CN103572973A - Construction method for arranging steel corbel on concrete frame column - Google Patents

Construction method for arranging steel corbel on concrete frame column Download PDF

Info

Publication number
CN103572973A
CN103572973A CN201310552986.9A CN201310552986A CN103572973A CN 103572973 A CN103572973 A CN 103572973A CN 201310552986 A CN201310552986 A CN 201310552986A CN 103572973 A CN103572973 A CN 103572973A
Authority
CN
China
Prior art keywords
steel corbel
concrete frame
top board
frame trestle
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310552986.9A
Other languages
Chinese (zh)
Other versions
CN103572973B (en
Inventor
严云德
黄金超
武玉涛
孙兵
许刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU XIANGSEN CONSTRUCTION ENGINEERING Co Ltd
Original Assignee
JIANGSU XIANGSEN CONSTRUCTION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XIANGSEN CONSTRUCTION ENGINEERING Co Ltd filed Critical JIANGSU XIANGSEN CONSTRUCTION ENGINEERING Co Ltd
Priority to CN201310552986.9A priority Critical patent/CN103572973B/en
Publication of CN103572973A publication Critical patent/CN103572973A/en
Application granted granted Critical
Publication of CN103572973B publication Critical patent/CN103572973B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a construction method for arranging a steel corbel on a concrete frame column. The construction method comprises the steps of assembling steel reinforcements to form a steel reinforcement framework, and fixing at least four pre-cast screws on at least one face of the steel reinforcement framework according to the designed elevation, wherein one end of each pre-cast screw and the steel reinforcements in the steel reinforcement framework are in point welding to be fixed, and the other end of each pre-cast screw is exposed out of the steel reinforcement framework; installing a formwork on the outer side of the steel reinforcement framework, wherein the portions, exposed out of the formwork, of the pre-cast screws are protected by being wound with adhesive plasters; pouring concrete in the steel reinforcement framework; after the concrete reaches the design strength, disassembling the formwork to form the concrete frame column; installing the steel corbel on the concrete frame column, wherein the steel corbel is provided with a plurality of transverse adjustable bolt holes, and the steel corbel is fixed on the pre-cast screws through bolt holes in an adjustable mode.

Description

The job practices of steel corbel is set on concrete frame trestle
Technical field
The present invention relates to technical field of buildings, relate in particular to the job practices that steel corbel is set on a kind of concrete frame trestle.
?
Background technology
In building construction process, according to the regulation of < < Code for design of concrete structures > >, in industrial premises design for concrete frame structure formula, need to bracket be set at the strong point place of the crossbeams such as truss, crane girder, technique track.
But the bracket structure on concrete frame trestle of the prior art is normally one-body molded by form and the concrete frame trestle of concreting.The position of joints that bracket is set like this on concrete frame trestle need to increase level be encrypted stirrup and bent-up bar, cause position of joints reinforcing bar intensive on the one hand, concreting difficulty, even can cause position of joints concrete vibrating leakiness, reveal the defects such as muscle, pitted skin; On the other hand, profiled template is made complicated, has reduced work efficiency.The situation of bracket is especially all set three of concrete frame trestle, four sides, and defect is even more serious, and is more unfavorable for construction.
Therefore, for small-sized industrial premises, particularly the carrying capacity of the crossbeam such as truss, crane girder, technique track is no more than in the situation of 20KN, such as mini-plant processing plant, pig, cattle and sheep slaughter hall etc., how proposing a kind of job practices that succinctly, bracket is set easily on concrete frame trestle is the current anxious technical issues that need to address.
 
Summary of the invention
The invention reside in provide a kind of succinctly, the job practices of steel corbel is set on concrete frame trestle easily, can guarantee concreting and the quality of vibrating, and improve work efficiency.
For reaching above-mentioned purpose, the invention provides the job practices that steel corbel is set on a kind of concrete frame trestle, comprise step: assembling reinforcement forms cage of reinforcement; According to design elevation fixing at least four pre embedded bolts at least one side of described cage of reinforcement, the described reinforcing bar spot welding in one end of described pre embedded bolt and described cage of reinforcement is fixed, and the other end of described pre embedded bolt exposes outside described cage of reinforcement; At the outside of described cage of reinforcement installation form, the part of exposing outside described template of described pre embedded bolt is wound around protection with adhesive plaster; Concreting in described cage of reinforcement, and the described concrete that vibrates; Until described concrete, reach after design strength, remove described template, form concrete frame trestle; On described concrete frame trestle, steel corbel is installed, described steel corbel is provided with several horizontal adjustable bolts hole, and described steel corbel is fixed on described pre embedded bolt by described bolt hole is adjustable.
In one embodiment of the invention, described steel corbel comprises top board, fixed head and two side plates, described top board and described fixed head are rectangle, described side plate is right-angled trapezium, described fixed head and two described side plates are positioned at the same side of described top board, and described fixed head is positioned at one side of described top board, and perpendicular to described top board, two described side plates lay respectively at adjacent both sides described top board and limit described fixed head place, and two described side plates are also all perpendicular to described top board.
In one embodiment of the invention, described bolt hole is arranged on the described fixed head and described top board of described steel corbel, and the described fixed head of described steel corbel is fixed on described pre embedded bolt by the described bolt hole on described fixed head.
In one embodiment of the invention, described pre embedded bolt is provided with external screw thread, and is fixed described steel corbel with packing ring, nut.
In one embodiment of the invention, described concrete frame trestle is provided with a crossbeam, on the described top board of described steel corbel, is also provided with described bolt hole, and the described top board of described steel corbel is fixed on described crossbeam by the described bolt hole on described top board.
In one embodiment of the invention, described crossbeam is truss, crane girder or technique track.
In one embodiment of the invention, the described top board of described steel corbel, described fixed head and two described side plates are hot-dip galvanizing sheet steel.
Compared to prior art, on concrete frame trestle of the present invention, arrange in the job practices of steel corbel, first form concrete frame trestle, and form pre embedded bolt in concrete frame trestle, and then on concrete frame trestle, steel corbel is installed, steel corbel is fixed on pre embedded bolt by the bolt hole on it is adjustable, thereby can reduce cage of reinforcement, the reinforcing bar density at steel corbel place is being set, facilitated and concretely built and vibrate, guaranteed concreting and the quality of vibrating; And do not need to make profiled template, reduced the complexity of work, improved work efficiency.Concrete frame trestle of the present invention also can make convenience such as truss, crane girder, technique rail beam, efficiently, fast, be mounted on steel corbel reliably.
 
Accompanying drawing explanation
Figure 1 shows that the flow chart that the job practices of steel corbel is set on concrete frame trestle of the present invention.
Figure 2 shows that the structure chart that steel corbel is set on concrete frame trestle of the present invention.
Figure 3 shows that the schematic perspective view of steel corbel of the present invention.
Figure 4 shows that the schematic diagram of the connected mode of steel corbel of the present invention and pre embedded bolt.
 
The specific embodiment
For further setting forth the present invention, reach technological means and the effect that predetermined goal of the invention is taked, below in conjunction with accompanying drawing and preferred embodiment, the specific embodiment, structure, feature and effect thereof to proposing according to the present invention, be described in detail as follows.
Figure 1 shows that the flow chart that the job practices of steel corbel is set on concrete frame trestle of the present invention, Figure 2 shows that the structure chart that steel corbel is set on concrete frame trestle of the present invention.Please refer to Fig. 1 and Fig. 2, the job practices of steel corbel be set on concrete frame trestle of the present invention, comprise step:
The first step, assembling reinforcement forms cage of reinforcement 10.The structure of cage of reinforcement 10 is identical with the shape of concrete frame trestle 20.
Second step, according to design elevation fixing at least four pre embedded bolts 30 at least one side of cage of reinforcement 10.Concrete, 2 pre embedded bolts 30 are set in the one side of cage of reinforcement 10, one end 31 of pre embedded bolt 30 is fixed with the reinforcing bar spot welding in cage of reinforcement 10, and the other end 32 of pre embedded bolt 30 exposes outside cage of reinforcement 10.Understandable, also can on the two sides of cage of reinforcement 10, three or four sides, pre embedded bolt 30 be set, the quantity of pre embedded bolt 30, also not as limit, can increase as required or reduce.
The 3rd step, at the outside of cage of reinforcement 10 installation form, the part of exposing outside template of pre embedded bolt 30 is wound around protection with adhesive plaster.
The 4th step, concreting in cage of reinforcement 10, and vibrated concrete.
The 5th step, after concrete reaches design strength, stripping, forms concrete frame trestle 20.Generally, concrete frame trestle 20 general about 7 days can form removal.
The 6th step after the adhesive plaster on pre embedded bolt 30 is removed, is installed the steel corbel 40 of making on concrete frame trestle 20.The schematic perspective view that Figure 3 shows that steel corbel of the present invention, refers to Fig. 3, and steel corbel 40 is provided with some bolts hole 44, and steel corbel 40 is fixed on pre embedded bolt 30 by bolt hole 44 is adjustable
Figure 4 shows that the schematic diagram of the connected mode of steel corbel of the present invention and pre embedded bolt.Please with reference to Fig. 1 to Fig. 4, concrete frame trestle 20 is provided with a crossbeam 50, and crossbeam 50 can be truss, crane girder or technique track.
When only having a side of concrete frame trestle 20 to be provided with pre embedded bolt 30, the one end 31 that is positioned at cage of reinforcement 10 is bending, and to increase pre embedded bolt 30 and concrete snap-in force, thereby pre embedded bolt 30 can be anchored in concrete frame trestle 20.The adhesive plaster for part outside template that exposes of pre embedded bolt 30 is wound around protection, thereby can prevent that pre embedded bolt 30 is corroded gets rusty.On pre embedded bolt 30, be also provided with external screw thread, and be fixed steel corbel 40 with packing ring (not shown), nut 60.
Steel corbel 40 comprises top board 41, fixed head 42 and two side plates 43, and top board 41 and fixed head 42 are rectangle, and side plate 43 is right-angled trapezium, and fixed head 42 and two side plates 43 are positioned at the same side of top board 41.Fixed head 42 is positioned at one side of top board 41, and perpendicular to top board 41.Two side plates 43 lay respectively at adjacent both sides top board 41 and limits fixed head 42 places, and two side plates 43 are also all perpendicular to top board 41.Top board 41 and fixed head 42 are provided with some bolts hole 44, and the fixed head 42 of steel corbel 40 is fixed on by the bolt hole 44 on fixed head 42 on one end 31 of pre embedded bolt 30, and the top board 41 of steel corbel 40 is fixed on crossbeam 50 by the bolt hole 44 on top board 41.
In one embodiment of the invention, every pre embedded bolt 30 can bear at least carrying capacity of 20KN.
In one embodiment of the invention, the top board 41 of steel corbel 40, fixed head 42 and two side plates 43 adopt Q235 or Q345 grade steel plate material to make, and the round steel that pre embedded bolt 30 adopts diameter to be not less than 16mm is made.
In one embodiment of the invention, the top board 41 of steel corbel 40, fixed head 42 and two side plates 43 are hot-dip galvanizing sheet steel, thereby make the steel corbel 40 can be antiseptic and rustproof.
In sum, on concrete frame trestle of the present invention, arrange in the job practices of steel corbel, first form concrete frame trestle, and form pre embedded bolt in concrete frame trestle, and then on concrete frame trestle, steel corbel is installed, steel corbel is fixed on pre embedded bolt by the bolt hole on it is adjustable, thereby can reduce cage of reinforcement, the reinforcing bar density at steel corbel place is being set, facilitated and concretely built and vibrate, guaranteed concreting and the quality of vibrating; And do not need to make profiled template, reduced the complexity of work, improved work efficiency.Concrete frame trestle of the present invention also can make convenience such as truss, crane girder, technique rail beam, efficiently, fast, be mounted on steel corbel reliably.
The above, it is only preferred embodiment of the present invention, not the present invention is done to any pro forma restriction, although the present invention discloses as above with preferred embodiment, yet not in order to limit the present invention, any those skilled in the art, do not departing within the scope of technical solution of the present invention, when can utilizing the technology contents of above-mentioned announcement to make a little change or being modified to the equivalent embodiment of equivalent variations, in every case be not depart from technical solution of the present invention content, any simple modification of above embodiment being done according to technical spirit of the present invention, equivalent variations and modification, all still belong in the scope of technical solution of the present invention.

Claims (7)

1. a job practices for steel corbel is set on concrete frame trestle, it is characterized in that, comprise step:
Assembling reinforcement forms cage of reinforcement;
According to design elevation fixing at least four pre embedded bolts at least one side of described cage of reinforcement, the described reinforcing bar spot welding in one end of described pre embedded bolt and described cage of reinforcement is fixed, and the other end of described pre embedded bolt exposes outside described cage of reinforcement;
At the outside of described cage of reinforcement installation form, the part of exposing outside described template of described pre embedded bolt is wound around protection with adhesive plaster;
Concreting in described cage of reinforcement;
Until described concrete, reach after design strength, remove described template, form concrete frame trestle;
On described concrete frame trestle, steel corbel is installed, described steel corbel is provided with several horizontal adjustable bolts hole, and described steel corbel is fixed on described pre embedded bolt by described bolt hole is adjustable.
2. the job practices of steel corbel is set on concrete frame trestle as claimed in claim 1, it is characterized in that, described steel corbel comprises top board, fixed head and two side plates, described top board and described fixed head are rectangle, described side plate is right-angled trapezium, described fixed head and two described side plates are positioned at the same side of described top board, described fixed head is positioned at one side of described top board, and perpendicular to described top board, two described side plates lay respectively at adjacent both sides described top board and limit described fixed head place, and two described side plates are also all perpendicular to described top board.
3. the job practices of steel corbel is set on concrete frame trestle as claimed in claim 2, it is characterized in that, described bolt hole is arranged on the described fixed head and described top board of described steel corbel, and the described fixed head of described steel corbel is fixed on described pre embedded bolt by the described bolt hole on described fixed head.
4. the job practices of steel corbel is set on concrete frame trestle as claimed in claim 3, it is characterized in that, described pre embedded bolt is provided with external screw thread, and is fixed described steel corbel with packing ring, nut.
5. the job practices of steel corbel is set on concrete frame trestle as claimed in claim 4, it is characterized in that, described concrete frame trestle is provided with a crossbeam, on the described top board of described steel corbel, be also provided with described bolt hole, and the described top board of described steel corbel is fixed on described crossbeam by the described bolt hole on described top board.
6. the job practices of steel corbel is set on concrete frame trestle as claimed in claim 5, it is characterized in that, described crossbeam is truss, crane girder or technique track.
7. the job practices of steel corbel is set on concrete frame trestle as claimed in claim 2, it is characterized in that, the described top board of described steel corbel, described fixed head and two described side plates are hot-dip galvanizing sheet steel.
CN201310552986.9A 2013-11-11 2013-11-11 Concrete frame trestle is arranged the construction method of steel corbel Expired - Fee Related CN103572973B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310552986.9A CN103572973B (en) 2013-11-11 2013-11-11 Concrete frame trestle is arranged the construction method of steel corbel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310552986.9A CN103572973B (en) 2013-11-11 2013-11-11 Concrete frame trestle is arranged the construction method of steel corbel

Publications (2)

Publication Number Publication Date
CN103572973A true CN103572973A (en) 2014-02-12
CN103572973B CN103572973B (en) 2015-11-18

Family

ID=50045625

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310552986.9A Expired - Fee Related CN103572973B (en) 2013-11-11 2013-11-11 Concrete frame trestle is arranged the construction method of steel corbel

Country Status (1)

Country Link
CN (1) CN103572973B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821362A (en) * 2014-03-07 2014-05-28 中化二建集团有限公司 Synchronous construction method for constructing suspended rail beam and roof
CN105781130A (en) * 2016-03-22 2016-07-20 济南陆枋志合信息技术有限公司 Assembled building wall plate mounting tool module
CN108726368A (en) * 2018-06-04 2018-11-02 河南罡源电子科技有限公司 A kind of crane fixing device and its construction method
CN113737960A (en) * 2021-08-06 2021-12-03 水利部交通运输部国家能源局南京水利科学研究院 Bracket with combined fixing plate wall corner

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000282469A (en) * 1999-03-31 2000-10-10 Hazama Gumi Ltd Cut-beam type earth retaining timbering and pit excavation method
CN102220763A (en) * 2011-04-02 2011-10-19 博坤建设集团有限公司 Supporting part of lower ends of spokewise inclined internal bracing of foundation ditch supporting structure and construction method
CN102587495A (en) * 2012-02-09 2012-07-18 北京建筑工程学院 Steel beam and concrete wall semi-rigid full-bolted-connection joint
CN102653991A (en) * 2012-02-28 2012-09-05 中建三局建设工程股份有限公司 Raised type turnable concrete bearing part with template function and construction method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000282469A (en) * 1999-03-31 2000-10-10 Hazama Gumi Ltd Cut-beam type earth retaining timbering and pit excavation method
CN102220763A (en) * 2011-04-02 2011-10-19 博坤建设集团有限公司 Supporting part of lower ends of spokewise inclined internal bracing of foundation ditch supporting structure and construction method
CN102587495A (en) * 2012-02-09 2012-07-18 北京建筑工程学院 Steel beam and concrete wall semi-rigid full-bolted-connection joint
CN102653991A (en) * 2012-02-28 2012-09-05 中建三局建设工程股份有限公司 Raised type turnable concrete bearing part with template function and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103821362A (en) * 2014-03-07 2014-05-28 中化二建集团有限公司 Synchronous construction method for constructing suspended rail beam and roof
CN103821362B (en) * 2014-03-07 2015-10-28 中化二建集团有限公司 Outstanding beam-and-rail and roofing construction method for synchronously constructing
CN105781130A (en) * 2016-03-22 2016-07-20 济南陆枋志合信息技术有限公司 Assembled building wall plate mounting tool module
CN108726368A (en) * 2018-06-04 2018-11-02 河南罡源电子科技有限公司 A kind of crane fixing device and its construction method
CN113737960A (en) * 2021-08-06 2021-12-03 水利部交通运输部国家能源局南京水利科学研究院 Bracket with combined fixing plate wall corner

Also Published As

Publication number Publication date
CN103572973B (en) 2015-11-18

Similar Documents

Publication Publication Date Title
US8375678B1 (en) Methods for construction of pre-fabricated modular reinforcement cages for concrete structures
CN106906955B (en) Shear wall integral prefabricated reinforcement mesh structure and construction method thereof
CN109707173B (en) Construction method of assembly type laminated beam plate installation auxiliary device
CN103572973A (en) Construction method for arranging steel corbel on concrete frame column
CN106884541B (en) Positioning assembly, positioning device and positioning method for reserved dowel bars in shear wall
CN102277835A (en) Method for constructing single-column bent cap by adopting hoop and A-frame composite system
CN106592777A (en) Assembly type steel-concrete combined beam column joint structure and implementation method thereof
JP6308502B2 (en) Construction method of pre-tension slab in overhang construction
CN103470027B (en) A kind of assembling presets the floor slab formerecting system of anchoring nut
JP2016017358A (en) Reinforcement method and reinforcement structure for hinge part of existing girder bridge
JP2008215042A (en) Method for composing rc floor slab and two main girder bridge
JP2009097197A (en) Method of constructing pillar head
CN206600005U (en) The positioning component and positioner of reserved joint bar in shear wall
KR20130090455A (en) Construction method for continuous bridge using confined concrete
JP2007211474A (en) Vibration control stud of building, and method of constructing the same
JP2007191899A (en) Concrete structure reinforcing method and concrete structure reinforcing structure
CN203411908U (en) Temporary tensioned prestress anchoring device
JP2009270432A (en) Construction method of steel frame exposed column base structure
KR20160039143A (en) Seismic strengthening structure and method for existing building
KR20060111751A (en) A concret-structure constructing system manufactured by pre-fabricating
CN202370168U (en) Precast beam structure construction member
CN216305072U (en) Combined floor slab and concrete beam connecting structure of combined tower
CN208899866U (en) A kind of flushing cinder pumping plant wall large-scale circular hole to be provided template construct mounting structure
KR20090120289A (en) Slab form for multi-layer structure and supporting method thereof
JP5968205B2 (en) Seismic isolation foundation and its construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151118

Termination date: 20191111

CF01 Termination of patent right due to non-payment of annual fee