JPH1164402A - Electronic watthour meter and error adjustment method therefor - Google Patents

Electronic watthour meter and error adjustment method therefor

Info

Publication number
JPH1164402A
JPH1164402A JP9216110A JP21611097A JPH1164402A JP H1164402 A JPH1164402 A JP H1164402A JP 9216110 A JP9216110 A JP 9216110A JP 21611097 A JP21611097 A JP 21611097A JP H1164402 A JPH1164402 A JP H1164402A
Authority
JP
Japan
Prior art keywords
adjustment
power supply
value
power
hour meter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9216110A
Other languages
Japanese (ja)
Other versions
JP3330519B2 (en
Inventor
Katsuhiko Takahashi
勝彦 高橋
Original Assignee
Mitsubishi Electric Corp
三菱電機株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp, 三菱電機株式会社 filed Critical Mitsubishi Electric Corp
Priority to JP21611097A priority Critical patent/JP3330519B2/en
Publication of JPH1164402A publication Critical patent/JPH1164402A/en
Application granted granted Critical
Publication of JP3330519B2 publication Critical patent/JP3330519B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R21/00Arrangements for measuring electric power or power factor
    • G01R21/133Arrangements for measuring electric power or power factor by using digital technique

Abstract

PROBLEM TO BE SOLVED: To automatically impart adjustment power and calculate an error adjustment value while conventionally an imaginary load test power source 13 manually changed every time, the adjustment power is imparted and the error adjustment value is calculated so as to obtain a voltage, a current and a power factor for error adjustment. SOLUTION: When an adjustment start switch 23 has been pressed, a CPU 41 supplies prescribed adjustment power from the imaginary load test power source to a test power source device 10 by the program of an EPROM 22. Digitization is performed in a current A/D converter 42 and a voltage A/D converter 43, multiplication is performed in a multiplier 44, the multiplied value and a stipulated value are compared and an adjustment value in a prescribed error range is preserved in an adjustment register 65 in the case of rate load adjustment, for instance. In such a manner, the respective adjustments of a rate load, a light load, inter-element balance and the power factor, etc., are performed by sequentially switching a power source switching device 11 and imparting the prescribed adjustment power corresponding to the program of the EPROM 22.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION
【0001】[0001]
【発明の属する技術分野】この発明は、電子式電力量計
の計量を許容誤差内に調整する誤差調整に関するもの
で、特に誤差調整を自動化できるようにした電子式電力
量計およびその誤差調整方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an error adjustment for adjusting the measurement of an electronic watt-hour meter within an allowable error, and more particularly to an electronic watt-hour meter capable of automating the error adjustment and a method of adjusting the error. It is about.
【0002】[0002]
【従来の技術】図21は、例えば特開平6−27160
号公報に示された従来の電子式電力量計の誤差調整を示
す構成図であり、この調整は相対比較によるマスターメ
ータ法によって行われるものである。
2. Description of the Related Art FIG.
FIG. 1 is a configuration diagram showing an error adjustment of a conventional electronic watt-hour meter disclosed in Japanese Unexamined Patent Application Publication No. H11-157, and this adjustment is performed by a master meter method based on relative comparison.
【0003】図において、1は電圧、電流、位相を自在
に変化出力可能な電源装置からなる虚負荷試験電源、2
は基準計器であるマスターメータ、3は被調整電力量計
である。31は電力量計3内の電子回路で処理できるレ
ベルに入力電流に比例した値に変換する変流器(C
T)、32は入力電圧に比例した値に変換する変圧器
(VT)、33は入力電流と入力電圧とを乗算して電力
に比例した周波数に変換するW/Fコンバータである。
In FIG. 1, reference numeral 1 denotes an imaginary load test power supply comprising a power supply device capable of freely changing and outputting voltages, currents and phases.
Is a master meter which is a reference meter, and 3 is a watt-hour meter to be adjusted. Reference numeral 31 denotes a current transformer (C) that converts a value proportional to the input current to a level that can be processed by an electronic circuit in the watt hour meter 3.
T) and 32 are transformers (VT) for converting to a value proportional to the input voltage, and 33 is a W / F converter for multiplying the input current and the input voltage to convert the frequency to a frequency proportional to the power.
【0004】34はマスターメータ2からの電力に比例
した周波数とW/Fコンバータ33の出力を比較してそ
の差から補正値を算出する補正値演算部、35は算出さ
れた補正値を記憶する不揮発メモリからなる補正値記憶
部である。36はW/Fコンバータ33の出力を補正値
により補正する補正部、37は補正された電力に比例し
た周波数を分周する分周部、38は分周された電力に比
例した周波数を計数するカウンタ、39はカウンタ38
の値を電力量として表示する表示部である。
A correction value calculator 34 compares a frequency proportional to the power from the master meter 2 with the output of the W / F converter 33 and calculates a correction value from the difference, and 35 stores the calculated correction value. This is a correction value storage unit composed of a nonvolatile memory. 36 is a correction unit for correcting the output of the W / F converter 33 with a correction value, 37 is a frequency division unit for dividing the frequency proportional to the corrected power, and 38 is counting the frequency proportional to the divided power. Counter 39, counter 38
Is a display unit that displays the value of the power amount as an electric energy.
【0005】次に、従来の誤差調整の動作について説明
する。虚負荷試験電源1からマスターメータ2と被調整
電力量計3を電圧を並列に、電流を直列に接続してそれ
ぞれに同一のテスト電力を通電する。マスターメータ2
とW/Fコンバータ33の出力差がなくなるように補正
値が算出され、補正値記憶部35に記憶される。そして
爾後の電力量計量は記憶された補正値によりW/Fコン
バータ33の出力を補正しながら行われる。
Next, the operation of the conventional error adjustment will be described. The same test power is supplied to each of the imaginary load test power supply 1 from the imaginary load test power supply 1 by connecting the master meter 2 and the regulated watt-hour meter 3 in voltage and current in series. Master meter 2
The correction value is calculated so that the difference between the output of the W / F converter 33 and the correction value is eliminated, and is stored in the correction value storage unit 35. The subsequent measurement of the electric energy is performed while correcting the output of the W / F converter 33 by the stored correction value.
【0006】このような、電子式電力量計の誤差調整は
自動調整化されているが、例えば定格電圧、定格電流、
力率100%の1ポイントのみの調整で、また、多素子
の場合はバランス調整を加えた調整のみである。このよ
うな電力量計は、CT31、VT32の励磁電流、ワッ
トロスの影響により軽負荷時、低力率時に誤差が図22
に示すように相対的に大きくなり、精度の高い電力量計
を得るには定格負荷、軽負荷、力率特性の各ポイントで
の誤差補正調整を行う必要がある。
[0006] The error adjustment of the electronic watt-hour meter is automatically adjusted.
Adjustment is performed only at one point with a power factor of 100%, and in the case of multiple elements, adjustment is performed with balance adjustment. In such a watt-hour meter, an error occurs at a light load and a low power factor due to the effects of the excitation currents of CT31 and VT32 and watt loss.
As shown in (1), in order to obtain a highly accurate watt-hour meter, it is necessary to perform error correction adjustment at each point of rated load, light load, and power factor characteristics.
【0007】図23は例えば特開平6−258362号
公報に示された他の従来の電子式電力量計の回路ブロッ
ク図であり、シグマ・デルタ変調を用いた多素子(3素
子)のデジタル電子式電力量計である。図において、
1、31、32、38、39は上記の説明と同様のもの
である。4はデジタル電子式電力量計、40はCPU4
1を含んで構成される該デジタル電子式電力量計4の演
算制御部である。
FIG. 23 is a circuit block diagram of another conventional electronic watt-hour meter disclosed in, for example, Japanese Patent Application Laid-Open No. 6-258362, which shows a multi-element (three-element) digital electronic device using sigma-delta modulation. It is a watt-hour meter. In the figure,
1, 31, 32, 38 and 39 are the same as those described above. 4 is a digital electronic watt-hour meter, 40 is a CPU4
1 is a calculation control unit of the digital electronic watt-hour meter 4 including
【0008】42はシグマ・デルタ変調回路421、デ
ジタルローパスフィルタ422、各相の電流レジスタ4
23、424、425からなる電流A/D変換回路であ
る。43はシグマ・デルタ変調回路431、力率調整用
のシフトレジスタ432、デジタルローパスフィルタ4
33、各相の電圧レジスタ434、435、436から
なる電圧A/D変換回路である。
Reference numeral 42 denotes a sigma-delta modulation circuit 421, a digital low-pass filter 422, and a current register 4 for each phase.
23, 424, and 425. 43 is a sigma-delta modulation circuit 431, a shift register 432 for power factor adjustment, and a digital low-pass filter 4
33, a voltage A / D conversion circuit including voltage registers 434, 435, and 436 for each phase.
【0009】44は各相の電流値と電圧値を乗算して電
力値にする乗算器、45は各相の電力値を合算する加算
器、46はデジタルローパスフィルタ、47は軽負荷調
整加算器である。48はアキュムレータ、49はレジス
タ、50はマグニチュードコンパレータであり、電力の
集計値が所定基準値を超える毎にカウンタ38へ計数パ
ルスを出力する。51はバランス調整乗算器である。
Reference numeral 44 denotes a multiplier which multiplies the current value and voltage value of each phase to obtain a power value, 45 denotes an adder for summing the power values of each phase, 46 denotes a digital low-pass filter, and 47 denotes a light load adjustment adder. It is. 48 is an accumulator, 49 is a register, and 50 is a magnitude comparator, which outputs a counting pulse to the counter 38 every time the total value of the power exceeds a predetermined reference value. 51 is a balance adjusting multiplier.
【0010】そして、計量精度を高めるために、定格負
荷、軽負荷、力率特性を加味した各調整値を設定する力
率調整レジスタ61〜63、軽負荷調整レジスタ64、
定格基準値レジスタ65、素子間バランス調整レジスタ
66、67がそれぞれ設けられている。
In order to improve the weighing accuracy, power factor adjustment registers 61 to 63 for setting respective adjustment values in consideration of rated load, light load and power factor characteristics, light load adjustment register 64,
A rating reference value register 65 and inter-element balance adjustment registers 66 and 67 are provided, respectively.
【0011】次に電子式電力量の計量動作について説明
する。シグマ・デルタ変調回路421、431は演算制
御部40からのサンプリング周波fsにより入力された
電圧、電流を、A/D変換する。この時、スイッチSW
を同期して順次切り替えて各相別にデジタル値の電圧、
電流を求め、乗算器44にてデジタル値の電力値にして
各相の電力値を加算器45で合算する。
Next, the operation of measuring the electronic power amount will be described. The sigma-delta modulation circuits 421 and 431 perform A / D conversion on the voltage and current input at the sampling frequency fs from the arithmetic control unit 40. At this time, switch SW
Are switched in synchronization with each other to change the digital value voltage for each phase,
The current is obtained, the power value is converted into a digital value by the multiplier 44, and the power value of each phase is added by the adder 45.
【0012】各相を合算した電力値はマグニチュードコ
ンパレータ50で、電力の集計値が所定基準値を超える
毎に演算制御部40とカウンタ38へ計数パルスを出力
する。この計数パルスをカウンタ38を介して表示器3
9へ累計の電力量値が表示される。
The power value obtained by adding the phases is a magnitude comparator 50, which outputs a count pulse to the arithmetic control unit 40 and the counter 38 every time the total power value exceeds a predetermined reference value. This counting pulse is sent to the display 3 via the counter 38.
A total power value is displayed at 9.
【0013】次に、このような電子式電力量の計量精度
を許容誤差範囲内にするための調整作業手順について説
明する。調整作業手順としては、 粗調整の定格負荷調整(暫定F値設定) 多素子の電力量での素子間バランス調整(B2 値、B
3 値設定)、 定格負荷調整(F値設定)、 軽負荷調整(L値設定)、 力率調整(P1 値、P2 値、P3 値設定)の順序で行
われる。
Next, a description will be given of an adjustment operation procedure for making the measurement accuracy of the electronic power amount within the allowable error range. The adjustment procedure is as follows: the rated load adjustment of the rough adjustment (provisional F-value setting) The element-to-element balance adjustment (B2 value, B
3 values), rated load adjustment (F value setting), light load adjustment (L value setting), and power factor adjustment (P1, P2 value, P3 value setting).
【0014】(1)まず、最初は粗くてもよいが定格負
荷調整(暫定F値設定)として、全素子へ同時に定格電
流、定格電圧、力率100%が入力されるように虚負荷
試験電源1を切り替えて所定時間の電力量を付与する。
相線式・定格電圧・定格電流等によって定格パルス定数
が規定値として定められているので、定格パルス定数が
得られるようにF値を変化させながら数回の試行を行い
暫定的なF値を設定して定格基準値レジスタ65へ記憶
させる。
(1) First, an imaginary load test power source may be initially rough, but as a rated load adjustment (tentative F value setting), a rated current, a rated voltage and a power factor of 100% are simultaneously input to all the elements. 1 is switched to apply the electric energy for a predetermined time.
Since the rated pulse constant is determined as a specified value by the phase wire system, rated voltage, rated current, etc., several trials are performed while changing the F value to obtain the rated pulse constant, and the provisional F value is determined. It is set and stored in the rated reference value register 65.
【0015】(2)素子間バランス調整は虚負荷試験電
源1を定格電流、定格電圧、力率100%に設定して代
表の素子に所定時間の電力量を付与して、この間の計数
パルスW01を記憶させる。そして、別の素子に定格電
流、定格電圧、力率100%が入力されるように虚負荷
試験電源1を切り替えて所定時間の電力量を付与する。
(2) To adjust the balance between the elements, the imaginary load test power supply 1 is set to a rated current, a rated voltage, and a power factor of 100%, a given amount of electric power is applied to a representative element, and a counting pulse W01 during this time. Is stored. Then, the imaginary load test power supply 1 is switched so that the rated current, the rated voltage, and the power factor of 100% are input to another element, and the electric energy for a predetermined time is applied.
【0016】この次の素子の電力量計数パルスW02を知
り、バランス調整値B2 をB2 =W02/W01により求め
バランス調整レジスタ66に記憶させる。別の素子の出
力にバランス調整乗算器51にてバランス調整値B2 を
乗算させることで、同じ電力量で同じ数の計数パルスを
得るように素子間のバラツキをなくするバランス調整が
なされる。さらに、他の別の素子のバランス調整値B3
設定も同様になされるので説明を省略する。
Knowing the power amount counting pulse W02 of the next element, the balance adjustment value B2 is obtained by B2 = W02 / W01 and stored in the balance adjustment register 66. By multiplying the output of another element by the balance adjustment value B2 in the balance adjustment multiplier 51, balance adjustment is performed to eliminate variations among elements so as to obtain the same number of count pulses with the same power amount. Further, the balance adjustment value B3 of another different element
Since the setting is made in the same manner, the description is omitted.
【0017】(3)定格負荷調整(F値設定)は、全素
子へ同時に定格電流、定格電圧、力率100%が入力さ
れるように虚負荷試験電源1を切り替えて所定時間の電
力量を付与する。相線式・定格電圧・定格電流等によっ
て定格パルス定数が定められているので、定格パルス定
数が得られるようにF値を変化させながら数回の試行を
行いF値を設定して定格基準値レジスタ65へ記憶させ
る。
(3) In the rated load adjustment (F value setting), the imaginary load test power supply 1 is switched so that the rated current, the rated voltage and the power factor of 100% are simultaneously inputted to all the elements, and the electric energy for a predetermined time is reduced. Give. Since the rated pulse constant is determined by the phase-wire system, rated voltage, rated current, etc., several trials are performed while changing the F value to obtain the rated pulse constant, and the F value is set and the rated reference value is set. It is stored in the register 65.
【0018】(4)次の軽負荷調整(L値設定)は、例
えば電流を定格電流の1/10、定格電圧、力率1.0
0に虚負荷試験電源1を切り替え設定して、所定時間の
電力量を付与する。そして、定格パルス定数の1/10
のパルス数が得られるように数回の試行を行いL値を設
定して軽負荷調整レジスタ64へ記憶させる。
(4) In the next light load adjustment (L value setting), for example, the current is reduced to 1/10 of the rated current, the rated voltage and the power factor are set to 1.0.
The imaginary load test power supply 1 is switched and set to 0, and the electric energy for a predetermined time is given. And 1/10 of the rated pulse constant
The L value is set and stored in the light load adjustment register 64 by performing several trials so as to obtain the number of pulses.
【0019】(5)力率調整(P1 値、P2 値、P3 値
設定)は、各素子毎に実施される。1つの素子に定格電
流、定格電圧、力率0.50が入力されるように虚負荷
試験電源1を切り替えて所定時間の電力量を付与する。
この時のパルス数が1素子当たりの定格電流、定格電
圧、力率1.00のときのパルス数の1/2となるよう
に力率調整レジスタ61にシフト段数を設定する。他の
力率調整レジスタ62、63も同様に設定する。
(5) Power factor adjustment (setting of P1, P2, and P3 values) is performed for each element. The imaginary load test power supply 1 is switched so that a rated current, a rated voltage, and a power factor of 0.50 are input to one element, and an electric energy for a predetermined time is applied.
The number of shift stages is set in the power factor adjustment register 61 so that the number of pulses at this time is の of the number of pulses at the rated current, rated voltage, and power factor of 1.00 per element. The other power factor adjustment registers 62 and 63 are set similarly.
【0020】[0020]
【発明が解決しようとする課題】以上のような電子式電
力量計の誤差調整においては、調整対象の電圧、電流、
力率を変更する都度、虚負荷試験電源1を手動にて切り
替え設定して、調整電力を付与しそのときの出力パルス
数を基準数(規定値)と比較して誤差量を把握して、各
調整レジスタへの誤差調整値として設定して入力する必
要があった。
In the error adjustment of the electronic watt-hour meter as described above, the voltage, current,
Each time the power factor is changed, the imaginary load test power supply 1 is manually switched and set, the adjusted power is applied, and the number of output pulses at that time is compared with a reference number (specified value) to grasp the error amount. It was necessary to set and input an error adjustment value to each adjustment register.
【0021】この発明は、かかる問題点を解決するため
になされたものであり、調整の為の人間の感覚を必要と
せず,調整のスタートスイッチを押すだけで調整そのも
のを自動化することが可能な電子式電力量計及びひその
誤差調整方法を得ることを目的としいる。
The present invention has been made to solve such a problem, and does not require a human sense for adjustment, and the adjustment itself can be automated simply by pressing a start switch for adjustment. It is an object of the present invention to obtain an electronic watt-hour meter and a method of adjusting an error of the wrist.
【0022】[0022]
【課題を解決するための手段】[Means for Solving the Problems]
(1)この発明に係る電子式電力量計は、入力される電
圧・電流を電力量に比例した電力パルス数に変換するデ
ジタル乗算器と、このデジタル乗算器の電力パルス数変
換時の誤差を調整する各調整ポイントの調整値が保持さ
れる調整レジスタと、誤差調整プログラム及び各規定値
が格納されるメモリ装置と、上記誤差調整プログラムが
各調整ポイントへの順次移行と各調整ポイントに対応す
る電源種類の出力とを外部の試験電源装置へ指示する指
示手段と、この指示に対応する上記試験電源装置からの
出力を上記ディジタル乗算器へ入力して得られる所定時
間での電力パルス数と上記指示に対応する上記メモリ装
置の規定値とを比較し、この比較結果が所定の誤差範囲
内に収まるよう調整する調整値を導出して上記調整レジ
スタに書き込む調整値設定手段とを備えたものである。
(1) An electronic watt-hour meter according to the present invention includes a digital multiplier for converting an input voltage / current into a power pulse number proportional to a power amount, and an error in converting the power pulse number of the digital multiplier. An adjustment register that holds the adjustment value of each adjustment point to be adjusted; a memory device that stores an error adjustment program and each specified value; and the error adjustment program corresponds to a sequential shift to each adjustment point and each adjustment point. Instruction means for instructing the output of the power supply type to an external test power supply; and the number of power pulses in a predetermined time obtained by inputting the output from the test power supply corresponding to the instruction to the digital multiplier. An adjustment value for adjusting the comparison result to be within a predetermined error range by comparing the specified value of the memory device corresponding to the instruction with an adjustment value to be written to the adjustment register. It is obtained by a value setting means.
【0023】(2)この発明に係る電子式電力量計の誤
差調整方法は、上記(1)の電子式電力量計と、所定の
電源種類に切り替え出力する電源種類切替手段を具備し
た試験電源装置とを接続し、上記試験電源装置は上記電
子式電力量計の指示手段からの指示に対応する電源種類
に切り替えて出力し、この出力を受けた上記電子式電力
量計は電力パルス数に変換して調整値設定手段で調整値
を導出し設定するものである。
(2) An error adjusting method for an electronic watt-hour meter according to the present invention is directed to a test power supply comprising the electronic watt-hour meter of (1) and a power supply type switching means for switching and outputting a predetermined power supply type. Connected to the device, the test power supply device switches to a power supply type corresponding to the instruction from the instruction means of the electronic watt-hour meter, and outputs the same. The adjustment value is derived and set by the adjustment value setting means.
【0024】(3)また、上記(2)の電子式電力量計
の誤差調整方法において、複数個の電子式電力量計と試
験電源装置とを接続し、上記試験電源装置は所定の電源
種類に切り替え出力する電源種類切替手段と、この出力
を上記電子式電力量計1個ずつ供給するよう切り替える
供給先切替手段と、制御手段とを具備する試験電源装置
を用い、上記制御手段は上記電子式電力量計の指示手段
からの指示を受けて、いずれの電子式電力量計に対しど
の種の電源種類に切り替えるかを判断し、上記電源種類
の切り替えと上記供給先の切り替えとを組み合わせて、
上記複数個の電子式電力量計の全ての調整ポイントを調
整するものである。
(3) In the method for adjusting an error of an electronic watt-hour meter according to the above (2), a plurality of electronic watt-hour meters are connected to a test power supply device, and the test power supply device has a predetermined power supply type. A power supply type switching means for switching and outputting the output, a supply destination switching means for switching the output to supply the electronic wattmeter one by one, and a control power supply. In response to an instruction from the instruction unit of the watt-hour meter, it is determined which type of power supply to switch to which electronic watt-hour meter, and the switching of the power supply type and the switching of the supply destination are combined. ,
It adjusts all adjustment points of the plurality of electronic watt-hour meters.
【0025】(4)この発明に係る電子式電力量計は、
入力される電圧・電流を電力量に比例した電力パルス数
に変換するデジタル乗算器と、このデジタル乗算器の電
力パルス数変換時の誤差を調整する各調整ポイントの調
整値が保持される調整レジスタと、上記電力パルス数を
外部へ送信可能とする送信手段と、外部から入力された
調整値を上記調整レジスタに書き込む調整値設定手段と
を備えたものである。
(4) An electronic watt-hour meter according to the present invention comprises:
A digital multiplier that converts the input voltage / current into a power pulse number proportional to the amount of power, and an adjustment register that holds an adjustment value of each adjustment point that adjusts an error in converting the power pulse number of the digital multiplier. And an adjustment value setting means for writing the adjustment value input from the outside to the adjustment register.
【0026】(5)この発明に係る電子式電力量計の誤
差調整方法は、上記(4)の電子式電力量計と、所定の
電源種類に切り替え出力する電源種類切替手段を具備す
る試験電源装置と、演算装置とを接続し、上記演算装置
は上記電子式電力量計の誤差調整プログラムおよび各規
定値が格納されたメモリ装置と、上記誤差調整プログラ
ムが各調整ポイントへの順次移行と各調整ポイントに対
応する電源種類の出力とを上記試験電源装置へ指示する
指示手段と、上記試験電源装置からの出力を上記ディジ
タル乗算器へ入力して得られる所定時間での電力パルス
数と上記指示に対応する上記メモリ装置の規定値とを比
較し、この比較結果が所定の誤差範囲内に収まるよう調
整する調整値を導出する調整値導出手段とを具備する演
算装置を用い、上記試験電源装置は上記演算装置の指示
手段からの指示に対応する電源種類に切り替えて出力
し、この出力を受けた上記電子式電力量計は電力パルス
数に変換して上記演算装置へ出力し、この電力パルス数
を受けて上記演算装置の調整値導出手段は調整値を導出
し、この導出された調整値を上記電子式電力量計の調整
値設定手段で調整レジスタに書き込み設定するものであ
る。
(5) An error adjusting method for an electronic watt-hour meter according to the present invention is directed to a test power supply comprising the electronic watt-hour meter of (4) and power supply type switching means for switching and outputting a predetermined power supply type. A device and an arithmetic device are connected, the arithmetic device is a memory device in which an error adjustment program of the electronic watt-hour meter and each specified value are stored, and the error adjustment program sequentially shifts to each adjustment point. Instruction means for instructing the test power supply device on the output of the power supply type corresponding to the adjustment point; and the number of power pulses in a predetermined time obtained by inputting the output from the test power supply to the digital multiplier and the instruction And an adjustment value deriving means for deriving an adjustment value for adjusting the comparison result to fall within a predetermined error range. The test power supply unit switches to a power supply type corresponding to the instruction from the instruction unit of the arithmetic unit and outputs the power, and the electronic wattmeter that receives this output converts the number into power pulses and outputs the number to the arithmetic unit, In response to the number of power pulses, the adjustment value deriving means of the arithmetic unit derives an adjustment value, and writes and sets the derived adjustment value in an adjustment register by the adjustment value setting means of the electronic wattmeter. .
【0027】(6)また、上記(4)の電子式電力量計
と、所定の電源種類に切り替え出力する電源種類切替手
段を具備する試験電源装置と、演算装置と、基準計器と
を接続し、上記基準計器は上記電子式電力量計と同一の
ディジタル乗算器を有し、所定の入力に対し得られる電
力パルス数が基準値となるよう校正された基準計器を用
いると共に、上記演算装置は、上記電子式電力量計の誤
差調整プログラムおよび各規定値が格納されたメモリ装
置と、上記誤差調整プログラムが各調整ポイントへの順
次移行と各調整ポイントに対応する電源種類の出力とを
上記試験電源装置へ指示する指示手段と、上記試験電源
装置からの出力を上記電子式電力量計のディジタル乗算
器へ入力して得られる所定時間での電力パルス数と、上
記試験電源装置からの出力を上記基準計器のディジタル
乗算器へ入力して得られる所定時間での電力パルス数と
を比較し、この比較結果が所定の誤差範囲内に収まるよ
う調整する調整値を導出する調整値導出手段とを具備す
る演算装置を用い、上記試験電源装置は上記演算装置の
指示手段からの指示に対応する電源種類に切り替えて出
力し、この出力を受けた上記電子式電力量計および上記
基準機器は各々電力パルス数に変換して出力し、上記演
算装置は出力された上記両電力パルス数を比較してその
比較結果に対応する調整値を調整値導出手段で導出して
出力し、この出力された調整値を上記電子式電力量計の
調整値設定手段で調整レジスタに書き込み設定するもの
である。
(6) Also, the electronic watt-hour meter of (4), a test power supply device having a power supply type switching means for switching and outputting a predetermined power supply type, an arithmetic unit, and a reference meter are connected. The reference meter has the same digital multiplier as the electronic watt-hour meter, uses a reference meter calibrated so that the number of power pulses obtained for a predetermined input becomes a reference value, and the arithmetic unit is The memory device in which the error adjustment program of the electronic watt-hour meter and each specified value are stored, and the error adjustment program performs the above-described test by sequentially shifting to each adjustment point and outputting the power supply type corresponding to each adjustment point. Instruction means for instructing the power supply device; the number of power pulses in a predetermined time obtained by inputting the output from the test power supply device to the digital multiplier of the electronic wattmeter; Is output to the digital multiplier of the reference instrument and is compared with the number of power pulses in a predetermined time, and an adjustment value is derived to derive an adjustment value for adjusting the comparison result to fall within a predetermined error range. Means, the test power supply unit switches to a power supply type corresponding to an instruction from the instruction unit of the arithmetic unit, outputs the switched power supply, and receives the output, the electronic wattmeter and the reference device. Are respectively converted into the number of power pulses and output, and the arithmetic unit compares the two output power pulse numbers and derives and outputs an adjustment value corresponding to the comparison result by adjustment value deriving means. The adjusted value thus set is written and set in an adjustment register by the adjustment value setting means of the electronic wattmeter.
【0028】(7)また、上記(5)または(6)の電
子式電力量計の誤差調整方法において、試験電源装置は
演算装置を内蔵させた試験電源装置を用いるようにした
ものである。
(7) In the error adjusting method for an electronic watt-hour meter according to the above (5) or (6), the test power supply uses a test power supply having a built-in arithmetic unit.
【0029】[0029]
【発明の実施の形態】BEST MODE FOR CARRYING OUT THE INVENTION
実施の形態1.図1はこの発明の実施の形態1を示す電
子式電力量計の誤差調整システムの構成図である。図に
おいて、1、31、32、38〜51、61〜67は上
記従来装置の説明と同様のものである。
Embodiment 1 FIG. FIG. 1 is a configuration diagram of an error adjusting system for an electronic watt-hour meter according to Embodiment 1 of the present invention. In the figure, 1, 31, 32, 38 to 51 and 61 to 67 are the same as those in the description of the conventional apparatus.
【0030】10は試験電源装置であり、虚負荷試験電
源1、電源切替装置11、制御CPU12、通信インタ
ーフェイス13、記憶装置(ROM)14、タイマー1
5から構成されている。電源切替装置11は制御CPU
12からの指令により虚負荷試験電源1の電圧、電流、
位相、出力相を選択して試験電源を出力てきるようにな
っている。16は試験電源装置10の制御CPU12と
後述の電子式電力量計20のCPU41とを通信インタ
ーフェイス13と通信インターフェイス21を介して接
続する通信線である。
Reference numeral 10 denotes a test power supply, which is an imaginary load test power supply 1, a power supply switching device 11, a control CPU 12, a communication interface 13, a storage device (ROM) 14, and a timer 1.
5 is comprised. The power supply switching device 11 is a control CPU
12, the voltage and current of the imaginary load test power supply 1
The test power is output by selecting the phase and output phase. Reference numeral 16 denotes a communication line that connects the control CPU 12 of the test power supply device 10 and a CPU 41 of an electronic watt-hour meter 20 described later via the communication interface 13 and the communication interface 21.
【0031】20は電子式電力量計であり、電力量を計
量する電力計量部は図23に示した従来装置と同様であ
る。21は通信インターフェイス、22は電子式電力量
計20を調整する調整プログラム及び各設定される調整
値が記憶される不揮発記憶装置(EPROM)、23は
調整スタートスイツチである。
Reference numeral 20 denotes an electronic watt-hour meter, and a power meter for measuring the amount of power is the same as the conventional device shown in FIG. Reference numeral 21 denotes a communication interface, 22 denotes a nonvolatile storage device (EPROM) in which an adjustment program for adjusting the electronic watt-hour meter 20 and each set adjustment value are stored, and 23 denotes an adjustment start switch.
【0032】そして電力計量部は3個の変流器31と3
個の変圧器32が設けてあり、各電流と電圧から電力を
演算するR相、S相、T相の3組の演算素子が形成され
ている。3組の演算素子の使用数、接続の組み合わせに
より単相2線・単相3線・三相3線・三相4線式いずれ
の配電方式の電力量の計量は可能である。
The power metering section includes three current transformers 31 and 3
A plurality of transformers 32 are provided, and three sets of calculation elements of R phase, S phase, and T phase for calculating power from each current and voltage are formed. It is possible to measure the electric energy of any of the single-phase two-wire, single-phase three-wire, three-phase three-wire, and three-phase four-wire power distribution systems depending on the number of used three sets of arithmetic elements and the combination of connections.
【0033】電子式電力量の計量精度を許容誤差範囲内
にするための調整作業手順については従来装置と同様に
次のように行われる。 (1)粗調整の定格負荷調整(暫定F値設定) (2)多素子の電力量での素子間バランス調整(B2
値、B3 値設定)、 (3)定格負荷調整(F値設定)、 (4)軽負荷調整(L値設定)、 (5)力率調整(P1 値、P2 値、P3 値設定)の順序
で行われる。
An adjustment operation procedure for keeping the measurement accuracy of the electronic power amount within the allowable error range is performed as follows in the same manner as the conventional apparatus. (1) Rated load adjustment for coarse adjustment (provisional F-value setting) (2) Element-to-element balance adjustment with multi-element power (B2
Value, B3 value setting), (3) Rated load adjustment (F value setting), (4) Light load adjustment (L value setting), (5) Power factor adjustment (P1, P2 value, P3 value setting) Done in
【0034】図2〜図4はこの発明の実施の形態1の自
動調整の動作手順を示すフローチャートである。電子式
電力量計20の自動調整をこのフローチャートに沿って
説明する。図示していない専用コネクタにより、試験電
源装置10の出力を電子式電力量計20の端子へ接続す
ると同時に通信インターフェイス13、21間を通信線
16で接続する。この状態で調整スタートスイツチ23
を押下すると、調整スタートスイツチ23からの押下信
号を受けて、CPU41はEPROM22に収納されて
いる調整プログラムを実行するところから調整が開始さ
れる。以下、フローチャートに沿って説明する。
FIGS. 2 to 4 are flowcharts showing the operation procedure of the automatic adjustment according to the first embodiment of the present invention. The automatic adjustment of the electronic watt-hour meter 20 will be described with reference to this flowchart. The output of the test power supply 10 is connected to the terminal of the electronic watt-hour meter 20 by a dedicated connector (not shown), and the communication interfaces 13 and 21 are connected by the communication line 16 at the same time. In this state, the adjustment start switch 23
Is pressed, the CPU 41 receives a press signal from the adjustment start switch 23, and the CPU 41 starts the adjustment from the point of executing the adjustment program stored in the EPROM 22. Hereinafter, description will be given along a flowchart.
【0035】(1)まず、EPROM22に予め記憶さ
れている各調整初期値を、力率調整レジスタ61〜6
3、軽負荷調整レジスタ64、定格基準値レジスタ6
5、素子間バランス調整レジスタ66、67へ読み込
む。また、調整対象電力量計の定格電流、定格電圧、相
線方式により定められる定格定数パルス数値WK 、力率
定数パルス数値WKPが選択入力される(ステップ20
1)。なお、各調整レジスタ内にはデジタル処理に適し
たコードで入力されている。
(1) First, the initial adjustment values stored in advance in the EPROM 22 are stored in the power factor adjustment registers 61 to 6.
3, light load adjustment register 64, rated reference value register 6
5. Read into the element balance adjustment registers 66 and 67. Further, a rated constant pulse value WK and a power factor constant pulse value WKP determined by the rated current, the rated voltage, and the phase wire method of the watt-hour meter to be adjusted are selectively inputted (step 20).
1). Each adjustment register is input with a code suitable for digital processing.
【0036】(2)最初に粗調整の定格負荷調整が行わ
れる。CPU41が試験電源装置10へR相、S相、T
相へ定格電流、定格電圧、力率1.00相当の虚負荷電
力の通電を指令する(ステップ202)。 (3)制御CPU12は電源切替装置11のタップ切替
により定格電流、定格電圧、力率1.00の電力を全相
へ一定時間例えば10秒間通電して、通電終了信号を返
信する(ステップ101、102)。
(2) First, the rated load adjustment of the rough adjustment is performed. The CPU 41 supplies the R, S, and T phases to the test power supply 10.
The phase is instructed to supply a rated current, a rated voltage, and an imaginary load power equivalent to a power factor of 1.00 (step 202). (3) The control CPU 12 supplies power having a rated current, a rated voltage, and a power factor of 1.00 to all the phases for a certain period of time, for example, 10 seconds by the tap switching of the power supply switching device 11, and returns an energization end signal (step 101, 102).
【0037】(4)電子式電力量計20はこの間でカウ
ントされた電力パルス数W0 を読み取る(ステップ20
3)。 (5)そして、ステップ201で予め読み込まれた定格
定数パルス数値WK との対比を行い、D=W0 /WK を
求め、Dが1.0を中心とした所定範囲(許容誤差範
囲)かどうかを判断する(ステップ204)。なお、こ
の場合の許容誤差は粗調整であるので、その値は大きく
しておく。
(4) The electronic watt-hour meter 20 reads the number of power pulses W0 counted during this period (step 20).
3). (5) Then, a comparison is made with the rated constant pulse value WK read in advance in step 201 to obtain D = W0 / WK, and it is determined whether D is within a predetermined range (permissible error range) centered at 1.0. A judgment is made (step 204). Since the allowable error in this case is a coarse adjustment, its value is set large.
【0038】(6)Dが所定範囲外のときは、定格基準
値レジスタ65の値(F)をD=1.0となる方向へC
PU41が移行設定する(ステップ205)。 (7)Dの値が所定範囲内に入るまでステップ101、
102、202〜205を繰り返し、Dの値が所定範囲
内に収まると、素子間のバランス調整へ進む。
(6) When D is out of the predetermined range, the value (F) of the rated reference value register 65 is increased in the direction where D = 1.0.
The PU 41 makes a transition setting (step 205). (7) Step 101 until the value of D falls within the predetermined range;
102, 202 to 205 are repeated, and when the value of D falls within a predetermined range, the process proceeds to balance adjustment between elements.
【0039】(8)素子間のバランス調整を実行するた
め、CPU41は通信線16を通じて試験電源装置10
へR相だけへ定格電流、定格電圧、力率1.00相当の
虚負荷電力の通電を指令する(ステップ206)。 (9)R相への虚負荷電力の通電を指令を受けた制御C
PU12はROM14に記憶されている電源切替装置1
1のタップの切替により例えば、定格電流30A、定格
電圧200V、力率1.00の虚負荷電力をR相へ通電
する(ステップ103)。
(8) To execute the balance adjustment between the elements, the CPU 41 transmits the test power supply 10 through the communication line 16.
Only the R-phase is instructed to supply a rated current, a rated voltage, and an imaginary load power equivalent to a power factor of 1.00 (step 206). (9) Control C instructed to supply imaginary load power to R phase
PU 12 is a power supply switching device 1 stored in ROM 14
By switching one tap, for example, imaginary load power having a rated current of 30 A, a rated voltage of 200 V, and a power factor of 1.00 is supplied to the R phase (step 103).
【0040】(10)タイマー14により電力通電を一
定時間、例えば10秒間供給したなら、制御CPU12
は通信線16を通じて電子式電力量計20へ通電終了信
号を返信する(ステップ104)。 (11)電子式電力量計20では電力通電中にカウント
された電力パルス数WRを一時記憶させる(ステップ2
07)。
(10) If power is supplied for a certain period of time, for example, 10 seconds by the timer 14, the control CPU 12
Returns an energization end signal to the electronic watt-hour meter 20 through the communication line 16 (step 104). (11) The electronic watt-hour meter 20 temporarily stores the number of power pulses WR counted during power supply (step 2).
07).
【0041】(12)次に、CPU41は試験電源装置
10へS相だけへ定格電流、定格電圧、力率1.00相
当の虚負荷電力の通電を指令する(ステップ208)。 (13)制御CPU12は電源切替装置11のタップ切
替により定格電流30A、定格電圧200V、力率1.
00の電力をS相へ一定時間例えば10秒間通電して、
通電終了信号を返信する(ステップ105、106)。
(12) Next, the CPU 41 instructs the test power supply 10 to supply only the S phase with a rated current, a rated voltage, and an imaginary load power equivalent to a power factor of 1.00 (step 208). (13) The control CPU 12 switches the tap of the power supply switching device 11 to a rated current of 30 A, a rated voltage of 200 V, and a power factor of 1.
00 power is supplied to the S phase for a certain time, for example, 10 seconds,
An energization end signal is returned (steps 105 and 106).
【0042】(14)電子式電力量計20はこの間でカ
ウントされた電力パルス数WS を読み取り、上記で一時
記憶されているR相の電力パルスWR 数と対比して、D
=WS/WR を求め、Dが1.0を中心とした所定範囲
(許容誤差範囲)かどうかを判断する(ステップ20
9、210)。
(14) The electronic watt-hour meter 20 reads the number of power pulses WS counted during this time and compares the number of power pulses WR temporarily stored with the number of power pulses WR of the R phase to obtain D
= WS / WR, and it is determined whether D is within a predetermined range (permissible error range) centered at 1.0 (step 20).
9, 210).
【0043】(15)Dが所定範囲外のときは、バラン
ス調整レジスタ66の値(B2 )をD=1.0となる方
向へCPU41が移行設定する(ステップ211)。こ
こで、D=(WR −WS )/WR として求めて、Dがゼ
ロを中心とした所定範囲かどうかを判断してもよい。 (16)Dの値が所定範囲内に入るまでステップ10
5、106、208〜211を繰り返し、Dの値が所定
範囲内に収まると、T相のバランス調整へ進む。
(15) If D is out of the predetermined range, the CPU 41 shifts the value (B2) of the balance adjustment register 66 in the direction where D = 1.0 (step 211). Here, D = (WR-WS) / WR may be obtained to determine whether D is within a predetermined range centered on zero. (16) Step 10 until the value of D falls within the predetermined range
5, 106, and 208 to 211 are repeated, and when the value of D falls within a predetermined range, the process proceeds to T-phase balance adjustment.
【0044】(17)CPU41は試験電源装置10へ
T相だけへ定格電流、定格電圧、力率1.00相当の虚
負荷電力の通電を指令する(ステップ212)。 (18)以降、上記と同様手順でD=WT /WR を所定
範囲内に収めバランス調整が終了し、定格負荷調整へ進
む(ステップ107、108、212〜215)。
(17) The CPU 41 instructs the test power supply device 10 to supply the rated current, the rated voltage, and the imaginary load power equivalent to the power factor of 1.00 to only the T phase (step 212). (18) Thereafter, D = WT / WR is set within a predetermined range by the same procedure as described above, balance adjustment is completed, and the process proceeds to rated load adjustment (steps 107, 108, 212 to 215).
【0045】(19)定格負荷調整では、CPU41が
試験電源装置10へR相、S相、T相へ定格電流、定格
電圧、力率1.00相当の虚負荷電力の通電を指令する
(ステップ216)。 (20)制御CPU12は電源切替装置11のタップ切
替により定格電流、定格電圧、力率1.00の電力を全
相へ一定時間例えば10秒間通電して、通電終了信号を
返信する(ステップ109、110)。
(19) In the rated load adjustment, the CPU 41 instructs the test power supply device 10 to supply the R-phase, S-phase, and T-phases with the rated current, the rated voltage, and the imaginary load power equivalent to the power factor of 1.00 (step S1). 216). (20) The control CPU 12 supplies the power of the rated current, the rated voltage, and the power factor of 1.00 to all the phases for a certain period of time, for example, 10 seconds by the tap switching of the power supply switching device 11, and returns an energization end signal (step 109, 110).
【0046】(21)電子式電力量計20はこの間でカ
ウントされた電力パルス数W0 を読み取る(ステップ2
17)。 (22)そして、ステップ201で予め読み込まれた定
格定数パルス数値WK との対比を行い、D=W0 /WK
を求め、Dが1.0を中心とした所定範囲(許容誤差範
囲)かどうかを判断する(ステップ218)。
(21) The electronic watt-hour meter 20 reads the number of power pulses W0 counted during this time (step 2).
17). (22) Then, a comparison is made with the rated constant pulse value WK read in advance in step 201, and D = W0 / WK
Is determined, and it is determined whether D is within a predetermined range (permissible error range) centered at 1.0 (step 218).
【0047】(23)Dが所定範囲外のときは、定格基
準値レジスタ65の値(F)をD=1.0となる方向へ
CPU41が移行設定する(ステップ219)。 (24)Dの値が所定範囲内に入るまでステップ10
9、110、216〜219を繰り返し、Dの値が所定
範囲内に収まると、力率調整へ進む。
(23) When D is out of the predetermined range, the CPU 41 shifts the value (F) of the rated reference value register 65 in the direction where D = 1.0 (step 219). (24) Step 10 until the value of D falls within the predetermined range.
9, 110, 216 to 219 are repeated, and when the value of D falls within a predetermined range, the process proceeds to power factor adjustment.
【0048】(25)力率調整では、CPU41が通信
線16を通じて試験電源装置10へR相のみに定格電
流、定格電圧、力率0.50相当の虚負荷電力の通電を
指令する(ステップ220)。 (26)制御CPU12は電源切替装置11のタップ切
替により定格電流、定格電圧、力率0.50の電力をR
相へ一定時間例えば10秒間通電して、通電終了信号を
返信する(ステップ111、112)。
(25) In the power factor adjustment, the CPU 41 instructs the test power supply 10 through the communication line 16 to supply only the R phase with the rated current, the rated voltage, and the imaginary load power equivalent to the power factor of 0.50 (step 220). ). (26) The control CPU 12 changes the power of the rated current, the rated voltage and the power of 0.50 to R
The phase is energized for a predetermined time, for example, 10 seconds, and an energization end signal is returned (steps 111 and 112).
【0049】(27)電子式電力量計20はこの間でカ
ウントされた電力パルス数WPRを読み取る(ステップ2
21)。 (28)そして、ステップ201で予め読み込まれた力
率定数パルス数値WPKとの対比を行う。D=WPR/WPK
を求め、Dが1.0を中心とした許容誤差範囲かどうか
を判断する(ステップ218)。
(27) The electronic watt-hour meter 20 reads the number of power pulses WPR counted during this time (step 2).
21). (28) Then, in step 201, a comparison is made with the power factor constant pulse numerical value WPK read in advance. D = WPR / WPK
Is determined, and it is determined whether D is within an allowable error range centered at 1.0 (step 218).
【0050】(29)Dが許容誤差範囲外のときは、力
率調整レジスタ61(P1 )をD=1.0となる方向へ
CPU41が移行設定する(ステップ223)。 (30)Dの値が許容誤差範囲内に入るまでステップ1
11、112、220〜223を繰り返し、Dの値が許
容誤差範囲内に収まると、S相の力率調整へ進む。 (31)以下、同様の処理によりS相、T相の力率調整
を行い、軽負荷調整へ進む(113、114、224〜
227、115、116、228〜231)。
(29) If D is outside the allowable error range, the CPU 41 shifts the power factor adjustment register 61 (P1) in the direction where D = 1.0 (step 223). (30) Step 1 until the value of D falls within the allowable error range
11, 112, 220 to 223 are repeated, and when the value of D falls within the allowable error range, the process proceeds to S-phase power factor adjustment. (31) Hereinafter, the power factor adjustment of the S phase and the T phase is performed by the same processing, and the process proceeds to the light load adjustment (113, 114, 224 ~).
227, 115, 116, 228-231).
【0051】(32)軽負荷調整では、CPU41が通
信線16を通じて試験電源装置10へR相、S相、T相
へ定格の10%電流、定格電圧、力率1.00相当の虚
負荷電力の通電を指令する(ステップ232)。 (33)制御CPU12は電源切替装置11を切替えて
定格の10%電流、定格電圧、力率1.00の電力を全
相へ一定時間例えば10秒間通電して、通電終了信号を
返信する(ステップ117、118)。
(32) In the light load adjustment, the CPU 41 supplies the test power supply 10 to the R, S, and T phases through the communication line 16 with the imaginary load power equivalent to the rated 10% current, the rated voltage, and the power factor 1.00. (Step 232). (33) The control CPU 12 switches the power supply switching device 11 to supply a power of 10% of the rated current, the rated voltage and the power factor of 1.00 to all the phases for a predetermined time, for example, 10 seconds, and returns an energization end signal (step). 117, 118).
【0052】(34)電子式電力量計20はこの間でカ
ウントされた電力パルス数WL を読み取る(ステップ2
33)。 (35)そして、予め読み込まれている定格定数パルス
数値WK との対比を行い、D=10*WL /WK を求
め、Dが1.0を中心とした許容誤差範囲かどうかを判
断する(ステップ234)。
(34) The electronic watt-hour meter 20 reads the number of power pulses WL counted during this period (step 2).
33). (35) Then, a comparison is made with the previously read rating constant pulse numerical value WK to obtain D = 10 * WL / WK, and it is determined whether or not D is within an allowable error range centered at 1.0 (step). 234).
【0053】(36)Dが所定範囲外のときは、軽負荷
調整レジスタ64の値(L)をD=1.0となる方向へ
CPU41が移行設定する(ステップ235)。 (37)Dの値が所定範囲内に入るまでステップ11
7、118、216〜235を繰り返し、Dの値が許容
誤差範囲内に収まると、誤差調整完了を通知し、誤差調
整完了の表示をする(236、119)。
(36) If D is outside the predetermined range, the CPU 41 shifts and sets the value (L) of the light load adjustment register 64 in the direction where D = 1.0 (step 235). (37) Step 11 until the value of D falls within the predetermined range
7, 118, 216 to 235 are repeated, and when the value of D falls within the allowable error range, completion of error adjustment is notified, and completion of error adjustment is displayed (236, 119).
【0054】この実施の形態1においては、電力通電時
間を一律10秒間としたが、これは電力量計の精度か
ら、例えば精度0.1%の計器では誤差判断を計算する
基準パルス数が最低1000個、精度0.01%のもの
では10000個のパルス数が得られる時間であればよ
い。従って、定各負荷調整と力率調整、軽負荷調整で通
電時間を適宜にして、この通電時間に見合った、定格定
数パルス数値WK 、力率定数パルス数値WPK、軽負荷定
数パルス数値を選択すればよい。
In the first embodiment, the power supply time is uniformly set to 10 seconds. However, this is based on the accuracy of the watt hour meter. In the case of 1000 pulses and the accuracy of 0.01%, it suffices that the time is such that 10,000 pulses can be obtained. Therefore, by setting the energizing time appropriately for each load adjustment, power factor adjustment, and light load adjustment, the rated constant pulse number WK, the power factor constant pulse number WPK, and the light load constant pulse number corresponding to the energizing time can be selected. I just need.
【0055】また、電子式電力量計20側でパルス数と
その計量時間から所定の精度の得られる時間当たりのパ
ルス数(計数率)を計算し、所定の精度になれば電力通
電を停止するようにしてもよい。また、上記では軽負荷
調整を定格の10%電流で説明したが5%電流で実施し
てもよい。
Further, the electronic watt-hour meter 20 calculates the number of pulses per time (counting rate) at which a predetermined accuracy can be obtained from the number of pulses and the measuring time thereof, and stops the power supply when the predetermined accuracy is reached. You may do so. In the above description, the light load adjustment has been described with the rated 10% current, but may be performed with the 5% current.
【0056】実施の形態2.この実施の形態は、電子式
電力量計が個々に自己の調整プログラム及び試験電源装
置10への命令等をEPROM22に保持させている
が、このEPROM22の保持プログラムが同一である
電力量計を複数個調整することで、量産性を向上するも
のである。
Embodiment 2 In this embodiment, the electronic watt-hour meter individually stores its own adjustment program and instructions to the test power supply device 10 in the EPROM 22. A plurality of watt-hour meters having the same EPROM 22 holding program are stored. By adjusting the number individually, mass productivity is improved.
【0057】図5はこの発明の実施の形態2を示す電子
式電力量計の誤差調整システムの構成図である。図にお
いて、電子式電力量計20は図1と同様のもので、複数
個が試験電源装置10と接続スイッチ101を介して接
続されている。試験電源装置10の17は制御CPUで
制御される供給先切替手段で、切替命令を送出して接続
スイッチ101をシーケンス制御する。
FIG. 5 is a configuration diagram of an error adjustment system for an electronic watt-hour meter according to a second embodiment of the present invention. In the figure, an electronic watt-hour meter 20 is the same as that in FIG. 1, and a plurality of electronic watt-hour meters are connected to a test power supply device 10 via a connection switch 101. Reference numeral 17 of the test power supply 10 is a supply destination switching unit controlled by the control CPU, and sends out a switching instruction to perform sequence control of the connection switch 101.
【0058】このシーケンス制御は、接続スイッチ10
1の電圧側R,S,Tは調整中は常にONしておき、電
子式電力量計20への動作用電源を供給し、調整が完了
するとOFFとする。接続スイッチ101の電流側R,
S,Tは調整対象となる電子式電力量計のみ接続する。
This sequence control is performed by the connection switch 10
The voltage sides R, S, and T of 1 are always turned on during adjustment, supply operating power to the electronic watt-hour meter 20, and turned off when the adjustment is completed. The current side R of the connection switch 101,
For S and T, only the electronic watt-hour meter to be adjusted is connected.
【0059】図6は調整手順のフローチャートで、複数
個の電子式電力量計を1個ずつ調整するフローである。
また、図7、図8は別の調整手順のフローチャートで、
複数個の電子式電力量計の同一調整項目を全ての電子式
電力量計で実行し、一つの調整項目が済むと次の調整項
目の調整を全ての電子式電力量計に対して実行するよう
にするフローである。
FIG. 6 is a flowchart of the adjustment procedure, which is a flow for adjusting a plurality of electronic watt-hour meters one by one.
7 and 8 are flowcharts of another adjustment procedure.
The same adjustment item of a plurality of electronic watt-hour meters is executed by all electronic watt-hour meters, and when one adjustment item is completed, the adjustment of the next adjustment item is executed for all the electronic watt-hour meters. This is the flow to be performed.
【0060】まず、図6のフローチャートで説明する。 (1)供給先切替手段17からの接続命令により、n個
の電子式電力量計20の内、1番目の電子式電力量計2
0へ接続し、初期値の読み込みを行う(161、26
1、262)。
First, a description will be given with reference to the flowchart of FIG. (1) The first electronic watt-hour meter 2 out of the n electronic watt-hour meters 20 in response to a connection command from the supply destination switching means 17
0 and read the initial values (161, 26)
1, 262).
【0061】(2)次に、図2〜図4のステップ101
からステップ119、ステップ202からステップ23
4が「Y」になるまで実行する(162、263)。こ
れは1個分の調整を全て実行することである。 (3)1番目の電子式電力量計20の調整が完了する
と、調整完了信号を送出し、試験電源装置10はこの信
号を受信する(264、163)。
(2) Next, step 101 in FIGS.
To step 119, steps 202 to 23
The process is executed until 4 becomes “Y” (162, 263). This is to execute all adjustments for one. (3) When the adjustment of the first electronic watt-hour meter 20 is completed, an adjustment completion signal is transmitted, and the test power supply device 10 receives this signal (264, 163).
【0062】(4)1番目の調整であるので最初のステ
ップ161に返る(164)。 (5)このようにしてn番目の電子式電力量計20の調
整が完了するまで、ステップ161〜164、ステップ
261〜264を繰り返し実行し、全ての調整作業を完
了する。
(4) Since the adjustment is the first adjustment, the process returns to the first step 161 (164). (5) Steps 161 to 164 and steps 261 to 264 are repeatedly executed until the adjustment of the n-th electronic watt-hour meter 20 is completed in this way, and all the adjustment operations are completed.
【0063】上記のように、1個ずつ電子式電力量計の
調整を完了していく場合は、1個で連続した調整が行わ
れることになり、調整条件が安定して行われるメリット
がある。
As described above, when the adjustment of the electronic watt-hour meter is completed one by one, continuous adjustment is performed by one, and there is an advantage that the adjustment condition is stably performed. .
【0064】次に、図7、図8のフローチャートの調整
手順を説明する。 (1)供給先切替手段17からの接続命令により、n個
の電子式電力量計20の内、1番目の電子式電力量計2
0へ接続し、初期値の読み込みを行う(171、27
1、272)。
Next, the adjustment procedure in the flowcharts of FIGS. 7 and 8 will be described. (1) The first electronic watt-hour meter 2 out of the n electronic watt-hour meters 20 in response to a connection command from the supply destination switching means 17
0 and read the initial value (171, 27)
1, 272).
【0065】(2)次に、図2のステップ101〜10
2、ステップ202〜205の「粗調整の定格負荷調整
(暫定F値設定)」を実行する。 (3)接続スイッチ101の切り替えと、上記(1)
(2)とを繰り返し、n個の全ての「初期値読み込みお
よび粗調整の定格負荷調整」を実行する(ステップ17
1〜173、271〜273)。なお、この場合ステッ
プ171、271、272の「初期値読み込み」を全て
の電子式電力量計に行った後、ステップ172、273
の「粗調整の定格負荷調整」を全ての電子式電力量計に
対して行うようにしてもよい。
(2) Next, steps 101 to 10 in FIG.
2. Execute "rated load adjustment for coarse adjustment (setting of provisional F value)" in steps 202 to 205. (3) Switching of the connection switch 101 and the above (1)
(2) is repeated, and all of the n “rated load adjustments for initial value reading and coarse adjustment” are executed (step 17).
1-173, 271-273). In this case, after the “initial value reading” of steps 171, 271, and 272 is performed on all the electronic watt-hour meters, steps 172 and 273
"Rated load adjustment for coarse adjustment" may be performed for all electronic watt-hour meters.
【0066】(4)次に、ステップ174〜176、ス
テップ274〜275を実行する。このステップは、素
子の間のバランス調整を行うもので、R相の電力パルス
数WRをカウントする。 (5)上記と同様にして、試験電源装置10は、供給先
切替手段17からi=1〜nまで接続指令の送出を繰り
返しながら、図2〜図4のステップ105〜118を実
行し、電子式電力量計20は、接続スイッチ101によ
るi=1〜nまでの接続を繰り返しながら図2〜図5の
ステップ208からステップ234が「Y」になるまで
実行する。
(4) Next, steps 174 to 176 and steps 274 to 275 are executed. In this step, the balance between the elements is adjusted, and the number of power pulses WR of the R phase is counted. (5) In the same manner as described above, the test power supply device 10 executes steps 105 to 118 in FIGS. 2 to 4 while repeatedly transmitting the connection command from the supply destination switching unit 17 to i = 1 to n. The formula watt-hour meter 20 executes steps 208 to 234 in FIGS. 2 to 5 until “Y” is reached while repeating the connection from i = 1 to n by the connection switch 101.
【0067】(6)各電子式電力量計20は調整が完了
すると1番目からn番目までの調整完了信号を順次送信
するので、試験電源装置10はこの信号を受信して、n
番目の調整完了を受信すると、調整完了表示を行う(ス
テップ276、177〜179)。
(6) Since each electronic watt-hour meter 20 transmits the first to n-th adjustment completion signals sequentially after the adjustment is completed, the test power supply 10 receives this signal and
When the completion of the adjustment is received, an adjustment completion display is performed (steps 276, 177 to 179).
【0068】上記調整手順は全調整工程を1台の電子式
電力量計毎に完了させているが、試験電源装置に接続さ
れた複数台の電子式電力量計を各調整工程毎に完了させ
てもよい。その実施の形態を図7、図8のフローチャー
トで説明する。このフローチャートの調整手順は、各ス
テップ毎に複数台の調整を行うので図6のフローように
1台ずつ調整するよりも短時間で調整することが可能と
なる。
In the above adjustment procedure, all the adjustment steps are completed for each electronic watt-hour meter, but a plurality of electronic watt-hour meters connected to the test power supply are completed for each adjustment step. You may. The embodiment will be described with reference to the flowcharts of FIGS. In the adjustment procedure of this flowchart, the adjustment of a plurality of units is performed for each step, so that the adjustment can be performed in a shorter time than the adjustment of each unit as in the flow of FIG.
【0069】上記のように、この実施の形態2は同一仕
様の電子式電力量計を複数個同時に調整することができ
る。
As described above, in the second embodiment, a plurality of electronic watt-hour meters having the same specifications can be adjusted simultaneously.
【0070】実施の形態3.上記実施の形態1の構成
は、電子式電力量計が個々に自己の調整プログラム及び
試験電源装置10への命令等をEPROM22に保持さ
せているため、試験電源装置10が1台に対して、電子
式電力量計は1台しか同時に調整作業ができなく量産性
に欠ける。また、調整プログラム、初期設定値が変更と
なった場合には、EPROM22の取り替え、または書
き換えを電子式電力量計に施さねばならず不経済であっ
た。該実施の形態3はこの点を改良するものである。
Embodiment 3 In the configuration of the first embodiment, since the electronic watt-hour meter individually stores its own adjustment program and instructions to the test power supply device 10 in the EPROM 22, the test power supply device 10 Only one electronic watt-hour meter can be adjusted at the same time and lacks mass productivity. Further, when the adjustment program and the initial set value are changed, the EPROM 22 must be replaced or rewritten to the electronic watt-hour meter, which is uneconomical. The third embodiment improves this point.
【0071】図9は、この発明の実施の形態3を示す電
子式電力量計の自動調整の接続図である。図において、
1、10〜16、31、32、38〜41、61〜67
は上記実施の形態1の説明と同様のものである。69は
既に説明した電流A/D変換回路42、電圧A/D変換
回路43、乗算器44、加算器45、マグニチュードコ
ンパレータ50等からなる電力演算回路であり、図及び
説明を簡素化するための符号である。
FIG. 9 is a connection diagram for automatic adjustment of an electronic watt-hour meter according to Embodiment 3 of the present invention. In the figure,
1, 10 to 16, 31, 32, 38 to 41, 61 to 67
Is the same as described in the first embodiment. Reference numeral 69 denotes a power operation circuit including the current A / D conversion circuit 42, the voltage A / D conversion circuit 43, the multiplier 44, the adder 45, the magnitude comparator 50, and the like, which have already been described. Sign.
【0072】70はパーソナルコンピュータ(パソコ
ン)である。71はパソコン70のメインCPU、72
はメモリ装置、73は通信インタフェイス、74はタイ
マー、75はCRT、76は操作キーボードである。通
信インタフェイス73は通信線16により試験電源装置
10の通信インタフェイス13及び電子式電力量計20
の通信インタフェイス21と接続され、相互に命令コマ
ンド、データのやり取りが可能になっている。なお、デ
ィスプレイは図示していないがパソコン10に接続され
ている。
Reference numeral 70 denotes a personal computer (personal computer). 71 is a main CPU of the personal computer 70;
Is a memory device, 73 is a communication interface, 74 is a timer, 75 is a CRT, and 76 is an operation keyboard. The communication interface 73 is connected to the communication interface 13 of the test power supply 10 and the electronic watt-hour meter 20 by the communication line 16.
And the command interface and the data can be exchanged with each other. Although not shown, the display is connected to the personal computer 10.
【0073】また、パソコン70の通信インタフェイス
73は複数の電子式電力量計20の通信インタフェイス
21と接続可能であり、調整される電子式電力量計20
は複数台(n台)が並列接続され、それぞれがパソコン
70と命令コマンド、データのやり取りが可能になって
いる。
The communication interface 73 of the personal computer 70 can be connected to the communication interface 21 of the plurality of electronic watt-hour meters 20 so that the electronic watt-hour meter 20 to be adjusted can be connected.
Are connected in parallel, and each of them is capable of exchanging command commands and data with the personal computer 70.
【0074】メモリ装置72には誤差調整プログラム及
び力率調整レジスタ61〜63、軽負荷調整レジスタ6
4、定格基準値レジスタ65、素子間バランス調整レジ
スタ66、67、定格定数パルス数値WK 、力率定数パ
ルス数値WKPへ読み込む各調整初期値が記憶されてい
る。
The memory device 72 has an error adjustment program and power factor adjustment registers 61 to 63, a light load adjustment register 6
4. Each adjustment initial value to be read into the rated reference value register 65, the inter-element balance adjustment registers 66 and 67, the rated constant pulse value WK, and the power factor constant pulse value WKP is stored.
【0075】図示していない専用コネクタにより、試験
電源装置10の出力を電子式電力量計20の端子へ接続
すると同時に通信インターフェイス13、21、73間
を通信線16で接続する。この状態で操作キーボード7
6から調整開始命令を入力すると、図10〜図13のフ
ローチャートに沿って調整作業が実行される。
The output of the test power supply 10 is connected to the terminal of the electronic watt-hour meter 20 by a dedicated connector (not shown), and at the same time, the communication interfaces 13, 21 and 73 are connected by the communication line 16. In this state, the operation keyboard 7
When an adjustment start command is input from Step 6, an adjustment operation is performed in accordance with the flowcharts of FIGS.
【0076】(1)パソコン70から調整初期値を送信
して接続された各電子式電力量計20へ調整初期値を読
み込ます(ステップ301、241、242)。 (2)図10のステップ302以降の素子間のバランス
調整を実行する前に、粗調整の定格負荷調整(暫定F値
設定)をする場合は、後述するステップ312〜318
と同様の手順をここで実行する。ただし、粗調整である
ので誤差範囲は大きくする。
(1) The adjustment initial value is transmitted from the personal computer 70, and the adjustment initial value is read into the connected electronic watt-hour meters 20 (steps 301, 241 and 242). (2) When performing the rated load adjustment (tentative F-value setting) of the coarse adjustment before executing the balance adjustment between the elements after step 302 in FIG. 10, steps 312 to 318 described later.
Here, the same procedure is performed. However, since the adjustment is a rough adjustment, the error range is increased.
【0077】(3)素子間のバランス調整を実行するた
め、パソコン70は通信線16を通じて試験電源装置1
0へR相だけへ定格電流、定格電圧、力率1.00相当
の虚負荷電力の通電を指令する(ステップ302)。 (4)R相への虚負荷電力の通電を指令を受けた試験電
源装置10は定格電流、定格電圧、力率1.00の虚負
荷電力をR相へ通電する(ステップ103)。
(3) The personal computer 70 is connected to the test power supply 1 through the communication line 16 in order to execute the balance adjustment between the elements.
To 0, an instruction is issued to only the R phase to supply imaginary load power equivalent to a rated current, a rated voltage, and a power factor of 1.00 (step 302). (4) Upon receiving the command to supply the imaginary load power to the R phase, the test power supply 10 supplies the imaginary load power having the rated current, the rated voltage, and the power factor 1.00 to the R phase (step 103).
【0078】(5)タイマー14により電力通電を一定
時間、例えば10秒間供給したなら、制御CPU12は
通信線16を通じて通電終了信号を返信する(ステップ
104)。 (6)電子式電力量計20では通電終了信号を受ける
と、電力通電中にカウントされた電力パルス数WR をパ
ソコン70へ送信しメモリ装置72に記憶させる(ステ
ップ243、303)。
(5) If the power supply is supplied for a predetermined time, for example, 10 seconds, by the timer 14, the control CPU 12 returns a power supply end signal via the communication line 16 (step 104). (6) When the electronic watt-hour meter 20 receives the energization end signal, it transmits the number of power pulses WR counted during energization to the personal computer 70 and stores it in the memory device 72 (steps 243 and 303).
【0079】(7)次に、パソコン70は試験電源装置
10へS相だけへ定格電流、定格電圧、力率1.00相
当の虚負荷電力の通電を指令する(ステップ304)。 (8)試験電源装置10は定格電流、定格電圧、力率
1.00の虚負荷電力をS相へ一定時間通電して、通電
終了信号を返信する(ステップ105、106)。
(7) Next, the personal computer 70 instructs the test power supply 10 to supply only the S phase with a rated current, a rated voltage, and an imaginary load power equivalent to a power factor of 1.00 (step 304). (8) The test power supply 10 supplies the imaginary load power having the rated current, the rated voltage, and the power factor 1.00 to the S phase for a certain period of time, and returns an energization end signal (steps 105 and 106).
【0080】(9)電子式電力量計20はこの間でカウ
ントされた電力パルス数WS を読み取り、パソコン70
へ送信する(ステップ244)。 (10)パソコン70は送信されたS相の電力パルス数
WS を各電子式電力量計20対応に記憶させ、上記一時
記憶されている各電子式電力量計20対応のR相の電力
パルスWR 数と対比して、D=WS /WR を求め、Dが
1.0を中心とした所定範囲内(許容誤差範囲)かどう
かを判断する(ステップ305、306)。
(9) The electronic watt-hour meter 20 reads the number of power pulses WS counted during this time, and
(Step 244). (10) The personal computer 70 stores the transmitted S-phase power pulse number WS for each electronic watt-hour meter 20, and stores the temporarily stored R-phase power pulse WR for each electronic watt-hour meter 20. D = WS / WR is determined by comparing with a number, and it is determined whether or not D is within a predetermined range (allowable error range) centered at 1.0 (steps 305 and 306).
【0081】(11)Dが所定範囲外のときは、対応す
る電子式電力量計20のD=1.0となる方向の値を電
子式電力量計20へ送信し、電子式電力量計20はバラ
ンス調整レジスタ66の値(B2 )を変更設定する(ス
テップ307、245)。 (12)変更設定されたB2 値で許容誤差範囲となるこ
とを確認するため、確認フラグをオンにしておく(ステ
ップ308)。
(11) When D is out of the predetermined range, the value of the corresponding electronic watt-hour meter 20 in the direction where D = 1.0 is transmitted to the electronic watt-hour meter 20, and 20 changes and sets the value (B2) of the balance adjustment register 66 (steps 307 and 245). (12) A confirmation flag is turned on to confirm that the changed and set B2 value is within the allowable error range (step 308).
【0082】(13)次に、接続されたn台全ての電子
式電力量計20のD=WS /WR をステップ306〜3
08を実行する(ステップ309)。 (14)そして、n台全てが許容誤差範囲内になるまで
ステップ306〜311を繰り返し、T相のバランス調
整へ進む。T相のバランス調整は上記S相のバランス調
整と同様手順であり、説明を省略する。
(13) Next, D = WS / WR of all the connected electronic watt-hour meters 20 is determined by the steps 306 to 306.
08 is executed (step 309). (14) Steps 306 to 311 are repeated until all the n units are within the allowable error range, and the process proceeds to the T-phase balance adjustment. The balance adjustment of the T phase is the same procedure as the balance adjustment of the S phase, and the description is omitted.
【0083】(15)定格負荷調整では、パソコン70
から試験電源装置10へR相、S相、T相へ定格電流、
定格電圧、力率1.00相当の虚負荷電力の通電を指令
する(ステップ312)。 (16)試験電源装置10定格電流、定格電圧、力率
1.00の虚負荷電力を全相へ一定時間、例えば10秒
間通電して、通電終了信号を返信する(ステップ10
9、110)。
(15) In the rated load adjustment, the PC 70
Rated power to R-phase, S-phase, and T-phase from
A command is issued to supply imaginary load power equivalent to a rated voltage and a power factor of 1.00 (step 312). (16) The test power supply 10 supplies imaginary load power with a rated current, a rated voltage, and a power factor of 1.00 to all the phases for a certain period of time, for example, 10 seconds, and returns an energization end signal (step 10).
9, 110).
【0084】(17)電子式電力量計20はこの間でカ
ウントされた電力パルス数W0 を読み取り、パソコン7
0へ送信する(ステップ246)。 (18)パソコン70は送信された電力パルス数W0 を
各電子式電力量計20対応に記憶させ、予め記憶されて
いる定格定数パルス数値WK と各電子式電力量計20対
応の電力パルス数W0 と対比して、D=W0 /WK を求
め、Dが1.0を中心とした所定範囲内(許容誤差範
囲)かどうかを判断する(ステップ313、314)。
(17) The electronic watt-hour meter 20 reads the number of power pulses W0 counted during this time, and
0 (step 246). (18) The personal computer 70 stores the transmitted power pulse number W0 in correspondence with each electronic watt-hour meter 20, and stores the pre-stored rated constant pulse value WK and the power pulse number W0 corresponding to each electronic watt-hour meter 20. Then, D = W0 / WK is determined, and it is determined whether D is within a predetermined range centered at 1.0 (allowable error range) (steps 313 and 314).
【0085】(19)Dが所定範囲外のときは、対応す
る電子式電力量計20のD=1.0となる方向の値を電
子式電力量計20へ送信し、電子式電力量計20の定格
基準値レジスタ65の値(F)を変更設定する(ステッ
プ315、247)。 (20)変更設定されたF値で許容誤差範囲内となるこ
とを確認するため、確認フラグをオンにして(ステップ
316)以下、n台全てが許容誤差範囲に入るまでステ
ップ314〜318を繰り返し、力率調整へ進む。
(19) When D is out of the predetermined range, the value of the corresponding electronic watt-hour meter 20 in the direction of D = 1.0 is transmitted to the electronic watt-hour meter 20, and The value (F) of the 20 rated reference value register 65 is changed and set (steps 315 and 247). (20) In order to confirm that the changed F value is within the allowable error range, the confirmation flag is turned on (step 316), and thereafter, steps 314 to 318 are repeated until all the n units enter the allowable error range. Proceed to power factor adjustment.
【0086】(21)力率調整では、まずパソコン70
は通信線16を通じて試験電源装置10へR相のみに定
格電流、定格電圧、力率0.50相当の虚負荷電力の通
電を指令する(ステップ320)。 (22)試験電源装置10は定格電流、定格電圧、力率
0.50の電力をR相へ一定時間例えば10秒間通電し
て、通電終了信号を返信する(ステップ111、11
2)。
(21) In the power factor adjustment, first, the personal computer 70
Commands the test power supply 10 to supply only the R phase with a rated current, a rated voltage, and an imaginary load power equivalent to a power factor of 0.50 through the communication line 16 (step 320). (22) The test power supply 10 supplies power of the rated current, the rated voltage, and the power factor of 0.50 to the R phase for a predetermined time, for example, 10 seconds, and returns an energization end signal (steps 111 and 11).
2).
【0087】(23)電子式電力量計20はこの間でカ
ウントされた電力パルス数WPRをパソコン70へ送信す
る(ステップ248)。 (24)パソコン70は送信されきた電力パルス数WPR
を各電子式電力量計20対応に記憶させ、ステップ30
1で予め読み込まれた力率定数パルス数値WPKとの対比
を行い、D=WPR/WPKを求め、Dが許容誤差範囲かど
うかを判断する(ステップ321、322)。
(23) The electronic watt-hour meter 20 transmits the number of power pulses WPR counted during this period to the personal computer 70 (step 248). (24) The personal computer 70 transmits the transmitted power pulse number WPR
Is stored in correspondence with each electronic watt-hour meter 20, and step 30
In step 1, comparison is made with the power factor constant pulse numerical value WPK read in advance to obtain D = WPR / WPK, and it is determined whether or not D is within the allowable error range (steps 321 and 322).
【0088】(25)Dが許容誤差範囲外のときは、力
率調整レジスタ61(P1 )をD=1.0となる方向の
値を電子式電力量計20へ送り、電子式電力量計20は
力率調整レジスタ61(P1 )を変更設定する(ステッ
プ249)。 (26)変更設定されたF値で許容誤差範囲内となるこ
とを確認するため、確認フラグをオンにして(ステップ
324)以下、n台全てが許容誤差範囲に入るまでステ
ップ320〜327を繰り返す。以下、同様の処理によ
りS相、T相の力率調整を行い、軽負荷調整へ進む。
(25) When D is out of the allowable error range, the power factor adjustment register 61 (P1) sends a value in the direction of D = 1.0 to the electronic watt-hour meter 20, and the electronic watt-hour meter 20 changes and sets the power factor adjustment register 61 (P1) (step 249). (26) In order to confirm that the changed F value is within the allowable error range, the confirmation flag is turned on (Step 324), and thereafter, Steps 320 to 327 are repeated until all the n units enter the allowable error range. . Hereinafter, the power factor adjustment of the S phase and the T phase is performed by the same processing, and the process proceeds to the light load adjustment.
【0089】(27)軽負荷調整では、パソコン70は
通信線16を通じて試験電源装置10へR相、S相、T
相へ定格の10%電流、定格電圧、力率1.00相当の
虚負荷電力の通電を指令する(ステップ328)。 (28)試験電源装置10は定格の10%電流、定格電
圧、力率1.00の電力を全相へ一定時間例えば10秒
間通電して、通電終了信号を返信する(ステップ11
7、118)。
(27) In the light load adjustment, the personal computer 70 transmits the R phase, the S phase, and the T phase to the test power supply 10 through the communication line 16.
A command is issued to the phase to supply imaginary load power equivalent to 10% of the rated current, rated voltage, and power factor of 1.00 (step 328). (28) The test power supply 10 supplies 10% of the rated current, the rated voltage, and the power factor of 1.00 to all the phases for a certain period of time, for example, 10 seconds, and returns an energization end signal (step 11).
7, 118).
【0090】(29)電子式電力量計20はこの間でカ
ウントされた電力パルス数WL をパソコン70へ送信す
る(ステップ250)。 (30)パソコン70は送信されきた電力パルス数WL
を各電子式電力量計20対応に記憶させ、ステップ30
1で予め読み込まれた定格定数パルス数値WK との対比
を行い、D=10*WL /WK を求め、Dが1.0を中
心とした許容誤差範囲かどうかを判断する(ステップ3
29、330)。
(29) The electronic watt-hour meter 20 transmits the number of power pulses WL counted during this period to the personal computer 70 (step 250). (30) The personal computer 70 transmits the transmitted power pulse number WL.
Is stored in correspondence with each electronic watt-hour meter 20, and step 30
In step 1, a comparison is made with the previously read rating constant pulse numerical value WK to obtain D = 10 * WL / WK, and it is determined whether D is within an allowable error range centered at 1.0 (step 3).
29, 330).
【0091】(31)Dが許容誤差範囲外のときは、電
子式電力量計20の軽負荷調整レジスタ64の値(L)
をD=0.1となる方向の値を電子式電力量計20へ送
信し、軽負荷調整レジスタ64の値(L)を変更設定す
る(ステップ331、251)。 (32)変更設定されたL値で許容誤差範囲内となるこ
とを確認するため、確認フラグをオンにして(ステップ
332)以下、n台全てが許容誤差範囲に入るまでステ
ップ328〜334を繰り返す。n台全てが許容誤差範
囲に収まると、誤差調整完了の表示をする。
(31) When D is out of the allowable error range, the value (L) of the light load adjustment register 64 of the electronic watt-hour meter 20
Is transmitted to the electronic watt-hour meter 20 to change the value (L) of the light load adjustment register 64 (steps 331 and 251). (32) In order to confirm that the changed L value is within the allowable error range, the confirmation flag is turned on (step 332), and thereafter, steps 328 to 334 are repeated until all n units enter the allowable error range. . When all the n units fall within the allowable error range, a message indicating that the error adjustment is completed is displayed.
【0092】上記のように、初期設定値、調整プログラ
ム及び試験電源装置10への命令等をパソコン70に持
たせ、試験電源装置10及び複数の電子式電力量計20
を通信インターフェイス13、21、73を介して通信
線16で接続して、誤差調整をすることにより、調整プ
ログラムの変更が容易となり、電子式電力量計20のメ
モリ容量を削減でき安価に、同時に複数の電子式電力量
計20の誤差調整が実行できるので量産性が向上する。
As described above, the personal computer 70 has the initial set values, the adjustment program, the command to the test power supply 10 and the like, and the test power supply 10 and the plurality of electronic wattmeters 20 are provided.
Is connected by the communication line 16 via the communication interfaces 13, 21, 73, and the error is adjusted, so that the adjustment program can be easily changed, the memory capacity of the electronic watt-hour meter 20 can be reduced, and the cost can be reduced. Since error adjustment of the plurality of electronic watt-hour meters 20 can be performed, mass productivity is improved.
【0093】実施の形態4.この実施の形態は、実施の
形態3のパソコンの機能を試験電源装置に内蔵したもの
てある。図14は実施の形態4の構成を示す図である。
パソコンにあったメモリ装置72は試験電源装置10に
内蔵させ、パソコンのCPUは制御CPU12で兼用し
ている。なお、ディスプレイは図示していないが試験電
源装置10と接続して用いる。調整手順については、実
施の形態3と同様であるので省略する。この実施の形態
4は実施の形態3よりも試験設備をコンパクトに構成す
ることができる。
Embodiment 4 In this embodiment, the functions of the personal computer of the third embodiment are incorporated in a test power supply. FIG. 14 is a diagram showing a configuration of the fourth embodiment.
The memory device 72 provided in the personal computer is built in the test power supply 10, and the CPU of the personal computer is also used as the control CPU 12. Although not shown, the display is connected to the test power supply 10 and used. The adjustment procedure is the same as in the third embodiment, and a description thereof will be omitted. In the fourth embodiment, the test equipment can be made more compact than in the third embodiment.
【0094】実施の形態5.上記実施の形態3の構成で
は、試験電源装置10から通電される虚負荷電力と通電
時間による電力パルス数を基準パルス数と比較して、誤
差調整しているが、通電時間中の電流、電圧の変動、通
電時間の精度などが、電子式電力量計20の精度を左右
する。従って、高性能の試験電源装置10を準備しなけ
ればならない。このために、電力量計の誤差調整には精
度の高い基準計器を使用する方法が採用されている。該
実施の形態5はこの基準計器を使用した誤差調整の構成
を示したものである。
Embodiment 5 In the configuration of the third embodiment, the error is adjusted by comparing the imaginary load power supplied from the test power supply device 10 and the number of power pulses according to the power supply time with the reference pulse number, but the current and voltage during the power supply time are adjusted. The accuracy of the electronic watt-hour meter 20 depends on the fluctuation of the power consumption and the accuracy of the energization time. Therefore, a high-performance test power supply 10 must be prepared. For this reason, a method of using a high-precision reference meter is adopted for adjusting the error of the watt hour meter. The fifth embodiment shows a configuration of error adjustment using this reference instrument.
【0095】図15は、この発明の実施の形態5を示す
電子式電力量計の自動調整の接続図である。図におい
て、1、10〜16、20、21、31、32、40、
61〜69、70〜76は上記実施の形態3の説明と同
様のものである。80は基準計器であり、精度を非常に
高く調整した電子式電力量計が採用されている。
FIG. 15 is a connection diagram for automatic adjustment of an electronic watt-hour meter according to Embodiment 5 of the present invention. In the figure, 1, 10 to 16, 20, 21, 31, 32, 40,
Reference numerals 61 to 69 and 70 to 76 are the same as those described in the third embodiment. Reference numeral 80 denotes a reference meter, which employs an electronic watt-hour meter whose accuracy is adjusted to be extremely high.
【0096】81は基準計器80の通信インターフェイ
スであり、通信線16を通じてパソコン70の通信イン
ターフェイス73と接続されている。そして、電子式電
力量計から計数電力パルス数をパソコン70へ送信でき
るが、パソコン70からの調整値の変更設定指令は無視
する。77はパソコン70内のカウンタであり、基準計
器80からの計数電力パルス数を計数する。
Reference numeral 81 denotes a communication interface of the reference meter 80, which is connected to the communication interface 73 of the personal computer 70 through the communication line 16. The electronic watt-hour meter can transmit the count power pulse number to the personal computer 70, but ignores the adjustment setting change command from the personal computer 70. A counter 77 in the personal computer 70 counts the number of counting power pulses from the reference meter 80.
【0097】図示していない専用コネクタにより、試験
電源装置10の出力を基準計器80及び電子式電力量計
20の端子へ接続すると同時に通信インターフェイス1
3、21、73、81間を通信線16で接続する。この
状態で操作キーボード76から調整開始命令を入力する
と、図16〜図19のフローチャートに沿って調整作業
が実行される。該実施の形態5のフローチャートにおけ
るステップ番号で上記実施の形態3の図10〜図13と
同一処理内容は同一ステップ番号を記している。
The output of the test power supply 10 is connected to the terminals of the reference meter 80 and the electronic watt-hour meter 20 by a dedicated connector (not shown), and at the same time, the communication interface 1 is connected.
The communication lines 16 are connected between 3, 21, 73 and 81. When an adjustment start command is input from the operation keyboard 76 in this state, the adjustment operation is performed according to the flowcharts of FIGS. The same processing contents as those in FIGS. 10 to 13 of the third embodiment are denoted by the same step numbers in the flowchart of the fifth embodiment.
【0098】(1)パソコン70から調整初期値を送信
して接続された各電子式電力量計20へ調整初期値を読
み込ます(ステップ301、241、242)。 (2)図13のステップ302以降の素子間のバランス
調整を実行するまえに、粗調整の定格負荷調整(F値設
定)をする場合は、後述するステップ312〜318と
同様の手順を実行する。ただし、粗調整であるので誤差
範囲は大きくする。
(1) The adjustment initial value is transmitted from the personal computer 70, and the adjustment initial value is read into the connected electronic watt-hour meters 20 (steps 301, 241 and 242). (2) When performing the rated load adjustment (F value setting) of the coarse adjustment before executing the balance adjustment between the elements after step 302 in FIG. 13, the same procedure as steps 312 to 318 described later is executed. . However, since the adjustment is a rough adjustment, the error range is increased.
【0099】(3)素子間のバランス調整を実行するた
め、パソコン70は通信線16を通じて試験電源装置1
0へR相だけへ定格電流、定格電圧、力率1.00相当
の虚負荷電力の通電を指令する(ステップ302)。 (4)R相への虚負荷電力の通電を指令を受けた試験電
源装置10は定格電流、定格電圧、力率1.00の虚負
荷電力をR相へ通電する(ステップ103)。 (5)この通電により、基準計器80及び各電子式電力
量計20では電力パルス計数がなされる。基準計器80
の電力計数パルスは通信線16を通じてパソコン70へ
送信され(ステップ401)カウンタ77で集計され
る。
(3) The personal computer 70 is connected to the test power supply 1 via the communication line 16 in order to execute the balance adjustment between the elements.
To 0, an instruction is issued to only the R phase to supply imaginary load power equivalent to a rated current, a rated voltage, and a power factor of 1.00 (step 302). (4) Upon receiving the command to supply the imaginary load power to the R phase, the test power supply 10 supplies the imaginary load power having the rated current, the rated voltage, and the power factor 1.00 to the R phase (step 103). (5) With this energization, the reference meter 80 and the electronic watt-hour meters 20 perform power pulse counting. Reference instrument 80
Is transmitted to the personal computer 70 through the communication line 16 (step 401) and counted by the counter 77.
【0100】(6)パソコン70ではカウンタ77の計
数パルス数を監視して、所定数に達したところで試験電
源装置10へ通電停止指示を行い、通電停止する(ステ
ップ351、352、121)。ここで、計数パルスの
所定数であるが、これは電力量計の精度から、例えば精
度0.1%の計器では誤差判断を計算する基準パルス数
が最低1000個、精度0.01%のものでは1000
0個のパルス数を得ればよい。 (7)パソコン70は各電子式電力量計20へ電力通電
中にカウントされた電力パルス数WR をパソコン70へ
送信させメモリ装置72に記憶させる(ステップ24
3、303)。
(6) The personal computer 70 monitors the number of pulses counted by the counter 77, and when it reaches a predetermined number, instructs the test power supply 10 to stop power supply and stops power supply (steps 351, 352, 121). Here, the predetermined number of counting pulses is based on the accuracy of the watt hour meter. For example, a meter having an accuracy of 0.1% has a minimum of 1,000 reference pulses for calculating an error judgment and an accuracy of 0.01%. Then 1000
What is necessary is just to obtain the number of zero pulses. (7) The personal computer 70 transmits the number of power pulses WR counted during power supply to each electronic watt-hour meter 20 to the personal computer 70 and stores it in the memory device 72 (step 24).
3, 303).
【0101】(8)次に、パソコン70は試験電源装置
10へS相だけへ定格電流、定格電圧、力率1.00相
当の虚負荷電力の通電を指令し、試験電源装置10は定
格電流、定格電圧、力率1.00の虚負荷電力をS相へ
通電する(ステップ304、105)。 (9)R相への通電により基準計器80及び各電子式電
力量計20では電力パルス計数がなされ、基準計器80
の電力計数パルスはカウンタ77で集計される(ステッ
プ402)。
(8) Next, the personal computer 70 instructs the test power supply 10 to supply only the S-phase with a rated current, a rated voltage, and an imaginary load power equivalent to a power factor of 1.00. Then, an imaginary load power having a rated voltage and a power factor of 1.00 is supplied to the S phase (steps 304 and 105). (9) When the R-phase is energized, the reference meter 80 and each electronic watt-hour meter 20 perform power pulse counting, and the reference meter 80
Are counted by the counter 77 (step 402).
【0102】(10)カウンタ77の計数パルス数を監
視して、所定数に達したところで試験電源装置10へ通
電停止指示を行い通電停止する(ステップ353、35
4、122)。 (11)以下、パソコン70は送信されたS相の電力パ
ルス数WS を各電子式電力量計20対応に記憶させ、上
記記憶されている各電子式電力量計20対応のR相の電
力パルスWR 数と対比して、各電子式電力量計20はバ
ランス調整レジスタ66の値(B2 )の変更設定、及び
T相のバランス調整レジスタ67の値(B3 )の変更設
定は、上記実施の形態3と同一であり説明を省略する。
(10) The number of pulses counted by the counter 77 is monitored, and when the number reaches a predetermined number, an instruction to stop power supply is issued to the test power supply 10 to stop power supply (steps 353 and 35).
4, 122). (11) Thereafter, the personal computer 70 stores the transmitted number of power pulses WS of the S phase in correspondence with each electronic watt-hour meter 20, and stores the stored R-phase power pulses corresponding to each electronic watt-hour meter 20. In contrast to the number of WRs, each electronic watt-hour meter 20 sets the change of the value (B2) of the balance adjustment register 66 and the change of the value (B3) of the T-phase balance register 67 in the above-described embodiment. 3 and the description is omitted.
【0103】(12)定格負荷調整においては、パソコ
ン70から試験電源装置10へR相、S相、T相へ定格
電流、定格電圧、力率1.00相当の虚負荷電力の通電
を指令し、試験電源装置10は定格電流、定格電圧、力
率1.00の虚負荷電力をR相、S相、T相へ通電する
(ステップ312、109)。 (13)この通電により基準計器80及び各電子式電力
量計20では電力パルス計数がなされ、基準計器80の
電力計数パルスはカウンタ77で集計される(ステップ
403)。
(12) In the rated load adjustment, the personal computer 70 instructs the test power supply 10 to supply the R-phase, S-phase, and T-phases with the imaginary load power equivalent to the rated current, the rated voltage, and the power factor of 1.00. The test power supply 10 supplies imaginary load power having a rated current, a rated voltage, and a power factor of 1.00 to the R, S, and T phases (steps 312 and 109). (13) With this energization, the reference meter 80 and each electronic watt-hour meter 20 perform power pulse counting, and the power counting pulses of the reference meter 80 are counted by the counter 77 (step 403).
【0104】(14)パソコン70はカウンタ77の計
数パルス数を監視して、所定数WK に達したところで試
験電源装置10へ通電停止指示を行い通電停止する(ス
テップ355、356、123)。 (15)パソコン70は各電子式電力量計20がこの通
電中に計数された電力パルス数W0 を受信記憶させ(ス
テップ313)、カウンタ77の計数パルス数WK と各
電子式電力量計20対応の電力パルス数W0 と対比し
て、電子式電力量計20の定格基準値レジスタ65の値
(F)を変更設定する(ステップ314〜315、24
7)。 (16)以下は、実施の形態3と同一であり説明を省略
する。
(14) The personal computer 70 monitors the number of pulses counted by the counter 77, and when it reaches the predetermined number WK, instructs the test power supply 10 to stop power supply and stops power supply (steps 355, 356, 123). (15) The personal computer 70 receives and stores the number of power pulses W0 counted by the electronic watt-hour meters 20 during the energization (step 313), and corresponds to the count pulse number WK of the counter 77 and the corresponding electronic watt-hour meter 20. The value (F) of the rated reference value register 65 of the electronic watt-hour meter 20 is changed and set in comparison with the power pulse number W0 (steps 314 to 315, 24).
7). (16) The following is the same as the third embodiment, and the description is omitted.
【0105】(17)力率調整では、パソコン70は試
験電源装置10へR相のみに定格電流、定格電圧、力率
0.50相当の虚負荷電力の通電を指令し、試験電源装
置10は定格電流、定格電圧、力率0.50の電力をR
相へ通電する(ステップ320、111)。 (18)この通電により基準計器80及び各電子式電力
量計20では電力パルス計数がなされ、基準計器80の
電力計数パルスはカウンタ77で集計される(ステップ
404)。
(17) In the power factor adjustment, the personal computer 70 instructs the test power supply 10 to supply only the R phase with a rated current, a rated voltage, and an imaginary load power equivalent to a power factor of 0.50. Rated current, rated voltage, power factor 0.50 power R
The phases are energized (steps 320, 111). (18) By this energization, the reference meter 80 and each electronic watt-hour meter 20 perform power pulse counting, and the power counting pulses of the reference meter 80 are counted by the counter 77 (step 404).
【0106】(19)パソコン70はカウンタ77の計
数パルス数を監視して、所定数WPKに達したところで試
験電源装置10へ通電停止指示を行い通電停止する(ス
テップ357、358、125)。 (20)パソコン70は各電子式電力量計20がこの通
電中に計数された電力パルス数WPRを受信記憶し(ステ
ップ321)、カウンタ77の計数パルス数WPKと各電
子式電力量計20対応の電力パルス数WPRと対比して、
D=WPR/WPKを求め、Dが許容誤差範囲に入るよう力
率調整レジスタ61(P1 )を変更設定する(ステップ
322〜324、249)。 (21)以下は、実施の形態3と同様の処理によりS
相、T相の力率調整を行い、軽負荷調整へ進む。
(19) The personal computer 70 monitors the number of counting pulses of the counter 77, and when it reaches a predetermined number WPK, instructs the test power supply 10 to stop power supply and stops power supply (steps 357, 358, and 125). (20) The personal computer 70 receives and stores the number of power pulses WPR counted by each electronic watt-hour meter 20 during this energization (step 321), and corresponds to the counted pulse number WPK of the counter 77 and each electronic watt-hour meter 20. In contrast to the number of power pulses WPR of
D = WPR / WPK is obtained, and the power factor adjustment register 61 (P1) is changed and set so that D falls within the allowable error range (steps 322 to 324, 249). (21) The following processes are performed by the same processing as in the third embodiment.
Phase and T phase power factor adjustments are performed, and proceed to light load adjustment.
【0107】(22)軽負荷調整では、パソコン70は
試験電源装置10へR相、S相、T相へ定格の10%電
流、定格電圧、力率1.00相当の虚負荷電力の通電を
指令し、試験電源装置10は定格の10%電流、定格電
圧、力率1.00の電力を全相へ通電する(ステップ3
28、117)。 (23)この通電により基準計器80及び各電子式電力
量計20では電力パルス計数がなされ、基準計器80の
電力計数パルスはカウンタ77で集計される(ステップ
405)。
(22) In light load adjustment, the personal computer 70 supplies the test power supply 10 with an imaginary load power equivalent to a rated 10% current, a rated voltage and a power factor of 1.00 to the R, S, and T phases. And the test power supply 10 supplies 10% of the rated current, rated voltage, and power factor 1.00 to all phases (step 3).
28, 117). (23) With this energization, the reference meter 80 and each electronic watt-hour meter 20 perform power pulse counting, and the power counting pulses of the reference meter 80 are counted by the counter 77 (step 405).
【0108】(24)パソコン70はカウンタ77の計
数パルス数を監視して、所定数WLKに達したところで試
験電源装置10へ通電停止指示を行い通電停止する(ス
テップ359、360、126)。 (25)パソコン70はこの通電中の各電子式電力量計
20の電力パルス数WLを収集記憶する(ステップ32
9)。
(24) The personal computer 70 monitors the number of pulses counted by the counter 77, and when it reaches the predetermined number WLK, instructs the test power supply 10 to stop power supply and stops power supply (steps 359, 360, 126). (25) The personal computer 70 collects and stores the number of power pulses WL of each of the electronic watt-hour meters 20 during energization (step 32).
9).
【0109】(26)そして、カウンタ77内の計数パ
ルス数WLKと収集された電力パルス数WL を各電子式電
力量計20対応に対比を行い、D=WL /WK を求めD
が許容誤差範囲内に入るように軽負荷調整レジスタ64
の値(L)を変更設定する(ステップ330〜322、
251)。 (27)以下、n台全てが許容誤差範囲に入るまでステ
ップ328〜334を繰り返す。n台全てが許容誤差範
囲に収まると、誤差調整完了の表示をする。
(26) Then, the number of counting pulses WLK in the counter 77 and the number of collected power pulses WL are compared with each electronic watt-hour meter 20 to obtain D = WL / WK.
Is set within the allowable error range.
Is changed and set (steps 330 to 322,
251). (27) Thereafter, steps 328 to 334 are repeated until all of the n units fall within the allowable error range. When all the n units fall within the allowable error range, a message indicating that the error adjustment is completed is displayed.
【0110】上記実施の形態5において、基準計器80
と電子式電力量計20の電力計数パルスとの対比をパソ
コン70のプログラムで処理する例を示したが、この部
分をロータリーカウンタを用いて実施しても、同等の効
果を奏する。例えばロータリーカウンタにする場合、図
15のカウンタ77の代わりにロータリーカウンタを用
い、各電子式電力量計20の電力パルス数WL を+(プ
ラス)カウントカウントし、基準計器80の電力パルス
数WLKを−(マイナス)カウントする。計数される値
は、 (電子式電力量計の電力パルス数WL )−(基準計器の
電力パルス数WLK) となり、この差が所定範囲内に入るように誤差調整行
う。
In the fifth embodiment, the reference meter 80
Although the example in which the comparison between the electric power meter 20 and the power counting pulse of the electronic watt-hour meter 20 are processed by the program of the personal computer 70 has been described, the same effect can be obtained even if this part is implemented using a rotary counter. For example, when a rotary counter is used, a rotary counter is used instead of the counter 77 in FIG. 15, the number of power pulses WL of each electronic watt-hour meter 20 is counted by + (plus), and the number of power pulses WLK of the reference meter 80 is calculated. -(Minus) count. The counted value is (the number of power pulses WL of the electronic watt-hour meter)-(the number of power pulses WLK of the reference meter), and the error is adjusted so that this difference falls within a predetermined range.
【0111】上記のように、実施の形態5の構成におい
ては、基準計器80の電力計数パルスを基準にして電子
式電力量計20の電力計数パルスとの対比して各調整レ
ジスタの設定値を設定するので、調整作業中の試験電源
装置10から通電される虚負荷電力の電圧変動、通電時
間の誤差等があっても、基準計器80と電子式電力量計
20は電力通電値は同一のレベルで把握しているので、
誤差調整精度は基準計器80の精度を維持すれば、電子
式電力量計20の精度が補償範囲に入れ易い。また、上
記実施の形態3で述べた、調整プログラムの変更の容
易、電子式電力量計20のメモリ容量の削減及び複数の
電子式電力量計20の同時誤差調整の実行が可能であ
る。
As described above, in the configuration of the fifth embodiment, the setting value of each adjustment register is compared with the power counting pulse of the electronic watt-hour meter 20 based on the power counting pulse of the reference meter 80. Therefore, the reference meter 80 and the electronic watt-hour meter 20 have the same power supply value even if there is a voltage fluctuation of the imaginary load power supplied from the test power supply device 10 during the adjustment operation, an error in the supply time, or the like. Because we know at the level,
As for the accuracy of error adjustment, if the accuracy of the reference meter 80 is maintained, the accuracy of the electronic watt-hour meter 20 can easily enter the compensation range. Further, it is possible to easily change the adjustment program, reduce the memory capacity of the electronic watt-hour meter 20, and execute the simultaneous error adjustment of the plurality of electronic watt-hour meters 20 described in the third embodiment.
【0112】実施の形態6.この実施の形態は、実施の
形態5のパソコンの機能を試験電源装置に内蔵したもの
てある。図20はこの実施の形態6の構成を示す図であ
る。パソコンにあったメモリ装置72は試験電源装置1
0に内蔵させ、パソコンのCPUは制御CPU12で兼
用している。なお、ディスプレイは図示していないが試
験電源装置10と接続して用いる。調整手順について
は、実施の形態5と同様であるので省略する。実施の形
態5よりもコンパクトに構成することができる。
Embodiment 6 FIG. In this embodiment, the functions of the personal computer of the fifth embodiment are incorporated in a test power supply. FIG. 20 is a diagram showing a configuration of the sixth embodiment. The memory device 72 in the personal computer is the test power supply 1
The CPU of the personal computer is also used as the control CPU 12. Although not shown, the display is connected to the test power supply 10 and used. The adjustment procedure is the same as that in the fifth embodiment, and thus the description is omitted. It can be configured more compactly than in the fifth embodiment.
【0113】[0113]
【発明の効果】以上のようにこの発明の電子式電力量計
およびその誤差調整方法によれば、誤差の自動調整を可
能としたので、量産する場合の生産性を向上することが
できる。
As described above, according to the electronic watt-hour meter and the error adjusting method of the present invention, since the error can be automatically adjusted, the productivity in mass production can be improved.
【図面の簡単な説明】[Brief description of the drawings]
【図1】 この発明の実施の形態1による電子式電力量
計の誤差調整システムの構成図である。
FIG. 1 is a configuration diagram of an error adjustment system for an electronic watt-hour meter according to Embodiment 1 of the present invention.
【図2】 この発明の実施の形態1による誤差調整のフ
ローチャートである。
FIG. 2 is a flowchart of error adjustment according to the first embodiment of the present invention.
【図3】 この発明の実施の形態1による誤差調整のフ
ローチャートである。
FIG. 3 is a flowchart of error adjustment according to the first embodiment of the present invention.
【図4】 この発明の実施の形態1による誤差調整のフ
ローチャートである。
FIG. 4 is a flowchart of error adjustment according to the first embodiment of the present invention.
【図5】 この発明の実施の形態2による電子式電力量
計の誤差調整システムの構成図である。
FIG. 5 is a configuration diagram of an error adjustment system for an electronic watt-hour meter according to a second embodiment of the present invention.
【図6】 この発明の実施の形態2による誤差調整のフ
ローチャートである。
FIG. 6 is a flowchart of error adjustment according to the second embodiment of the present invention.
【図7】 この発明の実施の形態2による誤差調整のフ
ローチャートである。
FIG. 7 is a flowchart of error adjustment according to the second embodiment of the present invention.
【図8】 この発明の実施の形態2による誤差調整のフ
ローチャートである。
FIG. 8 is a flowchart of an error adjustment according to the second embodiment of the present invention.
【図9】 この発明の実施の形態3による電子式電力量
計の誤差調整システムの構成図である。
FIG. 9 is a configuration diagram of an error adjustment system for an electronic watt-hour meter according to Embodiment 3 of the present invention.
【図10】 この発明の実施の形態3による誤差調整の
フローチャートである。
FIG. 10 is a flowchart of error adjustment according to Embodiment 3 of the present invention.
【図11】 この発明の実施の形態3による誤差調整の
フローチャートである。
FIG. 11 is a flowchart of error adjustment according to Embodiment 3 of the present invention.
【図12】 この発明の実施の形態3による誤差調整の
フローチャートである。
FIG. 12 is a flowchart of error adjustment according to Embodiment 3 of the present invention.
【図13】 この発明の実施の形態3による誤差調整の
フローチャートである。
FIG. 13 is a flowchart of error adjustment according to the third embodiment of the present invention.
【図14】 この発明の実施の形態4による電子式電力
量計の誤差調整システムの構成図である。
FIG. 14 is a configuration diagram of an error adjusting system for an electronic watt-hour meter according to a fourth embodiment of the present invention.
【図15】 この発明の実施の形態5による電子式電力
量計の誤差調整システムの構成図である。
FIG. 15 is a configuration diagram of an error adjustment system for an electronic watt-hour meter according to a fifth embodiment of the present invention.
【図16】 この発明の実施の形態5による誤差調整の
フローチャートである。
FIG. 16 is a flowchart of error adjustment according to Embodiment 5 of the present invention.
【図17】 この発明の実施の形態5による誤差調整の
フローチャートである。
FIG. 17 is a flowchart of error adjustment according to Embodiment 5 of the present invention.
【図18】 この発明の実施の形態5による誤差調整の
フローチャートである。
FIG. 18 is a flowchart of error adjustment according to Embodiment 5 of the present invention.
【図19】 この発明の実施の形態5による誤差調整の
フローチャートである。
FIG. 19 is a flowchart of error adjustment according to Embodiment 5 of the present invention.
【図20】 この発明の実施の形態6による電子式電力
量計の誤差調整システムの構成図である。
FIG. 20 is a configuration diagram of an error adjustment system for an electronic watt-hour meter according to Embodiment 6 of the present invention.
【図21】 従来の電子式電力量計の誤差調整を示す構
成図である。
FIG. 21 is a configuration diagram showing error adjustment of a conventional electronic watt-hour meter.
【図22】 電子式電力量計の誤差特性を示す図であ
る。
FIG. 22 is a diagram showing error characteristics of an electronic watt-hour meter.
【図23】 他の従来の電子式電力量計の誤差調整シス
テムの構成図である。
FIG. 23 is a configuration diagram of another conventional error adjusting system for an electronic watt-hour meter.
【符号の説明】[Explanation of symbols]
1 虚負荷試験電源、 10 試験電源装
置、11 電源切替装置、 12 制御
CPU、13、21、73、81 通信インターフェイ
ス 14 ROM、 16 通信線、 17 供給先切替手段、 20 電子式電
力量計、22 不揮発記憶装置(EPROM)、23
調整スタートスイッチ、31 変流器、
32 変圧器、38 カウンタ、
39 表示部、40 演算制御部、
41 CPU、42 電流A/D変換回路、
43 電圧A/D変換回路、44 乗算器、
45 加算器、46 デジタルロ
ーパスフィルタ、 47 軽負荷調整加算器、51
バランス調整乗算器、 61〜63 力率調整
レジスタ、64 軽負荷調整レジスタ、 65
定格基準値レジスタ、66、67 バランス調整レジ
スタ、 70 パーソナルコンピュータ、71 メイン
CPU、 72 メモリ装置、76は操
作キーボード、 80 基準計器、
Reference Signs List 1 imaginary load test power supply, 10 test power supply device, 11 power supply switching device, 12 control CPU, 13, 21, 73, 81 communication interface 14 ROM, 16 communication line, 17 supply destination switching means, 20 electronic watt-hour meter, 22 Non-volatile storage device (EPROM), 23
Adjustment start switch, 31 current transformer,
32 transformers, 38 counters,
39 display unit, 40 arithmetic control unit,
41 CPU, 42 current A / D conversion circuit,
43 voltage A / D conversion circuit, 44 multiplier,
45 adder, 46 digital low-pass filter, 47 light load adjustment adder, 51
Balance adjustment multiplier, 61-63 Power factor adjustment register, 64 Light load adjustment register, 65
Rating reference value register, 66, 67 Balance adjustment register, 70 personal computer, 71 main CPU, 72 memory device, 76 is operation keyboard, 80 reference instrument,

Claims (7)

    【特許請求の範囲】[Claims]
  1. 【請求項1】 入力される電圧・電流を電力量に比例し
    た電力パルス数に変換するデジタル乗算器と、このデジ
    タル乗算器の電力パルス数変換時の誤差を調整する各調
    整ポイントの調整値が保持される調整レジスタと、誤差
    調整プログラム及び各規定値が格納されるメモリ装置
    と、上記誤差調整プログラムが各調整ポイントへの順次
    移行と各調整ポイントに対応する電源種類の出力とを外
    部の試験電源装置へ指示する指示手段と、この指示に対
    応する上記試験電源装置からの出力を上記ディジタル乗
    算器へ入力して得られる所定時間での電力パルス数と上
    記指示に対応する上記メモリ装置の規定値とを比較し、
    この比較結果が所定の誤差範囲内に収まるよう調整する
    調整値を導出して上記調整レジスタに書き込む調整値設
    定手段とを備えたことを特徴とする電子式電力量計。
    1. A digital multiplier for converting an input voltage / current into a power pulse number proportional to a power amount, and an adjustment value at each adjustment point for adjusting an error in converting the power pulse number of the digital multiplier. An adjustment register to be held, a memory device in which an error adjustment program and each specified value are stored, and an external test in which the error adjustment program sequentially shifts to each adjustment point and outputs a power supply type corresponding to each adjustment point. Instruction means for instructing the power supply device, the number of power pulses in a predetermined time obtained by inputting the output from the test power supply device corresponding to the instruction to the digital multiplier, and the specification of the memory device corresponding to the instruction Value and compare
    An electronic watt-hour meter comprising: an adjustment value setting means for deriving an adjustment value for adjusting the comparison result to fall within a predetermined error range and writing the adjustment value in the adjustment register.
  2. 【請求項2】 請求項1の電子式電力量計と、所定の電
    源種類に切り替え出力する電源種類切替手段を具備した
    試験電源装置とを接続し、上記試験電源装置は上記電子
    式電力量計の指示手段からの指示に対応する電源種類に
    切り替えて出力し、この出力を受けた上記電子式電力量
    計は電力パルス数に変換して調整値設定手段で調整値を
    導出し設定するようにしたことを特徴とする電子式電力
    量計の誤差調整方法。
    2. An electronic watt-hour meter according to claim 1, wherein said electronic watt-hour meter is connected to a test power supply device having a power supply type switching means for switching and outputting a predetermined power supply type. The electronic watt-hour meter receiving the output is converted into the number of power pulses, and the adjustment value is derived and set by the adjustment value setting means. An error adjusting method for an electronic watt-hour meter.
  3. 【請求項3】 請求項2の電子式電力量計の誤差調整方
    法において、複数個の電子式電力量計と試験電源装置と
    を接続し、上記試験電源装置は所定の電源種類に切り替
    え出力する電源種類切替手段と、この出力を上記電子式
    電力量計1個ずつ供給するよう切り替える供給先切替手
    段と、制御手段とを具備する試験電源装置を用い、上記
    制御手段は、上記電子式電力量計の指示手段からの指示
    を受けて、いずれの電子式電力量計に対しどの種の電源
    種類に切り替えるかを判断し、上記電源種類の切り替え
    と上記供給先の切り替えとを組み合わせて、上記複数個
    の電子式電力量計の全ての調整ポイントを調整するよう
    にしたことを特徴とする電子式電力量計の誤差調整方
    法。
    3. An error adjusting method for an electronic watt-hour meter according to claim 2, wherein a plurality of electronic watt-hour meters are connected to a test power supply, and the test power supply is switched to a predetermined power supply type and outputs. A test power supply device comprising: a power supply type switching unit; a supply destination switching unit for switching the output so as to supply the electronic watt-hour meter one by one; and a control unit. In response to an instruction from the instruction means of the power meter, it is determined which type of power supply is to be switched to which electronic watt-hour meter, and the switching of the power supply type and the switching of the supply destination are combined, and An error adjustment method for an electronic wattmeter, wherein all adjustment points of the electronic wattmeters are adjusted.
  4. 【請求項4】 入力される電圧・電流を電力量に比例し
    た電力パルス数に変換するデジタル乗算器と、このデジ
    タル乗算器の電力パルス数変換時の誤差を調整する各調
    整ポイントの調整値が保持される調整レジスタと、上記
    電力パルス数を外部へ送信可能とする送信手段と、外部
    から入力された調整値を上記調整レジスタに書き込む調
    整値設定手段とを備えたことを特徴とする電子式電力量
    計。
    4. A digital multiplier for converting an input voltage / current into a power pulse number proportional to a power amount, and an adjustment value at each adjustment point for adjusting an error in converting the power pulse number of the digital multiplier. An electronic register comprising: an adjustment register to be held; transmission means for enabling transmission of the power pulse number to the outside; and adjustment value setting means for writing an adjustment value input from the outside to the adjustment register. Watt hour meter.
  5. 【請求項5】 請求項4の電子式電力量計と、所定の電
    源種類に切り替え出力する電源種類切替手段を具備する
    試験電源装置と、演算装置とを接続し、上記演算装置は
    上記電子式電力量計の誤差調整プログラムおよび各規定
    値が格納されたメモリ装置と、上記誤差調整プログラム
    が各調整ポイントへの順次移行と各調整ポイントに対応
    する電源種類の出力とを上記試験電源装置へ指示する指
    示手段と、上記試験電源装置からの出力を上記ディジタ
    ル乗算器へ入力して得られる所定時間での電力パルス数
    と上記指示に対応する上記メモリ装置の規定値とを比較
    し、この比較結果が所定の誤差範囲内に収まるよう調整
    する調整値を導出する調整値導出手段とを具備する演算
    装置を用い、上記試験電源装置は上記演算装置の指示手
    段からの指示に対応する電源種類に切り替えて出力し、
    この出力を受けた上記電子式電力量計は電力パルス数に
    変換して上記演算装置へ出力し、この電力パルス数を受
    けて上記演算装置の調整値導出手段は調整値を導出し、
    この導出された調整値を上記電子式電力量計の調整値設
    定手段で調整レジスタに書き込み設定するようにしたこ
    とを特徴とする電子式電力量計の誤差調整方法。
    5. An electronic wattmeter according to claim 4, a test power supply device having a power supply type switching means for switching and outputting a predetermined power supply type, and an arithmetic unit, wherein said arithmetic unit is connected to said electronic type. A memory device in which an error adjustment program of the watt-hour meter and each specified value are stored, and the error adjustment program instructs the test power supply device to sequentially shift to each adjustment point and output a power supply type corresponding to each adjustment point. And comparing the number of power pulses in a predetermined time obtained by inputting an output from the test power supply to the digital multiplier with a prescribed value of the memory device corresponding to the instruction. And an adjustment value deriving unit that derives an adjustment value that adjusts the value to fall within a predetermined error range. The test power supply unit responds to an instruction from an instruction unit of the arithmetic unit. Switch to the type of power supply
    Upon receiving the output, the electronic watt-hour meter converts the power pulse number into the number of power pulses and outputs it to the arithmetic device.
    An error adjustment method for an electronic watt-hour meter, wherein the derived adjustment value is written and set in an adjustment register by an adjustment value setting means of the electronic watt-hour meter.
  6. 【請求項6】 請求項4の電子式電力量計と、所定の電
    源種類に切り替え出力する電源種類切替手段を具備する
    試験電源装置と、演算装置と、基準計器とを接続し、上
    記基準計器は上記電子式電力量計と同一のディジタル乗
    算器を有し、所定の入力に対し得られる電力パルス数が
    基準値となるよう校正された基準計器を用いると共に、
    上記演算装置は、上記電子式電力量計の誤差調整プログ
    ラムおよび各規定値が格納されたメモリ装置と、上記誤
    差調整プログラムが各調整ポイントへの順次移行と各調
    整ポイントに対応する電源種類の出力とを上記試験電源
    装置へ指示する指示手段と、上記試験電源装置からの出
    力を上記電子式電力量計のディジタル乗算器へ入力して
    得られる所定時間での電力パルス数と、上記試験電源装
    置からの出力を上記基準計器のディジタル乗算器へ入力
    して得られる所定時間での電力パルス数とを比較し、こ
    の比較結果が所定の誤差範囲内に収まるよう調整する調
    整値を導出する調整値導出手段とを具備する演算装置を
    用い、上記試験電源装置は上記演算装置の指示手段から
    の指示に対応する電源種類に切り替えて出力し、この出
    力を受けた上記電子式電力量計および上記基準機器は各
    々電力パルス数に変換して出力し、上記演算装置は出力
    された上記両電力パルス数を比較してその比較結果に対
    応する調整値を調整値導出手段で導出して出力し、この
    出力された調整値を上記電子式電力量計の調整値設定手
    段で調整レジスタに書き込み設定するようにしたことを
    特徴とする電子式電力量計の誤差調整方法。
    6. An electronic watt-hour meter according to claim 4, a test power supply device comprising a power supply type switching means for switching and outputting a predetermined power supply type, an arithmetic unit, and a reference meter, wherein said reference meter is connected. Has the same digital multiplier as the electronic watt-hour meter, uses a reference meter calibrated so that the number of power pulses obtained for a predetermined input becomes a reference value,
    The arithmetic unit includes a memory device in which an error adjustment program of the electronic watt-hour meter and each specified value are stored, and the error adjustment program sequentially shifts to each adjustment point and outputs a power supply type corresponding to each adjustment point. Means for instructing the test power supply, and the number of power pulses in a predetermined time obtained by inputting an output from the test power supply to a digital multiplier of the electronic wattmeter; and The output value of the reference meter is input to the digital multiplier of the reference instrument, and the number of power pulses in a predetermined time obtained is compared. The adjustment value for deriving an adjustment value for adjusting the comparison result to fall within a predetermined error range is obtained. The test power supply device switches to the power supply type corresponding to the instruction from the instruction means of the arithmetic device and outputs the same. The watt-hour meter and the reference device are each converted into a power pulse number and output, and the arithmetic unit compares the output power pulse numbers and outputs an adjustment value corresponding to the comparison result by an adjustment value deriving unit. An error adjustment method for an electronic watt-hour meter, wherein the output value is derived and output, and the output adjustment value is written and set in an adjustment register by the adjustment value setting means of the electronic watt-hour meter.
  7. 【請求項7】 請求項5または請求項6の電子式電力量
    計の誤差調整方法において、試験電源装置は演算装置を
    内蔵させた試験電源装置を用いるようにしたことを特徴
    とする電子式電力量計の誤差調整方法。
    7. A method for adjusting an error of an electronic watt-hour meter according to claim 5, wherein the test power supply uses a test power supply having a built-in arithmetic unit. How to adjust the error of the meter.
JP21611097A 1997-08-11 1997-08-11 Electronic watt-hour meter and its error adjustment method Expired - Lifetime JP3330519B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21611097A JP3330519B2 (en) 1997-08-11 1997-08-11 Electronic watt-hour meter and its error adjustment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21611097A JP3330519B2 (en) 1997-08-11 1997-08-11 Electronic watt-hour meter and its error adjustment method

Publications (2)

Publication Number Publication Date
JPH1164402A true JPH1164402A (en) 1999-03-05
JP3330519B2 JP3330519B2 (en) 2002-09-30

Family

ID=16683406

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21611097A Expired - Lifetime JP3330519B2 (en) 1997-08-11 1997-08-11 Electronic watt-hour meter and its error adjustment method

Country Status (1)

Country Link
JP (1) JP3330519B2 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003060531A1 (en) * 2002-01-09 2003-07-24 Mitsubishi Denki Kabushiki Kaisha Electronic watt-hour meter, error adjusting method, and power calculating circuit
WO2008047428A1 (en) * 2006-10-18 2008-04-24 Osaki Electric Co., Ltd. Electronic watthour meter
CN102520608A (en) * 2011-12-19 2012-06-27 深圳市航盛电子股份有限公司 Method and device for automatically correcting automobile vehicle-mounted clock
CN102565521A (en) * 2011-12-14 2012-07-11 中国电子科技集团公司第四十一研究所 High-precision wide-dynamic-range microwave signal level test device
JP2013036855A (en) * 2011-08-08 2013-02-21 Sanki Eng Co Ltd Artificial load device for watt-hour meter
CN103091552A (en) * 2011-10-31 2013-05-08 无锡华润矽科微电子有限公司 Pre-calibrated electric energy metering circuit and calibration method
CN103149546A (en) * 2012-11-30 2013-06-12 河南工业大学 Portable electric energy measuring terminal comprehensive calibration instrument on site
CN103616660A (en) * 2013-12-02 2014-03-05 国家电网公司 Power-down processing reliability test device and method for intelligent ammeters in interference environment
CN105243829A (en) * 2015-09-30 2016-01-13 青岛世泽电子仪表有限公司 Portable simulated meter module
CN106597351A (en) * 2016-11-18 2017-04-26 云南电网有限责任公司电力科学研究院 Electric energy meter verification device online real-time monitoring realization method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101908368B1 (en) * 2017-01-24 2018-10-17 한국전력공사 Apparatus and method for verifying measurement mode of watt-hour meter

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003060531A1 (en) * 2002-01-09 2003-07-24 Mitsubishi Denki Kabushiki Kaisha Electronic watt-hour meter, error adjusting method, and power calculating circuit
WO2003060540A1 (en) * 2002-01-09 2003-07-24 Mitsubishi Denki Kabushiki Kaisha Electronic watthour meter, error adjusting method therefor and power computing circuit
WO2008047428A1 (en) * 2006-10-18 2008-04-24 Osaki Electric Co., Ltd. Electronic watthour meter
JP4896150B2 (en) * 2006-10-18 2012-03-14 大崎電気工業株式会社 Electronic energy meter
JP2013036855A (en) * 2011-08-08 2013-02-21 Sanki Eng Co Ltd Artificial load device for watt-hour meter
CN103091552A (en) * 2011-10-31 2013-05-08 无锡华润矽科微电子有限公司 Pre-calibrated electric energy metering circuit and calibration method
CN102565521A (en) * 2011-12-14 2012-07-11 中国电子科技集团公司第四十一研究所 High-precision wide-dynamic-range microwave signal level test device
CN102565521B (en) * 2011-12-14 2015-12-16 中国电子科技集团公司第四十一研究所 A kind of high-precision wide-dynamic-range microwave signal level test device and method of testing
CN102520608A (en) * 2011-12-19 2012-06-27 深圳市航盛电子股份有限公司 Method and device for automatically correcting automobile vehicle-mounted clock
CN103149546A (en) * 2012-11-30 2013-06-12 河南工业大学 Portable electric energy measuring terminal comprehensive calibration instrument on site
CN103616660A (en) * 2013-12-02 2014-03-05 国家电网公司 Power-down processing reliability test device and method for intelligent ammeters in interference environment
CN105243829A (en) * 2015-09-30 2016-01-13 青岛世泽电子仪表有限公司 Portable simulated meter module
CN106597351A (en) * 2016-11-18 2017-04-26 云南电网有限责任公司电力科学研究院 Electric energy meter verification device online real-time monitoring realization method

Also Published As

Publication number Publication date
JP3330519B2 (en) 2002-09-30

Similar Documents

Publication Publication Date Title
US8489346B2 (en) Parametric multi-cycle averaging in an intelligent electronic device
CA1129964A (en) Programmable time registering ac electric energy meter having electronic accumulators and display
US4261037A (en) System for monitoring utility usage
CA2353929C (en) Utility metering system having waveform capture for power quality monitoring
CN100523832C (en) Methods and apparatus for phase compensation in electronic energy meters
US7508190B2 (en) Test pulses for enabling revenue testable panel meters
US4931725A (en) Electronic electricity meters
US7548223B2 (en) Reduced cost automatic meter reading system and method using locally communicating utility meters
US7359809B2 (en) Electricity metering with a current transformer
US5764523A (en) Electronic watt-hour meter
CA1101073A (en) Digital processing and calculating ac electric energy metering system
US4839819A (en) Intelligent power monitor
EP0653070B1 (en) High speed power analyzer
AU697726B2 (en) Data collection and processing for digital AC power system monitor/analyzer
US6504357B1 (en) Apparatus for metering electrical power and electronically communicating electrical power information
US7102556B2 (en) Method and apparatus for obtaining power computation parameters
EP0462045B1 (en) Digital power metering
US4495463A (en) Electronic watt and/or watthour measuring circuit having active load terminated current sensor for sensing current and providing automatic zero-offset of current sensor DC offset error potentials
US4218737A (en) Revenue metering system for power companies
US4989155A (en) Intelligent power monitor
US5539304A (en) Calibration of power meters
EP1217381B1 (en) Multiple virtual meters in one physical meter
FI86224B (en) Statisk ELEKTRICITETSRAEKNARE OCH FOERFARANDE Foer DESS KALIBRERING.
US6735535B1 (en) Power meter having an auto-calibration feature and data acquisition capabilities
US8165834B2 (en) High density metering system

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070719

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080719

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090719

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100719

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100719

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110719

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110719

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120719

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120719

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130719

Year of fee payment: 11

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term