CN103590370A - 一种围海、排水、造地建筑方法 - Google Patents
一种围海、排水、造地建筑方法 Download PDFInfo
- Publication number
- CN103590370A CN103590370A CN201310253510.5A CN201310253510A CN103590370A CN 103590370 A CN103590370 A CN 103590370A CN 201310253510 A CN201310253510 A CN 201310253510A CN 103590370 A CN103590370 A CN 103590370A
- Authority
- CN
- China
- Prior art keywords
- sea
- draining
- enclosing
- land
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
Abstract
本发明属于一种围海排水造地建筑方法,特别是筑堤围海,排水、不填筑造地的建筑方法,它具有以下优点:1.降低填海工程造价90%;2.加快施工进度;3.充分利用地下空间;4.充分利用地上面积;5.收集淡水。本发明适应沿海浅海及岛屿暗礁区域的围海造地建筑工程。
Description
一、本发明属于建筑领域的一种围海、排水、造地建筑方法。
二、现有技术水平:
目前在我国沿海城市及岛屿填海造地施工时,普遍采用两种方法:一种是先填(向海域抛填大量的土石方)后护堤岸;二是先筑护堤后填土石方;两种方法都要向海域填筑大量的土石方,(占用地下大量空间)当海域填筑成平地后,再在填筑的土石方平地上开挖建筑物的基础及地下室的土石方,重复工作,增加工程造价和施工工期。
三、本发明的目的是:
提供一种安全可靠,快速高效,施工简便,充分利用地下空间,节省投资的一种围海、排水、造地建筑方法。
四、本发明的具体技术方案是:
1、先筑堤(厚度、高度由设计确定)围海(按规划设计和地形走向),筑堤围海有三种形式:沿陆围海(图1),海湾围海(图2),岛屿与暗礁围海(图3)。在筑堤围海时可分多段、多处施工(加快进度)最后合拢。
2、建立多处大型排水站,排尽筑堤围海合拢海域内的海水,使该海域变成一遍旱地,便于任何建筑施工的施工场地。
3、在筑堤围海排尽海水的旱地上,(按规划设计)全面展开各项建筑工作,地面±0.00宜高于海平面4米,地面由规划设计成由多项建筑物地面组成整体地面。±0.00以下部分全部采用框架结构,或框剪结构,形成巨大的地下空间。
五、本发明的优点是:
1、减少填海工程造价90%。
按(附图1)围海方式举例说明。
①按现有技术水平,填筑10平方公里(1千万平方米,计15000亩)的造地工程,平均填筑深度按10米计算,则需要填筑土石方料1亿立方米,按土石方料80元/立方米(爆破、开挖、运输、填筑),则需填筑费用80亿元人民币,即每亩的造价53.33万元/亩,8000元/平方米。
②如果按本发明的围筑堤围海,只围不填的方法,只需计算围堤工程造价:围堤总长3163米×3面(一面靠陆)=9489米,围堤厚度暂定6米,高度暂定10米,则围堤砼用量:9489×6×10=569340m3,是填筑造地土石方量的1/175(1亿立方米÷569340立方米=175.6)。
砼造价分析:569340立方米×1000元/立方米(材料、机械、人工、运输、模板费用)=5.7亿元人民币。
钢筋造价分析:钢筋含量按砼体积的0.4%计算
(569340×0.4%=2277.36平方米)×7.85吨/平方米=18000吨
18000吨×9000元/吨(材料、机械、人工、运输)=1.62亿元人民币。
围堤后排水造价:1亿立方米×0.6元/m3=0.6亿元人民币
围堤、排水总造价:5.7亿+1.6亿+0.6亿=8.0亿元人民币。
即是原有填海土石方方法造价的8/80=1/10.
折合每亩造价5.33万元/亩,每平方米造价80元/平方米。
2、加快工程进度,按上面造价分析时显示,围堤工程体积仅仅是填海体积的1/175,这就极大的减少了填海材料的开挖、运输、填筑(特别是远离陆地岛屿显得更重要),极大的加快施工进度,只围不填减小了各类建筑施工时的基础开挖;各类建筑的基础施工时均为干作业,加快了后期建设工程进度。
3、本发明只围不填可充分利用排水后地下的巨大空间:最低层可做水库库存淡水,生活、消防水池污水处理等。负一层可做各类仑库、车库、地铁、公路、人防地下室等。
4、充分利用地上面积:
沿堤可做轮船码头、货场、公路,堤内可建筑各类房屋、广场、街道,履土后可做花园和农田。
5、收集淡水:四周筑集水沟收集雨水(淡水)存入地下水库、净化后解决军民生产生活用水,特别是远离陆地的岛屿显得犹为重要,10平方公里集雨面积可收集淡水1800万立方米,可供5万人一年的生活用水。
六、附图说明:
图1是围海、排水、造地建筑方法流程示意图,下面结合附图加以说明。在附图中,(1)是围海筑堤的起始点,假定长宽高尺寸、为6米×6米×10m,施工时,四周安装钢模,后排尽钢模内的海水,再向模板内四周岩石植入钢筋(见《建筑地基基础设计规范》GBJ7-89.第七节:岩石锚杆基础),钢筋绑扎成型后,现浇模板内的砼。待砼强度达到折模强度后,折除钢模、重复上述工作内容一直按箭头方向施工直至合拢。(2)是加快进度多处施工的布置点。(3)是海域,(4)是围海堤内的排水区域及排干海水的旱地,可作各类建筑施工。(5)是陆地围海造地的依靠。
图2是海湾围海排水造地建筑平面示意图。
图3是暗礁、小岛围海排水造地建筑平面示意图。
Claims (1)
1.一种围海、排水(不填筑)的造地建筑方法,充分利用地下空间,筑沟收集淡水。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310253510.5A CN103590370A (zh) | 2013-06-09 | 2013-06-09 | 一种围海、排水、造地建筑方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310253510.5A CN103590370A (zh) | 2013-06-09 | 2013-06-09 | 一种围海、排水、造地建筑方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103590370A true CN103590370A (zh) | 2014-02-19 |
Family
ID=50080672
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310253510.5A Pending CN103590370A (zh) | 2013-06-09 | 2013-06-09 | 一种围海、排水、造地建筑方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103590370A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104005366A (zh) * | 2014-06-11 | 2014-08-27 | 国家海洋局第二海洋研究所 | 一种促淤蓄洪坝 |
CN107268536A (zh) * | 2017-06-15 | 2017-10-20 | 罗朝钦 | 一种筑堤围海、排水、不填筑架空造地建筑方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09242046A (ja) * | 1996-03-06 | 1997-09-16 | Pub Works Res Inst Ministry Of Constr | 軟弱土砂による海面埋立工法 |
CN101387113A (zh) * | 2008-09-25 | 2009-03-18 | 史汉祥 | 一种滨海盐土改良方法 |
CN101748705A (zh) * | 2008-12-22 | 2010-06-23 | 王锦文 | 围海造陆的方法 |
CN201794057U (zh) * | 2010-04-20 | 2011-04-13 | 陈匍林 | 一种浅海围垦结构 |
CN102296569A (zh) * | 2011-07-12 | 2011-12-28 | 长乐杭辉日用品有限公司 | 一种围海新型建筑及其该建筑的安装工艺 |
-
2013
- 2013-06-09 CN CN201310253510.5A patent/CN103590370A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09242046A (ja) * | 1996-03-06 | 1997-09-16 | Pub Works Res Inst Ministry Of Constr | 軟弱土砂による海面埋立工法 |
CN101387113A (zh) * | 2008-09-25 | 2009-03-18 | 史汉祥 | 一种滨海盐土改良方法 |
CN101748705A (zh) * | 2008-12-22 | 2010-06-23 | 王锦文 | 围海造陆的方法 |
CN201794057U (zh) * | 2010-04-20 | 2011-04-13 | 陈匍林 | 一种浅海围垦结构 |
CN102296569A (zh) * | 2011-07-12 | 2011-12-28 | 长乐杭辉日用品有限公司 | 一种围海新型建筑及其该建筑的安装工艺 |
Non-Patent Citations (1)
Title |
---|
杨树清: "《21世纪中国和世界水危机及对策》", 30 December 2004, article "修复海河流域的生态环境" * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104005366A (zh) * | 2014-06-11 | 2014-08-27 | 国家海洋局第二海洋研究所 | 一种促淤蓄洪坝 |
CN104005366B (zh) * | 2014-06-11 | 2015-12-16 | 国家海洋局第二海洋研究所 | 一种促淤蓄洪坝 |
CN107268536A (zh) * | 2017-06-15 | 2017-10-20 | 罗朝钦 | 一种筑堤围海、排水、不填筑架空造地建筑方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103953008B (zh) | 一种适用于尾矿库的改进型混合坝 | |
CN103924602B (zh) | 深厚软土基坑施工方法 | |
CN105714759B (zh) | 城市渣土场防范液化崩溃的排渗和加固方法 | |
CN104328766A (zh) | 生态石笼网箱挡墙及施工方法 | |
CN1948639A (zh) | 一种自流式地下水库的取水廊道 | |
KR100932091B1 (ko) | 방조제 내의 간척지 조성 방법 및 그에 따른 시설 구조 | |
CN102605791B (zh) | 软土地基中土方开挖方法 | |
CN103866774A (zh) | 用于护坡与崩岗排水固土的沟管网防护体 | |
CN113107061A (zh) | 一种近城市废弃露天矿地层重构方法 | |
CN104762937A (zh) | 一种应用于生态水库的抽水蓄能水电站及其污水处理方法 | |
CN206204972U (zh) | 一种兼作井点降水的预制管桩 | |
CN103334450B (zh) | 一种带排水沟的桩柱预制板挡土墙的施工方法 | |
CN108035423A (zh) | 用于海绵城市的势能加压雨水排蓄系统及方法 | |
CN103967015B (zh) | 一种深基坑止水开挖方法及其结构 | |
CN101761069B (zh) | 三墙合一地下连续墙施工方法 | |
CN101029490B (zh) | 一种岩/土体边坡的防护与治理方法 | |
CN110374181A (zh) | 一种雨水收集池及其施工方法 | |
CN203755322U (zh) | 用于护坡与崩岗排水固土的沟管网防护体 | |
CN103590370A (zh) | 一种围海、排水、造地建筑方法 | |
CN210684945U (zh) | 一种雨水收集池 | |
CN107268536A (zh) | 一种筑堤围海、排水、不填筑架空造地建筑方法 | |
CN112281912A (zh) | 一种陡峭山区河滩弃土场防护体系及其施工方法 | |
CN101967834A (zh) | 具有抗浮功能的矿浆浓缩池地下基础结构 | |
CN203007967U (zh) | 一种高原戈壁沙土地区光伏电站组件支架基础 | |
CN204238176U (zh) | 生态石笼网箱挡墙 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20140219 |