CN103615114A - Construction method for brick setting concrete steel tie anti-crack plate strip - Google Patents

Construction method for brick setting concrete steel tie anti-crack plate strip Download PDF

Info

Publication number
CN103615114A
CN103615114A CN201310636523.0A CN201310636523A CN103615114A CN 103615114 A CN103615114 A CN 103615114A CN 201310636523 A CN201310636523 A CN 201310636523A CN 103615114 A CN103615114 A CN 103615114A
Authority
CN
China
Prior art keywords
steel tie
brickwork
drawknot
concrete
belt construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310636523.0A
Other languages
Chinese (zh)
Other versions
CN103615114B (en
Inventor
尉烈扬
金凤娥
陈玲芬
陈铁军
邱云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Zhong Lian Construction Group Co Ltd
Original Assignee
Zhejiang Zhong Lian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Zhong Lian Construction Group Co Ltd filed Critical Zhejiang Zhong Lian Construction Group Co Ltd
Priority to CN201310636523.0A priority Critical patent/CN103615114B/en
Publication of CN103615114A publication Critical patent/CN103615114A/en
Application granted granted Critical
Publication of CN103615114B publication Critical patent/CN103615114B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Retaining Walls (AREA)

Abstract

The invention discloses a construction method for a brick setting concrete steel tie anti-crack plate strip, and belongs to one construction technology in the field of building. The construction method comprises the following construction technological processes: step a, conducting paying off and leveling, and arranging a height pole; step b, positioning a steel tie bar; step c, planting the steel tie bar; step d, conducting masonry on a wall, and installing clamps; step e, installing and shaping formworks; step f, pouring concrete, wherein the step b-step f can be repeated continuously after the step f, and when the step e is repeated, the formworks obtained in the last step e can be disassembled to be repeatedly used. The construction method is easy to implement, high in steel tie strength, firm in masonry structure and good in durability, the common quality problems of wall cracks are solved, and the construction method is quite suitable for construction of industrial and civil building framework infilled walls.

Description

Brickwork concrete drawknot anticracking board belt construction engineering method
Technical field
The invention belongs to a kind of construction technology of building field, be specifically related to a kind of brickwork concrete drawknot anticracking board belt construction engineering method.
Background technology
In housing construction, no matter which kind of materials for wall all be unable to do without, drawknot point is set.In construction, conventionally adopt at present tension rib to imbed in horizontal mortar joint, and this method drawknot intensity is little, produces thus wall body structure crack.
Summary of the invention
To the object of the invention is the deficiency existing in background technology in order overcoming, to propose a kind of construction simple, drawknot intensity is high, and masonry structure is firm, the brickwork concrete drawknot anticracking board belt construction engineering method of good endurance.
A brickwork concrete drawknot anticracking board belt construction engineering method, comprises following construction technology process:
Step a, unwrapping wire levelling, arrange marked rod: levelling Lou Huoliangmian basic unit arranges marked rod according to the requirement of fragment of brick and horizontal mortar joint on side wall;
Step b, location steel tie: according to marked rod, at side wall, set bar planting position;
Step c, bar planting: in the bar planting position boring of setting, with liquid honing boring, after in anchor adhesive injection hole, then steel tie is implanted in hole fixing;
Steps d, masonry panel and fixture are installed: according to marked rod, control thickness of mortarat bed joint masonry panel well, while building under steel tie two skin bricks, imbed fixture in perpends, then continue to lay bricks to steel tie;
Step e, template are installed and sizing; Two templates are held on fixture, then strike clamper, two templates are adjacent to masonry;
Step f, concreting: concreting, between two templates, forms drawknot strip;
After above-mentioned steps f, can continue repeating step b to f.
During above-mentioned repeating step e, after the form removable in last step e can being fallen, reuse.
Before above-mentioned steps f, suitable for reading by two clamp two templates.
Above-mentioned fixture comprises that fixture connector and live splint link closely.
In above-mentioned steps b, bar planting position is at drawknot strip mid-depth, and horizontally set quantity is 2, and its position is respectively at 1/3 and 2/3 place of masonry panel thickness.
In above-mentioned steps c, the size of boring is 1.5 times of steel tie cross-sectional diameter, the degree of depth be 10 times of steel tie diameter length and >=70mm.
In above-mentioned steps c, anchor adhesive accounts for space 80% in hole.
In above-mentioned steps d, fixture installation quantity is 3.
In above-mentioned steps f, before concreting, moistening fragment of brick surface, uses concrete mats under steel tie.
The present invention's beneficial effect is compared to existing technology: with in traditional brickwork horizontal mortar joint, bury tension rib ratio underground, this engineering method has that drawknot intensity is high, reinforcing bar is difficult for corrosion, eliminates or prevent the generation of Wall Temperature Crack.Use typified form and the fixture of customization, simple to operate, quick template supporting, form removal, after concreting, body of wall building construction continuously.This engineering method method has solved the common quality defect of wall body slit, improves workmanship level, has strengthened the durability of structure, has reduced the rate of complaints of user.
Accompanying drawing explanation
Fig. 1 is the step schematic diagram of brickwork concrete drawknot anticracking board belt construction engineering method;
Fig. 2 is the schematic diagram after bar planting in brickwork concrete drawknot anticracking board belt construction engineering method;
Fig. 3 is masonry panel and the fixture schematic diagram after installing in brickwork concrete drawknot anticracking board belt construction engineering method;
Fig. 4 is the schematic diagram after concreting in brickwork concrete drawknot anticracking board belt construction engineering method;
Fig. 5 is the sectional view of A-A in Fig. 3;
In figure: steel tie-1; Fixture-2; Template-3.
The specific embodiment
In order to make object of the present invention, technical scheme and advantage clearer, below in conjunction with Figure of description and embodiment, the present invention is further elaborated.
Embodiment: a kind of brickwork concrete drawknot anticracking board belt construction engineering method, comprises following construction technology process:
Step a, unwrapping wire levelling, arrange marked rod: levelling Lou Huoliangmian basic unit, while being greater than 20mm, can adopt the pea gravel concreten levelling that is not less than C20, and then according to the requirement of fragment of brick and horizontal mortar joint, marked rod is set on side wall;
Step b, location steel tie: according to marked rod, set ,Ci position, bar planting position be arranged on the center that is about to water the drawknot strip thickness building up at side wall, and horizontally set quantity is 2, its position is respectively at 1/3 and 2/3 place of masonry panel thickness;
Step c, bar planting: the bar planting position boring of setting, the size in this hole is 1.5 times of steel tie cross-sectional diameter, the degree of depth be 10 times of steel tie cross-sectional diameter length and >=70mm, after boring, with liquid honing, hole, then after using in anchor adhesive injection hole, then steel tie is implanted in hole fixing;
Steps d, masonry panel and fixture are installed: according to marked rod, control thickness of mortarat bed joint masonry panel well, while building under steel tie two skin bricks, imbed respectively 3 fixtures in perpends, this fixture comprises fixture connector and links closely step by step; Install after fixture, then continue to lay bricks to steel tie;
Step e, template are installed and sizing: two templates are held on respectively on 3 fixtures on masonry panel two sides, then slowly strike clamper, two templates are adjacent to masonry, general clamp is advisable, and should not excessively strike tightly, in case mobile masonry.Above-mentioned template can be fixing synthetic with steel nail by two veneers, and so template strength is more firm;
Step f, concreting: before concreting, in order to guarantee the fixed effect better effects if of template, template suitable for reading, fix two fixtures, then concreting is between two templates temporarily again, and then hand punning, forms drawknot strip.For the intensity of drawknot strip, best first moistening a little lower fragment of brick surface when concreting, and being first padded under steel tie with concrete, prevents that steel tie is out of shape and affects the quality of drawknot strip when concreting.
Complete after above step, two temporary fixtures that stripping is suitable for reading, can continue masonry panel again, repeat above-mentioned steps.In repeating step, after the fixture in last time step and template can being pulled down when needing fixture to install and template is installed, reuse.
The above; be only the specific embodiment of the present invention, but protection scope of the present invention is not limited to this, in the technical scope that any those of ordinary skill in the art disclose in the present invention; the variation that can expect easily or replacement, within all should being encompassed in the protection domain of invention.

Claims (10)

1. a brickwork concrete drawknot anticracking board belt construction engineering method, is characterized in that: comprise following construction technology process:
Step a, unwrapping wire levelling, arrange marked rod: levelling Lou Huoliangmian basic unit arranges marked rod according to the requirement of fragment of brick and horizontal mortar joint on side wall;
Step b, location steel tie: according to marked rod, at side wall, set bar planting position;
Step c, bar planting: in the bar planting position boring of setting, with liquid honing boring, after in anchor adhesive injection hole, then steel tie is implanted in hole fixing;
Steps d, masonry panel and fixture are installed: according to marked rod, control thickness of mortarat bed joint masonry panel well, while building under steel tie two skin bricks, imbed fixture in perpends, then continue to lay bricks to steel tie;
Step e, template are installed and sizing; Two templates are held on fixture, then strike clamper, two templates are adjacent to masonry;
Step f, concreting: concreting, between two templates, forms drawknot strip.
2. a kind of brickwork concrete drawknot anticracking board belt construction engineering method according to claim 1, is characterized in that: after described step f, continue repeating step b to f.
3. a kind of brickwork concrete drawknot anticracking board belt construction engineering method according to claim 2, is characterized in that: during described repeating step e, after the form removable in last step e is fallen, reuse.
4. according to a kind of brickwork concrete drawknot anticracking board belt construction engineering method described in any one in claims 1 to 3, it is characterized in that: before described step f, suitable for reading by two clamp two templates.
5. a kind of brickwork concrete drawknot anticracking board belt construction engineering method according to claim 4, is characterized in that: described fixture comprises fixture connector and links closely step by step.
6. according to a kind of brickwork concrete drawknot anticracking board belt construction method described in claim 2 or 3: it is characterized in that: in described step b, bar planting position is at drawknot strip mid-depth, and horizontally set quantity is 2, its position is respectively at 1/3 and 2/3 place of masonry panel thickness.
7. according to a kind of brickwork concrete drawknot anticracking board belt construction method described in claim 2 or 3: it is characterized in that: in described step c, the size of boring is 1.5 times of steel tie cross-sectional diameter, the degree of depth be 10 times of steel tie diameter length and >=70mm.
8. according to a kind of brickwork concrete drawknot anticracking board belt construction method described in claim 2 or 3: it is characterized in that: in described step c, anchor adhesive accounts for space 80% in hole.
9. according to a kind of brickwork concrete drawknot anticracking board belt construction method described in claim 2 or 3: it is characterized in that: in described steps d, fixture installation quantity is 3.
10. according to a kind of brickwork concrete drawknot anticracking board belt construction method described in claim 2 or 3: it is characterized in that: described template is fixing synthetic with steel nail by two veneers; In described step f, before concreting, moistening fragment of brick surface, uses concrete mats under steel tie.
CN201310636523.0A 2013-12-02 2013-12-02 Brick setting concrete drawknot anticracking board belt construction engineering method Expired - Fee Related CN103615114B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310636523.0A CN103615114B (en) 2013-12-02 2013-12-02 Brick setting concrete drawknot anticracking board belt construction engineering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310636523.0A CN103615114B (en) 2013-12-02 2013-12-02 Brick setting concrete drawknot anticracking board belt construction engineering method

Publications (2)

Publication Number Publication Date
CN103615114A true CN103615114A (en) 2014-03-05
CN103615114B CN103615114B (en) 2018-03-06

Family

ID=50165829

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310636523.0A Expired - Fee Related CN103615114B (en) 2013-12-02 2013-12-02 Brick setting concrete drawknot anticracking board belt construction engineering method

Country Status (1)

Country Link
CN (1) CN103615114B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989100A (en) * 2015-05-25 2015-10-21 中国十七冶集团有限公司 Construction method for crack prevention on connecting portion of masonry wall and concrete wall column

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1760486A (en) * 2004-10-15 2006-04-19 罗进南 Slot opening building blocks or bricks as well as light shear wall and related building, and construction method
CN201474116U (en) * 2009-08-17 2010-05-19 北京城建亚泰建设工程有限公司 Joint node for construction of ancient bricks and concrete structures
CN101858142A (en) * 2010-06-25 2010-10-13 中天建设集团有限公司天津分公司 Construction method for preventing vertical cracking between main structure and filled wall
CN102477797A (en) * 2010-11-24 2012-05-30 五冶集团上海有限公司 Construction method for preventing crack of infilled wall
KR20130006222A (en) * 2011-07-08 2013-01-16 권오준 Method for constructing stone block of housing
CN103266767A (en) * 2013-05-27 2013-08-28 中国航天建设集团有限公司 Construction method for preventing and treating cracks between concrete structure and filler wall

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1760486A (en) * 2004-10-15 2006-04-19 罗进南 Slot opening building blocks or bricks as well as light shear wall and related building, and construction method
CN201474116U (en) * 2009-08-17 2010-05-19 北京城建亚泰建设工程有限公司 Joint node for construction of ancient bricks and concrete structures
CN101858142A (en) * 2010-06-25 2010-10-13 中天建设集团有限公司天津分公司 Construction method for preventing vertical cracking between main structure and filled wall
CN102477797A (en) * 2010-11-24 2012-05-30 五冶集团上海有限公司 Construction method for preventing crack of infilled wall
KR20130006222A (en) * 2011-07-08 2013-01-16 권오준 Method for constructing stone block of housing
CN103266767A (en) * 2013-05-27 2013-08-28 中国航天建设集团有限公司 Construction method for preventing and treating cracks between concrete structure and filler wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104989100A (en) * 2015-05-25 2015-10-21 中国十七冶集团有限公司 Construction method for crack prevention on connecting portion of masonry wall and concrete wall column

Also Published As

Publication number Publication date
CN103615114B (en) 2018-03-06

Similar Documents

Publication Publication Date Title
CN207959612U (en) A kind of frame, shear wall cast-in-place structural fill wall with assembled light
CN103397658B (en) Construction method of single-side support-formwork system backing on brick mixing retaining wall
CN107829569A (en) Masonry panel fracture unit method
CN206189647U (en) Novel infilled wall brickwork drawknot muscle structure
CN109930455B (en) Municipal road curb mounting structure, construction device and construction method
CN103821253A (en) Constructing technique for aerated concrete block filler wall
CN203383508U (en) One-sided formwork body structure backing onto brick concrete retaining wall
CN110552370A (en) Reverse construction method based annular lining wall integral single-side formwork construction method
CN106968692B (en) Tunnel excavation supporting structure and construction method thereof
CN105442629A (en) Construction method for T-shaped platform vibration-isolating base of large-scale equipment
CN105649235A (en) Construction technique for MS dense thin-wall building block filling
CN203769274U (en) Horizontal floor tile laying positioning device
CN102926553A (en) Method for reinforcing row-lock wall through adopting wire entanglement and cement mortar
CN110409600A (en) Unit-combination type cesspool construction method
CN114215114A (en) Cantilever plate peripheral water distribution construction structure and construction method
CN103790168A (en) Application method of soil nailing wall in deep foundation pit supporting
CN206245560U (en) A kind of cast-in-place concrete board thickness controls prefabricated components
CN105256931A (en) Method for controlling cracks of cast-in-situ reinforced concrete plates
CN103615114A (en) Construction method for brick setting concrete steel tie anti-crack plate strip
CN103510537A (en) Construction method combining tower crane foundation and building basement floor
CN108978937A (en) A kind of building block construction technology
CN204531184U (en) For fixing the locator card of steel plastic compount anti-crack net in reinforced concrete wallboard
CN205444484U (en) Wall lacing wire subassembly
CN105569214A (en) Dense thin-wall filled building block construction technology
RU2387763C1 (en) Method for erection of monolithic walls of residential buildings, housings and structures in combined curb

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180306

Termination date: 20191202

CF01 Termination of patent right due to non-payment of annual fee