JP2009270432A - Construction method of steel frame exposed column base structure - Google Patents

Construction method of steel frame exposed column base structure Download PDF

Info

Publication number
JP2009270432A
JP2009270432A JP2009190849A JP2009190849A JP2009270432A JP 2009270432 A JP2009270432 A JP 2009270432A JP 2009190849 A JP2009190849 A JP 2009190849A JP 2009190849 A JP2009190849 A JP 2009190849A JP 2009270432 A JP2009270432 A JP 2009270432A
Authority
JP
Japan
Prior art keywords
column
anchor bolt
hoop
reinforcement
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009190849A
Other languages
Japanese (ja)
Other versions
JP5325709B2 (en
Inventor
Tatsuhiko Tanaka
達彦 田中
Yoshihiro Fujita
佳広 藤田
Katsuhisa Nishimura
勝尚 西村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Tokyo Tekko Co Ltd
Original Assignee
Obayashi Corp
Tokyo Tekko Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp, Tokyo Tekko Co Ltd filed Critical Obayashi Corp
Priority to JP2009190849A priority Critical patent/JP5325709B2/en
Publication of JP2009270432A publication Critical patent/JP2009270432A/en
Application granted granted Critical
Publication of JP5325709B2 publication Critical patent/JP5325709B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To reduce a construction period and cost, by simplifying construction, by improving earthquake resistant performance in a column base, in steel frame exposed column base structure. <P>SOLUTION: This construction method of the steel frame exposed column base includes a process of arranging an anchor bolt on foundation bed concrete, a process of arranging a hoop reinforcement binding erection reinforcement being a support for bundling a hoop reinforcement in parallel to this anchor bolt on the outside of the anchor bolt, a process of horizontally arranging the hoop reinforcement in an outer peripheral end part of a pilaster part to surround the hoop reinforcement binding erection reinforcement, a process of forming base concrete so that an upper part of the anchor bolt projects from a top surface of the base concrete without arranging a column main reinforcement, a process of arranging a baseplate integrated with a column of a building on the base concrete by being inserted into the anchor bolt, and a process of fixing the baseplate to the base concrete by using a nut. <P>COPYRIGHT: (C)2010,JPO&amp;INPIT

Description

本発明は鉄骨露出型柱脚構造の施工方法に関するものである。   The present invention relates to a method for constructing a steel-exposed type column base structure.

阪神大震災で多くの鋼構造建築物に倒壊、大破といった被害が生じ、そのうち、鉄骨露出型柱脚部における被害によるものもあった。これらの被害には、鉄骨露出型柱脚部のアンカーボルト自体の破断、基礎コンクリートからの抜け出し等のアンカーボルト製品ならびにそれに関連する設計・施工の不良によると思われるものが報告されている。この被害を受けて国土交通省(旧建設省)では、1995年12月に鉄骨造建築物の柱脚の設計に関して告示を出し(非特許文献1を参照)、その詳細な設計法については、日本建築センター刊行の「2001年版建築物の構造関係技術基準解説書」に記述されている。このような状況を背景として、鉄骨露出型柱脚構造の応力伝達性状況及び耐力などに関する基礎的研究が進められてきた。   The Great Hanshin Earthquake caused damage to many steel structures such as collapses and wrecking, some of which were due to damage to the exposed steel column bases. These damages have been reported to be due to anchor bolt products such as breakage of anchor bolts on steel-frame exposed column bases, slipping out of foundation concrete, and related design and construction defects. In response to this damage, the Ministry of Land, Infrastructure, Transport and Tourism (former Ministry of Construction) issued a notification in December 1995 regarding the design of column bases for steel structures (see Non-Patent Document 1). It is described in “2001 edition of structural technical standards for buildings” published by the Japan Architecture Center. Against this background, basic research has been conducted on the stress transferability and strength of steel-exposed column base structures.

従来の鉄骨露出型柱脚構造は図3に示すように、ベースプレート30の上面隅部はナット31を締め付けることによりアンカーボルト32の上端部と連結される。アンカーボルト32の下端部には板状の定着板33が、2つのナット34、35の間に挟まれて締め付け固定されている。   As shown in FIG. 3, in the conventional steel frame exposed column base structure, the upper surface corner of the base plate 30 is connected to the upper end of the anchor bolt 32 by tightening the nut 31. A plate-shaped fixing plate 33 is sandwiched between two nuts 34 and 35 and fixed to the lower end portion of the anchor bolt 32.

柱材36には、図4に示すとおり、曲げ応力M、柱の軸方向圧縮力N、せん断力Qの外力が加えられる。せん断力Qは、ベースプレート30の下面と基礎コンクリート37の天端面との間の摩擦抵抗によって基礎コンクリート37に伝達される。   As shown in FIG. 4, external force such as bending stress M, axial compression force N of the column, and shear force Q is applied to the column member 36. The shearing force Q is transmitted to the foundation concrete 37 by frictional resistance between the lower surface of the base plate 30 and the top end surface of the foundation concrete 37.

柱材36に曲げ応力Mが加わると、ベースプレート30の片側下面は圧縮領域となり、基礎コンクリート37からベースプレート30に向かって圧縮反力QPが作用する。そして、ベースプレートの反対側端部に連結するアンカーボルトには引き抜こうとする引張力QRに抵抗する引張反力QFが作用し、互いに反対向きの圧縮反力QPと引張反力QFとによって、曲げ応力Mは基礎コンクリート37に伝達される。   When bending stress M is applied to the column member 36, the lower surface on one side of the base plate 30 becomes a compression region, and a compression reaction force QP acts from the basic concrete 37 toward the base plate 30. A tensile reaction force QF that resists the pulling force QR to be pulled out acts on the anchor bolt connected to the opposite end of the base plate, and a bending stress is generated by the compression reaction force QP and the tensile reaction force QF opposite to each other. M is transmitted to the foundation concrete 37.

アンカーボルト32に作用する引張反力QFは、柱材36の軸方向圧縮力Nの大小によって変化する。地震時や暴風時のように、建築構造物全体が水平力を受けることによって柱材36には大きな曲げ応力Mが加わり、引張側のアンカーボルト32には大きな引張反力QFが作用する。   The tensile reaction force QF acting on the anchor bolt 32 varies depending on the magnitude of the axial compression force N of the column member 36. A large bending stress M is applied to the column member 36 due to the horizontal force of the entire building structure, such as during an earthquake or storm, and a large tensile reaction force QF acts on the anchor bolt 32 on the tension side.

したがって、アンカーボルトは、柱脚の塑性変形能力を左右する重要な要因であることから塑性変形能力を有するJIS規格の一般構造用圧延鋼材のSS400、SS490等が使用されている。さらに、アンカーボルト32を設置後、アンカーボルトの断面積とその強度との積が同等となる断面積と強度を有する鉄筋を主筋38として配筋して鉄筋コンクリート柱断面としていた。   Therefore, since anchor bolts are an important factor that affects the plastic deformation capacity of the column base, SS400, SS490, etc. of general structural rolled steel materials having plastic deformation capacity are used. Furthermore, after installing the anchor bolt 32, a reinforcing bar having a cross-sectional area and a strength equal to the product of the cross-sectional area of the anchor bolt and the strength thereof is arranged as a main reinforcing bar 38 to form a reinforced concrete column cross section.

また、アンカーボルト32の引張力QRが増加してあまりに大きくなると、定着板33が基礎コンクリート37の一部を上方に引き剥そうとする力が生じ、図4の点線で示すように、基礎コンクリート37にコーン状の剥離破壊を起こす可能性が発生する。   Further, when the tensile force QR of the anchor bolt 32 increases and becomes too large, a force is generated that the fixing plate 33 tries to peel a part of the foundation concrete 37 upward, and as shown by a dotted line in FIG. 37 may cause a cone-like peeling failure.

このコーン状破壊を抑止するためには、定着板33に対する基礎コンクリート37の支圧耐力、すなわちアンカーボルト32の引張力反力QFの強度を向上させる必要がある。   In order to suppress this cone-like fracture, it is necessary to improve the bearing strength of the foundation concrete 37 against the fixing plate 33, that is, the strength of the tensile force reaction force QF of the anchor bolt 32.

そこで、アンカーボルト32の長さを長くして、定着板33を設置する位置となる定着長さをアンカーボルト直径の20倍以上としている(非特許文献2を参照)。   Therefore, the anchor bolt 32 is lengthened, and the fixing length at which the fixing plate 33 is installed is set to be 20 times or more the anchor bolt diameter (see Non-Patent Document 2).

平12年建築基準法関係告示第1456条1456 Article 1456 related to the Building Standards Act 鋼管構造設計施工指針同解説、日本建築学会Explanation of steel pipe structure design and construction guidelines, Architectural Institute of Japan

しかしながら、従来から行われてきたアンカーボルトと柱主筋とを両方配置する場合においては、鉛直方向の柱主筋に太い径の鉄筋を多量に配筋するために地中梁の配筋作業が困難となり施工の手間がかかるという問題点があった。   However, in the case where both anchor bolts and column reinforcements are conventionally arranged, it is difficult to arrange underground beams because a large amount of thick reinforcing bars are arranged in the vertical column reinforcement. There was a problem that it took time for construction.

また、アンカーボルトの長さが長過ぎると柱に引張力が作用してアンカーボルトを引き抜こうとする力が作用した際に、アンカーボルトの伸びが大きくなり締め付ナット部に緩みを生じ、柱材固定度が低くなるという問題点があった。   Also, if the anchor bolt is too long, a tensile force will act on the column, and when the force to pull out the anchor bolt is applied, the anchor bolt will stretch and the tightening nut will loosen, causing the column material There was a problem that the degree of fixation was low.

そこで、本発明は、上記の問題点を鑑みてなされたものであり、鉄骨露出型柱脚構造において、柱脚の耐震性能を向上させ、かつ施工を簡略化し工期を短縮し、コストを低減する定着構造を提供する。     Therefore, the present invention has been made in view of the above problems, and in the steel frame exposed column base structure, the seismic performance of the column base is improved, the construction is simplified, the construction period is shortened, and the cost is reduced. Provide a fusing structure.

上記問題を解決する本発明の鉄骨露出型柱脚構造の施工方法は、鉄骨露出型柱脚の施工方法であって、アンカーボルトを、基礎底コンクリート上に配置する工程と、フープ筋を束ねる支持体となるフープ筋結束用建方筋を、前記アンカーボルトの外方にこれと平行に配置する工程と、前記フープ筋結束用建方筋を囲うように、前記フープ筋を柱型部の外周端部に水平に配置する工程と、柱主筋を配置することなく、アンカーボルトの上部が基礎コンクリートの頂面から突出するように、当該基礎コンクリートを形成する工程と、建築物の柱が一体化されたベースプレートを、前記アンカーボルトに挿通させて前記基礎コンクリート上に配置する工程と、ナットを用いて、前記ベースプレートを前記基礎コンクリートに固定する工程と、を備えることを特徴とする。     The construction method of the steel-exposed type column base structure of the present invention that solves the above problems is a method of constructing a steel-exposed type column base, the step of arranging anchor bolts on the foundation bottom concrete, and the support that bundles the hoop bars A hoop muscle bundling muscle that becomes a body is arranged on the outer side of the anchor bolt in parallel with the anchor bolt, and the hoop muscle is arranged on the outer periphery of the columnar part so as to surround the hoop muscle bundling braid The process of forming the foundation concrete and the pillar of the building are integrated so that the upper part of the anchor bolt protrudes from the top surface of the foundation concrete without arranging the column main reinforcement, the process of arranging the edge horizontally A step of inserting the fixed base plate through the anchor bolt and placing the base plate on the basic concrete, and a step of fixing the base plate to the basic concrete using a nut. It is characterized in.

また、前記フープ筋結束用建方筋を前記柱型部の外周端部に配置することとしてもよい。     Further, the hoop muscle bundling laying bar may be disposed at the outer peripheral end of the columnar part.

また、前記フープ筋結束用建方筋にU字形筋を用いることとしてもよい。     Moreover, it is good also as using a U-shaped muscle for the said hoop muscle binding erection muscle.

本発明によれば、鉄骨露出型柱脚構造において、柱脚の耐震性能を向上させ、かつ施工を簡略化し工期、コストを低減することが可能となる。
本発明において、フープ筋を柱型部の外周端部に配置することによってアンカーボルトの定着耐力が大きくなるために柱主筋を配置する必要が無くなる。したがって、従来の柱脚部で行われていた柱主筋の複雑な配筋が無くなり、配筋作業が省力化され、使用する鉄筋量を低減でき、かつ施工時間が短縮でき、コンクリートの充填性が容易になり品質を高くすることが可能となる。
ADVANTAGE OF THE INVENTION According to this invention, in a steel frame exposed type column base structure, it becomes possible to improve the earthquake resistance performance of a column base, to simplify construction, and to reduce a construction period and cost.
In the present invention, since the anchoring strength of the anchor bolt is increased by arranging the hoop reinforcement at the outer peripheral end of the columnar section, it is not necessary to arrange the column main reinforcement. Therefore, there is no complicated bar reinforcement of the column main bar which has been done in the conventional column base, labor saving work can be done, the amount of reinforcing bars to be used can be reduced, the construction time can be shortened, and the concrete filling ability can be reduced. It becomes easy and the quality can be increased.

また、フープ筋結束用建方筋は細い径の物を使用するために、地中梁の配筋作業が容易となり、工期の短縮、コストの低減が可能となる。
そして、U字形のフープ筋結束用建方筋を使用することにより、アンカーボルトの柱型部コンクリートへの定着力を向上させることが可能となる。
さらに、U字形のフープ筋結束用建方筋は容易に入手でき安い単価のため経済的で、他の資材と混在しないので管理が容易であるという利点がある。
In addition, since the hoop reinforcement bundling bars use thin objects, it is easy to place underground beams, shortening the work period and reducing costs.
And it becomes possible by using the U-shaped hoop reinforcement bundling reinforcement to improve the anchoring force of the anchor bolt to the columnar part concrete.
In addition, the U-shaped hoop tying tie bar is economical because it is easily available and cheap, and has the advantage of being easy to manage because it does not mix with other materials.

本発明の実施例に係る露出型固定柱脚の固定構造の全体側面図である。It is a whole side view of the fixation structure of the exposure type fixed column base which concerns on the Example of this invention. 本発明の実施例に係るU字形フープ筋結束用建方筋の配置方法を示し、(a)H型柱の場合、(b)角形柱の場合の配置例図である。The arrangement | positioning method of the U-shaped hoop muscle bundling construction reinforcement which concerns on the Example of this invention is shown, (a) In the case of an H-type column, (b) It is an example of arrangement | positioning in the case of a square column. 従来の鉄骨露出型柱脚構造図である。It is a conventional steel frame exposed column base structure diagram. 柱脚に作用する外力と反力を示す図である。It is a figure which shows the external force and reaction force which act on a column base.

以下に本発明の好ましい実施例について図面を用いて詳細に説明する。   Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.

図1は本発明の実施例に係る露出型固定柱脚の固定構造の全体側面図である。図1に示すとおり、本実施例の固定構造は、基礎コンクリート1内に基礎梁下端筋2、基礎梁上端筋3、あばら筋4を埋設し、柱型部5にU字形のフープ筋結束用建方筋6、フープ筋7、アンカーボルト8を配筋し、このアンカーボルト8の上端を柱材9に接続されたベースプレート10の挿通孔11に挿通し、アンカーボルト8の上部にナット12、13を取付け、この両ナット12、13を締め付けることで初期張力をアンカーボルト8に導入し、これによりベースプレート10を基礎コンクリート1に固定する。ベースプレート10と基礎コンクリート1の間には、無収縮性グラウト材14が充填されている。   FIG. 1 is an overall side view of a fixing structure of an exposed fixed column base according to an embodiment of the present invention. As shown in FIG. 1, the fixing structure of the present embodiment has a foundation beam 1 with a bottom beam 2, a foundation beam 3, and a rib 4 embedded therein, and a column-shaped portion 5 for binding a U-shaped hoop. The laying bar 6, the hoop bar 7, and the anchor bolt 8 are arranged, the upper end of the anchor bolt 8 is inserted into the insertion hole 11 of the base plate 10 connected to the column member 9, and the nut 12 13 is attached and the nuts 12 and 13 are tightened to introduce initial tension to the anchor bolt 8, thereby fixing the base plate 10 to the foundation concrete 1. A non-shrinkable grout material 14 is filled between the base plate 10 and the foundation concrete 1.

以下に、施工方法を示す。まず、コーン状破壊を防ぐために定着板15をアンカーボルト8に螺合して、定着板15の下面レベルが基礎コンクリート1の天端レベルから所定の定着長になる位置に移動する。   The construction method is shown below. First, the fixing plate 15 is screwed to the anchor bolt 8 to prevent the cone-like destruction, and the lower surface level of the fixing plate 15 is moved from the top end level of the foundation concrete 1 to a predetermined fixing length.

本実施例では、アンカーボルトとして、例えば、材質SD490のねじ節鉄筋を使用している。アンカーボルトの伸び能力について「2001年版建築物の構造関係技術基準解説書」によると、「ねじ部の有効断面積が軸部と同等以上であれば、素材の降伏比によらず伸び能力のあるアンカーボルトといえ、(以下略)」と記述されている。したがって、ねじ節鉄筋は、ねじ部と軸部の断面積が略等しいので伸び能力があり、アンカーボルトとして有効である。
また、本実施例では、定着板として、例えば、プレートナット(東京鉄鋼株式会社商品名、(財)日本建築センターの一般評定を取得済み)を使用している。
In the present embodiment, for example, a screw joint of material SD490 is used as the anchor bolt. According to the 2001 "Structure Related Technical Standards for Building Structures", the anchor bolts have the ability to extend as long as the effective cross-sectional area of the screw is equal to or greater than that of the shaft. It can be said that it is an anchor bolt (hereinafter abbreviated). Therefore, the screw joint reinforcing bar has an elongation capability because the cross-sectional areas of the screw portion and the shaft portion are substantially equal, and is effective as an anchor bolt.
In this embodiment, as the fixing plate, for example, a plate nut (trade name of Tokyo Steel Co., Ltd., a general rating of Nippon Building Center has been acquired) is used.

そして、図1に示すように、アンカーボルトとしてのねじ節鉄筋8の下端を、下部位置決めガイド16の端部に溶接固定されたナット17に螺合させ固定し、次に、ねじ節鉄筋8の上端側を、上部位置決めガイド(図示せず)の挿入孔に挿通し座金とナットで仮固定して、ねじ節鉄筋8の垂直度、水平度を確認し調整する。
そして、ねじ節鉄筋8を基礎底(捨て)コンクリート上の柱設置位置にセットし、下部位置決めガイド16をボルト18、ナット19で基礎底(捨て)コンクリートに固定する。 U字形のフープ筋結束用建方筋6は、U字形の両端部が上方を向き、かつU字形のそれぞれの鉛直線部が柱型部5の柱型部断面の角部になるようにそれぞれ配置し、U字形のフープ筋結束用建方筋6がねじ節鉄筋より外周側に位置し、かつ対向するように配筋する。 そして、柱型部5の四隅のU字形のフープ筋結束用建方筋6を囲むようにフープ筋7を所定の数だけ配筋する。
Then, as shown in FIG. 1, the lower end of the threaded reinforcing bar 8 as an anchor bolt is screwed and fixed to a nut 17 welded and fixed to the end of the lower positioning guide 16. The upper end side is inserted into an insertion hole of an upper positioning guide (not shown) and temporarily fixed with a washer and a nut, and the verticality and horizontality of the threaded bar 8 are confirmed and adjusted.
Then, the screw joint reinforcing bar 8 is set at the column installation position on the foundation bottom (discard) concrete, and the lower positioning guide 16 is fixed to the foundation bottom (discard) concrete with bolts 18 and nuts 19. The U-shaped hoop muscle bundling reinforcement 6 is such that both ends of the U-shape are directed upward, and each vertical line portion of the U-shape is a corner of the column-shaped section of the column-shaped portion 5. Arrangement is made so that the U-shaped hoop reinforcement bundling reinforcement 6 is located on the outer peripheral side of the threaded reinforcing bar and is opposed to the reinforcement. Then, a predetermined number of hoops 7 are arranged so as to surround the U-shaped hoop reinforcement bundling reinforcement 6 at the four corners of the columnar part 5.

ねじ節鉄筋8、フープ筋7を基礎底(捨て)コンクリート上に固定した後、プレートナット15の下面レベルが基礎コンクリート1の天端レベルから所定の定着長の位置にあることを確認し、プレートナット15とねじ節鉄筋8の間に無収縮性グラウト材を充填してプレートナット15を固定する。   After fixing the screw joints 8 and hoops 7 on the foundation bottom (discard) concrete, confirm that the lower surface level of the plate nut 15 is at a predetermined fixing length from the top edge level of the foundation concrete 1 and The plate nut 15 is fixed by filling a non-shrinkable grout material between the nut 15 and the screw joint reinforcing bar 8.

その後、所定のレベルまでコンクリートを打設して基礎コンクリート1を形成し、コンクリートが硬化すると、上部位置決めガイドを取り外し、モルタル(通称饅頭)で水平レベルを出す。モルタル(通称饅頭)が硬化した後に柱材の建て方を行う。
ベースプレート10が接続された柱材9を搬入し、ベースプレート10の挿通孔11をねじ節鉄筋8に挿入して立設する。
柱材は、例えば角形鋼管、円形鋼管、H形鋼等で、ベースプレート10は鋳鋼、鍛鋼、鋼板等で構成される。
柱材9の建入れ後、ベースプレート10と基礎コンクリート1の間に無収縮性グラウト材14を充填する。さらに、ねじ節鉄筋8とベースプレート10の挿通孔との隙間、ベースプレートとナットとの隙間に無収縮性グラウト材14を充填する。
Thereafter, the concrete is cast to a predetermined level to form the foundation concrete 1, and when the concrete is hardened, the upper positioning guide is removed and a horizontal level is obtained with a mortar (commonly known as a wharf). After the mortar (commonly known as the wharf) has hardened, the column is built.
The column material 9 to which the base plate 10 is connected is carried in, and the insertion hole 11 of the base plate 10 is inserted into the screw joint reinforcing bar 8 to stand.
The column material is, for example, a square steel pipe, a round steel pipe, an H-shaped steel, and the like, and the base plate 10 is made of cast steel, forged steel, steel plate, or the like.
After the column material 9 is installed, the non-shrinkable grout material 14 is filled between the base plate 10 and the foundation concrete 1. Further, a non-shrinkable grout material 14 is filled in the gap between the screw joint reinforcing bar 8 and the insertion hole of the base plate 10 and the gap between the base plate and the nut.

そして、両ナット12、13によりベースプレート10を締め付け、ベースプレート10とナット12との隙間から無収縮性グラウト材14が溢れ出てくることにより、ベースプレート10と基礎コンクリート1の隙間、ねじ節鉄筋8とベースプレート10の挿通孔との隙間、ベースプレート10とナット12との隙間の充填が十分にできたことを確認し、ねじ節鉄筋8に初期張力を導入してベースプレート10を基礎コンクリート1に固定する。   Then, the base plate 10 is tightened by the nuts 12 and 13, and the non-shrinkable grout material 14 overflows from the gap between the base plate 10 and the nut 12. After confirming that the gap between the base plate 10 and the insertion hole of the base plate 10 and the gap between the base plate 10 and the nut 12 are sufficiently filled, initial tension is introduced into the screw joint 8 to fix the base plate 10 to the foundation concrete 1.

したがって、本発明の実施例の構造によれば、専門の柱脚施工会社がU字形のフープ筋結束用建方筋、フープ筋の立上げを行うほどの精巧さを必要としない。また、基礎部配筋時やコンクリート打設時にも、精度確保のための専門の柱脚施工会社による立合い、手直しを必要としない。よって、各工種の技能者が必要なくなり、工程管理を簡素化することが可能である。   Therefore, according to the structure of the embodiment of the present invention, it is not necessary to have the sophistication that a specialized column base construction company raises the U-shaped hoop muscle bundling muscle and the hoop muscle. In addition, it is not necessary to arrange and rework by a specialized column base construction company to ensure accuracy when laying the foundation and placing concrete. This eliminates the need for technicians for each type of work and simplifies process management.

図2は本発明の実施例に係るU字形フープ筋結束用建方筋の配置方法を示し、(a)H型柱の場合、(b)角形柱の場合の配置例図である。   FIG. 2 shows an arrangement method of the U-shaped hoop muscle bundling laying bars according to the embodiment of the present invention, and is an arrangement example of (a) an H-shaped column and (b) a rectangular column.

図2に示すとおり、U字形のフープ筋結束用建方筋6はねじ節鉄筋8の相対する軸に加わる軸方向を考慮して、力の作用する方向に対しU字形の底板部分が抵抗できるような配置とすることが可能である。   As shown in FIG. 2, the U-shaped hoop reinforcement bundling reinforcement 6 can resist the U-shaped bottom plate portion in the direction in which the force acts in consideration of the axial direction applied to the opposite axis of the screw joint reinforcing bar 8. Such an arrangement is possible.

図2(a)に示すとおり、H型柱を使用する場合においては、複数本のU字形のフープ筋結束用建方筋をH型柱のフランジの向きとフープ筋結束用建方筋の両端部を結ぶ直線とが垂直になるように設置することにより、基礎コンクリートと柱脚との付着力を向上させることが可能となる。   As shown in FIG. 2 (a), in the case of using an H-shaped column, a plurality of U-shaped hoop muscle binding laying muscles are connected to the direction of the flange of the H-shaped column and both ends of the hoop muscle tying building muscle. By installing so that the straight line connecting the parts is vertical, the adhesion between the foundation concrete and the column base can be improved.

また、図2(b)に示すとおり、角形柱を使用する場合においては、2本のU字形のフープ筋結束用建方筋を角形柱の対角線の延長上に交差させて設置したり、4本のU字形のフープ筋結束用建方筋にて角形柱を囲うように設置角をすることにより、基礎コンクリートと柱脚との付着力を向上させることが可能となる。   In addition, as shown in FIG. 2B, in the case of using a square column, two U-shaped hoop muscle binding tie bars are installed so as to cross the diagonal extension of the square column, It is possible to improve the adhesion between the foundation concrete and the column base by setting the installation angle so as to surround the square column with the U-shaped hoop muscle binding laying bar.

本実施例では図2(a)及び図2(b)にてU字形のフープ筋結束用建方筋の設置例として3例のみ示したが、柱の形状、構造物の必要強度等によって配筋数、配筋箇所は変更可能である。   In this embodiment, only three examples of U-shaped hoop muscle bundling laying bars are shown in FIGS. 2 (a) and 2 (b), but they are arranged depending on the shape of the columns and the required strength of the structure. The number of muscles and the location of reinforcement can be changed.

1、37 基礎コンクリート
2 基礎梁下端筋
3 基礎梁上端筋
4 あばら筋
5 柱型部
6 U字形のフープ筋結束用建方筋
7 フープ筋
8 アンカーボルト(=ねじ節鉄筋)
9、36 柱材
10、30 ベースプレート
14 無収縮性グラウト材
15 定着板(=プレートナット)
32 アンカーボルト
33 定着板
38 主筋
1 and 37 Foundation concrete 2 Bottom beam 3 of the foundation beam Top bar 4 Stirrup 5 Columnar part 6 U-shaped hoop reinforcement tying bar 7 Hoop reinforcement 8 Anchor bolt (= screw joint reinforcement)
9, 36 Column material 10, 30 Base plate 14 Non-shrink grout material 15 Fixing plate (= plate nut)
32 Anchor bolt 33 Fixing plate 38 Main bar

Claims (3)

鉄骨露出型柱脚の施工方法であって、
アンカーボルトを、基礎底コンクリート上に配置する工程と、
フープ筋を束ねる支持体となるフープ筋結束用建方筋を、前記アンカーボルトの外方にこれと平行に配置する工程と、
前記フープ筋結束用建方筋を囲うように、前記フープ筋を柱型部の外周端部に水平に配置する工程と、
柱主筋を配置することなく、アンカーボルトの上部が基礎コンクリートの頂面から突出するように、当該基礎コンクリートを形成する工程と、
建築物の柱が一体化されたベースプレートを、前記アンカーボルトに挿通させて前記基礎コンクリート上に配置する工程と、
ナットを用いて、前記ベースプレートを前記基礎コンクリートに固定する工程と、
を備えることを特徴とする、鉄骨露出型柱脚の施工方法。
It is a construction method for steel exposed column bases,
Placing anchor bolts on the foundation bottom concrete;
Arranging a hoop muscle bundling laying muscle that becomes a support for bundling the hoop muscles in parallel to the outside of the anchor bolt;
A step of horizontally arranging the hoop muscles at the outer peripheral end of the columnar part so as to surround the hoop muscle bundling erection bars;
Forming the foundation concrete so that the upper part of the anchor bolt protrudes from the top surface of the foundation concrete without arranging the column main reinforcement;
A step of inserting a base plate integrated with a pillar of a building through the anchor bolt and placing it on the foundation concrete;
Fixing the base plate to the foundation concrete using a nut;
A method for constructing an exposed steel column base, comprising:
前記フープ筋結束用建方筋を前記柱型部の外周端部に配置することを特徴とする請求項1に記載の鉄骨露出型柱脚の施工方法。   The construction method of the steel-exposed type column base according to claim 1, wherein the hoop reinforcement bundling laying bar is disposed at an outer peripheral end of the column mold part. 前記フープ筋結束用建方筋にU字形筋を用いることを特徴とする請求項1又は2に記載の鉄骨露出型柱脚の施工方法。   The construction method of a steel-exposed type column base according to claim 1 or 2, wherein a U-shaped bar is used for the hoop barbing laying bar.
JP2009190849A 2009-08-20 2009-08-20 Method of constructing steel exposed column base structure Expired - Lifetime JP5325709B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009190849A JP5325709B2 (en) 2009-08-20 2009-08-20 Method of constructing steel exposed column base structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009190849A JP5325709B2 (en) 2009-08-20 2009-08-20 Method of constructing steel exposed column base structure

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2004069582A Division JP2005256424A (en) 2004-03-11 2004-03-11 Steel frame exposed type column base structure

Publications (2)

Publication Number Publication Date
JP2009270432A true JP2009270432A (en) 2009-11-19
JP5325709B2 JP5325709B2 (en) 2013-10-23

Family

ID=41437224

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009190849A Expired - Lifetime JP5325709B2 (en) 2009-08-20 2009-08-20 Method of constructing steel exposed column base structure

Country Status (1)

Country Link
JP (1) JP5325709B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011226174A (en) * 2010-04-21 2011-11-10 Nippon Chuzo Co Ltd Foundation structure for steel column base part
JP2020007868A (en) * 2018-07-12 2020-01-16 株式会社竹中工務店 Joint part structure
JP2020094460A (en) * 2018-12-14 2020-06-18 岡部株式会社 Reinforcement structure of column type foundation for exposure type column base

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6058645U (en) * 1983-09-29 1985-04-24 旭化成株式会社 Anchor for fixing column bases of buildings, etc.
JPH01203523A (en) * 1988-02-09 1989-08-16 Asahi Chem Ind Co Ltd Fixing of column base
JPH09296457A (en) * 1996-04-30 1997-11-18 Artes:Kk Anchorage structure of anchoring material in steel frame column base
JP2000319900A (en) * 1999-05-14 2000-11-21 Okabe Co Ltd Constructing method of foundation structure
JP2003013458A (en) * 2001-07-04 2003-01-15 Nippon Chuzo Kk Pilaster-section design assisting device, pilaster-section design assisting program and computer readable recording medium on which its program is recorded

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6058645U (en) * 1983-09-29 1985-04-24 旭化成株式会社 Anchor for fixing column bases of buildings, etc.
JPH01203523A (en) * 1988-02-09 1989-08-16 Asahi Chem Ind Co Ltd Fixing of column base
JPH09296457A (en) * 1996-04-30 1997-11-18 Artes:Kk Anchorage structure of anchoring material in steel frame column base
JP2000319900A (en) * 1999-05-14 2000-11-21 Okabe Co Ltd Constructing method of foundation structure
JP2003013458A (en) * 2001-07-04 2003-01-15 Nippon Chuzo Kk Pilaster-section design assisting device, pilaster-section design assisting program and computer readable recording medium on which its program is recorded

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011226174A (en) * 2010-04-21 2011-11-10 Nippon Chuzo Co Ltd Foundation structure for steel column base part
JP2020007868A (en) * 2018-07-12 2020-01-16 株式会社竹中工務店 Joint part structure
JP2020094460A (en) * 2018-12-14 2020-06-18 岡部株式会社 Reinforcement structure of column type foundation for exposure type column base
JP7134084B2 (en) 2018-12-14 2022-09-09 岡部株式会社 Reinforcement structure of column foundation for exposed column base

Also Published As

Publication number Publication date
JP5325709B2 (en) 2013-10-23

Similar Documents

Publication Publication Date Title
JP4929331B2 (en) Steel frame exposed column base construction method
KR101170922B1 (en) The rahmen bridge construction technique for which tendon and the connection support stand was used
JP4284056B2 (en) Non-embedded column base construction method and non-embedded column base structure
JP2009281066A (en) Building structure using composite structural beam having pc structure on its ends
JP5325709B2 (en) Method of constructing steel exposed column base structure
KR20200068205A (en) Seismic retrofit using strand and length adjustable truss
JP4472726B2 (en) Base-isolated building structure
JP6026794B2 (en) Column base structure of steel column
JP5509374B1 (en) Seismic strengthening structure and seismic strengthening method for existing buildings
JP2011084967A (en) Connection structure of column of building and prefabricated pile
JP2005256424A (en) Steel frame exposed type column base structure
CN114045750A (en) Construction method of high pier column tie beam
JP4436149B2 (en) Steel frame exposed column base structure
JP5162036B2 (en) Strengthening structure of wooden building
KR20190123408A (en) Mounting Apparatus For Supporting Frames
JP3702322B2 (en) Anchor bolt installation structure
JP2003161041A (en) Aseismatic reinforcing structure of existing building and execution method therefor
JP6021497B2 (en) Composite structural beam
KR101249129B1 (en) An anchor-bolt using screw iron
JP2012077531A (en) Bar arrangement structure of upper steel structure column base foundation
JP2012107429A (en) Method for constructing prestressed concrete structure
JP4382576B2 (en) Non-embedded column base construction method and non-embedded column base structure
JPH09296457A (en) Anchorage structure of anchoring material in steel frame column base
JP5350334B2 (en) Rebuilding method and building structure
JP4884200B2 (en) Seismic reinforcement structure for existing columns and construction method of the seismic reinforcement structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090820

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120110

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120302

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120305

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120807

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20121002

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20130212

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130509

A911 Transfer to examiner for re-examination before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20130517

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130625

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130722

R150 Certificate of patent or registration of utility model

Ref document number: 5325709

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term