CN103628410B - A kind of transverse partition plate reinforcement cage and making, mounting method - Google Patents
A kind of transverse partition plate reinforcement cage and making, mounting method Download PDFInfo
- Publication number
- CN103628410B CN103628410B CN201310588787.3A CN201310588787A CN103628410B CN 103628410 B CN103628410 B CN 103628410B CN 201310588787 A CN201310588787 A CN 201310588787A CN 103628410 B CN103628410 B CN 103628410B
- Authority
- CN
- China
- Prior art keywords
- diaphragm
- cage
- reinforcement
- partition plate
- reinforcing bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
The invention discloses a kind of transverse partition plate reinforcement cage and making, mounting method, relate to reinforced bar engineering technical field in bridge construction, aim to provide a kind of quality assurance, the transverse partition plate reinforcement cage of saving the segmental construction used time and making, mounting method.Described transverse partition plate reinforcement cage comprises diaphragm reinforcing bar (1), the main muscle of diaphragm level (2), also comprises diaphragm stirrup (3); Described diaphragm reinforcing bar (1) is positioned at the below of the main muscle of diaphragm level (2), and diaphragm stirrup (3) is positioned at the right-hand member of diaphragm reinforcing bar (1), mutually vertical with the main muscle of diaphragm level (2).Construction sequence comprises cage of reinforcement block section and divides, moulding bed designing and making, reinforcement detailing, cutting stock, processing and fabricating, and the colligation of cage of reinforcement piecemeal section is shaped, the handling of reinforcing bar piecemeal section, installation.Steel Reinforcing Bar Material of the present invention, processing and fabricating etc. all belong to on-the-spot standardized construction, quality assurance.
Description
Technical field
The present invention relates to reinforced bar engineering technical field in bridge construction, particularly a kind of transverse partition plate reinforcement cage and making, mounting method.
Background technology
In steel concrete and Prestressed Concrete Bridges construction, reinforced bar engineering is often longer for man-hour used, comparatively large on duration impact, particularly the bridge (as cable stayed bridge, continuous girder bridge etc.) of front fulcrum or rear-support hanging basket cantilever casting construction section by section; The major part reinforcing bar binding time often that its sections duration can be compressed, therefore in order to meet sections construction period, usually need to drop into more labour when sections reinforcing bar binding, but in the strong times such as concrete seven sky, surplus labour force result in again a large amount of work holdup, there is with between allocation of labor resources conflict in duration progress.And traditional whole original positions install simple coarse, and construction quality is not high.
Summary of the invention
In order to overcome above-mentioned defect, the technical problem to be solved in the present invention is: provide a kind of quality assurance, save the transverse partition plate reinforcement cage of segmental construction used time and making, mounting method.
The present invention is the technical scheme solving the problems of the technologies described above employing: a kind of transverse partition plate reinforcement cage, comprises diaphragm reinforcing bar, the main muscle of diaphragm level, it is characterized in that: also comprise diaphragm stirrup; Described diaphragm reinforcing bar is positioned at the below of the main muscle of diaphragm level, and described diaphragm stirrup is positioned at the right-hand member of diaphragm reinforcing bar, mutually vertical with the main muscle of diaphragm level.
A kind of making of transverse partition plate reinforcement cage and the step of installation as follows:
The first step: cage of reinforcement block section divides
According to diaphragm bar diameter size, cage of reinforcement size, cage of reinforcement rigidity, crane gear ability, whole transverse partition plate reinforcement cage is divided into one or several block section.
Second step: moulding bed designing and making
The feature such as shape, framework according to each piece of section of transverse partition plate reinforcement cage designs and makes corresponding moulding bed.
3rd step: reinforcement detailing, cutting stock, processing and fabricating
Carry out reinforcement detailing according to design drawing and job specfication, carrying out cutting stock according to turning over sample detail drawing and manufacturing semiproduct.
4th step: the colligation of cage of reinforcement piecemeal section is shaped
Select suitable place erection moulding bed, and on moulding bed, each block section colligation is shaped.The main muscle of overlap joint between each piece of section should be staggeredly arranged, and this position stirrup cover is become owner of with skeleton integral hoisting in muscle, but temporarily delocalization, until two sections of skeletons all install fixing after colligation location again.
5th step: the handling of reinforcing bar piecemeal section, installation
The cage of reinforcement block section that colligation is shaped is carried out handling and installation in a certain order, should coordinate with form work engineering and prestress engineering in process and carry out.Being out of shape excessive when lifting for avoiding cage of reinforcement, using shaped steel as the many suspension centre liftings of lifting moulding bed.
The invention has the beneficial effects as follows:
Steel Reinforcing Bar Material of the present invention, processing and fabricating and the colligation of piecemeal section are shaped and all belong to on-the-spot standardized construction, can abundant quality assurance; The arrangement of time of diaphragm reinforcing bar piecemeal section colligation forming construction is carried out in advance within the construction break period caused because of process characteristic, take full advantage of free time, make the job placement of constructor more reasonable, the method of installing afterwards that is first shaped can save the segmental construction used time, shortens the construction period and creates benefit.
Accompanying drawing explanation
A kind of transverse partition plate reinforcement cage of the present invention and making, mounting method is illustrated below in conjunction with accompanying drawing.
Fig. 1 is transverse partition plate reinforcement cage structural representation.
In figure: 1-diaphragm reinforcing bar, the main muscle of 2-diaphragm level, 3-diaphragm stirrup.
Detailed description of the invention
As shown in Figure 1, a kind of transverse partition plate reinforcement cage, comprises diaphragm reinforcing bar 1, the main muscle 2 of diaphragm level, it is characterized in that: also comprise diaphragm stirrup 3; Described diaphragm reinforcing bar 1 is positioned at the below of the main muscle 2 of diaphragm level, and described diaphragm stirrup 3 is positioned at the right-hand member of diaphragm reinforcing bar 1, mutually vertical with the main muscle of diaphragm level 2.
A kind of making of transverse partition plate reinforcement cage and the step of installation as follows:
The first step: cage of reinforcement block section divides
According to diaphragm bar diameter size, cage of reinforcement size, cage of reinforcement rigidity, crane gear ability, whole transverse partition plate reinforcement cage is divided into one or several block section.
Second step: moulding bed designing and making
The feature such as shape, framework according to each piece of section of transverse partition plate reinforcement cage designs and makes corresponding moulding bed.
3rd step: reinforcement detailing, cutting stock, processing and fabricating
Carry out reinforcement detailing according to design drawing and job specfication, carrying out cutting stock according to turning over sample detail drawing and manufacturing semiproduct.
4th step: the colligation of cage of reinforcement piecemeal section is shaped
Select suitable place erection moulding bed, and on moulding bed, each block section colligation is shaped.The main muscle of overlap joint between each piece of section should be staggeredly arranged, and this position stirrup cover is become owner of with skeleton integral hoisting in muscle, but temporarily delocalization, until two sections of skeletons all install fixing after colligation location again.
5th step: the handling of reinforcing bar piecemeal section, installation
The cage of reinforcement block section that colligation is shaped is carried out handling and installation in a certain order, should coordinate with form work engineering and prestress engineering in process and carry out.Being out of shape excessive when lifting for avoiding cage of reinforcement, using shaped steel as the many suspension centre liftings of lifting moulding bed.
Should be understood that, above-mentioned detailed description of the invention of the present invention only for exemplary illustration or explain principle of the present invention, and does not form the restriction to invention.Therefore, any amendment made when without departing from the spirit and scope of the present invention, equivalent replacement, improvement etc., all should be included within protection scope of the present invention.In addition, claims of the present invention be intended to contain fall into claims scope and border or this scope and border equivalents in whole change and modification.
Claims (2)
1. a transverse partition plate reinforcement cage, comprises diaphragm reinforcing bar (1), the main muscle of diaphragm level (2), it is characterized in that: also comprise diaphragm stirrup (3); Described diaphragm reinforcing bar (1) is positioned at the below of the main muscle of diaphragm level (2), described diaphragm stirrup (3) is positioned at the right-hand member of diaphragm reinforcing bar (1), mutually vertical with the main muscle of diaphragm level (2);
Described transverse partition plate reinforcement cage is divided into several pieces of sections, and the main muscle of overlap joint between each piece of section should be staggeredly arranged, and this position stirrup cover is become owner of with skeleton integral hoisting in muscle, but temporarily delocalization, until two sections of skeletons all install fixing after colligation location again.
2. the making of a transverse partition plate reinforcement cage and the steps characteristic of installation as follows:
The first step: cage of reinforcement block section divides
According to diaphragm bar diameter size, cage of reinforcement size, cage of reinforcement rigidity, crane gear ability, whole transverse partition plate reinforcement cage is divided into several pieces of sections;
Second step: moulding bed designing and making
Design according to the shape of each piece of section of transverse partition plate reinforcement cage, construction characteristic and make corresponding moulding bed;
3rd step: reinforcement detailing, cutting stock, processing and fabricating
Carry out reinforcement detailing according to design drawing and job specfication, then carry out cutting stock according to turning over sample detail drawing and manufacture semiproduct;
4th step: the colligation of cage of reinforcement piecemeal section is shaped
Select suitable place erection moulding bed, and on moulding bed, each block section colligation is shaped, the main muscle of overlap joint between each piece of section should be staggeredly arranged, and this position stirrup cover is become owner of in muscle with skeleton integral hoisting, but temporarily delocalization, until two sections of skeletons all install fixing after colligation location again;
5th step: the handling of reinforcing bar piecemeal section, installation
The cage of reinforcement block section that colligation is shaped is carried out handling and installation in a certain order, should coordinating with form work engineering and prestress engineering in process and carry out, being out of shape excessive when lifting for avoiding cage of reinforcement, use shaped steel as the many suspension centre liftings of lifting moulding bed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310588787.3A CN103628410B (en) | 2013-11-21 | 2013-11-21 | A kind of transverse partition plate reinforcement cage and making, mounting method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310588787.3A CN103628410B (en) | 2013-11-21 | 2013-11-21 | A kind of transverse partition plate reinforcement cage and making, mounting method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103628410A CN103628410A (en) | 2014-03-12 |
CN103628410B true CN103628410B (en) | 2016-04-13 |
Family
ID=50209837
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310588787.3A Active CN103628410B (en) | 2013-11-21 | 2013-11-21 | A kind of transverse partition plate reinforcement cage and making, mounting method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103628410B (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105926446B (en) * | 2016-05-04 | 2017-12-29 | 中国十九冶集团有限公司 | Bridge pier column self-lifting outer frame turnover formwork closing beam |
CN110826152B (en) * | 2019-11-21 | 2023-10-27 | 上海宝冶集团有限公司 | Method and device for overturning special-shaped structural steel bars |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101403212A (en) * | 2008-11-13 | 2009-04-08 | 中铁二局股份有限公司 | Construction method for pretensioned prestressing concrete simply supported T-beam |
KR101045929B1 (en) * | 2010-10-27 | 2011-07-01 | 홍석희 | Pro-environment prestressed long span light-weight precast concrete panel and this construction technique |
CN102220739A (en) * | 2011-04-01 | 2011-10-19 | 河南省交通规划勘察设计院有限责任公司 | Corrugated steel web prestressed concrete continuous box girder and construction method thereof |
CN102808371A (en) * | 2012-08-20 | 2012-12-05 | 杨众 | Simply-supported-to-continuous prefabricated integrally-cast superposed continuous bridge and construction method |
CN202610696U (en) * | 2012-06-25 | 2012-12-19 | 河南省交通规划勘察设计院有限责任公司 | Corrugated steel web pre-tensioning pre-stressed concrete continuous box beam |
CN202969248U (en) * | 2012-08-16 | 2013-06-05 | 杨众 | Prefabricated diaphragm plate for bridge |
-
2013
- 2013-11-21 CN CN201310588787.3A patent/CN103628410B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101403212A (en) * | 2008-11-13 | 2009-04-08 | 中铁二局股份有限公司 | Construction method for pretensioned prestressing concrete simply supported T-beam |
KR101045929B1 (en) * | 2010-10-27 | 2011-07-01 | 홍석희 | Pro-environment prestressed long span light-weight precast concrete panel and this construction technique |
CN102220739A (en) * | 2011-04-01 | 2011-10-19 | 河南省交通规划勘察设计院有限责任公司 | Corrugated steel web prestressed concrete continuous box girder and construction method thereof |
CN202610696U (en) * | 2012-06-25 | 2012-12-19 | 河南省交通规划勘察设计院有限责任公司 | Corrugated steel web pre-tensioning pre-stressed concrete continuous box beam |
CN202969248U (en) * | 2012-08-16 | 2013-06-05 | 杨众 | Prefabricated diaphragm plate for bridge |
CN102808371A (en) * | 2012-08-20 | 2012-12-05 | 杨众 | Simply-supported-to-continuous prefabricated integrally-cast superposed continuous bridge and construction method |
Non-Patent Citations (3)
Title |
---|
基于时变可靠度的横隔板耐用构造设计;徐岳等;《2008年全国既有桥梁加固、改造与评价学术会议论文集》;20090323;第12-20页 * |
箱梁的施工工艺;王瑛;《山西建筑》;20060831;第32卷(第16期);全文 * |
铁路大型箱梁钢筋绑扎、吊装方案对比;官嘉;《中国新技术新产品》;20121231(第24期);第141-142页 * |
Also Published As
Publication number | Publication date |
---|---|
CN103628410A (en) | 2014-03-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106869489A (en) | Super High Core Walls Structure level and vertical synchronous construction top module system and construction method | |
CN104863362B (en) | The arch barrel lattice shell construction technology that the sliding of arch steel lattice moulding bed is installed is set | |
CN109083320A (en) | Combine prefabricated panel and laminated floor slab structure and laminated floor slab construction method | |
CN103628410B (en) | A kind of transverse partition plate reinforcement cage and making, mounting method | |
CN103215898A (en) | Variable-cross-section concrete continuous bridge construction method | |
CN106529065A (en) | Installation construction method for carrying out component optimization by software | |
CN109183616A (en) | Inside and outside double steel plate steel reinforced concrete synthetic rope tower structure and its assembling method of construction | |
CN103924526B (en) | A kind of bridge spanning the sea roomy pier shaft integral prefabricated moulding bed of steel reinforcement cage | |
CN204252001U (en) | A kind of cable stayed bridge and Sarasota thereof | |
CN104294752B (en) | The hollow slab bridge structure of a kind of band end crossbeam and constructional method thereof | |
CN203187288U (en) | Box girder hanger | |
CN101956372B (en) | Quick construction method for No. 0 section of prestressed concrete beam type bridge | |
CN204850139U (en) | Prefabricated assembled concrete shear force wall that reinforcing bar dislocation was laid | |
CN204235678U (en) | A kind of overall pulling type prefabricated box girder inner formwork device | |
CN208884808U (en) | Combine prefabricated panel and laminated floor slab structure | |
CN201458544U (en) | Carrying pole for mounting component | |
CN203729211U (en) | Suspension type curved bridge panel cast-in-situ formwork | |
CN101748915B (en) | Modularization construction method for nuclear power station nuclear island | |
CN203448301U (en) | Thick sand and fine sand separator | |
CN101736925A (en) | Modular construction method for nuclear island of nuclear power station | |
CN101752017A (en) | Modularization construction method for nuclear power station nuclear island | |
CN105350718A (en) | Reinforcement permanency beam formwork and manufacturing method for concrete structural member with shearing resistance | |
CN105735136B (en) | Box beam roof steel bar global formation mould bases and construction method | |
CN108756023A (en) | A kind of fabricated shear wall system and its assembly method | |
CN210828837U (en) | Prefabricated window component that wafts of assembled building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |