装置及び推進工法
JPH08291694A (ja) * 1995-04-20 1996-11-05 Osaka Gas Co Ltd 推進工法用二重鋼管の中押し構造
CN201738929U (zh) * 2010-04-21 2011-02-09 朱伯锦 刀臂破碎型顶管机
CN102748533A (zh) * 2012-06-27 2012-10-24 中铁上海工程局有限公司 一种机械顶管迎面土压自动控制装置及方法
CN102966793A (zh) * 2012-11-06 2013-03-13 广东省基础工程公司 一种泥水平衡式顶管机及泥浆循环排渣的方法
CN103398214A (zh) * 2013-08-13 2013-11-20 上海力行工程技术发展有限公司 一种泥水平衡顶管机
CN203628020U (zh) * 2013-12-24 2014-06-04 中铁上海工程局有限公司 一种顶管用润滑减阻泥浆自动压注装置

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08284140A (ja) * 1995-04-11 1996-10-29 Iseki Tory Tech Inc 掘進装置及び推進工法
JPH08291694A (ja) * 1995-04-20 1996-11-05 Osaka Gas Co Ltd 推進工法用二重鋼管の中押し構造
CN201738929U (zh) * 2010-04-21 2011-02-09 朱伯锦 刀臂破碎型顶管机
CN102748533A (zh) * 2012-06-27 2012-10-24 中铁上海工程局有限公司 一种机械顶管迎面土压自动控制装置及方法
CN102966793A (zh) * 2012-11-06 2013-03-13 广东省基础工程公司 一种泥水平衡式顶管机及泥浆循环排渣的方法
CN103398214A (zh) * 2013-08-13 2013-11-20 上海力行工程技术发展有限公司 一种泥水平衡顶管机
CN203628020U (zh) * 2013-12-24 2014-06-04 中铁上海工程局有限公司 一种顶管用润滑减阻泥浆自动压注装置

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104265326A (zh) * 2014-08-06 2015-01-07 上海隧道工程有限公司 一种控制大型矩形顶管掘进土体变形的方法
CN104265326B (zh) * 2014-08-06 2016-04-27 上海隧道工程有限公司 一种控制大型矩形顶管掘进土体变形的方法
CN104632252A (zh) * 2015-01-09 2015-05-20 广州鑫桥建筑劳务有限公司 自动注浆系统
CN106015733A (zh) * 2016-08-03 2016-10-12 北京政平建设投资集团有限公司 一种直顶钢管管道顶进施工方法
CN106015733B (zh) * 2016-08-03 2018-05-04 北京政平建设投资集团有限公司 一种直顶钢管管道顶进施工方法
CN108331967A (zh) * 2018-03-14 2018-07-27 安徽路鼎科技股份有限公司 自动定压注浆系统
CN110700859A (zh) * 2019-10-28 2020-01-17 煤科集团沈阳研究院有限公司 一种井下救援用顶管注浆装置及方法
CN110700859B (zh) * 2019-10-28 2024-04-30 中煤科工集团沈阳研究院有限公司 一种井下救援用顶管注浆装置及方法
CN112308838A (zh) * 2020-10-30 2021-02-02 广东博智林机器人有限公司 螺杆洞的封堵方法、封堵装置、螺杆洞封堵设备和处理器
CN112305988A (zh) * 2020-11-02 2021-02-02 上海市基础工程集团有限公司 顶管减阻注浆无线远程控制系统
CN112901178A (zh) * 2021-01-18 2021-06-04 中铁上海工程局集团第五工程有限公司 中长距离超大直径顶管触变泥浆减阻注浆系统及注浆方法
CN112901178B (zh) * 2021-01-18 2023-03-24 中铁上海工程局集团第五工程有限公司 中长距离超大直径顶管触变泥浆减阻注浆系统及注浆方法

Also Published As

Publication number Publication date
CN103644369B (zh) 2015-11-18

Similar Documents

Publication Publication Date Title
CN103644369B (zh) 一种顶管用润滑减阻泥浆自动压注装置及方法
CN103423598B (zh) 一种基于供水管网流量实时监测的渗漏判断方法
CN101787873B (zh) 注水井智能配注工艺
CN201941779U (zh) 铁路客车上水溢流自动控制装置
CN104632252A (zh) 自动注浆系统
CN103217948B (zh) 电缆敷设远程控制系统
CN203755168U (zh) 双循环式自动制浆灌浆系统
CN103485268B (zh) 一种公路信息化智能注浆系统
CN203628020U (zh) 一种顶管用润滑减阻泥浆自动压注装置
CN204057820U (zh) 绞车控制装置
CN204782866U (zh) 控压钻井节流管汇装置
CN204832983U (zh) 智能灌浆压力控制系统
CN207297085U (zh) 一种用于矿山井下的无人值守自动排水系统
CN103616908A (zh) 用于矿山充填站砂仓及放砂管路的检测清理方法及装置
CN203797148U (zh) 一种管道顶进浆液自动加注系统
CN202533815U (zh) 一种智能张力机
CN206818239U (zh) 地铁暗挖隧道注浆联合监控系统
CN205315005U (zh) 一种泥水盾构机环流系统的应急液压装置
CN203684052U (zh) 铣刨机洒水控制系统和具有该洒水控制系统的铣刨机
CN203616225U (zh) 一种盾构渣土改良泡沫剂发泡性能鉴定装置
CN206647110U (zh) 隧道预埋槽道安装结构
CN203255555U (zh) 一种散装物料防堵装置及控制系统
CN205477753U (zh) 一种矿井风水管网安全监测与远程调度系统
CN205003483U (zh) 一种融雪剂撒布机控制装置
CN203925506U (zh) 泥水平衡顶管掘进机开挖面压力自动平衡装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 200436 Shanghai Road, Zhabei District, No. three, No. 278

Applicant after: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC

Applicant after: China Railway Shanghai Engineering Bureau Group Municipal Engineering Co.,Ltd.

Address before: 200436 Shanghai, Zhabei District River Road, No. 272, No. three, layer 278, 10

Applicant before: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC

Applicant before: Shanghai CIVIL Engineering Municipal Engineering Co.,Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: SHANGHAI CIVIL ENGINEERING CO., LTD. OF CREC TO: SHANGHAI CIVIL ENGINEERING CO., LTD. OF CREC

CB03 Change of inventor or designer information

Inventor after: Wu Hangzhou

Inventor after: Deng Yongchi

Inventor after: Sun Huanbin

Inventor after: Wang Jing

Inventor after: Zhang Haitao

Inventor after: Liu Guangchao

Inventor before: Sun Huanbin

Inventor before: Liu Guangchao

Inventor before: Zhang Lixin

Inventor before: Sun Dongxiao

Inventor before: Wang Jing

Inventor before: Zhang Haitao

Inventor before: Wu Hangzhou

COR Change of bibliographic data
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 200436, No. three, 278 Road, Zhabei District, Shanghai

Co-patentee after: China Railway Municipal Environmental Construction Co.,Ltd.

Patentee after: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC

Address before: 200436, No. three, 278 Road, Zhabei District, Shanghai

Co-patentee before: China Railway Shanghai Engineering Bureau Group Municipal Engineering Co.,Ltd.

Patentee before: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200526

Address after: 200331 A District, building 88, Lane 3, Wuwei Road, Shanghai, Putuo District, China

Patentee after: China Railway Municipal Environmental Construction Co.,Ltd.

Address before: 200436, No. three, 278 Road, Zhabei District, Shanghai

Co-patentee before: China Railway Municipal Environmental Construction Co.,Ltd.

Patentee before: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC