CN103556710A - Exposed aggregate connecting method of prefabricated half shear wall and beam - Google Patents
Exposed aggregate connecting method of prefabricated half shear wall and beam Download PDFInfo
- Publication number
- CN103556710A CN103556710A CN201310462598.1A CN201310462598A CN103556710A CN 103556710 A CN103556710 A CN 103556710A CN 201310462598 A CN201310462598 A CN 201310462598A CN 103556710 A CN103556710 A CN 103556710A
- Authority
- CN
- China
- Prior art keywords
- shear wall
- prefabricated
- concrete
- connecting method
- aggregate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
The invention relates to an exposed aggregate connecting method of a prefabricated half shear wall and a beam. The method comprises pouring the shear wall in two steps, pouring concrete only to the bottom of the beam during shear wall fabrication, aggregate-exposing the cross section of the shear wall, mounting the prefabricated beam with reserved anchoring bars after binding steel bars on the upper portion of the shear wall, extending the anchoring bars on the beam into the shear wall and lastly pouring concrete for the upper portion of the shear wall, accordingly the shear wall and the beam are reliably connected to form a whole. The cross section of the connection of the prefabricated portion and the upper pour-in-site portion of the shear wall is aggregate-exposed to well combine new concrete and oil concrete and further achieve more reliable connection. The exposed aggregate connecting method for the prefabricated shear wall and the beam achieves the object of being provided with bearing capacity and reliability which are equal to or even higher than those of the connection of a pour-in-site shear wall and a pour-in-site beam by connecting the prefabricated shear wall and the beam in a prefabricated-frame-corewall structure on a flat surface, provides technical support for application of an assembly-type concrete frame-corewall structure, achieves industrialized prefabricated component production, effectively improves the engineering quality and the production efficiency, reduces building pollution, advocates green and environmental construction and advances the development of modern architectural industrialization. The tooth-form connecting method for the prefabricated half shear wall and the beam can be applied to a prefabricated frame and shear wall structure.
Description
Technical field
The present invention relates to the link technique in shear wall and Liangping face in precast frame-core wall structure.Provide a kind of prefabricated half sheet shear wall and beam undisguisedly to expect method of attachment.
Background technology
Since nineteen sixty-eight, Japan proposed this concept of housing industrialization, precast concrete assembled-type house has experienced different developing stage, up to the present, external and China's Hongkong assembled-type house system construction technology comparative maturity, China mainland is still slower in research and experimental stage development, though have successful story, and quantity seldom.Prefabricated dwelling house is the effective way that realizes housing industrialization, and it is one of the key link that prefabricated units are connected in this approach; Prefabricated units are produced in batch production, can effectively improve workmanship and production efficiency, reduce pollution form construction, advocate environmental protection construction.Along with prefabricated costruction development, prefabricated assembled shear wall structure becomes the primary structure form of current China house.
Prefabricated building are houses that the members such as a kind of lightweight heat-insulating composite wallboard by batch production Prefabrication, floor, roof panel and pillar of genus building trade are assembled.Precast frame-core wall structure system also will become a main trend of building trade development in the future, and one end that its beam is connected with Core Walls Structure usually there will be beam and situation about being connected in wall plane.For beam, at home and abroad study seldom with the technology and the method that are connected in shear wall plane.
Summary of the invention
In order to advance the development of modern architecture industrialization, the invention provides the connected mode of a kind of precast shear wall and beam, present technique is by building shear wall at twice, realizes being connected of precast shear wall and beam, finally makes the two become the integral body with reliable connection.
The technical scheme that technical solution problem of the present invention adopts is: during precast shear wall, concrete only accomplishes that beam bottom and its cross section should do undisguised material and process, tie up after the reinforcing bar of shear wall the first half the precast beam install with reserved anchor bar to corresponding position (it is interior that the anchor bar on beam stretches into shear wall), be finally shear wall the first half concreting, the vertical muscle of its central sill should be determined according to actual conditions in anchorage length within the walls.
The invention has the beneficial effects as follows: by prefabricated half sheet shear wall and beam, undisguisedly expect that link technique makes the two firm and reliable connection that becomes one, realize the reliable connection planar of precast shear wall and precast beam.Reach to be connected with beam with cast-in-place shear wall and compare the object with identical even higher supporting capacity and reliability, for the application of assembly concrete framework core wall structure provides technical support, realize batch production and produce prefabricated units, can effectively improve workmanship and production efficiency, reduce pollution form construction, advocate environmental protection construction, advance the development of modern architecture industrialization.
Accompanying drawing explanation
Accompanying drawing is that prefabricated half sheet shear wall and beam are undisguisedly expected connection procedure figure, the first step: precast shear wall and beam; Second step: beam is installed to relevant position; The 3rd step: build shear wall the first half concrete.
The specific embodiment
1. by reinforcing bar the formwork supporting plate of designing requirement colligation shear wall the latter half;
2. by reinforcing bar the formwork supporting plate of designing requirement colligation beam, during assembling reinforcement, beam-ends should reserve one section, the anchorage length that this segment length should meet design requirement;
3. concreting maintenance, and process doing undisguised material with the cross section of shear wall the first half junction;
4. the reinforcing bar on colligation shear wall top formwork supporting plate;
5. beam is installed to relevant position and the reserved anchor bar of beam-ends is inserted in shear wall fixing;
6. build shear wall the first half concrete maintenance.
Claims (2)
1. prefabricated half sheet shear wall and beam are undisguisedly expected method of attachment, it is characterized in that: by shear wall is built at twice, during precast shear wall, concrete only accomplishes that beam bottom and its cross section should do undisguised material and process, tie up after the reinforcing bar of shear wall the first half the precast beam install with reserved anchor bar to corresponding position, anchor bar on beam stretches in shear wall, be finally shear wall the first half concreting, finally make the two become the integral body with reliable connection.
2. prefabricated half sheet shear wall according to claim 1 and beam are undisguisedly expected method of attachment, it is characterized in that: the cross section that the pre-erection of shear wall is connected with the cast-in-place part of the first half should be done undisguised material and be processed, make the better combination of new-old concrete, connect more reliable.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310462598.1A CN103556710A (en) | 2013-10-08 | 2013-10-08 | Exposed aggregate connecting method of prefabricated half shear wall and beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310462598.1A CN103556710A (en) | 2013-10-08 | 2013-10-08 | Exposed aggregate connecting method of prefabricated half shear wall and beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103556710A true CN103556710A (en) | 2014-02-05 |
Family
ID=50011047
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310462598.1A Pending CN103556710A (en) | 2013-10-08 | 2013-10-08 | Exposed aggregate connecting method of prefabricated half shear wall and beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103556710A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103590492A (en) * | 2013-10-23 | 2014-02-19 | 沈阳建筑大学 | Prefabricated-type external connection structure for lower half wall frame, shear wall and girder plane |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101298796A (en) * | 2008-03-31 | 2008-11-05 | 姚攀峰 | Self-bearing type preprocessing component, self-bearing type preprocessing concrete structure and construction method thereof |
CN201395870Y (en) * | 2009-02-04 | 2010-02-03 | 南通建筑工程总承包有限公司 | Connection node between reinforced concrete fully pre-fabricated assembly structural shear wall and beam |
WO2010019044A2 (en) * | 2008-08-13 | 2010-02-18 | Svein Berg Holding As | Device for joining constructional elements |
CN102912862A (en) * | 2012-11-08 | 2013-02-06 | 沈阳建筑大学 | Prefabricated assembly type frame-shear wall-beam plane outer connection structure |
CN102912895A (en) * | 2012-11-04 | 2013-02-06 | 西安建筑科技大学 | High-ductility coupled shear wall |
CN102995745A (en) * | 2012-12-27 | 2013-03-27 | 沈阳易筑建材经销有限公司 | Integrally-assembled concrete structural system adopting steel bar lapping mode |
-
2013
- 2013-10-08 CN CN201310462598.1A patent/CN103556710A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101298796A (en) * | 2008-03-31 | 2008-11-05 | 姚攀峰 | Self-bearing type preprocessing component, self-bearing type preprocessing concrete structure and construction method thereof |
WO2010019044A2 (en) * | 2008-08-13 | 2010-02-18 | Svein Berg Holding As | Device for joining constructional elements |
CN201395870Y (en) * | 2009-02-04 | 2010-02-03 | 南通建筑工程总承包有限公司 | Connection node between reinforced concrete fully pre-fabricated assembly structural shear wall and beam |
CN102912895A (en) * | 2012-11-04 | 2013-02-06 | 西安建筑科技大学 | High-ductility coupled shear wall |
CN102912862A (en) * | 2012-11-08 | 2013-02-06 | 沈阳建筑大学 | Prefabricated assembly type frame-shear wall-beam plane outer connection structure |
CN102995745A (en) * | 2012-12-27 | 2013-03-27 | 沈阳易筑建材经销有限公司 | Integrally-assembled concrete structural system adopting steel bar lapping mode |
Non-Patent Citations (1)
Title |
---|
住房和城乡建设部住宅产业化促进中心: "《保障性住房产业化成套技术集成指南》", 30 November 2012, article "新旧混凝土连接技术", pages: 43-45 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103590492A (en) * | 2013-10-23 | 2014-02-19 | 沈阳建筑大学 | Prefabricated-type external connection structure for lower half wall frame, shear wall and girder plane |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205475850U (en) | Cast -in -place dismounting -free assembled outer wall tectosome of building with heat preservation function | |
CN105714961A (en) | Cast-in-situ dismantling-free assembling-type heat-preservation external formwork assembly, external wall structure and construction method | |
CN105696817A (en) | Multilayer cold-formed steel integrally prefabricated house and splicing method thereof | |
CN205444882U (en) | Cast -in -placely build that prefabricated dismounting -free is whole to be assembled assembly of heat preservation exterior sheathing and use outer die carrier | |
CN111424849A (en) | Prefabricated reinforced concrete shear wall convenient to install and construction method | |
CN108316466B (en) | Prefabricated bay window component, assembled bay window node structure and construction method thereof | |
CN110359597B (en) | Cross-layer beam connecting structure and installation method for reinforced bar formwork integrated component shear wall | |
CN105714962A (en) | External wall system of cast-in-situ prefabricated dismantling-free integral assembling heat-preservation external formwork and construction method | |
CN116084660A (en) | Prefabricated assembled steel-concrete frame elevator shaft structure for additionally installing old residential elevator | |
CN108775084B (en) | Steel-concrete combined precast beam and precast column connecting structure and construction method | |
CN108708452B (en) | U-shaped integral prefabricated bay window component, assembled bay window node structure and construction method thereof | |
CN102660995A (en) | Prefabricated composite plate formwork wall post-pouring concrete frame shear structure house and construction method | |
CN113719029A (en) | Assembly type beam-column connecting joint based on hidden corbels and construction method thereof | |
CN201730456U (en) | Combined prefabricated concrete door and window mounting auxiliary frame | |
CN108385869A (en) | A kind of wall element of overlapped shear wall and construction method using its progress | |
CN105040823A (en) | Partition plate and floor beam connecting structure for scissors staircase and construction method of partition plate and floor beam connecting structure | |
KR100814732B1 (en) | Manufacturing method of light weight precast concrete wall panel and the panel manufactured by the same method | |
CN103556753A (en) | Tooth-form connecting method of prefabricated integral shear wall and beam | |
CN103556710A (en) | Exposed aggregate connecting method of prefabricated half shear wall and beam | |
CN105544815A (en) | Cast-in-situ prefabricated non-dismantling integrally-assembled heat preservation outer formwork assembling structure | |
CN105649259A (en) | Prefabricated concrete wallboard and wallboard structural system constructed through prefabricated concrete wallboards and provided with hidden frame | |
CN103556821A (en) | Tooth-form connecting method for prefabricated half shear wall and beam | |
CN102926463A (en) | Plane external connection structure of cast-in-situ shear wall and prefabricated beam of assembly type concrete frame core tube structure | |
CN103556752A (en) | Exposed aggregate connecting method of prefabricated integral shear wall and beam | |
CN104563281B (en) | A kind of prefabricated balcony structure and its construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20140205 |