CN103616660A - Power-down processing reliability test device and method for intelligent ammeters in interference environment - Google Patents

Power-down processing reliability test device and method for intelligent ammeters in interference environment Download PDF

Info

Publication number
CN103616660A
CN103616660A CN201310631198.9A CN201310631198A CN103616660A CN 103616660 A CN103616660 A CN 103616660A CN 201310631198 A CN201310631198 A CN 201310631198A CN 103616660 A CN103616660 A CN 103616660A
Authority
CN
China
Prior art keywords
electric energy
energy meter
intelligent electric
inductive load
tested
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310631198.9A
Other languages
Chinese (zh)
Other versions
CN103616660B (en
Inventor
徐晴
纪峰
田正其
穆小星
鲍进
周超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Electric Power Research Institute of State Grid Jiangsu Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201310631198.9A priority Critical patent/CN103616660B/en
Publication of CN103616660A publication Critical patent/CN103616660A/en
Application granted granted Critical
Publication of CN103616660B publication Critical patent/CN103616660B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

The invention discloses an automatic power-down processing reliability test device and method for intelligent ammeters in an interference environment. The automatic power-down processing reliability test device comprises an automatic test controller, an inductive load switching device and at least two ammeters to be tested, wherein the automatic test controller is computer equipment which automatic testing software is installed in and is provided with a communication interface. The automatic power-down processing reliability test method comprises the following steps: an input power supply inside a switching device is switched off by controlling the inductive load switching device, a power supply of a paralleling reactor inside the switching device is switched off while the ammeters to be tested which are connected to a switching device voltage loop in parallel are powered down, an inductive load switching interference is generated in a simulated mode, and the inductive load switching interference is output to the voltage loop of the ammeters to be tested through a voltage interface; communication with the ammeters to be tested is conducted through an RS485 interface, operating data of the ammeters to be tested before being powered down and operating data of the ammeters to be tested after being powered up again for operation are detected, so that whether power-down processing of the intelligent ammeters to be tested under the inductive load switching interference is normal is judged, an assessment of the power-down processing reliability of the intelligent ammeters under the interference is realized, and faults are prevented from happening.

Description

The proving installation of power down process reliability and method under intelligent electric energy meter interference environment
?
Technical field
The present invention relates to a kind of intelligent electric energy meter and at inductive load, switch the automatic test approach of power down process reliability under interference environment, belong to intelligent electric energy meter detection technique field.
Background technology
Intelligent electric energy meter at the scene in linked network by being subject to electric power loop, the RS485 communication loop of the effect of various interference stress, particularly electric energy meter, be the main thoroughfare that various interference enter electric energy meter logic card.Although electric energy meter electric source and RS485 mouth have isolating transformer or opto-electronic conversion chip to isolate conventionally, but owing to having distributed capacitance and coupling inductance, the impulse disturbances that some rising edges are very steep is easy to cross these isolation by distributed capacitance and coupling inductance, when impulse disturbances enters electric energy meter logical circuit, electric energy meter can produce various unexpected consequences, as chaotic in clock entanglement, loss of data, internal storage data, even crash etc.
In electrical network, when switch, relay, contactor etc. suit, inductive load is carried out to switching and can cause interference, this interference has that pulse occurs in groups, waveform rise time is short, amplitude and repetition frequency high, and its spectrum distribution is wider simultaneously, and digital circuit is more responsive to it.A large number of experiments show that, this interference can cause intelligent electric energy meter software to break down to a certain extent, as program confusion, loss of data etc.
When there is power failure situation in electrical network, intelligent electric energy meter externally fed stops, the MCU of intelligent electric energy meter will receive the power-off signal that in table, other hardware circuits produce, produce an interruption, intelligent electric energy meter software enters power down process flow process according to the interruption receiving, to internal memory chip, write relevant service data and preserve, then enter low power operation state, rely on internal cell power supply.At electrical network, again power, intelligent electric energy meter recovers after externally fed, and intelligent electric energy meter software rejuvenation normally moves, and the service data of storing when internal memory chip reads last time power down is as the data basis of reruning.If intelligent electric energy meter is interfered when power down, may causes power-off signal or storage data to occur abnormal, thereby cause intelligent electric energy meter operation to be broken down.Because this interference is uncertain on the impact of intelligent electric energy meter power down, the probability that this fault occurs is very low, by general detection method, is difficult to detect.Once but fault appearance, the consequence causing is unpredictable, and fault analysis is afterwards also very difficult.Therefore it is necessary intelligent electric energy meter being taked to the multisample reliability that repeatedly method of repeated test detects its power down process under interference environment.
Summary of the invention
For the deficiency existing in prior art, the object of the invention is subject to inductive load and switches interference while being to provide a kind of simulated field intelligent electric energy meter power down, to being no less than two intelligent electric energy meters, carry out repeatedly revision test simultaneously, by detecting electric energy meter service data, automatic testing equipment and the method thereof of judgement intelligent electric energy meter power down process reliability under disturbing.
To achieve these goals, the present invention realizes by the following technical solutions:
The proving installation of power down process reliability under a kind of intelligent electric energy meter interference environment, it is characterized in that, it comprises the automatic test controller for detection of intelligent electric energy meter power down process reliability under inductive load switching interference environment, inductive load switching device shifter and be no less than two by intelligence inspection electric energy meters, described automatic test controller is connected with inductive load switching device shifter by the first communication interface, described automatic test controller is connected with tested intelligent electric energy meter by the second communication interface, service data while re-powering operation by detecting after the service data of tested intelligent electric energy meter before power down and power down, judge that whether tested intelligent electric energy meter power down process under inductive load switching is disturbed is normal, described inductive load switching device shifter is in parallel with tested intelligent electric energy meter by voltage interface, for simulating, produces inductive load switching interference, outputs in the voltage circuit of tested intelligent electric energy meter by voltage interface.
Described inductive load switching device shifter device comprises the Programmable Logic Controller of the shunt reactor of analog electrical perception load, the vacuum A. C. contactor of controlling shunt reactor and tested intelligent electric energy meter input power and control vacuum A. C. contactor break-make; A.C. contactor and the shunt reactor respectively tested intelligent electric energy meter parallel with one another with voltage circuit are connected in series, described A.C. contactor and shunt reactor are connected in parallel, described Programmable Logic Controller communicates by the first communication interface and automatic test controller, receive the order that automatic test controller sends, by the order of automatic test controller, control the power supply that vacuum A. C. contactor is switched on or switched off tested intelligent electric energy meter and shunt reactor.
As priority scheme, described the first communication interface is RS232 or TCP/IP interface.
As priority scheme, described the second communication interface is RS232 interface.
The method of testing of power down process reliability under a kind of intelligent electric energy meter interference environment that utilizes above-mentioned proving installation, it is characterized in that, it comprises that detecting intelligent electric energy meter switches automatic test controller, the inductive load switching device shifter of power down process reliability under interference environment and be no less than two tested electric energy meters at inductive load, automatic test controller is connected with inductive load switching device shifter by the first communication interface, and is connected with tested intelligent electric energy meter by the second communication interface; Inductive load switching device shifter is in parallel with tested intelligent electric energy meter by voltage interface; Described method of testing comprises the steps:
(1) simulation produces inductive load switching interference; Automatic test controller cuts off the input power in switching device shifter by controlling inductive load switching device shifter, to when being connected in parallel on the tested electric energy meter power down on inductive load switching device shifter voltage circuit, disconnect a power supply in inductive load switching device shifter, simulation produces inductive load and switches interference, by voltage interface, output in the voltage circuit of tested intelligent electric energy meter, the power-off signal of tested intelligent electric energy meter and storage data are exerted an influence;
(2) judge that whether tested intelligent electric energy meter power down process under inductive load switching is disturbed is normal, automatic test controller communicates by the second communication interface and tested electric energy meter, and contrast detection by the service data detecting while re-powering operation after the service data of tested intelligent electric energy meter before power down and power down, judge that whether tested intelligent electric energy meter power down process under inductive load switching is disturbed is normal, if intelligent electric energy meter service data power-down operation front and back numerical value change on carrying out detected, surpassed setting threshold values, be judged to be normal, otherwise it is undesired to be judged to be, thereby intelligent electric energy meter is switched to power down process reliability under interference environment at inductive load and make evaluation,
(3), by automatically repeating step N time (this setting value can be done corresponding change according to testing requirements) of (1)-(2), complete and many intelligent electric energy meters are switched to the detection of power down process reliability under interference environment at inductive load.
In described step (1), the power supply that in described inductive load switching device shifter, a power supply is shunt reactor.
In described step (1), Programmable Logic Controller communicates by built-in RS232 or TCP/IP interface and automatic test controller, receive the order that automatic test controller sends, by the order of automatic test controller, control the power supply that vacuum A. C. contactor is switched on or switched off tested intelligent electric energy meter and shunt reactor.
The present invention is by proving installation and method thereof, during by the power down of simulated field intelligent electric energy meter, be subject to inductive load and switch interference, to being no less than two intelligent electric energy meters, carry out repeatedly revision test simultaneously, by detecting electric energy meter service data, judgement intelligent electric energy meter power down process reliability under disturbing, realize the assessment of intelligent electric energy meter power down process reliability under disturbing, avoided the generation of fault.
 
Accompanying drawing explanation
Below in conjunction with the drawings and specific embodiments, describe the present invention in detail;
Fig. 1 is the structured flowchart of the proving installation of power down process reliability under intelligent electric energy meter interference environment of the present invention;
Fig. 2 is process chart of the present invention;
Fig. 3 is the control principle drawing of inductive load switching device shifter of the present invention
embodiment
For technological means, creation characteristic that the present invention is realized, reach object and effect is easy to understand, below in conjunction with embodiment, further set forth the present invention.
As can be seen from Figure 1, under the present embodiment intelligent electric energy meter interference environment, the proving installation of power down process reliability comprises that detecting intelligent electric energy meter switches automatic test controller, the inductive load switching device shifter of power down process reliability under interference environment and be no less than two intelligent electric energy meters at inductive load.Its implementation is that automatic test controller passes through RS232 or TCP/IP interface is connected with inductive load switching device shifter, by RS485 interface be no less than two tested intelligent electric energy meters and be connected; Tested electric energy meter is parallel on inductive load switching device shifter voltage circuit by voltage interface.
As can be seen from Figure 2, the automatic test controller of the present embodiment is, at controller CPU, the automatic testing software that detects intelligent electric energy meter power down process reliability under inductive load switching interference environment is installed, utilize the method for realization test of the automatic testing software of said apparatus the present embodiment to be: first, first automatic test controller is switched on power the shunt reactor in tested intelligent electric energy meter and inductive load switching device shifter is powered on by control inductive load switching device shifter, by RS485 mouth, examine and determine and record every service data 1 of tested intelligent electric energy meter, comprise clock, all kinds of electric quantity datas etc.
Then, control inductive load switching device shifter and cut off input power, to shunt reactor and the power down simultaneously of tested intelligent electric energy meter, control again inductive load switching device shifter and switch on power the shunt reactor in tested intelligent electric energy meter and inductive load switching device shifter is powered on, by RS485 mouth, examine and determine and record every service data 2 of tested intelligent electric energy meter.
Finally, service data 1 and service data 2 are contrasted, judge tested intelligent electric energy meter power down process under disturbing line item of whether normally going forward side by side, decision method is: if intelligent electric energy meter service data power-down operation front and back numerical value change on carrying out detected, surpassed setting threshold values, be judged to be normal, otherwise be judged to be undesired.Above detecting step can rerun automatically according to detecting needs or testing result.
As shown in Figure 3, the present embodiment, inductive load switching device shifter is mainly comprised of the Programmable Logic Controller PLC of the shunt reactor L of analog electrical perception load, the vacuum A. C. contactor K that controls shunt reactor L and tested intelligent electric energy meter input power, control vacuum A. C. contactor K break-make.PLC communicates by built-in RS232 or TCP/IP interface and automatic test controller, receive the order that automatic test controller sends, by the order of automatic test controller, control the power supply that vacuum A. C. contactor K is switched on or switched off tested intelligent electric energy meter and shunt reactor.Programmable Logic Controller PLC can guarantee the stable operation of switching device shifter, is not easy to be subject to external interference, and what energy Reliable guarantee detected carries out for a long time; Adopt vacuum A. C. contactor to disconnect shunt reactor and can produce the impulse disturbances that obvious rising edge is very steep at tested electrical energy meter electricity hydraulic circuit, and can exert an influence to many tested electric energy meters, realize the long-time repeatedly object of revision test of multisample.
The present invention is by proving installation and method thereof, during by the power down of simulated field intelligent electric energy meter, be subject to inductive load and switch interference, to being no less than two intelligent electric energy meters, carry out repeatedly revision test simultaneously, by detecting electric energy meter service data, judgement intelligent electric energy meter power down process reliability under disturbing, realize the assessment of intelligent electric energy meter power down process reliability under disturbing, avoided the generation of fault.
More than show and described ultimate principle of the present invention and principal character and advantage of the present invention.The technician of the industry should understand; the present invention is not restricted to the described embodiments; that in above-described embodiment and instructions, describes just illustrates principle of the present invention; without departing from the spirit and scope of the present invention; the present invention also has various changes and modifications, and these changes and improvements all fall in the claimed scope of the invention.The claimed scope of the present invention is defined by appending claims and equivalent thereof.

Claims (10)

1. the proving installation of power down process reliability under an intelligent electric energy meter interference environment, it is characterized in that, it comprises the automatic test controller for detection of intelligent electric energy meter power down process reliability under inductive load switching interference environment, inductive load switching device shifter and be no less than two by intelligence inspection electric energy meters, described automatic test controller is connected with inductive load switching device shifter by the first communication interface, described automatic test controller is connected with tested intelligent electric energy meter by the second communication interface, service data while re-powering operation by detecting after the service data of tested intelligent electric energy meter before power down and power down, judge that whether tested intelligent electric energy meter power down process under inductive load switching is disturbed is normal, described inductive load switching device shifter is in parallel with tested intelligent electric energy meter by voltage interface, for simulating, produces inductive load switching interference, outputs in the voltage circuit of tested intelligent electric energy meter by voltage interface.
2. proving installation according to claim 1, it is characterized in that, described inductive load switching device shifter device comprises the Programmable Logic Controller of the shunt reactor of analog electrical perception load, the vacuum A. C. contactor of controlling shunt reactor and tested intelligent electric energy meter input power and control vacuum A. C. contactor break-make; A.C. contactor and the shunt reactor respectively tested intelligent electric energy meter parallel with one another with voltage circuit are connected in series, described A.C. contactor and shunt reactor are connected in parallel, described Programmable Logic Controller communicates by the first communication interface and automatic test controller, receive the order that automatic test controller sends, by the order of automatic test controller, control the power supply that vacuum A. C. contactor is switched on or switched off tested intelligent electric energy meter and shunt reactor.
3. proving installation according to claim 1 and 2, is characterized in that, described the first communication interface is RS232 or TCP/IP interface.
4. proving installation according to claim 1 and 2, is characterized in that, described the second communication interface is RS232 interface.
5. the method for testing of power down process reliability under an intelligent electric energy meter interference environment, it is characterized in that, it comprises that detecting intelligent electric energy meter switches automatic test controller, the inductive load switching device shifter of power down process reliability under interference environment and be no less than two tested electric energy meters at inductive load, automatic test controller is connected with inductive load switching device shifter by the first communication interface, and is connected with tested intelligent electric energy meter by the second communication interface; Inductive load switching device shifter is in parallel with tested intelligent electric energy meter by voltage interface; Described method of testing comprises the steps:
(1) simulation produces inductive load switching interference; Automatic test controller cuts off the input power in switching device shifter by controlling inductive load switching device shifter, to when being connected in parallel on the tested electric energy meter power down on inductive load switching device shifter voltage circuit, disconnect a power supply in inductive load switching device shifter, simulation produces inductive load and switches interference, by voltage interface, output in the voltage circuit of tested intelligent electric energy meter, the power-off signal of tested intelligent electric energy meter and storage data are exerted an influence;
(2) judge that whether tested intelligent electric energy meter power down process under inductive load switching is disturbed is normal, automatic test controller communicates by the second communication interface and tested electric energy meter, and contrast detection by the service data detecting while re-powering operation after the service data of tested intelligent electric energy meter before power down and power down, judge that whether tested intelligent electric energy meter power down process under inductive load switching is disturbed is normal, if intelligent electric energy meter service data power-down operation front and back numerical value change on carrying out detected, surpassed setting threshold values, be judged to be normal, otherwise it is undesired to be judged to be, thereby intelligent electric energy meter is switched to power down process reliability under interference environment at inductive load and make evaluation,
(3), by automatically repeating step N time (this setting value can be done corresponding change according to testing requirements) of (1)-(2), complete and many intelligent electric energy meters are switched to the detection of power down process reliability under interference environment at inductive load.
6. method of testing according to claim 5, it is characterized in that, described inductive load switching device shifter device comprises the Programmable Logic Controller of the shunt reactor of analog electrical perception load, the vacuum A. C. contactor of controlling shunt reactor and tested intelligent electric energy meter input power and control vacuum A. C. contactor break-make; A.C. contactor and the shunt reactor respectively tested intelligent electric energy meter parallel with one another with voltage circuit are connected in series, described A.C. contactor and shunt reactor are connected in parallel, and described Programmable Logic Controller communicates by the first communication interface and automatic test controller.
7. method of testing according to claim 6, is characterized in that, in described step (1), and the power supply that described inductive load switching device shifter internal electric source is shunt reactor.
8. according to the method for testing described in claim 5 to 7 any one, it is characterized in that, described the first communication interface is RS232 or TCP/IP interface.
9. according to the proving installation described in claim 5 to 7 any one, it is characterized in that, described the second communication interface is RS232 interface.
10. method of testing according to claim 7, it is characterized in that, in described step (1), Programmable Logic Controller communicates by built-in RS232 or TCP/IP interface and automatic test controller, receive the order that automatic test controller sends, by the order of automatic test controller, control the power supply that vacuum A. C. contactor is switched on or switched off tested intelligent electric energy meter and shunt reactor.
CN201310631198.9A 2013-12-02 2013-12-02 The testing arrangement of power down process reliability and method under intelligent electric energy meter interference environment Active CN103616660B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310631198.9A CN103616660B (en) 2013-12-02 2013-12-02 The testing arrangement of power down process reliability and method under intelligent electric energy meter interference environment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310631198.9A CN103616660B (en) 2013-12-02 2013-12-02 The testing arrangement of power down process reliability and method under intelligent electric energy meter interference environment

Publications (2)

Publication Number Publication Date
CN103616660A true CN103616660A (en) 2014-03-05
CN103616660B CN103616660B (en) 2016-05-25

Family

ID=50167364

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310631198.9A Active CN103616660B (en) 2013-12-02 2013-12-02 The testing arrangement of power down process reliability and method under intelligent electric energy meter interference environment

Country Status (1)

Country Link
CN (1) CN103616660B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103913719A (en) * 2014-04-18 2014-07-09 国家电网公司 Method for judging mistaken powering-down fault causes of single-phase carrier intelligent electric meter
CN104407211A (en) * 2014-12-06 2015-03-11 宁波迦南电子有限公司 Power consumption metering device
CN105242235A (en) * 2015-11-04 2016-01-13 国网冀北电力有限公司电力科学研究院 Multi-meter position electrical fast transient burst immunity test device
CN105425202A (en) * 2015-12-22 2016-03-23 国网天津宝坻供电有限公司 Intelligent electric energy meter voltage jitter simulation test device and test method
CN105929356A (en) * 2016-05-13 2016-09-07 威胜集团有限公司 Method for detecting performance of intelligent electric energy meter under power-on and power-off conditions
CN106019204A (en) * 2016-06-01 2016-10-12 国网河北省电力公司电力科学研究院 Electric energy meter automatic verification assembly line epitope fault alarming and positioning method
CN112882454A (en) * 2021-01-11 2021-06-01 阳光电源股份有限公司 Road spectrum testing method, system and computer readable storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1164402A (en) * 1997-08-11 1999-03-05 Mitsubishi Electric Corp Electronic watthour meter and error adjustment method therefor
CN2557955Y (en) * 2002-06-27 2003-06-25 深圳市欣瑞利电子有限公司 Electricity cut off detector for electricity meter
CN102692616A (en) * 2012-01-11 2012-09-26 华北电网有限公司计量中心 Automatic test and collection device and method of smart meter
CN103116102A (en) * 2013-02-04 2013-05-22 深圳佰维存储科技有限公司 Intelligent power failure testing method and system
CN103323809A (en) * 2013-06-18 2013-09-25 国家电网公司 Electric energy meter test equipment

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1164402A (en) * 1997-08-11 1999-03-05 Mitsubishi Electric Corp Electronic watthour meter and error adjustment method therefor
CN2557955Y (en) * 2002-06-27 2003-06-25 深圳市欣瑞利电子有限公司 Electricity cut off detector for electricity meter
CN102692616A (en) * 2012-01-11 2012-09-26 华北电网有限公司计量中心 Automatic test and collection device and method of smart meter
CN103116102A (en) * 2013-02-04 2013-05-22 深圳佰维存储科技有限公司 Intelligent power failure testing method and system
CN103323809A (en) * 2013-06-18 2013-09-25 国家电网公司 Electric energy meter test equipment

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103913719A (en) * 2014-04-18 2014-07-09 国家电网公司 Method for judging mistaken powering-down fault causes of single-phase carrier intelligent electric meter
CN103913719B (en) * 2014-04-18 2015-11-04 国家电网公司 A kind of method judging single-phase carrier intelligent electric meter mistake power down failure cause
CN104407211A (en) * 2014-12-06 2015-03-11 宁波迦南电子有限公司 Power consumption metering device
CN104407211B (en) * 2014-12-06 2017-02-08 宁波迦南智能电气股份有限公司 Power consumption metering device
CN105242235A (en) * 2015-11-04 2016-01-13 国网冀北电力有限公司电力科学研究院 Multi-meter position electrical fast transient burst immunity test device
CN105425202A (en) * 2015-12-22 2016-03-23 国网天津宝坻供电有限公司 Intelligent electric energy meter voltage jitter simulation test device and test method
CN105929356A (en) * 2016-05-13 2016-09-07 威胜集团有限公司 Method for detecting performance of intelligent electric energy meter under power-on and power-off conditions
CN105929356B (en) * 2016-05-13 2018-10-26 威胜集团有限公司 Intelligent electric energy meter powers on and the method for testing performance under power down operating mode
CN106019204A (en) * 2016-06-01 2016-10-12 国网河北省电力公司电力科学研究院 Electric energy meter automatic verification assembly line epitope fault alarming and positioning method
CN106019204B (en) * 2016-06-01 2019-09-27 国网河北省电力公司电力科学研究院 Electric energy meter automatic verification assembly line epitope fault alarming and positioning method
CN112882454A (en) * 2021-01-11 2021-06-01 阳光电源股份有限公司 Road spectrum testing method, system and computer readable storage medium
CN112882454B (en) * 2021-01-11 2022-05-24 阳光电源股份有限公司 Road spectrum testing method, system and computer readable storage medium

Also Published As

Publication number Publication date
CN103616660B (en) 2016-05-25

Similar Documents

Publication Publication Date Title
CN103616660A (en) Power-down processing reliability test device and method for intelligent ammeters in interference environment
CN104246521B (en) The method and device that intelligent substation relay protection function is tested automatically
CN103954925B (en) A kind of fault oscillograph dynamic testing method based on RTDS real-time simulation
CN103869190A (en) Real time simulation system-based power distribution terminal automatic closed-loop test platform
CN105259561A (en) Device and method for testing exception handling ability of satellite time synchronization device
CN104133146A (en) On-site test method for feeder automation fault treatment logic
CN104020761A (en) Automatic feeder testing system free of networking
CN104090259A (en) Automatic gauge test platform and method based on Python script
CN103616659A (en) Automatic reliability test device and method for intelligent ammeters under circumstance of instant voltage interruption
CN104483567A (en) 500kV line relay protection device detection method and system
CN103227662A (en) Safety detection method and system of electric power communication equipment based on state control
CN104577942A (en) Monitoring device and monitoring method for real-time voltage of communication chip
CN104020376A (en) Three-remote automatic testing method for power distribution terminal
CN203732715U (en) Electric energy meter withstand voltage test device
CN204206183U (en) A kind of system of testing smart machine luminous power receiving sensitivity
CN203519784U (en) Testing device capable of realizing comprehensive testing for optimization board cards
CN111948478B (en) Power distribution terminal detection system and method under real working condition
CN103163402B (en) Relay protection device state monitoring apparatus based on secondary circuit and monitoring method
CN105071337A (en) Self-feedback intelligent earth leakage protection controlling device and method
CN210835189U (en) Arc fault and electric leakage fault detection protection system and charging pile
CN102426304A (en) Automatic tester of direct current microcomputer protective device and testing method thereof
CN103995207A (en) Three-remote automatic test device for power distribution terminal
CN209746015U (en) Frequency signal wiring switching device
CN107834311A (en) Network interface plug-in and pull-off device, network interface insert-pull detection system and method
CN203870470U (en) Feeder automation test system without network

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant